Movable guide wall temporary supporting device

By designing a temporary support device including the temporary support rod of the guide wall, the temporary supporting rack of the guide wall and the concrete block, the problem of insufficient anti -bending capacity of the existing guide wall support structure and the inability to recycling can be solved. Install and adapt to the effects of different sizes and efficient support.

CN222413055UActive Publication Date: 2025-01-28天津港航工程有限公司
View PDF 2 Cites 0 Cited by

Patent Information

Application Number
CN202420010210.8
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-01-03
Publication Date
2025-01-28
Estimated Expiration
2034-01-03

AI Technical Summary

Technical Problem

The existing guide wall support structure has insufficient bending ability, which poses a risk of bending after extrusion, and requires custom-made measuring scales, resulting in the inability to recycle, increasing construction costs and waste of resources.

Method used

A temporary support device of a mobile guide wall is designed, including the temporary support rods of the two guide walls, the temporary supporting rack of multiple guide walls, and multiple concrete blocks. The size of the wall and support the pressure through the concrete block to improve the support strength.

Benefits of technology

The temporary support of convenient installation and adapting to the size of different guides, and the device can be used circularly, reducing construction costs and waste of resources, and ensuring the temporary support strength of the guide wall through the pressure resistance of the concrete block.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222413055U_ABST
    Figure CN222413055U_ABST
Patent Text Reader

Abstract

The utility model discloses a movable guide wall temporary supporting device which comprises two guide wall temporary supporting rods, a plurality of guide wall temporary supporting frames and a plurality of concrete blocks. The two guide wall temporary supporting rods are erected on the guide walls on the two sides. Each guide wall temporary supporting frame comprises a U-shaped frame body and a sleeve horizontally fixed to the top side of the U-shaped frame body, and the multiple guide wall temporary supporting frames are linearly arranged at equal intervals and movably arranged on the two guide wall temporary supporting rods in a sleeving mode through the sleeves. The concrete blocks are cubic blocks, the multiple concrete blocks are linearly arranged and connected and are arranged in the multiple guide wall temporary supporting frames, and the concrete blocks located at the two ends partially stretch out to the outer sides of the guide wall temporary supporting frames located on the two end sides; the device is simple in structure and convenient to install, can be assembled by different numbers of individuals according to the sizes of different guide walls, and can be recycled; the device can give full play to the advantage of high compressive strength of the concrete blocks, the temporary supporting strength of the guide wall is guaranteed, and the construction efficiency is high.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the field of building construction, in particular to a movable temporary support device for guiding walls. Background Art

[0002] The underground continuous wall is a foundation project that uses a trenching machine on the ground to dig a long and narrow deep trench along the peripheral axis of the deep excavation project under the condition of mud wall protection. After the trench is cleared, a steel cage is suspended in the trench, and then underwater concrete is poured using the conduit method to form a unit trench section. This process is carried out section by section to build a continuous reinforced concrete wall underground as a water interception, anti-seepage, load-bearing and water retaining structure.

[0003] The guide wall of the ground-anchored wall is the first step in the construction of the ground-anchored wall. Its main functions are to retain soil, store mud and guide the construction of the ground-anchored wall, which directly affects the subsequent construction quality of the ground-anchored wall. After the construction of the guide wall of the ground-anchored wall is completed, effective support must be taken to prevent the guide wall from being squeezed and deformed; however, these support structures will cause the trenching machine to be unable to grasp the trench during the subsequent trenching construction. Therefore, during the trenching construction process, the support structure located in the trenching section and the support structure adjacent to the trenching section for laying mud circulation equipment also need to be removed. Due to the large removal area, in order to avoid the risk of extrusion and deformation of the guide wall during the trenching construction, a temporary support structure needs to be set between the guide walls adjacent to the trenching section to ensure the trenching construction effect.

[0004] At present, the common construction practice is to process small-sized steel according to the size of the guide wall for support. However, one disadvantage of using small-sized steel as a support structure is that the small-sized steel has poor bending resistance and there is a risk of bending due to extrusion of the guide wall, resulting in support failure. Another disadvantage is that the small-sized steel support structure needs to be customized, which makes it impossible to recycle, resulting in excessively high construction costs and a large waste of resources.

[0005] In order to solve the above technical problems, the published patent CN202011587666.3 proposes an adjustable formwork device for supporting a guide wall and a guide wall supporting method, including a first supporting formwork, a second supporting formwork sleeved on one end of the first supporting formwork and a locking mechanism, the second supporting formwork is configured to be able to reciprocate along the length direction of the first supporting formwork, and the end of the first supporting formwork away from the second supporting formwork and the end of the second supporting formwork away from the first supporting formwork are respectively hinged with L-shaped guide wall hanging plates, the locking mechanism is used to lock or unlock the first supporting formwork and the second supporting formwork, and a grouting port is provided on the top of the first supporting formwork and / or the second supporting formwork. The advantage is that it can adapt and support guide walls with different spacings, thereby improving the utilization rate of the device, but the disadvantage is that the process is complicated and the structural stability is poor. The published patent CN201922135367.5 proposes a guide wall support device for underground continuous wall engineering, which includes a middle support assembly, and end support assemblies are arranged on both sides of the middle support assembly, and the end support assemblies are clamped in the clamping grooves on both sides of the middle support assembly, and the middle support assembly can move in the vertical direction to adjust its position relative to the end support assemblies. The utility model provides a guide wall support device for underground continuous wall engineering, which has a reasonable structure and convenient construction, and realizes reliable support of the guide wall for underground continuous wall engineering. Its advantages are convenient construction and the device can be recycled, but its disadvantages are insufficient support structure strength and the risk of bending after extrusion. Utility Model Content

[0006] The utility model aims to provide a mobile temporary guide wall support device which is convenient to install, can adapt to different guide wall sizes and can be recycled.

[0007] To this end, the technical solution of the utility model is as follows:

[0008] A movable guide wall temporary support device comprises two guide wall temporary support rods, a plurality of guide wall temporary support frames and a plurality of concrete blocks; wherein:

[0009] The two temporary support rods of the guide walls are two cylindrical rods of equal length, and the lengths of the two rods are greater than the width of the guide groove between the guide walls on both sides, so as to be erected on the guide walls on both sides;

[0010] The temporary support frame for the guide wall comprises a U-shaped frame body formed by vertically arranging and connecting a first vertical plate, a horizontal plate and a second vertical plate in sequence, and a sleeve is horizontally fixed on the top surface of the first vertical plate and the second vertical plate respectively along the length direction of the vertical plate, and the inner diameter of the sleeve is larger than the outer diameter of the temporary support rod for the guide wall; a plurality of temporary support frames for the guide wall are arranged in a straight line at equal intervals, and each temporary support frame for the guide wall is movably sleeved on two temporary support rods for the guide wall through two sleeves thereon;

[0011] The concrete block is a cubic block that can be set in a temporary support frame for the guide wall; multiple concrete blocks are arranged in a line and connected and built into multiple temporary support frames for the guide wall, and the concrete blocks at both ends partially extend to the outside of the temporary support frames for the guide walls at both ends.

[0012] Furthermore, the length of a single-side rod end of each guide wall temporary support rod mounted on the top surface of the guide wall 1 is 0.3m to 0.5m.

[0013] Furthermore, the length of the concrete block is greater than the spacing between adjacent temporary support frames of the guide walls.

[0014] Furthermore, the total length of multiple temporary support frames for guide walls arranged in a line at equal intervals is smaller than the width of the guide groove; the total length of multiple concrete blocks arranged in a line is smaller than the width of the guide groove and greater than the total length of multiple temporary support frames for guide walls arranged in a line at equal intervals.

[0015] Furthermore, two handles are symmetrically arranged on the top surface of each concrete block.

[0016] Compared with the prior art, the mobile temporary support device for guide walls is assembled from temporary support rods for guide walls, temporary support frames for guide walls and concrete blocks, and has the advantages of simple structure and convenient installation; wherein, the temporary support frames for guide walls and concrete blocks can be assembled from different numbers of individuals according to different guide wall sizes, and can be recycled, and the supporting pressure of the device is borne by the concrete blocks, giving full play to the advantages of the high compressive strength of the concrete blocks, and ensuring the temporary support strength of the guide walls; in addition, due to the assembly and application characteristics of the device, the weight of a single structure is light, and manual construction is required, which greatly improves construction efficiency. BRIEF DESCRIPTION OF THE DRAWINGS

[0017] Figure 1 It is a structural schematic diagram of a movable guide wall temporary support device of the utility model;

[0018] Figure 2 It is a schematic diagram of the split structure of the mobile temporary support device for guide wall of the utility model;

[0019] Figure 3 It is a structural schematic diagram of a movable guide wall and a supporting structure in an embodiment of the utility model;

[0020] Figure 4 This is a schematic diagram of the construction status of the movable guide wall and the supporting structure in the embodiment of the utility model;

[0021] Figure 5 for Figure 4 A partial enlarged view of . DETAILED DESCRIPTION

[0022] The present invention will be further described below in conjunction with the accompanying drawings and specific embodiments, but the following embodiments are by no means intended to limit the present invention in any way.

[0023] See also Figure 3 , Figure 4 and Figure 5 The movable guide wall temporary support device 3 is used in the trenching construction stage of the ground-connected wall construction. After the original support structure 2 between the guide walls 1 on both sides is removed, the movable guide wall temporary support device 3 is used as a temporary support structure to avoid the risk of the guide wall being squeezed and deformed during the trenching construction stage.

[0024] See also Figure 1 and Figure 2 The movable guide wall temporary support device 3 includes two guide wall temporary support rods 3-1, a plurality of guide wall temporary support frames 3-2 and a plurality of concrete blocks 3-3.

[0025] The two temporary guide wall support rods 3-1 are two cylindrical rods of equal length, and their lengths are greater than the width of the guide groove between the guide walls 1, so that both ends of the temporary guide wall support rods 3-1 are mounted on the top surfaces of the guide walls 1 on both sides of the guide groove; in the present embodiment, the temporary guide wall support rods 3-1 are formed by cutting steel bars into appropriate lengths; the length of a single-side rod end of each temporary guide wall support rod 3-1 mounted on the top surface of the guide wall 1 is 0.5m, so as to ensure that the temporary guide wall support rods 3-1 have sufficient supporting force on the guide walls 1 on both sides to avoid slipping.

[0026] The temporary support frame 3-2 for the guide wall includes a U-shaped frame body formed by a first vertical plate, a horizontal plate and a second vertical plate which are vertically arranged and connected in sequence, and a sleeve is horizontally fixed on the top surface of the first vertical plate and the second vertical plate respectively along the length direction of the vertical plate; wherein the axial length of the sleeve is the same as the top surface length of the vertical plate, and the inner diameter of the sleeve is slightly larger than the outer diameter of the temporary support rod 3-1 for the guide wall, so that the temporary support frame 3-2 for the guide wall can be movably sleeved on the two temporary support rods 3-1 for the guide wall through the two sleeves thereon, and the position of the temporary support frame 3-2 for the guide wall on the temporary support rod 3-1 can be adjusted according to actual needs; in this embodiment, the U-shaped frame body is formed by cutting and welding, and the sleeve is formed by cutting a steel round tube into a suitable length, and the sleeve is welded and fixed on the top side of the U-shaped frame body; the number of temporary support frames 3-2 for the guide wall is adapted to the size of a single temporary support frame 3-2 for the guide wall and the width of the guide groove between the guide walls 1 on both sides, so that when multiple temporary support frames 3-2 for the guide wall are arranged in a straight line with equal intervals, their total length is less than the width of the guide groove.

[0027] The concrete block 3-3 is a cubic block formed by pouring and curing concrete, and its size is adapted to the temporary support frame 3-2 for the guide wall, so that multiple concrete blocks 3-3 are arranged in a line and set in the temporary support frame 3-2 for the guide wall; wherein, the length of the concrete block 3-3 is greater than the spacing between adjacent temporary support frames 3-2 for the guide wall, so as to avoid the concrete block from being unstable and falling to the bottom of the guide groove due to excessive spacing; the number of concrete blocks 3-3 is adapted to the size of a single concrete block 3-3 and the width of the guide groove between the guide walls 1 on both sides, so that when multiple concrete blocks 3-3 are arranged in a line and built into multiple temporary support frames 3-2 for the guide wall, the concrete blocks 3-3 located at both ends partially extend to the outside of the temporary support frames 3-2 for the guide wall located at both ends; as a preferred technical solution of this embodiment, two handles 3-4 are symmetrically arranged on the top surface of each concrete block 3-3, so as to transport or lift the concrete block 3-3 into the U-shaped frame built into the temporary support frame 3-2 for the guide wall by the handles 3-4.

[0028] In this embodiment, according to the width of the guide groove, there are five temporary guide wall support frames 3-2, which are arranged at equal intervals; there are two concrete blocks 3-3, the length of which is 2.5 times the length of the temporary guide wall support frame 3-2, the width is adapted to the spacing between the two vertical plates of the temporary guide wall support frame 3-2, and the height is the same as the height of the vertical plates of the temporary guide wall support frame 3-2. When used, five temporary guide wall support frames 3-2 are inserted into two temporary guide wall support rods 3-1, two concrete blocks 3-3 are built into the strip groove formed by the five temporary guide wall support frames 3-2, the adjacent ends of the two concrete blocks 3-3 are arranged on the temporary guide wall support frame 3-2 located in the middle position and are connected to each other, and the other ends of the two concrete blocks 3-3 are extended to the outside of the temporary guide wall support frame 3-2 located on the end side, so that when the guide wall 1 is squeezed and deformed, the squeezing force of the guide wall 1 acts on the concrete blocks 3-3, but not on the temporary guide wall support frame 3-2, thereby avoiding deformation of the mobile temporary guide wall support device.

[0029] See also Figure 3 to Figure 5 The specific process of using the mobile guide wall temporary support device to complete the ground-connected wall grooving construction is as follows:

[0030] S1. Use a trenching machine to break the supporting structure of the trenching section and the original guide wall support 2 at the trench section adjacent to the trenching section and used to set up the mud circulation equipment; wherein the trenching depth adjacent to the trenching section is controlled at 1m to 2m to ensure that the mud from the trenching section can be circulated to the trenching section on the adjacent side;

[0031] S2. According to the width of the guide groove, multiple sets of mobile guide wall temporary support devices 3 are configured to support the groove section where the mud circulation equipment is arranged; each set of mobile guide wall temporary support devices 3 is composed of two guide wall temporary support rods 3-1, multiple guide wall temporary support frames 3-2 and multiple concrete blocks 3-3;

[0032] S3. For each set of mobile temporary guide wall support device 3, firstly, two temporary guide wall support rods 3-1 are arranged horizontally and in parallel, and multiple temporary guide wall support frames 3-2 are sequentially inserted into the two temporary guide wall support rods 3-1 through their top side sleeves; then, the two temporary guide wall support rods 3-1 with multiple temporary guide wall support frames 3-2 are installed on the two side guide walls 1 adjacent to the original support structure setting position of the slot section, and the multiple temporary guide wall support frames 3-2 are adjusted to be arranged at equal intervals, and the two temporary guide wall support frames 3-2 located at the end side are spaced apart from the side wall of the guide wall; finally, the multiple concrete blocks 3-3 are transported or hoisted into the U-shaped frame body built into the multiple temporary guide wall support frames 3-2 through their upper handles 3-4;

[0033] S4, after completing the temporary support device setting in step S3, a circulating pump hanger 4 and a circulating pump 5 are placed in the trough section, a circulating mud pipe 6 is connected to the circulating pump 5, and a mud delivery pipe 7 is connected to supply mud;

[0034] S5, the trenching machine 8 performs trenching operation of the ground-connected wall in the trenching section;

[0035] S6. After the trenching section is completed, the trenching operation is further carried out on the adjacent trench section. At this time, multiple sets of guide wall temporary support devices 3 are dismantled in turn and moved to the newly opened mud circulation equipment to lay out the trench section, and the above steps are repeated to continue the trenching operation of the ground-connected wall.

[0036] It should be noted that the parts of the utility model that are not disclosed in detail belong to the common knowledge in the field; in addition, although the above describes the illustrative specific implementation methods of the utility model to facilitate technical personnel in this technical field to understand the utility model, it should be clear that the utility model is not limited to the scope of the specific implementation methods. For ordinary technical personnel in this technical field, as long as various changes are within the spirit and scope of the utility model defined and determined by the attached claims, these changes are obvious, and all utility model creations using the concept of the utility model are protected.

Claims

1. A movable guide wall temporary support device, characterized in that: It comprises two temporary guide wall support rods (3-1), a plurality of temporary guide wall support frames (3-2) and a plurality of concrete blocks (3-3); wherein, The two temporary guide wall support rods (3-1) are two cylindrical rods of equal length, and the lengths of the two rods are greater than the width of the guide groove between the guide walls (1) on both sides, so as to be erected on the guide walls (1) on both sides; The temporary guide wall support frame (3-2) comprises a U-shaped frame body formed by a first vertical plate, a horizontal plate and a second vertical plate arranged vertically in sequence and connected, and a sleeve is horizontally fixed on the top surface of the first vertical plate and the second vertical plate respectively along the length direction of the vertical plate, and the inner diameter of the sleeve is larger than the outer diameter of the temporary guide wall support rod (3-1); a plurality of temporary guide wall support frames (3-2) are arranged in a straight line at equal intervals, and each temporary guide wall support frame (3-2) is movably sleeved on two temporary guide wall support rods (3-1) through two sleeves thereon; The concrete block (3-3) is a cubic block that can be arranged in a temporary guide wall support frame (3-2); a plurality of concrete blocks (3-3) are connected and arranged in a line and built into a plurality of temporary guide wall support frames (3-2), and the concrete blocks (3-3) at both ends partially extend outward of the temporary guide wall support frames (3-2) at both ends.

2. The movable guide wall temporary support device according to claim 1, characterized in that: The length of a single-side rod end of each guide wall temporary support rod (3-1) mounted on the top surface of the guide wall (1) is 0.3m to 0.5m.

3. The movable guide wall temporary support device according to claim 1, characterized in that: The length of the concrete block (3-3) is greater than the spacing between adjacent guide wall temporary support frames (3-2).

4. The movable guide wall temporary support device according to claim 1, characterized in that: The total length of the plurality of temporary guide wall support frames (3-2) arranged in a line at equal intervals is less than the width of the guide groove; the total length of the plurality of concrete blocks (3-3) arranged in a line is less than the width of the guide groove and greater than the total length of the plurality of temporary guide wall support frames (3-2) arranged in a line at equal intervals.

5. The movable guide wall temporary support device according to claim 1, characterized in that: Two handles (3-4) are symmetrically arranged on the top surface of each concrete block (3-3).

Citation Information

Patent Citations

  • Adjustable formwork device for supporting guide walls and guide wall supporting method

    CN112709219A

  • Guide wall supporting device for underground diaphragm wall engineering

    CN211285563U