Concrete pouring equipment
By setting up a twisted dragon in the conveying pipeline of the concrete pouring equipment and driving it by a driving motor, and adjusting the angle of the conveying pipeline with the electric push rod, the problem of poor stability of existing equipment is solved, and the stability and adjustability of concrete transportation at high places is achieved.
Patent Information
- Application Number
- CN202420338297.1
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-02-23
- Publication Date
- 2025-03-07
- Estimated Expiration
- 2034-02-23
AI Technical Summary
The existing concrete transportation equipment has poor stability and is easily affected by hardened concrete, resulting in unstable transportation.
A concrete pouring equipment is designed, including a mixing bin, drainage trough, conveying pipeline and twisted dragon. By setting a twisted dragon in the conveying pipeline and driving it by a driving motor, and adjusting the angle of the conveying pipeline with an electric push rod, the stability and adjustability of concrete transportation at high places can be achieved.
By installing conveying pipes on the drainage trough and setting up a twisted dragon, the stability of concrete transportation is ensured, and the hard pipes are not easily affected by hardened concrete, which improves the reliability and flexibility of transportation.
Smart Images

Figure CN222576158U_ABST
Abstract
Description
Technical Field
[0001] The utility model belongs to the technical field of construction engineering, and specifically relates to a concrete pouring device. Background Art
[0002] Concrete is the main material required by the construction industry. It is mainly made of cement, water, sand, gravel, and chemical admixtures and mineral admixtures when necessary to form an artificial stone in appropriate proportions. The pouring of concrete is mainly divided into mixing, transportation and material filling.
[0003] During the pouring process, it is often necessary to lift and transport the mixed materials. Currently, the equipment used to transport the mixed concrete to a high place for pouring is a pump body with a transport hose. The problem with the transport hose is that it has poor stability and is easily affected by hardened concrete. Utility Model Content
[0004] The utility model provides a concrete pouring device, the purpose of which is to increase the stability and adjustability of high-altitude concrete pouring and transportation.
[0005] The embodiments of the present invention are implemented by the following technical solutions:
[0006] A concrete pouring equipment comprises a mixing bin, the mixing bin is connected to a drainage trough, a delivery pipe is installed on the drainage trough, an auger is arranged in the delivery pipe, the auger is driven by a drive motor installed on the delivery pipe, an electric push rod is installed on the mixing bin, and an output end of the electric push rod is rotatably connected to the delivery pipe.
[0007] Furthermore, the drainage trough is tilted and has a certain height difference. A cover plate is rotatably connected to one end of the delivery pipe close to the drainage trough. The cover plate is detachably connected to the drainage trough. A sealing plate is fixedly installed on the bottom of one side of the cover plate.
[0008] Furthermore, the cover plate is detachably connected to the drainage groove by screws.
[0009] Furthermore, mounting plates are installed on both sides of the cover plate, and limiting strips are installed on both sides of the drainage groove. Screw holes arranged at equal intervals are installed on the limiting strips.
[0010] Furthermore, a ferrule is installed on the driving end of the electric push rod, and the ferrule is slidably connected to the outside of the mixing chamber and fixed by screws.
[0011] Furthermore, a pressure plate is installed on one end of the screw, and the pressure plate is located on the inner side of the ring.
[0012] Furthermore, the outer edge of the auger is in close contact with the interior of the conveying pipe.
[0013] The technical solution of the embodiment of the utility model has at least the following advantages and beneficial effects:
[0014] By installing the delivery pipe on the drainage trough and setting a screw in the delivery pipe to transport concrete at high altitudes, the stability of transportation can be ensured, and the hard pipe is not easily affected by hardened concrete. The angle adjustment of the delivery pipe is completed by the extension and retraction of the electric push rod. BRIEF DESCRIPTION OF THE DRAWINGS
[0015] In order to more clearly illustrate the technical solutions of the embodiments of the utility model, the drawings required for use in the embodiments will be briefly introduced below. It should be understood that the following drawings only show certain embodiments of the utility model and therefore should not be regarded as limiting the scope. For ordinary technicians in this field, other relevant drawings can be obtained based on these drawings without paying creative work.
[0016] Figure 1 This is a schematic diagram of the overall structure of Embodiment 1 of the present utility model;
[0017] Figure 2 for Figure 1 The cross-sectional view of the enlarged view at A in the middle;
[0018] Figure 3 This is a side view of the cover structure.
[0019] Icons: 1-mixing chamber, 2-drainage trough, 3-bracket, 4-cover plate, 41-sealing plate, 42-mounting plate, 5-conveying pipeline, 6-driving motor, 7-electric push rod, 8-ring, 9-auger, 10-limiting strip. DETAILED DESCRIPTION
[0020] In order to make the purpose, technical scheme and advantages of the embodiments of the utility model clearer, the technical scheme in the embodiments of the utility model will be clearly and completely described below in conjunction with the drawings in the embodiments of the utility model. Obviously, the described embodiments are part of the embodiments of the utility model, not all of the embodiments. Generally, the components of the embodiments of the utility model described and shown in the drawings here can be arranged and designed in various different configurations.
[0021] Therefore, the following detailed description of the embodiments of the present invention provided in the accompanying drawings is not intended to limit the scope of the present invention to be protected, but merely represents selected embodiments of the present invention. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0022] Example 1
[0023] A concrete pouring equipment includes a mixing bin 1, wherein the mixing bin 1 is fixedly connected to a drainage trough 2 through a bracket 3, and the drainage trough 2 is arranged below the discharge port of the mixing bin 1. The drainage trough 2 includes a shorter flat section and a longer inclined section, and a cover plate 4 is arranged on the inclined section of the drainage trough 2, and downward extensions are arranged on both sides of the cover plate 4, so that the cover plate 4 can be buckled on the outside of the inclined section of the drainage trough 2 through the extensions on both sides, and a blocking plate 41 is fixedly installed on the side other than the side where the cover plate 4 extends, and the height of the blocking plate 41 is consistent with the depth of the drainage trough 2. When the cover plate 4 is buckled on the inclined section of the drainage trough 2, the blocking plate 41 blocks the lower end of the drainage trough 2 below the cover plate 4, and cooperates with the cover plate 4 to concentrate the materials at the cover plate 4 for convenient transportation. A perforation is provided in the middle of the cover plate 4, a conveying pipe 5 is provided in the perforation, and the conveying pipe 5 is hinged to the ear plate on the cover plate 4, so that the conveying pipe can adjust the inclination angle relative to the cover plate; an auger 9 is installed inside the conveying pipe 5, and the outer edge of the auger 9 is close to the inside of the conveying pipe 5. The auger 9 is controlled to rotate by a drive motor 6 fixedly installed on the end of the conveying pipe 5 away from the drainage groove 2, thereby realizing the material transportation of the conveying pipe 5. An opening is provided on the side of the end where the drive motor 6 of the conveying pipe 5 is located for discharging, and the conveying pipe 5 can be used to complete the high-altitude transportation of concrete during the pouring process, and then the pipe is connected at the opening to complete the pouring.
[0024] A ferrule 8 is slidably connected to the outside of the mixing chamber 1, and an electric push rod 7 is installed on the ferrule 8. The driving end of the electric push rod 7 is rotatably connected to the ferrule 8, and the output end of the electric push rod 7 is rotatably connected to the conveying pipe 5. When the cover plate 4 is fixed, the extension and retraction of the electric push rod 7 can be controlled to adjust the inclination angle of the conveying pipe 5.
[0025] By installing the cover plate 4 at different positions of the inclined section of the drainage trough 2, the overall height of the delivery pipe 5 can be adjusted, which is convenient for coping with different delivery scenarios. After the position of the delivery pipe 5 is adjusted, it is locked and fixed by screws. Mounting plates 42 are fixed outward at the extensions on both sides of the cover plate 4. Limiting strips 10 arranged along the length direction of the drainage trough are provided on both sides of the drainage trough 2. Screw holes arranged at equal intervals are installed on the limiting strips 10. The cover plate 4 can be installed on the limiting strips 10 by screws. After the position of the cover plate 4 is adjusted, the telescopic stroke of the electric push rod 7 will be affected accordingly. The height of the driving end of the electric push rod 7 can be adjusted by sliding the ring 8 to the outside of the mixing chamber 1, thereby adjusting the telescopic stroke of the electric push rod 7.
[0026] A pressing plate is arranged inside the ferrule 8 , and the pressing plate is connected by screws. The screws are rotated to adjust the depth of the pressing plate, and the ferrule 8 can be tightened or loosened.
[0027] The above-mentioned embodiments only express the specific implementation methods of the present application, and the descriptions thereof are relatively specific and detailed, but they cannot be understood as limiting the protection scope of the present application. It should be pointed out that, for ordinary technicians in this field, several variations and improvements can be made without departing from the technical solution concept of the present application, and these all belong to the protection scope of the present application.
Claims
1. A concrete pouring equipment, characterized in that: The invention comprises a stirring chamber (1), wherein the stirring chamber (1) is connected to a drainage trough (2), a conveying pipe (5) is installed on the drainage trough (2), an auger (9) is arranged in the conveying pipe (5), and the auger (9) is driven by a driving motor (6) installed on the conveying pipe (5), and an electric push rod (7) is installed on the stirring chamber (1), and the output end of the electric push rod (7) is rotatably connected to the conveying pipe (5).
2. A concrete pouring equipment according to claim 1, characterized in that: The drainage trough (2) is arranged obliquely with a certain height difference; a cover plate (4) is rotatably connected to one end of the conveying pipe (5) close to the drainage trough (2); the cover plate (4) is detachably connected to the drainage trough (2); and a blocking plate (41) is fixedly installed at the bottom of one side of the cover plate (4).
3. A concrete pouring equipment according to claim 2, characterized in that: The cover plate (4) is detachably connected to the drainage groove (2) via screws.
4. A concrete pouring equipment according to claim 3, characterized in that: Mounting plates (42) are installed on both sides of the cover plate (4), and limiting strips (10) are installed on both sides of the drainage groove (2), and screw holes arranged at equal intervals are installed on the limiting strips (10).
5. A concrete pouring equipment according to claim 1, characterized in that: A ferrule (8) is mounted on the driving end of the electric push rod (7), and the ferrule (8) is slidably connected to the outside of the stirring chamber (1) and fixed by screws.
6. A concrete pouring equipment according to claim 5, characterized in that: A pressure plate is installed on one end of the screw, and the pressure plate is located on the inner side of the ring (8).
7. A concrete pouring equipment according to claim 1, characterized in that: The outer edge of the auger (9) is in close contact with the interior of the conveying pipe (5).