Feeding and discharging system for pre-assembled dialyzer to enter centrifugal sealing and filling process
By designing an automatic loading and unloading system, the problem of high manual loading and unloading work intensity in the hemodialyzer production line was solved, the automated assembly and glue injection of dialyzers and distributors was realized, and the automation and efficiency of the production line were improved.
Patent Information
- Application Number
- CN202421208041.5
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-05-30
- Publication Date
- 2025-01-21
- Estimated Expiration
- 2034-05-30
AI Technical Summary
In the hemodialyzer production line, the loading and unloading work of pre-assembled dialyzers mainly relies on manual labor, resulting in high work intensity and serious human resource occupation.
An automatic loading and unloading system for pre-assembled dialyzers entering the centrifugal sealing and filling process is designed. It utilizes an annular transmission line mechanism and a variety of transmission mechanisms to realize automatic loading, glue injection and unloading of dialyzers and distributors.
Through the automated loading and unloading system, the automation level of the hemodialyzer production line is improved, manual operations are reduced, work intensity is reduced, and production efficiency is improved.
Smart Images

Figure CN222373753U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of hemodialyzer production, and more specifically to a loading and unloading system for a preassembled dialyzer entering a centrifugal sealing and filling process. Background Art
[0002] The hemodialyzer (hemodialyzer for short) is the core device in the hemodialysis process. It is mainly composed of a membrane bundle, an outer shell, a sealing layer and end caps. The membrane bundle is placed in a transparent cylindrical outer shell, and the two sides are sealed with non-toxic medical polyurethane adhesive and fixed to the outer shell. The membrane bundle opens outside the sealing layer, and the outer end is screwed closed with a cover to form a blood chamber. The top of the cover is open to connect the inlet and outlet of the blood circuit. The space formed by the dialyzer outer shell and the polyurethane adhesive sealing layers on both sides is divided into a blood chamber and a dialysate chamber by the membrane bundle. There are inlets and outlets for the dialysate on both sides of the outer shell. When in use, the outlet and inlet of the blood chamber are respectively connected to the venous tube and arterial tube of the blood circuit, and the flow direction of the dialysate in and out is opposite to that of the blood.
[0003] In the hemodialysis machine assembly production line, after the dialyzer has gone through the pre-assembly process, the membrane bundle has been placed in the outer shell, and sealing caps are installed at both ends to form a pre-assembled dialyzer, which is then unloaded into the transfer box. When the traditional pre-assembled dialyzer is unloaded into the transfer box, it is usually manually carried to the transfer box to the centrifugal sealing process. The pre-assembled dialyzer is manually clamped on the turntable in the centrifugal sealing process, and the dispenser is manually placed. The motor drives the turntable to rotate at high speed centrifugally, so that the polyurethane glue passes through the dispenser and is "thrown" to both ends of the dialyzer shell to achieve sealing. After the sealing and pouring of the glue is completed, it is still necessary to manually remove the dispenser, dialyzer, etc. in turn. It can be seen that the loading and unloading work of the pre-assembled dialyzer entering the centrifugal sealing process is all done manually, with high work intensity and serious occupation of human resources. Utility Model Content
[0004] In order to solve the above problems, the utility model provides a loading and unloading system for a preassembled dialyzer entering a centrifugal sealing process, the purpose of which is to automatically load the preassembled dialyzer and automatically assemble it with a distributor, and then enter the centrifugal sealing line for glue injection. The dialyzer after glue injection is automatically unloaded and output to a rapid curing line.
[0005] In order to solve the above technical problems, the utility model adopts the following technical solutions:
[0006] The loading and unloading system of the preassembled dialyzer entering the centrifugal sealing process includes a closed annular transmission line mechanism, which is used to transfer the tray equipped with a turntable to each station, and the tray equipped with a turntable is used to carry the dialyzer and the distributor. The annular transmission line mechanism is sequentially provided with a dialyzer loading station, a distributor loading station, a distributor pressing station, a turntable loading station, a turntable unloading station, a distributor unloading station and a dialyzer unloading station along the transportation direction, wherein the dialyzer is transported through the dialyzer transmission line mechanism, the dialyzer loading transmission line mechanism and the dialyzer loading station. The preassembled dialyzers transported by the mechanism arrive at the dialyzer loading station, a distributor loading mechanism is arranged at the distributor loading station, a distributor pressing mechanism is arranged at the distributor pressing station, a turntable loading and unloading mechanism is arranged at the turntable loading station and the turntable unloading station, the turntable loading and unloading mechanism is connected to the centrifugal sealing line, a distributor unloading mechanism is arranged at the distributor unloading station, a dialyzer unloading mechanism is arranged at the dialyzer unloading station, the dialyzer unloading mechanism is connected to the quick curing line, and a distribution line circulation line mechanism is connected across the distributor loading station and the distributor unloading station.
[0007] Preferably, a pallet positioning assembly is provided at each workstation, and the pallet positioning assembly is used to position the pallet on the ring conveyor line mechanism to a suitable workstation.
[0008] Preferably, the dialyzer transport transmission line mechanism includes a first chain drive for transmitting preassembled dialyzers, and a visual inspection component for detecting whether the preassembled dialyzers are qualified is provided at a certain position on the first chain drive, and unqualified preassembled dialyzers fall into an unqualified product box provided at the end of the first chain drive, and qualified preassembled dialyzers wait to be grabbed by the dialyzer loading transmission line mechanism.
[0009] Preferably, the dialyzer loading transmission line mechanism includes a second chain drive, a dialyzer grabbing assembly is provided at the feeding end of the second chain drive, a dialyzer lifting assembly is provided at the discharging end of the second chain drive, and a dialyzer code scanning assembly for scanning codes to obtain dialyzer information is provided at a certain position on the second chain drive.
[0010] Preferably, the dialyzer loading mechanism and the dialyzer unloading mechanism have the same structure, including a dialyzer transverse movement and vertical grabbing assembly, which is used to grab the dialyzer on the loading transmission line mechanism into the turntable on the ring transmission line mechanism, or to grab the dialyzer in the turntable of the ring transmission line mechanism to the next process.
[0011] Preferably, the distributor loading mechanism and the distributor unloading mechanism have the same structure, including a dialyzer positioning assembly and a distributor transverse movement and vertical grasping assembly. The dialyzer positioning assembly is used to locate the position and angle of the preassembled dialyzer in the turntable, and the distributor transverse movement and vertical grasping assembly is used to grasp the distributor on the distribution line circulation line mechanism and install it on the preassembled dialyzer in the turntable, or to disassemble the distributor in the turntable and place it on the distribution line circulation line mechanism.
[0012] Preferably, the dispenser pressing mechanism comprises a rubber pressing head assembly.
[0013] Preferably, the turntable loading and unloading mechanism includes a turntable loading assembly and a turntable unloading assembly. The turntable loading assembly is used to place the turntable on the circular transmission line mechanism into the centrifugal sealing pot on the centrifugal sealing pot line. The turntable unloading assembly is used to take out the turntable in the centrifugal sealing pot on the centrifugal sealing pot line and place it in an empty tray on the circular transmission line mechanism.
[0014] Preferably, the distribution line circulation line mechanism includes lifting components at both ends and a transmission component in the middle, which are used to transmit the distributor disassembled from the distributor unloading mechanism to the distributor loading station.
[0015] The beneficial effects of the utility model are as follows: the system assembles the dialyzer and the dispenser together by setting up a ring transmission line mechanism, and then automatically places them into the centrifugal sealing and filling of the centrifugal sealing and filling line for glue injection, and takes the dialyzer with glue injection out to the rapid curing line, thereby realizing the automated connection of the pre-assembly line, the centrifugal sealing and filling line, and the rapid curing line in the dialyzer production line, improving the degree of automation between the processes, and is an important step in realizing an automated factory. BRIEF DESCRIPTION OF THE DRAWINGS
[0016] Figure 1 This is a schematic diagram of the automatic loading and unloading system of the dialyzer described in the utility model;
[0017] Figure 2 It is a schematic diagram of the dialyzer transport transmission line mechanism of the utility model;
[0018] Figure 3 It is a schematic diagram of the dialyzer feeding transmission line mechanism of the utility model;
[0019] Figure 4 It is a plan view of the operation of the dialyzer feeding mechanism of the utility model;
[0020] Figure 5 It is a schematic diagram of the dialyzer feeding mechanism of the utility model;
[0021] Figure 6 It is a schematic diagram of the dialyzer positioning assembly of the distributor feeding mechanism of the utility model;
[0022] Figure 7 It is a schematic diagram of a distributor grabbing assembly of the distributor feeding mechanism of the utility model;
[0023] Figure 8 It is a schematic diagram of the pressing mechanism of the dispenser of the utility model;
[0024] Fig. 9 This is a schematic diagram of the turntable loading and unloading mechanism of the utility model;
[0025] Fig.10 It is a schematic diagram of the dialyzer positioning assembly of the distributor unloading mechanism of the utility model;
[0026] Fig.11 It is a schematic diagram of a distributor grabbing assembly of the distributor unloading mechanism of the utility model;
[0027] Fig.12 It is a plan view of the operation of the dialyzer feeding mechanism of the utility model;
[0028] Fig.13 It is a schematic diagram of the dialyzer feeding mechanism of the utility model;
[0029] Fig.14 It is a schematic diagram of the circulating line mechanism of the distributor of the utility model;
[0030] Fig.15 It is a schematic diagram of the ring transmission line mechanism of the utility model;
[0031] Description of the figure numbers: dialyzer transport transmission line mechanism 1, dialyzer feeding transmission line mechanism 2, dialyzer feeding mechanism 3, distributor feeding mechanism 4, distributor pressing mechanism 5, turntable loading and unloading mechanism 6, distributor unloading mechanism 7, dialyzer unloading mechanism 8, distributor circulation line mechanism 9, annular transmission line mechanism 10, pre-assembly line 11, centrifugal sealing and filling line 12, rapid curing line 13;
[0032] Pre-assembled dialyzer 101, first chain drive 102, visual inspection assembly 103, defective product box 104;
[0033] Dialyzer grabbing assembly 201, dialyzer code scanning assembly 202, second chain transmission 203, dialyzer lifting assembly 204;
[0034] A first linear module 301, a first linear guide rail 302, a first electric cylinder 303, a first guide shaft 304, a first three-position swing table 305, a first vacuum suction cup 306, and a tray positioning assembly 307;
[0035] A first dialyzer positioning assembly 401, a second linear guide rail 402, a second linear module 403, a second electric cylinder 404, a second guide shaft 405, a first air gripper 406, and a distributor 407;
[0036] Sensor 501, rubber pressure head 502;
[0037] Rotary table loading assembly 610, third electric cylinder 611, third linear module 612, second air gripper 613, rotary table unloading assembly 620, fourth electric cylinder 621, fourth linear module 622, third air gripper 623;
[0038] A second dialyzer positioning assembly 701, a fifth linear guide rail 702, a fifth linear module 703, a fifth electric cylinder 704, a fifth guide shaft 705, and a fourth air claw 706;
[0039] The sixth linear module 801, the sixth linear guide rail 802, the sixth electric cylinder 803, the sixth guide shaft 804, the second three-position swing table 805, and the second vacuum suction cup 806;
[0040] Dispenser unloading elevator 901, dispenser upper transmission line 902, dispenser loading elevator 903, dispenser lower transmission line 904, dispenser empty tray 905;
[0041] Turntable 1001, tray 1002. DETAILED DESCRIPTION
[0042] The utility model is further described below in conjunction with the accompanying drawings and embodiments.
[0043] like Figure 1 As shown, after the dialyzer has gone through the process of the pre-assembly line 11, the membrane bundle has been placed in the shell, and the two ends are equipped with sealing caps to form a pre-assembled dialyzer 101. After the loading action of the utility model, the pre-assembled dialyzer 101 is transferred to the centrifugal sealing 12 to complete the sealing and filling of glue; and then after the unloading action of the utility model, the dialyzer that has completed the filling of glue is transferred to the rapid curing line 13.
[0044] like Figure 2 As shown, the preassembled dialyzer 101 that has completed the preassembly process is placed on the carrier of the first chain drive 102 of the transfer transmission mechanism 1, and is inspected by the visual inspection component 103. Qualified products go to the next process, and unqualified products go to the unqualified product box 104.
[0045] like Figure 3 As shown, the dialyzer grabbing assembly 201 grabs the qualified preassembled dialyzer 101, rotates it 90 degrees, and places it on the carrier of the second chain drive 203 in the dialyzer feeding transmission line mechanism 2. The dialyzer code scanning assembly 202 reads the product information of the preassembled dialyzer 101, and the dialyzer lifting assembly 204 lifts the preassembled dialyzer 101 into position, with the dialysate inlet and outlet facing vertically upward, waiting to be grabbed by the next process.
[0046] like Figure 4and Figure 5 As shown, at the dialyzer loading mechanism 3 station, the turntable 1001 is on the tray 1002, and is positioned by the tray positioning assembly 307, and the tray 1002 is stationary at the loading position of the dialyzer loading mechanism 3. The first electric cylinder 303, with the cooperation of the first guide shaft 304, the two groups of first vacuum suction cups 306 move downward to absorb the two preassembled dialyzers I and II on the dialyzer loading transmission line 2, and the first linear module 301, with the cooperation of the first linear guide rail 302, the two preassembled dialyzers are transversely moved to the top of the turntable 1001, the first three-position swing table 305 acts to rotate the preassembled dialyzers 35 degrees to the right, and the first electric cylinder 303 acts to place the two preassembled dialyzers at positions i and ii of the turntable 1001. The dialyzer loading mechanism 3 operates as above and grabs two preassembled dialyzers again. The first and third position table 305 is used to rotate the preassembled dialyzers 35 degrees to the left and place the two preassembled dialyzers at positions ⅲ and ⅳ of the turntable 1001. Each turntable contains two preassembled dialyzers stacked up and down and placed at 70 degrees. At the same time, RFID is activated to write the barcode information of the preassembled dialyzer into the electronic tag of the tray.
[0047] like Figure 6 and Figure 7 As shown, the tray 1002 with the preassembled dialyzers is moved to the distributor loading mechanism station 4 under the action of the circular transmission line mechanism 10, the tray positioning assembly 307 positions the tray 1002, and the dialyzer positioning assembly 401 positions the dialysate inlet and outlet to ensure that the inlet and outlet are vertically upward. The second electric cylinder 404, with the cooperation of the second guide shaft 405, drives the first air claw 406 to move downward to grab the distributor 407 from the loading position of the distributor circulation line mechanism 9, and the second linear module 403 cooperates with the second linear guide rail 402 to move the distributor 407 horizontally to the top of the preassembled dialyzer. The second electric cylinder 404 acts to insert the distributor 407 into the dialysate inlet and outlet of the preassembled dialyzer to complete the distributor loading action.
[0048] like Figure 8 As shown, the tray 1002 equipped with the preassembled dialyzer 101 and the dispenser 407 moves to the dispenser pressing mechanism station 5, the sensor 501 detects and confirms whether there are preassembled dialyzers 101 and dispensers 407 in the tray 1002, the tray positioning assembly 307 lifts up the tray 1002, and there is a rubber pressure head 502 on the top to press the dispenser 407 into the preassembled dialyzer 101.
[0049] like Fig. 9As shown, the turntable 1002 equipped with the preassembled dialyzer 101 and the dispenser 407 is moved to the turntable loading assembly 601 station, and the RFID is activated to read the barcode information in the tray electronic tag; under the action of the third electric cylinder 611, the second air claw 613 clamps the turntable 1002, and the third linear module 612 transfers the two groups of turntables to above the empty tray tube at the upper position of the centrifugal sealing and filling line 12, and the third electric cylinder 611 drives to descend, placing the two groups of turntables 1002 on the centrifugal sealing and filling line 12. The preassembled dialyzer 101 and the dispenser 407 on the turntable 1002 are injected with glue to the unloading position after the centrifugal sealing process. The fourth electric cylinder 621 of the turntable unloading assembly 620 drives the third air claw 623 to descend, clamp the turntable 1002 that has been injected with glue, and then rise. Under the action of the fourth linear module 622, it moves to the top of the empty tray of the annular transmission line mechanism 10. The fourth electric cylinder 621 descends and places the turntable 1002 on the empty tray of the annular transmission line mechanism 10, completing the loading and unloading process of the preassembled dialyzer in the centrifugal sealing process.
[0050] like Fig.10 and Fig.11 As shown, the turntable 1002 with completed glue injection is moved to the workstation of the distributor unloading mechanism 7 under the action of the circular transmission line mechanism 10, the tray positioning assembly 307 positions the tray, the dialyzer positioning assembly 701 positions the dialyzer's dialysate inlet and outlet, and lifts up the distributor 407, the fifth electric cylinder 704 cooperates with the fifth guide shaft 705, and the fourth air claw 706 moves downward to grab the distributor 407, the fifth linear module 703 cooperates with the fifth linear guide rail 702 to move the distributor 407 horizontally to above the unloading position of the distributor circulation line mechanism 9, and the fifth electric cylinder 704 acts to insert the distributor 407 into the carrier of the distributor empty tray 905 on the distributor circulation line mechanism 9 to complete the distributor unloading action.
[0051] like Fig.12 and Fig.13 As shown, the turntable 1001 with the dispenser 407 removed is moved to the dialyzer unloading mechanism 8 station through the annular transmission line mechanism 10, and is positioned by the tray positioning assembly 307. The second three-position swing table 805 acts to rotate the dialyzer 55 degrees to the right. The sixth electric cylinder 803, with the cooperation of the sixth guide shaft 804, the two groups of second vacuum suction cups 806 move downward to absorb the two dialyzers ⅲ and ⅳ on the turntable 1001. The sixth linear module 801, with the cooperation of the sixth linear guide rail 802, moves the two dialyzers horizontally to the top of the carrier of the rapid curing line 13. The sixth electric cylinder 803 acts to place the two dialyzers at positions Ⅰ and Ⅱ of the rapid curing line 13. The dialyzer unloading mechanism 8 operates as above, the second and third position swing table 805 is activated, the dialyzer is rotated 55 degrees to the left, and two dialyzers are grabbed again and placed on the carrier of the rapid curing line 13. All the dialyzers on the turntable 1001 are removed, and the loading process of the rapid curing line 13 is completed.
[0052] like Fig.14 As shown, the distributor 407 is placed on the empty pallet 905 carrier at the α position of the distributor upper transmission line 902 through the distributor unloading mechanism 7, and after being transferred to the β position, the distributor loading mechanism 4 takes away the distributor 407. The distributor unloading elevator 901, the distributor upper transmission line 902, the distributor loading elevator 903 and the distributor lower transmission line 904 form a closed loop to circulate the empty pallet 905.
[0053] like Fig.15 As shown, a plurality of trays 1002 are arranged on the ring transmission line mechanism 10, and under the action of the toothed belt, the trays 1002 move to corresponding positions of the mechanism.
[0054] In summary, the working process of the utility model is as follows: Figures 1 to 15 As shown, after the pre-assembled dialyzer 101 passes through the pre-assembly line 11, it is already equipped with a membrane bundle and a sealing cap, and is placed on the carrier of the dialyzer transfer transmission line mechanism, and is transmitted by the chain drive 102. After being inspected by the visual inspection component 103, unqualified products fall into the unqualified product box 104, and qualified products are placed on the carrier of the dialyzer feeding transmission line mechanism 2 through the dialyzer grabbing component 201, and are transmitted by the chain drive 203. The dialyzer scanning component 202 reads the product information of the pre-assembled dialyzer 101; after the two dialyzers are transmitted to the loading position, the dialyzer lifting component 204 lifts and positions the two dialyzers. , the vacuum suction cup 306 of the dialyzer loading mechanism 3 sucks two dialyzers, and at the same time, the first three-position swing table 305 rotates clockwise 35 degrees, and the dialyzers move to the top of the A and B positions of the ring transmission line mechanism 10, and then the two dialyzers are placed in the two groups of empty turntables that have been positioned by the tray positioning component 307; the dialyzer loading mechanism 3 moves again to take two dialyzers, and the first three-position swing table 305 rotates counterclockwise 35 degrees, and the two dialyzers are placed in the turntable again, so that each group of turntables contains two dialyzers stacked up and down and placed at 70 degrees, and at the same time, RFID is started to write the barcode information into the tray electronic tag;
[0055] After the dialyzer is loaded, it moves to the distributor loading mechanism 4 at the C and D positions, the tray positioning assembly 307 positions the tray at the D position, the dialyzer positioning assembly 401 fixes the two dialyzers 101 on the turntable, the first air claw 406 grabs the distributor 407 at the β position of the distributor circulation line mechanism 9, and inserts the distributor 407 into the dialysate inlet and outlet of the dialyzer on the turntable at the D position, completing the distributor loading action;
[0056] The two groups of turntables pass through the distributor feeding mechanism 4 and the distributor pressing mechanism 5 in turn, and arrive at the F and G positions, which are two groups of turntables that have been assembled with preassembled dialyzers and distributors; the tray positioning component 307 positions the trays at F and G, and the RFID starts to read the barcode information in the tray electronic tag, and the turntable feeding component 610 grabs the two groups of turntables and puts them into the empty trays of the centrifugal sealing and potting 12. At this time, the trays at the H and J positions are empty, and the turntable unloading component 620 takes out the turntables that have been injected with glue in the centrifugal sealing and potting 12, and places them at the H and J positions of the annular transmission line mechanism 10, completing the dialyzer loading and unloading process of the centrifugal sealing and potting process;
[0057] The turntable that has been injected with glue moves to the distributor unloading mechanism 7 at the K and L positions under the action of the circular transmission line mechanism 10, the tray positioning component 307 positions the tray, the dialyzer positioning component 701 positions the dialyzate inlet and outlet of the dialyzer, and lifts up the distributor 407, the fourth air claw 706 moves downward to grab the distributor 407, and moves horizontally to above the α position of the distributor circulation line mechanism 9, and then inserts the distributor 407 into the empty tray 905 carrier at the α position of the distributor circulation line mechanism 9, completing the distributor unloading action;
[0058] The distributor unloading elevator 901, the distributor upper transmission line 902, the distributor loading elevator 903 and the distributor lower transmission line 904 form a closed loop, and the distributor 407 taken down and placed at position α is transmitted through the distributor circulation line mechanism 9 and is moved to position β in turn for use by the distributor loading mechanism 4;
[0059] The turntable with the dispenser 407 removed is moved to the dialyzer unloading mechanism 8 at the M and N positions, the tray positioning assembly 307 is positioned, the second three-position swing table 805 is activated, the dialyzer is rotated 55 degrees to the right, and the two sets of second vacuum suction cups 806 move downward to absorb the two dialyzers ⅲ and ⅳ on the turntable, and move horizontally to the top of the carrier of the rapid curing line 13, and the two dialyzers are placed at positions Ⅰ and Ⅱ of the rapid curing line 13; the dialyzer unloading mechanism 8 acts as above, the second three-position swing table 805 is activated, the dialyzer is rotated 55 degrees to the left, and the two dialyzers are grabbed again and placed on the carrier of the rapid curing line 13. All the dialyzers in the turntable are removed, and the loading process of the rapid curing line 13 is completed;
[0060] Thus, the utility model realizes the automated production process of pre-assembly, centrifugal sealing and rapid curing line. The system operates reliably in the production line and improves the degree of automation.
Claims
1. The loading and unloading system of the pre-assembled dialyzer entering the centrifugal sealing process is characterized by: The invention comprises a closed annular transmission line mechanism (10), wherein the annular transmission line mechanism (10) is used to transport a tray (1002) equipped with a turntable (1001) to each station, wherein the tray (1002) equipped with the turntable (1001) is used to carry a dialyzer and a distributor, and the annular transmission line mechanism (10) is sequentially provided with a dialyzer loading station, a distributor loading station, a distributor pressing station, a turntable loading station, a turntable unloading station, a distributor unloading station and a dialyzer unloading station along the transport direction, wherein the dialyzer is transported via the dialyzer transport transmission line mechanism (1), the dialyzer loading transmission line mechanism (2) and the dialyzer loading mechanism (3). The preassembled dialyzers arrive at the dialyzer loading station, a distributor loading mechanism (4) is provided at the distributor loading station, a distributor pressing mechanism (5) is provided at the distributor pressing station, a turntable loading and unloading mechanism (6) is provided at the turntable loading station and the turntable unloading station, the turntable loading and unloading mechanism (6) is connected to the centrifugal sealing line (12), a distributor unloading mechanism (7) is provided at the distributor unloading station, a dialyzer unloading mechanism (8) is provided at the dialyzer unloading station, the dialyzer unloading mechanism (8) is connected to the rapid curing line (13), and a distribution line circulation line mechanism (9) is connected across the distributor loading station and the distributor unloading station.
2. The loading and unloading system for the preassembled dialyzer entering the centrifugal sealing process as claimed in claim 1, characterized in that: A pallet positioning assembly (307) is provided at each workstation, and the pallet positioning assembly (307) is used to position the pallet on the ring transmission line mechanism (10) at a suitable workstation.
3. The loading and unloading system for the preassembled dialyzer entering the centrifugal sealing process as claimed in claim 1, characterized in that: The dialyzer transport transmission line mechanism (1) comprises a first chain drive (102) for transmitting preassembled dialyzers (101), and a visual inspection component (103) for detecting whether the preassembled dialyzers (101) are qualified is provided at a certain position on the first chain drive (102); unqualified preassembled dialyzers (101) fall into a unqualified product box (104) provided at the end of the first chain drive (102), and qualified preassembled dialyzers (101) wait to be grabbed by the dialyzer loading transmission line mechanism (2).
4. The loading and unloading system for the preassembled dialyzer entering the centrifugal sealing process as claimed in claim 1, characterized in that: The dialyzer feeding transmission line mechanism (2) comprises a second chain drive (203), a dialyzer grabbing assembly (201) is provided at the feeding end of the second chain drive (203), a dialyzer lifting assembly (204) is provided at the discharging end of the second chain drive (203), and a dialyzer code scanning assembly (202) for scanning a code to obtain dialyzer information is provided at a certain position on the second chain drive (203).
5. The loading and unloading system for the preassembled dialyzer entering the centrifugal sealing process as claimed in claim 1, characterized in that: The dialyzer loading mechanism (3) and the dialyzer unloading mechanism (8) have the same structure, and include a dialyzer transverse movement and vertical grabbing assembly, which is used to grab the dialyzer on the loading transmission line mechanism (2) to the turntable on the ring transmission line mechanism (10), or to grab the dialyzer in the turntable of the ring transmission line mechanism (10) to the next process.
6. The loading and unloading system for the preassembled dialyzer entering the centrifugal sealing process according to claim 1, characterized in that: The distributor loading mechanism (4) and the distributor unloading mechanism (7) have the same structure, including a dialyzer positioning component and a distributor transverse movement and vertical grasping component. The dialyzer positioning component is used to locate the position and angle of the preassembled dialyzer (101) in the turntable (1001). The distributor transverse movement and vertical grasping component is used to grasp the distributor on the distribution line circulation line mechanism (9) and install it on the preassembled dialyzer (101) in the turntable (1001), or to disassemble the distributor (407) in the turntable (1001) and place it on the distribution line circulation line mechanism (9).
7. The loading and unloading system for the preassembled dialyzer entering the centrifugal sealing process as claimed in claim 1, characterized in that: The dispenser pressing mechanism (5) comprises a rubber pressing head assembly.
8. The loading and unloading system for the preassembled dialyzer entering the centrifugal sealing process as claimed in claim 1, characterized in that: The turntable loading and unloading mechanism (6) comprises a turntable loading assembly (610) and a turntable unloading assembly (620), wherein the turntable loading assembly (610) is used to place the turntable on the annular transmission line mechanism (10) into the centrifugal sealing pot on the centrifugal sealing pot line (12), and the turntable unloading assembly (620) is used to take out the turntable in the centrifugal sealing pot on the centrifugal sealing pot line (12) and place it into an empty tray on the annular transmission line mechanism (10).
9. The loading and unloading system for the preassembled dialyzer entering the centrifugal sealing process as claimed in claim 1, characterized in that: The distribution line circulation line mechanism (9) comprises lifting components at both ends and a transmission component in the middle, which is used to transmit the distributor (407) disassembled by the distributor unloading mechanism (7) to the distributor loading station.