Concrete pole with stable structure
By designing the base and correcting steel bars buried in the surface soil layer, the stability and ease of correction of cement poles are achieved, solving the problems of tilt and collapse of existing cement poles, extending service life and improving the safety and reliability of the system.
Patent Information
- Application Number
- CN202420670246.9
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-04-03
- Publication Date
- 2025-03-07
- Estimated Expiration
- 2034-04-03
AI Technical Summary
Existing cement poles are prone to tilt after strong winds or long periods of time, and are difficult to correct. The soft soil after rain may cause the poles to collapse.
A cement pole with a stable structure was designed, with the base and correction steel bars at its lower end buried in the surface soil layer. When the cement pole is inclined, the correction steel bars are exposed by digging the surface soil layer, and the correction steel bars are pulled to penetrate deep into the ground to correct and stabilize the pole.
It effectively solves the problems of tilting and collapse of cement poles, extends the service life of the poles, and improves the safety and reliability of the power distribution system.
Smart Images

Figure CN222576291U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the field of cement poles, in particular to a cement pole with a stable structure. Background Art
[0002] Cement poles refer to power transmission equipment pillars made of cement concrete, which are used to support and fix transmission lines. Cement poles are usually used in power distribution systems in urban, rural or industrial areas, and are responsible for the bearing and stabilization of transmission lines.
[0003] Rural power grids have long suffered from weak grid structures and disrepair, which has led to frequent accidents such as pole collapse and wire breakage, and burning of distribution transformers. This has not only seriously affected the safety, economy and reliability of power supply, but also caused personal electric shock casualties. In order to provide more reliable, safe and high-quality electricity to the majority of rural power grid users, the construction of rural power distribution network transformation projects has received more and more attention.
[0004] The existing technology has the following deficiencies: Currently, most cement poles are only installed by digging holes and then burying the cement poles in the soil. When there is a strong wind or after a long time, the cement poles may tilt. When the cement poles tilt, it is difficult to correct the tilted cement poles. Only support rods can be installed on the sides of the cement poles, but the support rods are usually not inserted too deep into the soil layer. After raining, the soil will become soft, and the support rods will lose their supporting function, which may still cause the cement poles to collapse.
[0005] Therefore, it is necessary to invent a cement pole with a stable structure. Utility Model Content
[0006] To this end, the utility model provides a cement pole with a stable structure, in which the base and correction steel bars at the lower end of the cement support are buried in the surface soil layer. When the cement pole tilts, the surface soil layer is dug to expose the correction steel bars, and the correction steel bars on one side are pulled and made to continue to go deep into the ground to correct and alleviate the tilt of the cement pole, so as to solve the problem that the cement pole may tilt when there is a strong wind or after a long time, it is difficult to correct the tilted cement pole, and the soil will become soft after raining, which may cause the cement pole to collapse.
[0007] In order to achieve the above-mentioned purpose, the utility model provides the following technical solutions: a cement pole with a stable structure, comprising a cement support and a surface soil layer, a base is arranged at the lower end of the cement support, an opening is arranged around the side of the outer wall of the base, the base is completely inserted into the surface soil layer, a correction steel bar is embedded in the cement support at one end close to the base, the middle part of the correction steel bar is bent in a U shape, both ends of the correction steel bar penetrate downward through the cement support and are inserted and extended into the base, the two ends of the correction steel bar inserted into the base are respectively passed through two different openings in the outer wall of the base, and the two ends of the correction steel bar pass through the openings in the outer wall of the base and then are obliquely inserted into the surface soil layer.
[0008] Preferably, the plurality of correction steel bars are arranged in a surrounding manner in a base at the lower end of the cement pillar, and the lower ends of the plurality of correction steel bars are radially inserted into the surface soil layer. The correction steel bars can pull the base firmly fixed in the surface soil layer through their own stress.
[0009] Preferably, the outer walls at both ends of the correction steel bar are fixedly installed with fixing rings, steel pins are inserted into the fixing rings, end plates are fixedly installed at the upper ends of the steel pins, and the lower ends of the steel pins pass through the fixing rings and continue to be inserted deep into the surface soil layer.
[0010] Preferably, an inner core steel bar is embedded and installed in the cement pillar, the inner core steel bar is surrounded and arranged in the cement pillar, the inner core steel bar is arranged on the inner side of the correction steel bar, and the lower end of the inner core steel bar extends downward out of the cement pillar and penetrates the base and is inserted into the surface soil layer.
[0011] Preferably, support rings are installed inside the plurality of inner core steel bars that are arranged in a surrounding manner, and the plurality of support rings are vertically arranged inside the plurality of inner core steel bars at fixed intervals.
[0012] Preferably, support rings are installed inside the plurality of inner core steel bars that are arranged in a surrounding manner, and the plurality of support rings are vertically arranged inside the plurality of inner core steel bars at fixed intervals.
[0013] Preferably, in the initial stage of installation, a large soil pit is opened on the surface of the surface soil layer, and a small soil pit is opened in the center of the bottom surface of the inner wall of the large soil pit.
[0014] Preferably, at the initial stage of installation, the base is inserted into the large pit, the inner core steel bar extending from the lower end of the base is inserted into the small pit, the lower end of the correction steel bar is against the bottom surface of the inner wall of the large pit, and the steel pin is inserted into the bottom surface of the inner wall of the large pit.
[0015] The beneficial effect of the utility model is that the base and the correction steel bars at the lower end of the cement support are buried in the surface soil layer. When the cement pole tilts, the surface soil layer is dug to expose the correction steel bars, and the correction steel bars on one side are pulled and made to continue to go deep into the ground, so as to achieve the effect of correcting and alleviating the tilting state of the cement pole, avoid the collapse of the cement pole, and extend the service life of the cement pole. BRIEF DESCRIPTION OF THE DRAWINGS
[0016] Figure 1 A diagram showing a usage scenario of a cement pole with a stable structure provided by the utility model;
[0017] Figure 2 A structural schematic diagram of a cement pole with a stable structure provided by the utility model;
[0018] Figure 3 A schematic diagram of the inner structure of a cement support column of a cement pole with a stable structure provided by the utility model;
[0019] Figure 4 The utility model provides a schematic diagram of the installation of a cement pole with a stable structure.
[0020] In the figure: cement pillar 11, base 12, opening 13, inner core steel bar 14, support ring 15, iron wire 16, correction steel bar 17, fixing ring 18, steel pin 19, end plate 20, surface soil layer 21, large soil pit 22, small soil pit 23. DETAILED DESCRIPTION
[0021] The preferred embodiments of the present invention are described below in conjunction with the accompanying drawings. It should be understood that the preferred embodiments described herein are only used to illustrate and explain the present invention, and are not used to limit the present invention.
[0022] Example 1
[0023] like Figure 1 As shown, a cement pole with a stable structure in an embodiment of the first aspect of the utility model includes a cement support 11 and a surface soil layer 21, a base 12 is arranged at the lower end of the cement support 11, an opening 13 is arranged around the side of the outer wall of the base 12, the base 12 is completely inserted into the surface soil layer 21, and a correction steel bar 17 is embedded in the end of the cement support 11 close to the base 12, the middle part of the correction steel bar 17 is U-shaped, and both ends of the correction steel bar 17 penetrate downward through the cement support 11 and are inserted and extended into the base 12, and the two ends of the correction steel bar 17 inserted into the base 12 respectively pass through two different openings 13 on the outer wall of the base 12, and the two ends of the correction steel bar 17 pass through the openings 13 on the outer wall of the base 12 and then are obliquely inserted into the surface soil layer 21.
[0024] In the above embodiment, it should be noted that the base 12 and the cement pillar 11 are integrally cast by cement, and the structures in the cement pillar 11 and the base 12 are formed by first manufacturing the internal structure and then pouring and wrapping the cement during the manufacturing process. When the cement pole tilts, the correction steel bars 17 are exposed by digging up the surface soil layer, and the correction steel bars 17 on one side of the cement pillar 11 are pulled and continued to penetrate into the ground, so as to achieve the effect of correcting and alleviating the tilt of the cement pole, avoid the collapse of the cement pole, and extend the service life of the cement pole.
[0025] Example 2
[0026] like Figure 1 As shown, a cement pole with a stable structure includes all the contents of Example 1. In addition, the plurality of correction steel bars 17 are arranged in a surrounding manner in the base 12 at the lower end of the cement pillar 11, and the lower ends of the plurality of correction steel bars 17 are radially inserted into the surface soil layer 21. The correction steel bars 17 can pull the base 12 firmly fixed in the surface soil layer 21 through their own stress, and the outer walls of the two ends of the correction steel bars 17 are fixedly installed with fixing rings 18, and steel pins 19 are inserted into the fixing rings 18. The upper ends of the steel pins 19 are fixedly installed with end plates 20, and the lower ends of the steel pins 19 pass through the fixing rings 18 and continue to be inserted deep into the surface soil layer 21.
[0027] In the above embodiment, it should be noted that after the steel pin 19 is inserted into the fixing ring 18 and further inserted into the deep surface soil layer 21, the steel pin 19 is pushed to continuously extend into the deep surface soil layer 21 by knocking on the end plate 20 on one side, so as to achieve the effect of pulling the two ends of the correction steel bar 17 downward. At this time, the downward stress of the correction steel bar 17 continues to increase, so as to achieve the effect of pulling one side of the base 12 and improving the tilt condition of the cement pillar 11.
[0028] Example 3
[0029] like Figure 1 As shown, a cement pole with a stable structure includes all the contents of Example 2. In addition, an inner core steel bar 14 is embedded and installed in the cement pillar 11, and the inner core steel bar 14 is arranged in a surrounding manner in the cement pillar 11. The inner core steel bar 14 is arranged on the inner side of the correction steel bar 17. The lower end of the inner core steel bar 14 extends downward from the cement pillar 11 and penetrates the base 12 and is inserted into the surface soil layer 21. Support rings 15 are installed on the inner side of the several inner core steel bars 14 arranged in a surrounding manner. The several support rings 15 are vertically arranged on the inner side of the several inner core steel bars 14 at a fixed interval. Iron wires 16 are wrapped and fixed on the outer side of the several inner core steel bars 14, and the several iron wires 16 are vertically arranged on the outer wall of the several inner core steel bars 14 at a fixed interval.
[0030] In the above embodiment, it should be noted that the inner core steel bar 14 is the skeleton of the cement pillar 11, which has the function of supporting the cement pillar 11 and improving the strength of the cement pillar 11. The inner core steel bar 14 will be tightened during the production process to increase the stress of the inner core steel bar 14 itself, thereby enhancing the crack resistance and rigidity of the cement pillar 11. The support ring 15 has the function of fixing the inner side of the inner core steel bar 14, and the iron wire 16 has the function of improving the adhesion of cement during the production process.
[0031] Example 4
[0032] like Figure 1 As shown, a cement pole with a stable structure includes all the contents of Example 3. In addition, at the initial stage of installation, a large pit 22 is opened on the surface of the surface soil layer 21, and a small pit 23 is opened in the center of the bottom surface of the inner wall of the large pit 22. The base 12 is inserted into the large pit 22, and the inner core steel bar 14 extending from the lower end of the base 12 is inserted into the small pit 23. The lower end of the correction steel bar 17 is against the bottom surface of the inner wall of the large pit 22, and the steel pin 19 is inserted into the bottom surface of the inner wall of the large pit 22.
[0033] In the above embodiment, it should be noted that when installing the cement pole, a large pit 22 and a small pit 23 are first dug out on the surface of the surface soil layer 21, and the lower end of the inner core steel bar 14 is first inserted into the small pit 23, and the base 12 is inserted into the large pit 22, and then the small pit 23 is backfilled and the bottom surface of the inner wall of the large pit 22 is compacted, and then the steel pin 19 is inserted into the fixing ring 18 and continues to be inserted into the deep surface soil layer 21 of the bottom surface of the inner wall of the large pit 22 to tighten the correction steel bar 17, backfill the large pit 22 and compact the ground to complete the installation, and when the cement pole is tilted, the large pit 22 is dug to achieve the effect of exposing the end plate 20.
[0034] The use process of the utility model is as follows: when installing the cement pole, the technicians in this field first dig a large pit 22 and a small pit 23 on the surface of the surface soil layer 21, insert the lower end of the inner core steel bar 14 into the small pit 23, and insert the base 12 into the large pit 22, then backfill the small pit 23 and tamp the bottom of the inner wall of the large pit 22, then insert the steel pin 19 into the fixing ring 18 and continue to insert it into the deep surface soil layer 21 of the bottom of the inner wall of the large pit 22 to tighten the correction steel bar 17, backfill the large pit 22 and tamp the ground to complete the installation. When the cement pole is tilted, dig the large pit 22, knock on one side of the end plate 20, push the steel pin 19 on one side to continuously extend into the deep surface soil layer 21, so that the correction steel bar 17 on one side pulls the tilted side of the base 12 to improve the tilt condition of the cement pillar 11.
[0035] The above is only a preferred embodiment of the utility model. Any person skilled in the art may modify the utility model by using the above technical solution or modify it into an equivalent technical solution. Therefore, any simple modification or equivalent replacement based on the technical solution of the utility model shall fall within the scope of protection claimed by the utility model.
Claims
1. A cement pole with a stable structure, comprising a cement support (11) and a surface soil layer (21), wherein a base (12) is arranged at the lower end of the cement support (11), an opening (13) is arranged around the side of the outer wall of the base (12), and the base (12) is completely inserted into the surface soil layer (21), characterized in that: A correction steel bar (17) is embedded in one end of the cement pillar (11) close to the base (12); the middle portion of the correction steel bar (17) is bent in a U shape; both ends of the correction steel bar (17) penetrate downward through the cement pillar (11) and are inserted into and extend into the base (12); both ends of the correction steel bar (17) inserted into the base (12) respectively pass through two different openings (13) on the outer wall of the base (12); and both ends of the correction steel bar (17) pass through the openings (13) on the outer wall of the base (12) and then are obliquely inserted into the surface soil layer (21).
2. A cement pole with a stable structure according to claim 1, characterized in that: The plurality of correction steel bars (17) are arranged around the base (12) at the lower end of the cement pillar (11), and the lower ends of the plurality of correction steel bars (17) are radially inserted into the surface soil layer (21). The correction steel bars (17) can pull the base (12) through their own stress to be firmly fixed in the surface soil layer (21).
3. A structurally stable cement pole according to claim 2, characterized in that: The outer walls of both ends of the correction steel bar (17) are fixedly mounted with fixing rings (18), a steel pin (19) is inserted into the fixing ring (18), an end plate (20) is fixedly mounted on the upper end of the steel pin (19), and the lower end of the steel pin (19) passes through the fixing ring (18) and continues to be inserted deep into the surface soil layer (21).
4. A cement pole with a stable structure according to claim 3, characterized in that: An inner core steel bar (14) is embedded and installed in the cement pillar (11), the inner core steel bar (14) is arranged around the cement pillar (11), the inner core steel bar (14) is arranged on the inner side of the correction steel bar (17), and the lower end of the inner core steel bar (14) extends downward out of the cement pillar (11) and penetrates through the base (12) and is inserted into the surface soil layer (21).
5. A structurally stable cement pole according to claim 4, characterized in that: A support ring (15) is installed inside the plurality of inner core steel bars (14) arranged in a surrounding manner, and the plurality of support rings (15) are vertically arranged inside the plurality of inner core steel bars (14) at a fixed interval.
6. A structurally stable cement pole according to claim 5, characterized in that: Iron wires (16) are wound and fixed on the outer sides of the plurality of inner core steel bars (14), and the plurality of iron wires (16) are vertically arranged at fixed intervals on the outer walls of the plurality of inner core steel bars (14).
7. A structurally stable cement pole according to claim 4, characterized in that: In the initial stage of installation, a large soil pit (22) is opened on the surface of the surface soil layer (21), and a small soil pit (23) is opened in the center of the bottom surface of the inner wall of the large soil pit (22).
8. A structurally stable cement pole according to claim 7, characterized in that: In the initial stage of installation, the base (12) is inserted into the large earth pit (22), the inner core steel bar (14) extending from the lower end of the base (12) is inserted into the small earth pit (23), the lower end of the correction steel bar (17) is against the bottom surface of the inner wall of the large earth pit (22), and the steel pin (19) is inserted into the bottom surface of the inner wall of the large earth pit (22).