Super high-rise steel structure cantilever conversion construction structure capable of being quickly connected

By designing a cantilever conversion construction structure of ultra-high-rise steel structures that can be quickly connected, using clamping connection methods and adjustment components, the problems of complex connections of cantilever beams in the existing technology are solved, and the construction efficiency and safety of fast and safe construction results are achieved.

CN222614801UActive Publication Date: 2025-03-14CHINA CONSTR FIRST GRP THE SECOND CONSTR +1
View PDF 2 Cites 0 Cited by

Patent Information

Application Number
CN202421231217.9
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-05-31
Publication Date
2025-03-14
Estimated Expiration
2034-05-31

AI Technical Summary

Technical Problem

In the prior art, the connection method of cantilever beams is complicated, and workers need to carry a variety of pins and locking pins, which leads to inconvenience in high altitude operations and low construction efficiency and safety.

Method used

A super high-rise steel structure cantilever conversion construction structure that can be quickly connected is designed, and the first connecting block and the second connecting block are clamped and connected to the upper and lower pull rods. By adjusting the length of the pull rod, the connection process between the cantilever beam and the building body is simplified.

Benefits of technology

The rapid installation of the pull-up rod and the pull-up rod is realized, reducing the difficulty of workers' aerial work, and improving construction efficiency and safety.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222614801U_ABST
    Figure CN222614801U_ABST
Patent Text Reader

Abstract

The utility model discloses a super high-rise steel structure overhanging conversion construction structure capable of being quickly connected, which comprises an overhanging beam, a first connecting block, a second connecting block, a first connecting rod and a second connecting rod, and is characterized in that one end of the overhanging beam is fixed on a super high-rise building body; the second connecting block is fixedly arranged on the super high-rise building body above the cantilever beam; the upper end of the upper pull rod is clamped with the second connecting block, the lower end of the lower pull rod is clamped with the first connecting block, and the upper end of the lower pull rod is connected with the lower end of the upper pull rod; the adjusting assembly is arranged between the upper pull rod and the lower pull rod, a first hook groove is formed in the right side wall of the first connecting block in an inwards-inclined mode, a first connecting column is arranged at one end of the lower pull rod and clamped in the first hook groove, a second hook groove is formed in the top of the second connecting block in an inwards-inclined mode, and a second connecting column is arranged at one end of the upper pull rod and clamped in the second hook groove. And the second connecting column is clamped in the second hook groove. According to the utility model, the upper pull rod and the lower pull rod can be quickly mounted between the cantilever beam and the super high-rise building body.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to a super high-rise steel structure cantilever conversion structure, in particular to a super high-rise steel structure cantilever conversion construction structure which can be quickly connected. Background Art

[0002] In order to achieve the effect of superimposed building facade blocks, the upper structure needs to be cantilevered. For example, if the upper structure requires a large space due to the building function setting, the lower structure columns cannot be raised to the upper part, and the cantilever beam must be used as a conversion component for the outer side columns of the upper protruding part.

[0003] For example, Chinese patent CN214884337U discloses a high-rise large-span cantilever steel structure, which includes a cantilever beam for connecting to the exterior wall of a building, a sleeve assembly is arranged between the cantilever beam and the exterior wall of the building, the sleeve assembly includes a base plate, a sleeve and a connecting piece, the base plate is arranged on the side of the exterior wall of the building away from the cantilever beam, the sleeve is fixed on the side of the base plate facing the exterior wall of the building, the sleeve is penetrated into the exterior wall of the building, the connecting piece is penetrated in the sleeve for fixing the cantilever beam, and a pull rod assembly for suspending the cantilever beam is arranged between the top side of the cantilever beam and the exterior wall of the building.

[0004] Chinese patent CN214884337U discloses a rotatable cantilever structure and a construction method for a structural height difference portion. In the structure, a structural plate has a first support portion and a second support portion; a U-shaped ring is invertedly fixed to the second support portion; a cantilever beam passes through the U-shaped ring and is fixed between the pair of second fixing portions via a screw member; a filler is filled between the cantilever beam and the two sides of the U-shaped ring with an interference fit; one end of a lower rigid inclined rod is rotatably connected to the connecting member, and the other end is provided with a first thread; one end of an adjustable rigid sleeve is connected to the lower rigid inclined rod via the first thread; one end of an upper rigid inclined rod is provided with a second thread connected to the other end of the adjustable rigid sleeve; a wall-mounted support is fixed to the wall, the wall support is higher than the structural plate, and the other end of the upper rigid inclined rod is connected to the wall support.

[0005] Chinese patent CN214462397U discloses a cantilever bracket for construction, including a cantilever beam, a tie rod and an embedded part set in the wall. The web of the cantilever beam I-beam is provided with weight-reducing and reinforcing holes arranged at intervals, and the two ends of the tie rod are respectively threadedly connected with hooks and pull rings; the embedded sleeve provided in the embedded part is a metal sleeve, which is embedded in the wall, and one end of the embedded sleeve is provided with a fixing part connecting part, and the connecting fixing part is provided with a fixing bolt and a fixing ear seat. The cantilever beam of the cantilever bracket is provided with a weight-reducing and reinforcing hole, and the dead weight can be reduced; one end of the cantilever bracket is a fixing ring, and the other end is a hook, which is easy to use, and the pull ring, the hook and the tie rod are connected by threaded matching, and the required length of the tie rod can be adjusted, which is convenient to use.

[0006] In the prior art, cantilever beams are usually used as supports for upper component columns. When working, the cantilever beam is fixed on the outer wall of the building, and a pull rod is connected between the cantilever beam and the building to improve the support capacity of the cantilever beam. Pull rings are provided at both ends of the traditional pull rod, and two connecting plates connected to the pull rings are fixed on the top of the cantilever beam and the building. The connecting plates are provided with connecting holes. When connected, the pull rings at both ends of the pull rod are respectively located between the corresponding two connecting plates, and the connecting plates and the pull rings are connected in series through the latch. After the latch is inserted into the connecting hole, a lock pin is required to lock one end of the latch to prevent the latch from falling off the connecting hole. This connection method has many working steps, which causes certain inconveniences to the installation of the pull rod. At the same time, the operator needs to carry a certain number of latches and lock pins, which further increases the inconvenience of high-altitude operations. Utility Model Content

[0007] The utility model aims to provide a cantilever conversion construction structure of a super-high-rise steel structure that can be quickly connected, so as to solve the problems raised in the above-mentioned background technology.

[0008] To achieve the above-mentioned purpose, the utility model provides a cantilever conversion construction structure of a super-high-rise steel structure that can be quickly connected, including: a cantilever beam, one end of which is fixed on the super-high-rise building body, and the other end extends to the outside of the super-high-rise building body, and a first connecting block is fixedly arranged on the top of the cantilever beam; a second connecting block, which is fixedly arranged on the super-high-rise building body above the cantilever beam; an upper pull rod, an upper end of which is clamped and connected with the second connecting block, and a lower pull rod, a lower end of which is clamped and connected with the first connecting block, and the upper end of the lower pull rod is connected with the lower end of the upper pull rod; an adjusting component, which is arranged between the upper pull rod and the lower pull rod, and is used to adjust the length between the upper pull rod and the lower pull rod; wherein, a first hook groove is opened on the right side wall of the first connecting block, a first connecting column is arranged at one end of the lower pull rod, the first connecting column is clamped in the first hook groove, a second hook groove is opened on the top of the second connecting block, and a second connecting column is arranged at one end of the upper pull rod, and the second connecting column is clamped in the second hook groove.

[0009] In a preferred embodiment, a first connecting head is fixedly provided at the lower end of the lower pull rod, the first connecting head is a gate-shaped structure, a first connecting column is fixedly connected inside the first connecting head, and the first connecting column is perpendicular to the two side walls of the first connecting head.

[0010] In a preferred embodiment, a second connector is fixedly provided at the upper end of the upper pull rod, the second connector is a U-shaped structure, a second connector column is fixedly connected inside the second connector, and the second connector column is perpendicular to the two side walls of the second connector.

[0011] In a preferred embodiment, the groove bottom of the first hook groove is an arc surface that fits with the outer side wall of the first connecting column, and the groove bottom of the second hook groove is an arc surface that fits with the outer side wall of the second connecting column.

[0012] In a preferred embodiment, a first limit block is fixed on the groove wall of the first hook groove, a transition groove for the first connecting column to pass through the first limit block is opened on the side wall of the first connecting column, a second limit block is fixed on the groove wall of the second hook groove, and a second transition groove for the second connecting column to pass through the second limit block is opened on the side wall of the second connecting column.

[0013] In a preferred embodiment, the adjustment assembly includes two internal threaded sleeves with opposite rotation directions, and the two internal threaded sleeves are respectively mounted on the upper end of the lower pull rod and the lower end of the upper pull rod. The upper end of the lower pull rod and the lower end of the upper pull rod are both provided with external threads that threadably match the internal threaded sleeves. The two internal threaded sleeves are connected by multiple connecting ribs, and all the connecting ribs are evenly spaced and distributed on the circumference of the outer wall of the internal threaded sleeve.

[0014] Compared with the prior art, the beneficial effect of the utility model is as follows: the utility model enables the lower pull rod to be quickly connected to the cantilever beam through the cooperation between the first connecting column and the first connecting block, and realizes the rapid connection between the upper pull rod and the super high-rise building through the cooperation between the second connecting column and the second connecting block, thereby achieving the purpose of conveniently and quickly installing the upper pull rod and the lower pull rod between the cantilever beam and the super high-rise building, further improving the construction efficiency and construction safety. BRIEF DESCRIPTION OF THE DRAWINGS

[0015] Figure 1 It is a structural schematic diagram of the utility model;

[0016] Figure 2 It is a structural schematic diagram of the first connecting head and the first connecting column of the utility model;

[0017] Figure 3 For the utility model Figure 1 A schematic diagram of the local enlarged structure at point A in the middle;

[0018] Figure 4 For the utility model Figure 1 Schematic diagram of the local enlarged structure at point B in the middle.

[0019] Description of reference numerals:

[0020] 1-cantilever beam, 10-super high-rise building, 11-first connecting block, 12-second connecting block, 111-first hook groove, 21-second connecting column, 22-first connecting head, 23-second limiting block, 2-upper pull rod, 121-second hook groove, 31-first connecting column, 32-second connecting head, 33-first limiting block, 3-lower pull rod, 4-inner threaded sleeve, 5-connecting rib, 6-second embedded part, 7-first embedded part. DETAILED DESCRIPTION

[0021] The technical solutions in the embodiments of the utility model are described clearly and completely below. The embodiments of the utility model and all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the utility model.

[0022] like Figures 1 to 4 As shown, the cantilever conversion construction structure of a super-high-rise steel structure that can be quickly connected in a preferred embodiment of the utility model includes: a cantilever beam 1, a first connecting block 11, a second connecting block 12, an upper tie rod 2, a lower tie rod 3 and an adjustment assembly, wherein one end of the cantilever beam 1 is fixed on the super-high-rise building body 10, and the other end extends to the outside of the super-high-rise building body 10. The first connecting block 11 is fixedly arranged on the top of the cantilever beam 1, and the second connecting block 12 is fixedly arranged on the super-high-rise building body 10 above the cantilever beam 1. The upper end of the upper tie rod 2 is connected by clamping with the second connecting block 12, the lower end of the lower tie rod 3 is connected by clamping with the first connecting block 11, and the upper end of the lower tie rod 3 is connected with the lower end of the upper tie rod 2. The adjustment component is arranged between the upper pull rod 2 and the lower pull rod 3, and the adjustment component includes two internal thread sleeves 4 with opposite rotation directions, and the two internal thread sleeves 4 are respectively mounted on the upper end of the lower pull rod 3 and the lower end of the upper pull rod 2, and the upper end of the lower pull rod 3 and the lower end of the upper pull rod 2 are both provided with external threads that are threadedly matched with the internal thread sleeves 4, and the two internal thread sleeves 4 are connected by a plurality of connecting ribs 5, and all the connecting ribs 5 are evenly spaced and distributed on the circumference of the outer wall of the internal thread sleeve 4. The length between the upper pull rod 2 and the lower pull rod 3 is adjusted by setting the adjustment component. During use, the adjustment component can also be a threaded tube, and the inner side wall of the threaded tube is provided with two sections of internal threads with opposite rotation directions, and the internal threads are threadedly matched with the external threads on the lower pull rod 3 and the upper pull rod 2. When in use, the internal threaded sleeve 4 is rotated simultaneously through the connecting rib 5. Since the internal threads of the two internal threaded sleeves 4 are arranged in opposite directions, when the internal threaded sleeve 4 rotates, the adjacent ends of the upper pull rod 2 and the lower pull rod 3 are simultaneously moved closer or farther away, thereby achieving the purpose of adjusting the length between the upper pull rod 2 and the lower pull rod 3. Among them, a first hook groove 111 is provided on the right side wall of the first connecting block 11, and a first connecting column 31 is provided at one end of the lower pull rod 3, and the first connecting column 31 is clamped in the first hook groove 111. The top of the second connecting block 12 is provided with a second hook groove 121, which is tilted inwards. A second connecting column 21 is provided at one end of the upper pull rod 2, and the second connecting column 21 is clamped in the second hook groove 121.

[0023] The cantilever beam 1 of this embodiment is an I-beam used in traditional construction. The cantilever beam 1 is fixed to the super high-rise building 10 through a fixing plate. The fixing plate is provided with mounting holes communicating with each other at the front and rear sides of the cantilever beam 1. A first embedded part 7 is embedded in the super high-rise building. The fixed end of the first embedded part 7 passes through the mounting hole and is fixed by a nut 8 to complete the installation of the cantilever beam 1. The cantilever beam 1 is vertically arranged with the super high-rise building 10. The second connecting block 12 is fixed to the super high-rise building 10 directly above the cantilever beam 1 through the second embedded part 6.

[0024] Furthermore, the lower end of the lower pull rod 3 is fixedly provided with a first connector 22, which is a gate-shaped structure, and a first connecting column 31 is fixedly connected inside the first connecting column 22, and the first connecting column 31 is perpendicular to the two side walls of the first connecting column 22. During installation, the lower pull rod 3 is hooked in the first hook groove 111 of the first connecting block 11 through the first connecting column 31, completing the connection between the lower pull rod 3 and the cantilever beam 1. The first connecting head 22 and the first connecting column 31 form a "mouth"-shaped structure as a whole, and the two are integrally formed.

[0025] Furthermore, a second connector 32 is fixedly provided at the upper end of the upper rod 2. The second connector 32 is a U-shaped structure. A second connecting column 21 is fixedly connected inside the second connecting column 32. The second connecting column 21 is perpendicular to the two side walls of the second connecting column 32. During installation, the upper rod 2 is hooked in the second hook groove 121 through the second connecting column 21 to achieve a quick connection between the upper rod 2 and the second connecting block 12. The second connecting column 21 and the second connector 32 form a "mouth"-shaped structure as a whole, and the two are integrally formed. The first hook groove 111 is tilted and set to be lower on the right and higher on the left, and the second hook groove 121 is tilted and set to be upper left, lower right. During installation, the first connecting column enters the first hook groove from the right side of the first connecting block, and the second connecting column enters the second hook groove from the top of the second connecting block.

[0026] Furthermore, the bottom of the first hook groove 111 is an arc surface that fits the outer wall of the first connecting column 31, and the bottom of the second hook groove 121 is an arc surface that fits the outer wall of the second connecting column 21, so as to increase the force-bearing area between the two. In actual use, the first connecting column 31 is hooked into the first hook groove, so as to realize the quick connection between the lower tie rod 3 and the cantilever beam 1, and the second connecting column 21 is hooked into the second hook groove 121, so as to realize the quick connection between the upper tie rod 2 and the super high-rise building, so as to conveniently and quickly complete the installation of the lower tie rod 5 and the upper tie rod 2, and reduce the construction difficulty of workers working at high altitude.

[0027] Example 2

[0028] In this embodiment, a first limit block 33 is fixed on the groove wall of the first hook groove 111, and a transition groove for the first connecting column 31 to pass through the first limit block 33 is opened on the side wall of the first connecting column 31; a second limit block 23 is fixed on the groove wall of the second hook groove 121, and a second transition groove for the second connecting column 21 to pass through the second limit block 23 is opened on the side wall of the second connecting column 21.

[0029] When the first connecting post 31 enters the first hook groove 111 and the second connecting post 21 enters the second hook groove 121, when the upper pull rod 2 is connected to the lower pull rod 3 and in the subsequent use process, in order to prevent the first connecting post 31 from escaping from the first hook groove 111, a first limit block 33 is fixed in the first hook groove 111, and the distance between the first limit block 33 and the other side of the first hook groove 111 is smaller than the diameter of the first connecting post 31. In this way, the first connecting post 31 can be prevented from escaping from the first hook groove 111. When the first connecting post 31 needs to enter the first hook groove, the lower pull rod 3 is swung so that the first transition groove on the first connecting post 31 is opposite to the first limit block 33, and the first limit block 33 passes through the first transition groove, so that the first connecting post 31 enters the first hook groove 111. After the lower pull rod 3 is connected to the upper pull rod 2, the first transition groove and the first limit block 33 are staggered, and the first connecting post 31 cannot escaping from the first hook groove. The function of the second limiting block 23 is similar to that of the first limiting block 33 , which is to prevent the second connecting column 21 from being separated from the second hook groove 121 .

[0030] Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that changes, modifications, substitutions and variations may be made to the embodiments without departing from the principles and spirit of the present invention, and that the scope of the present invention is defined by the appended claims and their equivalents.

Claims

1. A super high-rise steel structure cantilever conversion construction structure that can be quickly connected, characterized by: include: A cantilever beam (1), one end of which is fixed to the super high-rise building (10) and the other end of which extends to the outside of the super high-rise building (10), wherein a first connecting block (11) is fixedly provided on the top of the cantilever beam (1); A second connecting block (12) fixedly disposed on the super high-rise building body (10) above the cantilever beam (1); An upper pull rod (2), the upper end of which is snap-connected to the second connecting block (12); A lower pull rod (3), the lower end of which is snap-connected to the first connecting block (11), and the upper end of the lower pull rod (3) is connected to the lower end of the upper pull rod (2); An adjustment component, which is arranged between the upper pull rod (2) and the lower pull rod (3) and is used to adjust the length between the upper pull rod (2) and the lower pull rod (3); A first hook groove (111) is provided on the right side wall of the first connecting block (11) and is inclined inwardly, a first connecting column (31) is provided at one end of the lower pull rod (3), and the first connecting column (31) is engaged in the first hook groove (111), a second hook groove (121) is provided on the top of the second connecting block (12) and is inclined inwardly, and a second connecting column (21) is provided at one end of the upper pull rod (2), and the second connecting column (21) is engaged in the second hook groove (121).

2. The super high-rise steel structure cantilever conversion construction structure capable of rapid connection according to claim 1 is characterized in that: A first connecting head (22) is fixedly provided at the lower end of the lower pull rod (3); the first connecting head (22) is a gate-shaped structure; a first connecting column (31) is fixedly connected inside the first connecting head (22); the first connecting column (31) is perpendicular to two side walls of the first connecting head (22).

3. The super high-rise steel structure cantilever conversion construction structure capable of rapid connection according to claim 1 is characterized in that: A second connecting head (32) is fixedly provided at the upper end of the upper pull rod (2); the second connecting head (32) is a U-shaped structure; a second connecting column (21) is fixedly connected inside the second connecting head (32); the second connecting column (21) is perpendicular to two side walls of the second connecting head (32).

4. The super high-rise steel structure cantilever conversion construction structure capable of rapid connection according to claim 2 or 3, characterized in that: The groove bottom of the first hook groove (111) is an arcuate surface that fits the outer wall of the first connecting column (31), and the groove bottom of the second hook groove (121) is an arcuate surface that fits the outer wall of the second connecting column (21).

5. The super high-rise steel structure cantilever conversion construction structure capable of rapid connection according to claim 4 is characterized in that: A first limiting block (33) is fixed on the groove wall of the first hook groove (111), a transition groove for the first connecting column (31) to pass through the first limiting block (33) is provided on the side wall of the first connecting column (31), a second limiting block (23) is fixed on the groove wall of the second hook groove (121), and a second transition groove for the second connecting column (21) to pass through the second limiting block (23) is provided on the side wall of the second connecting column (21).

6. The super high-rise steel structure cantilever conversion construction structure capable of rapid connection according to claim 1 is characterized in that: The adjustment assembly comprises two internally threaded sleeves (4) with opposite rotation directions, the two internally threaded sleeves (4) are respectively sleeved on the upper end of the lower pull rod (3) and the lower end of the upper pull rod (2), the upper end of the lower pull rod (3) and the lower end of the upper pull rod (2) are both provided with external threads that are threadedly matched with the internally threaded sleeves (4), the two internally threaded sleeves (4) are connected by a plurality of connecting ribs (5), and all the connecting ribs (5) are evenly spaced and distributed on the circumference of the outer wall of the internally threaded sleeves (4).

Citation Information

Patent Citations

  • Cantilever support for building construction

    CN214462397U

  • High-rise large-span cantilever steel structure

    CN214884337U