Water and soil loss prevention structure for side slope of dumping site
By planting slope protection plants in the protective bricks of the dumpsite slope protection, and using a combination of supporting square columns and reinforcing components, the problem of soil erosion in the dumpsite slope protection during the rainy season was solved, and the stability and aesthetics of the slope protection were achieved. Promotes plant growth and survival.
Patent Information
- Application Number
- CN202420331251.7
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-02-22
- Publication Date
- 2025-01-21
- Estimated Expiration
- 2034-02-22
AI Technical Summary
The slope protection site is easily threatened by soil erosion during the rainy season, and a single planted slope protection plant is difficult to survive and lacks aesthetics.
Use the method of planting slope protection plants within the protective bricks. By supporting the combination of square columns, multiple triangular bricks and hexagonal hollow bricks, combined with reinforcing components such as circular casings, anti-detachment pins and anti-detachment, the plant planting position is ensured to be stable and beautiful. .
It achieves the stability and waterproofing and soil erosion prevention effect of the slope protection of the dump site, and at the same time beautifies the environment and promotes the growth and survival of slope protection plants.
Smart Images

Figure CN222375444U_ABST
Abstract
Description
Technical Field
[0001] The utility model belongs to the technical field of spoil dump slope protection, in particular to a spoil dump slope waterproofing structure. Background Art
[0002] A spoil dump, also known as a waste rock dump, refers to a place where mining waste is concentratedly discharged. Mining refers to open-pit mining and underground mining, including open-pit stripping and shaft excavation and development during mine infrastructure construction. The waste generally includes humus topsoil, weathered rock and soil, hard rock and mixed rock and soil, and sometimes also includes potentially recoverable off-surface ores and lean ores.
[0003] During the greening and land restoration process of the spoil dump, the bottom layer of the spoil dump needs to be protected by stone masonry to prevent rainwater erosion and river water in the rainy season from endangering the safety of the spoil dump. However, the use of stone masonry without green embellishment is not beautiful enough, and a single slope protection plant is easily affected by rainwater erosion, and the plants are not easy to survive. For this reason, it is necessary to provide an external spoil dump slope waterproofing structure, and adopt the method of planting slope protection plants in the masonry bricks to stabilize the spoil dump, prevent soil and water loss and beautify the environment at the same time. Utility Model Content
[0004] The utility model aims to provide a structure for preventing soil loss on the slope of an external dump site, which adopts the method of planting slope protection plants in masonry bricks to stabilize the dump site, prevent soil and water loss and beautify the environment, so as to solve the above technical problems.
[0005] The utility model provides a technical solution to the above-mentioned technical problems as follows: a structure for preventing soil erosion on the slope of an external dump site, comprising supporting square columns laid at the bottom of the slope protection surface of the dump site: a plurality of triangular bricks are laid on the top of the supporting square columns, a rectangular slot matching the supporting square columns is opened at the bottom of the triangular bricks, a plurality of hexagonal hollow bricks are laid on the top of the triangular bricks, the inner cavity of the hexagonal hollow bricks is filled with culture soil, slope protection plants are planted inside the culture soil, circular through holes are opened on both sides of the top of the hexagonal hollow bricks, and a reinforcing component is provided in the inner cavity of the circular through hole.
[0006] Preferably, the reinforcing component includes a circular sleeve rotatably connected to the inner cavity of the circular through hole, the inner cavity of the circular sleeve is penetrated by an anti-slip pin, the anti-slip pin penetrates into the interior of the spoil dump slope protection, and the bottom of both sides of the anti-slip pin are fixedly connected with multiple anti-slip hooks.
[0007] Preferably, two wedge-shaped teeth are welded to the bottom of both sides of the inner cavity of the circular sleeve, and a plurality of wedge-shaped grooves matching with the wedge-shaped teeth are provided on both sides of the anti-dropping pin.
[0008] Preferably, the surface of the hexagonal hollow brick is provided with a plurality of anti-slip grooves.
[0009] Preferably, an expansion joint is provided on the front surface of the anti-drop pin.
[0010] Preferably, positioning sleeves are engaged on both sides of the top of the supporting square column, and two limit pins are provided through the top of the positioning sleeve. The limit pins penetrate the positioning sleeve and are implanted inside the slope protection of the spoil dump.
[0011] 1. The beneficial effect of the utility model is as follows: the utility model supports the bottom of the slope of the spoil field through the coordinated use of supporting square columns and triangular bricks, and then lays and fixes the hexagonal hollow bricks through the setting of reinforcing components. Finally, the coordinated use of hexagonal hollow bricks and culture soil provides a planting position for slope protection plants, thereby achieving the purpose of maintaining the stability of the slope and firmly positioning the soil for planting plants.
[0012] 2. The utility model strengthens the arrangement of the components, wherein the circular sleeve, the anti-dropout pin and the anti-dropout hook are used in coordination, so that the hexagonal hollow bricks can stably cover the slope surface of the spoil dump slope protection, thereby preventing the impact of rainwater on the hexagonal hollow bricks, causing the hexagonal hollow bricks to deflect. At the same time, the coordinated use of the wedge-shaped groove and the wedge-shaped tooth plays a one-way check role for the anti-dropout pin, thereby preventing the anti-dropout pin from sliding out of the inner cavity of the circular sleeve by itself.
[0013] 3. The utility model plays a role of pressing and fixing the supporting square column through the coordinated use of the positioning sleeve and the limit pin, so that the supporting square column can provide stable support for the triangular bricks and ensure the stability of the triangular bricks and hexagonal hollow bricks after installation. BRIEF DESCRIPTION OF THE DRAWINGS
[0014] in:
[0015] Figure 1 A side cross-sectional schematic diagram of an embodiment of the utility model;
[0016] Figure 2 It is a top view schematic diagram of supporting square columns, triangular bricks and hexagonal hollow bricks according to an embodiment of the utility model;
[0017] Figure 3 It is a three-dimensional schematic diagram of a hexagonal hollow brick and a reinforcement assembly in one embodiment of the utility model;
[0018] Figure 4 It is a three-dimensional schematic diagram of supporting square columns and triangular bricks according to an embodiment of the utility model.
[0019] In the accompanying drawings, the components represented by the reference numerals are listed as follows:
[0020] 1. Slope protection of spoil dump, 2. Supporting square columns, 3. Triangular bricks, 4. Rectangular slots, 5. Hexagonal hollow bricks, 6. Cultivated soil, 7. Slope protection plants, 8. Circular through holes, 9. Reinforcement components, 91. Circular sleeves, 92. Anti-slip pins, 93. Wedge-shaped teeth, 94. Wedge-shaped slots, 95. Anti-slip hooks, 10. Anti-slip patterns, 11. Expansion joints, 12. Positioning sleeves, 13. Limit pins. DETAILED DESCRIPTION
[0021] Hereinafter, an embodiment of the external dump slope waterproofing structure of the present invention will be described with reference to the accompanying drawings.
[0022] Figure 1-4 The utility model shows an external spoil dump slope waterproof soil loss structure of an embodiment of the utility model, including a supporting square column 2 laid at the bottom of the slope surface of the spoil dump slope protection 1, and both sides of the top of the supporting square column 2 are engaged with a positioning sleeve 12, and the top of the positioning sleeve 12 is penetrated by two limit pins 13, and the limit pin 13 penetrates the positioning sleeve 12 and is implanted in the spoil dump slope protection 1. Through the coordinated use of the positioning sleeve 12 and the limit pin 13, the supporting square column 2 is pressed and fixed, so that the supporting square column 2 can be stably formed into a triangular brick 3 provides support to ensure the stability of the triangular bricks 3 and the hexagonal hollow bricks 5 after installation. A plurality of triangular bricks 3 are laid on the top of the supporting square column 2. A rectangular slot 4 matching the supporting square column 2 is provided at the bottom of the triangular brick 3. A plurality of hexagonal hollow bricks 5 are laid on the top of the triangular brick 3. The surface of the hexagonal hollow brick 5 is provided with a plurality of anti-slip grooves 10. The inner cavity of the hexagonal hollow brick 5 is filled with culture soil 6. Slope protection plants 7 are planted inside the culture soil 6. Circular through holes 8 are provided on both sides of the top of the hexagonal hollow brick 5. The inner cavity of the circular through hole 8 is provided with a reinforcement component 9, which includes a circular sleeve 91 rotatably connected to the inner cavity of the circular through hole 8, and an anti-drop pin 92 is provided through the inner cavity of the circular sleeve 91, and an expansion joint 11 is provided on the front surface of the anti-drop pin 92, and the anti-drop pin 92 passes through the interior of the spoil field slope protection 1, and the bottoms of both sides of the anti-drop pin 92 are fixedly connected with a plurality of anti-drop hooks 95, and the bottoms of both sides of the inner cavity of the circular sleeve 91 are welded with two wedge-shaped teeth 93, and both sides of the anti-drop pin 92 are provided with a plurality of wedge-shaped teeth 93. The adaptive wedge-shaped slot 94, through the setting of the reinforcement component 9, the coordinated use of the circular sleeve 91, the anti-slip pin 92 and the anti-slip hook 95, enables the hexagonal hollow brick 5 to stably cover the slope surface of the spoil dump slope protection 1, preventing the impact of rainwater on the hexagonal hollow brick 5 and causing the hexagonal hollow brick 5 to shift. At the same time, the coordinated use of the wedge-shaped slot 94 and the wedge-shaped tooth 93 plays a one-way check role for the anti-slip pin 92, thereby preventing the anti-slip pin 92 from sliding out of the inner cavity of the circular sleeve 91 by itself.
[0023] Working principle: When the utility model is used, the user first levels the slope surface of the spoil field slope protection 1, then lays the supporting square column 2, and engages the positioning sleeve 12 on both sides of the top of the supporting square column 2, and fixes it with the spoil field slope protection 1 through the limit pin 13, thereby fixing the positioning sleeve 12 and the supporting square column 2, and then the user lays the triangular bricks 3 so that the rectangular card slot 4 is sleeved on the surface of the supporting square column 2, and then the user lays the hexagonal hollow bricks 5. During the laying process of the hexagonal hollow bricks 5, the anti-drop pin 92 is pressed down so that the anti-drop pin 92 The pin 92 moves down from the inner cavity of the circular sleeve 91 and is implanted into the interior of the spoil dump slope protection 1, so that the hexagonal hollow bricks 5 can be installed and fixed. After the hexagonal hollow bricks 5 are completely laid, the user fills the culture soil 6 in the inner cavity of the hexagonal hollow bricks 5. After a certain period of time, the seeds inside the culture soil 6 grow into slope protection plants 7. It should be noted that the culture soil 6 is a slurry formed by mixing plant seeds, soil, fertilizer, water and chopped straw, and the slope protection plants 7 are alfalfa seeds, red bean grass seeds or Astragalus membranaceus seeds, which are grown into mature plants.
[0024] To sum up: the anti-soil loss structure of the external spoil dump slope supports the bottom of the slope 1 of the spoil dump through the coordinated use of supporting square columns 2 and triangular bricks 3, and then lays and fixes the hexagonal hollow bricks 5 through the setting of reinforcing components 9. Finally, with the coordinated use of hexagonal hollow bricks 5 and culture soil 6, a planting position is provided for the slope protection plants 7, thereby achieving the purpose of maintaining the stability of the slope and firmly positioning the soil for planting plants.
Claims
1. A structure for preventing soil loss on the slope of an external dump site, characterized in that: The invention comprises a supporting square column (2) laid at the bottom of a slope protection (1) of a spoil dump: a plurality of triangular bricks (3) are laid on the top of the supporting square column (2); a rectangular slot (4) matching the supporting square column (2) is provided at the bottom of the triangular brick (3); a plurality of hexagonal hollow bricks (5) are laid on the top of the triangular brick (3); the inner cavity of the hexagonal hollow brick (5) is filled with culture soil (6); slope protection plants (7) are planted inside the culture soil (6); circular through holes (8) are provided on both sides of the top of the hexagonal hollow brick (5); and a reinforcing component (9) is provided in the inner cavity of the circular through hole (8).
2. The structure for preventing soil loss from the slope of an external dump site according to claim 1, characterized in that: The reinforcing assembly (9) comprises a circular sleeve (91) rotatably connected to the inner cavity of the circular through hole (8); an anti-dropout pin (92) is provided through the inner cavity of the circular sleeve (91); the anti-dropout pin (92) penetrates into the interior of the spoil dump slope protection (1); and a plurality of anti-dropout hooks (95) are fixedly connected to the bottoms of both sides of the anti-dropout pin (92).
3. The structure for preventing soil loss from the slope of an external dump site according to claim 2, characterized in that: Two wedge-shaped teeth (93) are welded to the bottom of both sides of the inner cavity of the circular sleeve (91), and a plurality of wedge-shaped grooves (94) matching the wedge-shaped teeth (93) are provided on both sides of the anti-drop pin (92).
4. The structure for preventing soil loss from the slope of an external dump site according to claim 3, characterized in that: The surface of the hexagonal hollow brick (5) is provided with a plurality of anti-slip grooves (10).
5. The structure for preventing soil loss from the slope of an external dump site according to claim 4, characterized in that: An expansion joint (11) is provided on the front surface of the anti-drop pin (92).
6. The structure for preventing soil loss from the slope of an external dump site according to claim 5, characterized in that: Both sides of the top of the supporting square column (2) are engaged with positioning sleeves (12), and two limit pins (13) are arranged through the top of the positioning sleeve (12). The limit pins (13) penetrate the positioning sleeve (12) and are implanted in the interior of the spoil dump slope protection (1).