Anti-seepage and leaking stoppage structure for mud underground engineering
By using bentonite mud paste in underground projects and adding carbon fiber mesh layers, the problems of failure to meet standards, leakage, freezing and swelling of water in the existing technology have been solved, and efficient and long-term waterproofing effect has been achieved.
Patent Information
- Application Number
- CN202420882279.X
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-04-25
- Publication Date
- 2025-03-18
- Estimated Expiration
- 2034-04-25
AI Technical Summary
The existing underground engineering waterproofing technology has problems such as leakage caused by failure to meet the standards of the base layer, short life of building materials, difficulty in maintenance in the later stage, freezing deformation, and non-woven layer isolation.
A mud paste made of bentonite and water is used as an anti-seepage material, and a carbon fiber mesh layer is laid on it to replace the non-woven layer to improve waterproof performance and durability.
Through the use of bentonite mud paste, the non-aging and anti-seepage effect of underground projects is achieved, the problems of leakage, freezing and water splicing are solved, and later maintenance is simplified.
Smart Images

Figure CN222632357U_ABST
Abstract
Description
Technical Field
[0001] The utility model discloses a mud paste underground engineering anti-seepage and leakage plugging structure, which relates to the technical field of underground engineering waterproof structures, and in particular to a structure using mud paste to carry out anti-seepage and leakage plugging for basements, tunnels, garages, artificial rivers and lakes. Background Art
[0002] Underground engineering waterproofing refers to underground waterproofing projects for industrial and civil buildings. Underground waterproofing projects are a systematic project, which involves various aspects of building management such as engineering waterproofing materials, waterproofing node design, and waterproofing construction. Its purpose is to ensure that the building is not eroded by water, the internal space is not harmed, and to improve the use function and life of the building. With the development of the times and the advancement of science and technology, underground projects have gradually increased. For this reason, underground waterproofing is an important project of underground engineering. The quality of its waterproofing technology will directly affect the use function and service life. However, in the past ten years, according to the comparison of unit projects, the leakage of basements and underground garage roof projects can reach more than 60% to varying degrees. The main reason is that the current waterproofing materials are not suitable and unreasonable for building structures. Due to the leakage, the corrosion of underground engineering structures is also huge.
[0003] There are many kinds of waterproof materials for underground projects, which can be divided into two types of roll materials according to their main raw materials: 1. Asphalt waterproof materials. Asphalt felt, paper-based asphalt felt, etc. are made with natural asphalt, petroleum asphalt and coal tar as the main raw materials. 2. Bentonite waterproof blankets can be divided into needle-punched sodium-based bentonite waterproof blankets, needle-punched film-coated sodium-based bentonite waterproof blankets and adhesive sodium-based bentonite waterproof blankets according to the production process.
[0004] Bentonite waterproof blanket is a geosynthetic material specially used for anti-seepage in artificial lake waterscape, landfill, underground garage, roof garden, pool, oil depot and chemical storage yard. It is composed of highly expansive sodium-based bentonite filled between special composite geotextile and non-woven fabric. The bentonite anti-seepage mat made by needle punching can form many small fiber spaces, so that the bentonite particles cannot flow in one direction. When encountering water, a uniform and high-density colloidal waterproof layer is formed in the mat, which effectively prevents water leakage.
[0005] The mineralogical name of bentonite is montmorillonite. Natural bentonite is mainly divided into two categories according to its chemical composition: sodium-based and calcium-based. Bentonite has the characteristic of swelling when it comes into contact with water. Generally, when bentonite swells, its swelling is about 1-2.5 times, and when it swells, it swells more than 2-15 times. Locking the bentonite between two layers of geosynthetics plays a role of protection and reinforcement, so that the bentonite blanket has a certain overall shear strength. Most of its underground membrane waterproofing technology applications are to set a membrane waterproofing layer on the water surface of buildings and structures, and add a protective layer outside the waterproofing layer. Due to the structure of the membrane itself, it cannot meet the waterproofing requirements of existing buildings, resulting in the following problems in the existing waterproofing construction technology:
[0006] 1. Because the underground engineering structural base does not meet the technical requirements of the waterproofing membrane, it is estimated that the waterproofing purpose cannot be achieved, causing most of the underground waterproofing membranes to be separated from the base and hollow, resulting in engineering leakage;
[0007] 2. The quality life of the waterproofing material itself (15-20 years) is too different from the main body life (generally 100 years);
[0008] 3. Due to the phenomenon of underground waterproof engineering membrane and base layer being separated from the base layer, water leakage occurs in the later maintenance and plugging, which causes great difficulties;
[0009] 4. The coiled material is not suitable for frost heave in cold areas within a certain range of the earth. Because the coiled material is integrated with the frozen soil after freezing in the frozen soil range, the coiled material loses its elongation index. When the frozen soil produces frost heave deformation, the coiled material will inevitably break and leak.
[0010] 5. Currently, bentonite blanket is used for anti-seepage projects. Bentonite blanket is a bentonite anti-seepage roll made of high-swelling sodium-based bentonite filled between special composite geotextile and non-woven fabric by needle punching. Its disadvantage is that the non-woven fabric isolates the bentonite from the structural base layer. The non-woven fabric itself is a permeable material, so it forms a seepage and water-penetrating layer, which leads to leakage.
[0011] In view of the problems existing in the above-mentioned prior art, it is very necessary to study and design a new type of mud paste underground engineering anti-seepage and leakage plugging structure to overcome the problems existing in the prior art. Summary of the invention
[0012] According to the above-mentioned technical problems that the underground engineering base structure proposed in the prior art cannot meet the requirements of waterproof roll materials, resulting in leakage, short service life of building materials, difficulty in later maintenance, freezing expansion, deformation and fracture of roll materials in cold areas, and water leakage caused by the separation of the bearing layer by the non-woven fabric layer, a mud paste underground engineering anti-seepage and plugging structure is provided. The utility model mainly utilizes the performance of bentonite itself to completely solve the leakage problem of underground engineering that never ages, and at the same time uses a carbon fiber mesh layer to replace the non-woven fabric layer to prevent the problem of water leakage.
[0013] The technical means adopted by the utility model are as follows:
[0014] A mud paste underground engineering anti-seepage and plugging structure includes: an independent foundation anti-seepage structure, a cap foundation anti-seepage structure, a pool structure anti-seepage structure, a raft / beam anti-seepage structure, a raft / beam / wall anti-seepage structure, a civil air defense basement roof engineering anti-seepage structure, a stream / stream / river anti-seepage structure, a raft / wall plugging structure and a cap / raft plugging structure; the mud paste is a mud paste-like substance formed by mixing bentonite and water.
[0015] Furthermore, the independent foundation anti-seepage structure includes: a basement reinforced concrete independent foundation raft slab mud plaster anti-seepage structure without coiled materials and a basement reinforced concrete independent foundation raft slab mud plaster anti-seepage structure with coiled materials.
[0016] Furthermore, the overall structure of the reinforced concrete independent foundation raft slab mud plaster anti-seepage structure of the basement without coils is a concave structure, which is divided into: a central concave surface structure A, a side slope surface structure A and a top surface structure A;
[0017] Furthermore, the structure of the central concave surface is, from bottom to top, the original soil layer, reinforced concrete structure cushion layer, mud board anti-seepage bearing layer, carbon fiber grid layer, 30 thick cement mortar protective layer, plain concrete cushion layer and reinforced concrete independent foundation;
[0018] Furthermore, the side slope surface structure is from bottom to top: original soil layer, 30mm thick cement mortar protective layer, 50mm thick mud paste anti-seepage layer, carbon fiber mesh layer, 30mm thick cement mortar protective layer, plain concrete cushion layer and reinforced concrete independent foundation;
[0019] Furthermore, the top surface structure from bottom to top is: original soil layer, 100mm thick sub-clay rolling layer, 50mm thick mud paste anti-seepage layer, carbon fiber grid layer, 30mm thick cement mortar protective layer, plain concrete cushion layer and reinforced concrete raft slab.
[0020] Furthermore, the mud slab anti-seepage bearing layer is formed by paving a 50mm thick mud plaster anti-seepage layer and a 50mm thick natural stone slab at intervals.
[0021] Furthermore, the natural stone slab is made of granite, has a length of 150 mm, a width of 150 mm, and a height of 50 mm, and the spacing between every two pads is designed as required.
[0022] Furthermore, the overall structure of the reinforced concrete independent foundation raft slab mud plaster anti-seepage structure of the coiled basement is a concave structure, which is divided into: a central concave surface structure B, a side slope surface structure B and a top surface structure B;
[0023] Furthermore, the central concave surface structure B is composed of the original soil layer, plain concrete cushion layer, coiled material anti-seepage layer, 30 thick cement mortar protective layer and reinforced concrete independent foundation from bottom to top;
[0024] Furthermore, the side slope surface structure B is composed of the original soil layer, plain concrete cushion layer, coiled material anti-seepage layer, 30mm thick cement mortar protective layer and reinforced concrete independent foundation from bottom to top;
[0025] Furthermore, the top surface structure B is composed from bottom to top: original soil layer, 100mm thick sub-clay rolling layer, 50mm thick mud paste anti-seepage layer, carbon fiber mesh layer, 30mm thick cement mortar protective layer, plain concrete cushion layer and reinforced concrete raft slab.
[0026] Furthermore, the roll material anti-seepage layer is embedded more than 200 mm inside the 50-thick mud paste anti-seepage layer.
[0027] Furthermore, the anti-seepage structure of the pedestal foundation includes: a basement reinforced concrete pedestal, a raft slab mud plaster anti-seepage structure and a basement exterior wall reinforced concrete pedestal / raft slab / exterior wall mud plaster anti-seepage structure.
[0028] Furthermore, the basement reinforced concrete cap and raft slab mud paste anti-seepage structure are overall concave structures, which are divided into: central concave surface structure C, side slope surface structure C and top surface structure C;
[0029] Furthermore, the structure C of the central concave surface is composed of the original soil layer, 100mm thick sub-clay rolling layer, 50mm thick mud paste anti-seepage layer, carbon fiber grid layer, 30mm thick cement mortar protective layer, plain concrete cushion layer and reinforced concrete cap from bottom to top;
[0030] Furthermore, the side slope surface structure C is composed from bottom to top: original soil layer, 30mm thick cement mortar protective layer, 50mm thick mud paste anti-seepage layer, carbon fiber mesh layer, 30mm thick cement mortar protective layer, reinforced concrete cap;
[0031] Furthermore, the top surface structure C is composed from bottom to top: original soil layer, 100mm thick sub-clay rolling layer, 50mm thick mud paste anti-seepage layer, carbon fiber grid layer, 30mm thick cement mortar protective layer, plain concrete cushion layer and reinforced concrete raft slab.
[0032] Furthermore, the overall structure of the basement exterior wall reinforced concrete cap / raft slab / exterior wall mud plaster anti-seepage structure is a concave structure, which is divided into: a central concave surface structure D, a side slope surface structure D, a top surface structure D and a basement exterior wall structure;
[0033] Furthermore, the structure D of the central concave surface is composed of the original soil layer, 100-mm thick sub-clay rolling layer, 50-mm thick mud paste anti-seepage layer, carbon fiber grid layer, 30-mm thick cement mortar protective layer, plain concrete cushion layer and reinforced concrete cap from bottom to top;
[0034] Furthermore, the side slope surface structure D is composed from bottom to top: original soil layer, 100mm thick sub-clay rolling layer, 50mm thick mud paste anti-seepage layer, carbon fiber mesh layer, 30mm thick cement mortar protective layer, and reinforced concrete cap.
[0035] Furthermore, the top surface structure D is composed from bottom to top: original soil layer, 100mm thick sub-clay rolling layer, 50mm thick mud paste anti-seepage layer, carbon fiber mesh layer, 30mm thick cement mortar protective layer, plain concrete cushion layer and reinforced concrete raft slab;
[0036] Further, the basement exterior wall structure includes: an exterior wall underground portion and an exterior wall ground portion;
[0037] Furthermore, the underground part of the exterior wall is composed of the original soil layer, 50mm thick mud plaster anti-seepage layer, 60mm thick plain concrete precast slab and reinforced concrete cap from the inside to the outside;
[0038] Furthermore, the exterior wall ground part is composed of: backfill soil compaction layer, 60mm thick plain concrete precast slab, 50mm thick mud plaster anti-seepage layer and reinforced concrete exterior wall from the inside to the outside;
[0039] Furthermore, the corners at the junction of the underground part of the exterior wall and the ground part of the exterior wall are, from bottom to top, reinforced concrete capping platform, 50mm thick mud paste anti-seepage layer, 60mm thick plain concrete precast slab and backfill soil compaction layer.
[0040] Furthermore, the anti-seepage structure of the pool and well structure includes: the anti-seepage structure of the pool and well first with anti-seepage and then with mud paste for structural anti-seepage and the anti-seepage structure of the pool and well first with structural and then with high-pressure mud paste injection;
[0041] Furthermore, the anti-seepage structure of the well firstly prevents seepage and then structures the mud paste anti-seepage structure, including: the well bottom surface structure, the well vertical wall structure and the well top surface structure;
[0042] Furthermore, the bottom surface structure of the pool well is, from bottom to top, the original soil layer, reinforced concrete structure cushion layer, mud board anti-seepage bearing layer, carbon fiber mesh layer, 30 thick cement mortar protective layer and the pool well reinforced concrete bottom plate;
[0043] Furthermore, the vertical wall structure of the pool and well is composed of the following from the inside to the outside: original soil layer, 50mm thick mud plaster anti-seepage layer, 60mm thick plain concrete prefabricated board and the reinforced concrete wall of the pool and well wall;
[0044] Furthermore, the top surface structure of the pool is, from bottom to top: original soil layer, 100mm thick sub-clay compacted layer, 50mm thick mud paste anti-seepage layer, carbon fiber mesh layer, 30mm thick cement mortar protective layer, plain concrete cushion layer and reinforced concrete raft slab.
[0045] Furthermore, the anti-seepage structure of the well first and then the mud paste includes: the well bottom surface structure, the well vertical wall anti-seepage structure and the well top surface structure;
[0046] Furthermore, the bottom surface structure of the pool well is, from bottom to top, the original soil layer, reinforced concrete structure cushion layer, mud board anti-seepage bearing layer, carbon fiber mesh layer, 30 thick cement mortar protective layer and the pool well reinforced concrete bottom plate;
[0047] Furthermore, the anti-seepage structure of the pool wall is composed of the following from the inside to the outside: original soil layer, backfill soil ramming layer, 50-100 thick polystyrene board isolation layer, 50 thick mud plaster anti-seepage layer and pool wall reinforced concrete wall;
[0048] Furthermore, the top surface structure of the pool is, from bottom to top: original soil layer, 100mm thick sub-clay compacted layer, 50mm thick mud paste anti-seepage layer, carbon fiber mesh layer, 30mm thick cement mortar protective layer, plain concrete cushion layer and reinforced concrete raft slab.
[0049] Further, the raft / beam anti-seepage structure includes: a beam bottom surface structure A, a beam side elevation structure and a raft bottom surface structure;
[0050] Furthermore, the bottom surface structure A of the beam is composed of the original soil layer, 100-mm thick sub-clay rolling layer, 50-mm thick mud paste anti-seepage layer, 60-mm thick plain concrete precast slab, reinforced concrete beam and reinforced concrete raft slab from bottom to top;
[0051] Furthermore, the side elevation structure of the beam is composed of the original soil layer, 50mm thick mud plaster anti-seepage layer, 60mm thick plain concrete precast slab and reinforced concrete beam from inside to outside;
[0052] Furthermore, the bottom surface structure of the raft slab is, from bottom to top: original soil layer, 100mm thick sub-clay rolling layer, 50mm thick mud paste anti-seepage layer, carbon fiber mesh layer, 30mm thick cement mortar protective layer, plain concrete cushion layer and reinforced concrete raft slab.
[0053] Furthermore, the raft / beam / wall anti-seepage structure includes: a beam bottom surface structure B, a beam side elevation structure, a beam side elevation structure under the wall, a wall side elevation structure and a raft bottom plugging structure A;
[0054] Furthermore, the bottom surface structure B of the beam is composed of the original soil layer, 100mm thick sub-clay rolling layer, 50mm thick mud paste anti-seepage layer, 60mm thick plain concrete precast slab and reinforced concrete beam from bottom to top;
[0055] Furthermore, the side elevation structure of the beam is composed of the original soil layer, 50mm thick mud plaster anti-seepage layer, 60mm thick plain concrete precast slab and reinforced concrete beam from inside to outside;
[0056] Furthermore, the side elevation structure of the beam under the wall is, from the inside to the outside, the original soil layer, 60mm thick plain concrete precast slab, 50mm thick mud plaster anti-seepage layer, 60mm thick plain concrete precast slab and reinforced concrete beam;
[0057] Furthermore, the side elevation structure of the wall is composed of: backfill soil compaction layer, 60mm thick plain concrete precast slab, 50mm thick mud plaster anti-seepage layer and reinforced concrete exterior wall from the inside to the outside;
[0058] Furthermore, between the backfill soil ramming layer and the reinforced concrete beam, from top to bottom, there are 60mm thick plain concrete cover plate and 50mm thick mud paste anti-seepage layer to prevent leakage at the connection between the beam and the wall;
[0059] Furthermore, the plugging structure A at the bottom of the raft slab is composed of, from bottom to top: original soil layer, 100mm thick sub-clay rolling layer, 50mm thick mud paste anti-seepage layer, carbon fiber mesh layer, 30mm thick cement mortar protective layer, plain concrete cushion layer and reinforced concrete raft slab.
[0060] Furthermore, the anti-seepage structure of the civil air defense basement roof project includes: the basement outer ground structure, the basement outer wall side elevation structure and the basement outer water dispersion bottom surface structure;
[0061] Furthermore, the outer ground structure of the basement is composed of the following from bottom to top: reinforced concrete top plate, 50mm thick mud anti-seepage layer, carbon fiber mesh layer, plain concrete cushion layer, and backfill soil compaction layer;
[0062] Furthermore, a planting soil layer may be provided on the upper part of the backfill soil ramming layer of the outer ground structure of the basement;
[0063] Furthermore, the side elevation structure of the basement exterior wall is composed of reinforced concrete wall panels, 50mm thick mud plaster anti-seepage layer, 50mm thick polystyrene board isolation layer and backfill soil compaction layer from the inside to the outside;
[0064] Furthermore, the bottom surface structure of the basement external scattered water is, from bottom to top: backfill soil compaction layer, 400mm thick shaken sand layer, 100mm thick polystyrene board insulation layer, 100mm thick reinforced concrete base layer, and 30mm thick cement mortar surface layer.
[0065] Furthermore, the stream / stream / river anti-seepage structure is, from bottom to top, the following: a rammed soil layer, a sub-clay rolling layer, a 50-100 thick mud paste anti-seepage layer, a carbon fiber mesh layer, a sub-clay rolling layer, a 30-50 thick sand layer, and water;
[0066] Furthermore, the thickness of the sub-clay rolling layer on the upper part of the carbon fiber mesh layer needs to be calculated and set according to the silt thickness required in the aquatic plant area.
[0067] Furthermore, the 30-50 thick sand layer is not provided when there are aquatic plants.
[0068] Further, the raft / wall plugging structure includes: a raft lower plugging structure and a wall internal plugging structure;
[0069] Furthermore, the plugging structure of the lower part of the raft slab is, from bottom to top, the original soil layer, the high-pressure mud injection paste plugging layer, the plain concrete cushion layer, the coiled material anti-seepage layer and the reinforced concrete raft slab;
[0070] Furthermore, the internal plugging structure of the wall is, from the inside to the outside, the original soil layer, the backfill soil compaction layer, the high-pressure mud injection plugging layer, the coiled material anti-seepage layer and the reinforced concrete outer wall;
[0071] Furthermore, the high-pressure mud-injection plugging layer is a post-injection structure, which is formed by mud-injection pipes arranged on the plugging structure at the bottom of the raft and the plugging structure inside the wall.
[0072] Furthermore, the front end of the grouting pipe provided on the plugging structure at the lower part of the raft is provided between the original soil layer and the plain concrete cushion layer;
[0073] Furthermore, the front end of the grouting pipe arranged on the leak-proof structure inside the wall is arranged between the backfill soil compaction layer and the coiled material anti-seepage layer.
[0074] Further, the cap / raft plugging structure includes: a cap bottom plugging structure and a raft bottom plugging structure B;
[0075] Furthermore, the plugging structure at the bottom of the cap is, from bottom to top, the original soil layer, the high-pressure mud injection plugging layer, the plain concrete cushion layer, the coiled material anti-seepage layer and the reinforced concrete cap;
[0076] Furthermore, the plugging structure B at the bottom of the raft slab is composed of, from bottom to top: original soil layer, high-pressure mud injection plugging layer, plain concrete cushion layer, coiled material anti-seepage layer and reinforced concrete raft slab;
[0077] Furthermore, the high-pressure mud injection plugging layer is a post-injection structure, which is formed by mud injected by a grouting pipe arranged on the plugging structure at the bottom of the cap and the plugging structure B at the bottom of the raft;
[0078] Furthermore, the front end of the grouting pipe is arranged between the original soil layer and the plain concrete cushion layer of the plugging structure at the bottom of the cap and the plugging structure B at the bottom of the raft.
[0079] Compared with the prior art, the utility model has the following advantages:
[0080] 1. The utility model provides a mud paste underground engineering anti-seepage plugging structure. A carbon fiber grid is laid on the mud paste waterproof layer. Its purpose is to support the 30-thick cement mortar protective layer and to absorb the mud paste and underground structures. When the mud paste meets water, it has a 10-28 times expansion capacity. At the same time, the mud paste is permanently produced and absorbed by the structure, completely solving the problem of the anti-seepage layer and the object being separated. Due to the flexibility of the mud paste, even if the structure vibrates and settles, the mud paste can repair the cracks on the surface within 20mm;
[0081] 2. The mud paste underground engineering anti-seepage plugging structure provided by the utility model is obtained through more than 20 years of experience in plugging leaks. It has been verified that there has been no reverse repair phenomenon for many years. It mainly adopts natural bentonite non-aging flexible material. According to the material characteristics, the bentonite mud paste is combined with the underground engineering structure and construction to adopt different degrees of technology to achieve the construction simplicity, which is not affected by the environment and temperature, and can self-heal when there are slight cracks in the structure due to various factors. At the same time, it always permanently guarantees the overall effect of the underground waterproof layer and can completely solve the leakage problem of underground engineering. At the same time, it creates favorable conditions for the future maintenance of underground engineering;
[0082] 3. The mud paste underground engineering anti-seepage and plugging structure provided by the utility model fully utilizes the advantages of bentonite materials and can fully achieve the integrity of the waterproof layer. In particular, based on the advantage of the material's strong adsorption, it can completely solve the waterproof leakage problems of various pile head nodes. This material is a flexible material and can achieve self-adjustment for slight structural deformation. When the material encounters water, it expands itself and forms a highly integral plastic waterproof layer within a certain period of time;
[0083] 4. The anti-seepage and plugging structure of the underground mud-paste engineering provided by the utility model has a long waterproof life: because bentonite is a natural inorganic material, it will not age or corrode even after a long time or when the surrounding environment changes, so the waterproof performance can last for more than hundreds of years;
[0084] 5. The anti-seepage and plugging structure of the mud paste underground engineering provided by the utility model is convenient for later maintenance. During the use of the construction project, drilling and reconstruction are not excluded. Since this waterproof technology does not have the hidden danger of water leakage, the cause and surface of the water seepage are clear. In addition, this material is a flexible material, and the combination of new and old materials is not required, which undoubtedly achieves the purpose of simple maintenance;
[0085] 6. The mud paste underground engineering anti-seepage and leak-proofing structure provided by the utility model adopts natural bentonite mud paste anti-seepage technology. The underground engineering structure anti-seepage technology of the utility model has the function of never aging.
[0086] In summary, the technical solution of the utility model solves the problem that the technical conditions of the underground engineering structure base in the existing waterproofing technology do not meet the bonding requirements of the waterproof membrane, resulting in detachment, water seepage, leakage, short service life of building materials, difficulty in later maintenance, freezing deformation and breakage of the membrane in cold areas, and water seepage caused by the non-woven fabric layer dividing the bearing layer. BRIEF DESCRIPTION OF THE DRAWINGS
[0087] In order to more clearly illustrate the embodiments of the utility model or the technical solutions in the prior art, the drawings required for use in the embodiments or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are some embodiments of the utility model. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative labor.
[0088] Figure 1 This is a schematic diagram of the structure of Embodiment 1 of the present utility model;
[0089] Figure 2 This is a schematic diagram of the structure of Embodiment 2 of the present utility model;
[0090] Figure 3 This is a schematic diagram of the structure of Embodiment 3 of the present utility model;
[0091] Figure 4 This is a schematic diagram of the structure of Embodiment 4 of the present utility model;
[0092] Figure 5 This is a schematic diagram of the structure of Embodiment 5 of the present utility model;
[0093] Figure 6 This is a schematic diagram of the structure of Embodiment 6 of the present utility model;
[0094] Figure 7 This is a schematic diagram of the structure of Embodiment 7 of the present utility model;
[0095] Figure 8 This is a schematic diagram of the structure of Embodiment 8 of the present utility model;
[0096] Fig. 9 This is a schematic diagram of the structure of Example 9 of the utility model;
[0097] Fig.10 This is a schematic diagram of the structure of Embodiment 10 of the present utility model;
[0098] Fig.11 This is a schematic diagram of the structure of Embodiment 11 of the present utility model;
[0099] Fig.12 This is a structural schematic diagram of Example 12 of the utility model.
[0100] In the figure: 1. Original soil layer 2. 100mm thick sub-clay rolling layer 3. 50mm thick mud paste anti-seepage layer 4. Carbon fiber mesh layer 5. 30mm thick cement mortar protective layer 6. Plain concrete cushion layer 7. Reinforced concrete raft 8. Reinforced concrete structure cushion layer 9. Reinforced concrete independent foundation 10. 50mm thick natural stone slab 11. Rolled material anti-seepage layer 12. Reinforced concrete pedestal 13. Backfill soil compaction layer 14. Reinforced concrete outer wall 15. 60mm thick plain concrete precast board 16. Reinforced concrete bottom plate of pool well 17. Reinforced concrete wall of pool well wall 18. 50-10 0mm thick polystyrene board isolation layer 19, grouting pipe 20, reinforced concrete beam 21, 60mm thick plain concrete cover slab 22, reinforced concrete structure top slab 23, planting soil layer 24, reinforced concrete wall panel 25, 50mm thick polystyrene board isolation layer 26, 400mm thick shaken sand layer 27, 100mm thick polystyrene board insulation layer 28, 100mm thick reinforced concrete base layer 29, steps 30, plain soil ramming layer 31, sub-clay rolling layer 32, 50-100mm thick mud paste anti-seepage layer 33, 30-50mm thick sand layer 34, water 35, high-pressure mud injection paste plugging layer. DETAILED DESCRIPTION
[0101] It should be noted that, in the absence of conflict, the embodiments and features of the embodiments of the present invention can be combined with each other. The present invention will be described in detail below with reference to the accompanying drawings and in combination with the embodiments.
[0102] In order to make the purpose, technical scheme and advantages of the embodiments of the utility model clearer, the technical scheme in the embodiments of the utility model will be clearly and completely described below in conjunction with the drawings in the embodiments of the utility model. Obviously, the described embodiments are only part of the embodiments of the utility model, not all of the embodiments. The following description of at least one exemplary embodiment is actually only illustrative and is by no means a limitation on the utility model and its application or use. Based on the embodiments in the utility model, all other embodiments obtained by ordinary technicians in this field without making creative work are within the scope of protection of the utility model.
[0103] It should be noted that the terms used herein are only for describing specific embodiments and are not intended to limit the exemplary embodiments according to the utility model. As used herein, unless the context clearly indicates otherwise, the singular form is also intended to include the plural form. In addition, it should be understood that when the terms "comprise" and / or "include" are used in this specification, it indicates the presence of features, steps, operations, devices, components and / or combinations thereof.
[0104] Unless otherwise specifically stated, the relative arrangement of the parts and steps described in these embodiments, numerical expressions and numerical values do not limit the scope of the utility model. At the same time, it should be clear that, for ease of description, the sizes of the various parts shown in the drawings are not drawn according to the actual proportional relationship. The technology, method and equipment known to ordinary technicians in the relevant field may not be discussed in detail, but in appropriate cases, the technology, method and equipment should be regarded as a part of the authorization specification. In all examples shown and discussed here, any specific value should be interpreted as merely exemplary, rather than as a limitation. Therefore, other examples of exemplary embodiments may have different values. It should be noted that similar numbers and letters represent similar items in the following drawings, so once a certain item is defined in one drawing, it does not need to be further discussed in subsequent drawings.
[0105] In the description of the present utility model, it needs to be understood that the directions or positional relationships indicated by directional words such as "front, back, up, down, left, right", "lateral, vertical, perpendicular, horizontal" and "top, bottom" are usually based on the directions or positional relationships shown in the drawings. They are only for the convenience of describing the present utility model and simplifying the description. Unless otherwise stated, these directional words do not indicate or imply that the device or element referred to must have a specific direction or be constructed and operated in a specific direction. Therefore, they cannot be understood as limiting the scope of protection of the present utility model: the directional words "inside and outside" refer to the inside and outside relative to the contours of each component itself.
[0106] For ease of description, spatially relative terms such as "above", "above", "on the upper surface of", "above", etc. may be used here to describe the spatial positional relationship between a device or feature and other devices or features as shown in the figure. It should be understood that spatially relative terms are intended to include different orientations of the device in use or operation in addition to the orientation described in the figure. For example, if the device in the accompanying drawings is inverted, the device described as "above other devices or structures" or "above other devices or structures" will be positioned as "below other devices or structures" or "below their position devices or structures". Thus, the exemplary term "above" may include both "above" and "below". The device may also be positioned in other different ways (rotated 90 degrees or in other orientations), and the spatially relative descriptions used here are interpreted accordingly.
[0107] In addition, it should be noted that the use of terms such as "first" and "second" to limit components is only for the convenience of distinguishing the corresponding components. If not otherwise stated, the above terms have no special meaning and therefore cannot be understood as limiting the scope of protection of the utility model.
[0108] Example 1
[0109] like Figure 1 As shown, the utility model provides a mud-paste underground engineering anti-seepage and plugging structure, which is a non-rolled basement reinforced concrete independent foundation raft mud-paste anti-seepage structure;
[0110] The overall structure of the reinforced concrete independent foundation raft slab mud plaster anti-seepage structure of the basement without coils is a concave structure, which is divided into: the central concave surface structure A, the side slope surface structure A and the top surface structure A;
[0111] The structure of the central concave surface is from bottom to top: original soil layer 1, reinforced concrete structure cushion layer 8, mud board anti-seepage bearing layer, carbon fiber grid layer 4, 30 thick cement mortar protective layer 5, plain concrete cushion layer 6 and reinforced concrete independent foundation 9;
[0112] The side slope surface structure is from bottom to top: original soil layer 1, 30mm thick cement mortar protective layer 5, 50mm thick mud paste anti-seepage layer 3, carbon fiber mesh layer 4, 30mm thick cement mortar protective layer 5, plain concrete cushion layer 6 and reinforced concrete independent foundation 9;
[0113] The top surface structure from bottom to top is: original soil layer 1, 100mm thick sub-clay rolling layer 2, 50mm thick mud paste anti-seepage layer 3, carbon fiber mesh layer 4, 30mm thick cement mortar protective layer 5, plain concrete cushion layer 6 and reinforced concrete raft slab 7.
[0114] The mud slab anti-seepage bearing layer is formed by paving a 50mm thick mud paste anti-seepage layer 3 and a 50mm thick natural stone slab 10 at intervals.
[0115] This embodiment is applied to an underground independent foundation. In the implementation design, since the independent foundation belongs to the bearing relationship between the independent foundation and the earth, the natural stone bearing blocks in the mud paste anti-seepage layer and the reinforced concrete bearing cushion layer under the mud paste need to be designed separately.
[0116] Example 2
[0117] like Figure 2 As shown, (based on Example 1,) the utility model also provides a mud-paste underground engineering anti-seepage and plugging structure, which is a mud-paste anti-seepage structure with a coiled basement reinforced concrete independent foundation raft;
[0118] The overall structure of the reinforced concrete independent foundation raft slab mud plaster anti-seepage structure of the coiled basement is a concave structure, which is divided into: the central concave surface structure B, the side slope surface structure B and the top surface structure B;
[0119] The structure B of the central concave surface is composed of: original soil layer 1, plain concrete cushion layer 6, coiled material anti-seepage layer 11, 30mm thick cement mortar protective layer 5 and reinforced concrete independent foundation 9 from bottom to top;
[0120] The side slope structure B is composed from bottom to top: original soil layer 1, plain concrete cushion layer 6, coiled material anti-seepage layer 11, 30mm thick cement mortar protective layer 5 and reinforced concrete independent foundation 9;
[0121] The top surface structure B is composed from bottom to top: original soil layer 1, 100mm thick sub-clay rolling layer 2, 50mm thick mud paste anti-seepage layer 3, carbon fiber mesh layer 4, 30mm thick cement mortar protective layer 5, plain concrete cushion layer 6 and reinforced concrete raft slab 7.
[0122] The coiled anti-seepage layer 11 is embedded in the 50-thick mud paste anti-seepage layer 3 for more than 200 mm.
[0123] This embodiment is applied to the anti-seepage structure of embodiment 1 which is not suitable for various conditions. Therefore, when using the roll material anti-seepage layer in the construction implementation, it is necessary to emphasize the embedding length requirement of the roll material and the mud paste.
[0124] Example 3
[0125] like Figure 3 As shown, (based on Example 1,) the utility model also provides a mud-paste underground engineering anti-seepage and plugging structure, which is a basement reinforced concrete cap and raft mud-paste anti-seepage structure;
[0126] The overall structure of the basement reinforced concrete cap and raft slab mud paste anti-seepage structure is a concave structure, which is divided into: the central concave surface structure C, the side slope surface structure C and the top surface structure C;
[0127] The structure C of the central concave surface is composed of the following from bottom to top: original soil layer 1, 100mm thick sub-clay rolling layer 2, 50mm thick mud paste anti-seepage layer 3, carbon fiber mesh layer 4, 30mm thick cement mortar protective layer 5, plain concrete cushion layer 6 and reinforced concrete cap 12;
[0128] The side slope surface structure C is composed from bottom to top: original soil layer 1, 30mm thick cement mortar protective layer 5, 50mm thick mud paste anti-seepage layer 3, carbon fiber mesh layer 4, 30mm thick cement mortar protective layer 5, reinforced concrete cap 12;
[0129] The top surface structure C is composed from bottom to top: original soil layer 1, 100mm thick sub-clay rolling layer 2, 50mm thick mud paste anti-seepage layer 3, carbon fiber mesh layer 4, 30mm thick cement mortar protective layer 5, plain concrete cushion layer 6 and reinforced concrete raft slab 7.
[0130] This embodiment is suitable for underground reinforced concrete cap-type foundation. In actual construction, it is necessary to ensure the neatness of the cap foundation bored piles to meet the quality requirements for ensuring the adsorption of mud paste and bored piles.
[0131] Example 4
[0132] like Figure 4As shown, (based on Example 1,) the utility model also provides a mud-plaster underground engineering anti-seepage and plugging structure, which is a basement outer wall reinforced concrete cap / raft slab / external wall mud-plaster anti-seepage structure;
[0133] The overall structure of the reinforced concrete cap / raft slab / external wall mud plaster anti-seepage structure of the basement exterior wall is a concave structure, which is divided into: the central concave surface structure D, the side slope surface structure D, the top surface structure D and the basement exterior wall structure;
[0134] The structure D of the central concave surface is composed of the following from bottom to top: original soil layer 1, 100mm thick sub-clay rolling layer 2, 50mm thick mud paste anti-seepage layer 3, carbon fiber mesh layer 4, 30mm thick cement mortar protective layer 5, plain concrete cushion layer 6 and reinforced concrete cap 12;
[0135] The side slope structure D is composed from bottom to top: original soil layer 1, 100mm thick sub-clay rolling layer 2, 50mm thick mud paste anti-seepage layer 3, carbon fiber mesh layer 4, 30mm thick cement mortar protective layer 5, reinforced concrete cap 12;
[0136] The top surface structure D is composed from bottom to top: original soil layer 1, 100mm thick sub-clay rolling layer 2, 50mm thick mud paste anti-seepage layer 3, carbon fiber mesh layer 4, 30mm thick cement mortar protective layer 5, plain concrete cushion layer 6 and reinforced concrete raft slab 7;
[0137] The basement exterior wall structure includes: the exterior wall underground part and the exterior wall ground part;
[0138] The underground part of the outer wall is composed of: original soil layer 1, 50mm thick mud plaster anti-seepage layer 3, 60mm thick plain concrete prefabricated board 15 and reinforced concrete cap 12 from the inside to the outside;
[0139] The outer wall ground part is composed of: backfill soil compaction layer 13, 60 thick plain concrete prefabricated board 15, 50 thick mud paste anti-seepage layer 3 and reinforced concrete outer wall 14 from the inside to the outside;
[0140] The corner of the junction between the underground part of the outer wall and the ground part of the outer wall is composed of a reinforced concrete cap 12, a 50-thick mud paste anti-seepage layer 3, a 60-thick plain concrete prefabricated board 15 and a backfill soil compaction layer 13 from bottom to top.
[0141] This embodiment is applicable to the basement exterior wall pedestal foundation, which has a relatively complex structure. In actual construction, in addition to ensuring that the mud is full and tightly connected, the requirements for neat mud adsorption at the poured pile head must also be met, while ensuring the dimensions of each structure and angle.
[0142] Example 5
[0143] like Figure 5 As shown, (based on Example 1,) the utility model also provides a mud paste underground engineering anti-seepage plugging structure, which is a mud paste anti-seepage structure for a pool and well that first prevents seepage and then structures;
[0144] The anti-seepage structure of the well includes: the bottom surface structure of the well, the vertical wall structure of the well and the top surface structure of the well;
[0145] The bottom surface structure of the pool is composed of original soil layer 1, reinforced concrete structure cushion layer 8, mud plate anti-seepage bearing layer, carbon fiber mesh layer 4, 30 thick cement mortar protective layer 5 and pool reinforced concrete bottom plate 16; the mud plate anti-seepage bearing layer is formed by 50 thick mud paste anti-seepage layer 3 and 50 thick natural stone slab 10 laid alternately;
[0146] The vertical wall structure of the pool and well is composed of: original soil layer 1, 50mm thick mud plaster anti-seepage layer 3, 60mm thick plain concrete prefabricated board 15 and pool and well wall reinforced concrete wall 17 from inside to outside;
[0147] The top surface structure of the pool is from bottom to top: original soil layer 1, 100mm thick sub-clay rolled layer 2, 50mm thick mud paste anti-seepage layer 3, carbon fiber mesh layer 4, 30mm thick cement mortar protective layer 5, plain concrete cushion layer 6 and reinforced concrete raft slab 7.
[0148] This embodiment is suitable for the corresponding shallow pool and well anti-seepage structure. In actual construction, there is no need for a large open structure, and the anti-seepage around the top of the pool and well can be designed separately according to actual conditions.
[0149] Example 6
[0150] like Figure 6 As shown, (based on Example 1,) the utility model also provides a mud paste underground engineering anti-seepage plugging structure, which is a pond well first structure and then mud paste anti-seepage structure;
[0151] The anti-seepage structure of the pool well first and then the mud paste includes: the bottom surface structure of the pool well, the anti-seepage structure of the pool well vertical wall and the top surface structure of the pool well;
[0152] The bottom surface structure of the pool is composed of: original soil layer 1, reinforced concrete structure cushion layer 8, mud plate anti-seepage bearing layer, carbon fiber mesh layer 4, 30 thick cement mortar protective layer 5 and pool well reinforced concrete bottom plate 16; the mud plate anti-seepage bearing layer is formed by paving 50 thick mud paste anti-seepage layer 3 and 50 thick natural stone slab 10 at intervals;
[0153] The anti-seepage structure of the pool wall is composed of: original soil layer 1, backfill soil ramming layer 13, 50-100 thick polystyrene board isolation layer 18, 50 thick mud paste anti-seepage layer 3 and pool wall reinforced concrete wall 17 from inside to outside;
[0154] The top surface structure of the pool is, from bottom to top, original soil layer 1, 100mm thick sub-clay rolling layer 2, 50mm thick mud paste anti-seepage layer 3, carbon fiber grid layer 4, 30mm thick cement mortar protective layer 5, plain concrete cushion layer 6 and reinforced concrete raft slab 7.
[0155] This embodiment is suitable for the corresponding deep pool and well anti-seepage structure. In actual construction, if anti-seepage around the top of a large open structure pool and well is required, it can be designed separately according to actual conditions.
[0156] Example 7
[0157] like Figure 7 As shown, (based on Example 1,) the utility model also provides a mud paste underground engineering anti-seepage plugging structure, which is a raft / beam anti-seepage structure;
[0158] The raft / beam anti-seepage structure includes: beam bottom surface structure A, beam side elevation structure and raft bottom surface structure;
[0159] The structure A of the bottom surface of the beam is, from bottom to top, original soil layer 1, 100-thick sub-clay rolling layer 2, 50-thick mud paste anti-seepage layer 3, 60-thick plain concrete precast slab 15, reinforced concrete beam 20 and reinforced concrete raft slab 7;
[0160] The beam side elevation structure is from inside to outside: original soil layer 1, 50mm thick mud paste anti-seepage layer 3, 60mm thick plain concrete precast slab 15 and reinforced concrete beam 20;
[0161] The bottom surface structure of the raft slab is, from bottom to top, original soil layer 1, 100mm thick sub-clay rolling layer 2, 50mm thick mud paste anti-seepage layer 3, carbon fiber mesh layer 4, 30mm thick cement mortar protective layer 5, plain concrete cushion layer 6 and reinforced concrete raft slab 7.
[0162] This embodiment is applicable to the anti-seepage structure of the raft beam in the basement. This structure is relatively complex. In actual construction, in addition to achieving full and tight connection of the mud paste, it is necessary to ensure the scale of each structure and angle.
[0163] Example 8
[0164] like Figure 8 As shown, (based on Example 1,) the utility model also provides a mud paste underground engineering anti-seepage plugging structure, which is a raft / beam / wall anti-seepage structure;
[0165] The raft / beam / wall anti-seepage structure includes: beam bottom surface structure B, beam side elevation structure, wall bottom beam side elevation structure, wall side elevation structure and raft bottom plugging structure A;
[0166] The structure B of the bottom surface of the beam is, from bottom to top, original soil layer 1, 100mm thick sub-clay rolling layer 2, 50mm thick mud paste anti-seepage layer 3, 60mm thick plain concrete precast slab 15 and reinforced concrete beam 20;
[0167] The beam side elevation structure is from inside to outside: original soil layer 1, 50mm thick mud paste anti-seepage layer 3, 60mm thick plain concrete precast slab 15 and reinforced concrete beam 20;
[0168] The side elevation structure of the beam under the wall is as follows from the inside to the outside: original soil layer 1, 60mm thick plain concrete precast slab 15, 50mm thick mud paste anti-seepage layer 3, 60mm thick plain concrete precast slab 15 and reinforced concrete beam 20;
[0169] The side elevation structure of the wall is, from the inside to the outside, composed of: backfill soil compaction layer 13, 60mm thick plain concrete precast board 15, 50mm thick mud paste anti-seepage layer 3 and reinforced concrete outer wall 14;
[0170] Between the backfill soil ramming layer 13 and the reinforced concrete beam 20, from top to bottom, there are a 60mm thick plain concrete cover plate 21 and a 50mm thick mud paste anti-seepage layer 3 to prevent leakage at the connection between the beam and the wall;
[0171] The plugging structure A at the bottom of the raft slab is composed from bottom to top: original soil layer 1, 100mm thick sub-clay rolling layer 2, 50mm thick mud paste anti-seepage layer 3, carbon fiber mesh layer 4, 30mm thick cement mortar protective layer 5, plain concrete cushion layer 6 and reinforced concrete raft slab 7.
[0172] This embodiment is applied to the anti-seepage structure of underground pools and wells. In the implementation design, the pools and wells have an independent foundation and a bearing relationship with the earth, so the natural stone bearing blocks in the mud and plaster anti-seepage layer and the reinforced concrete bearing cushion layer under the mud and plaster need to be designed separately.
[0173] Example 9
[0174] like Fig. 9 As shown, (based on Example 1,) the utility model also provides a mud paste underground engineering anti-seepage plugging structure, which is an anti-seepage structure for the roof engineering of the air defense basement;
[0175] The anti-seepage structure of the civil air defense basement roof project includes: the basement outer ground structure, the basement outer wall side elevation structure and the basement outer water dispersion bottom surface structure;
[0176] The outer ground structure of the basement is, from bottom to top, a reinforced concrete structure top plate 22, a 50mm thick mud paste anti-seepage layer 3, a carbon fiber mesh layer 4, a plain concrete cushion layer 6, and a backfill soil compaction layer 13;
[0177] A planting soil layer 23 may also be provided on the upper part of the backfill soil ramming layer 13 of the outer ground structure of the basement;
[0178] The side elevation structure of the basement exterior wall is composed of reinforced concrete wall panels 24, 50mm thick mud plaster anti-seepage layer 3, 50mm thick polystyrene board isolation layer 25 and backfill soil compaction layer 13 from the inside to the outside.
[0179] The bottom surface structure of the basement external scattered water is as follows from bottom to top: backfill soil compaction layer 13, 400 thick shaken sand layer 26, 100 thick polystyrene board insulation layer 27, 100 thick reinforced concrete base layer 28, 30 thick cement mortar surface layer 29.
[0180] This example is suitable for underground civil air defense roof anti-seepage projects. Its main purpose is to solve the anti-seepage problem at the intersection of the roof fill area and the main building of the civil air defense project. In actual construction, the gap spacing and cleanliness of all wall pipes must be ensured.
[0181] Example 10
[0182] like Fig.10 As shown, (based on Example 1,) the utility model also provides a mud paste underground engineering anti-seepage plugging structure, which is a stream / stream / river anti-seepage structure;
[0183] The stream / stream / river anti-seepage structure is as follows from bottom to top: plain soil compaction layer 30, sub-clay rolling layer 31, 50-100 thick mud paste anti-seepage layer 32, carbon fiber mesh layer 4, sub-clay rolling layer 31, 30-50 thick sand layer 33, water 34;
[0184] The thickness of the sub-clay rolling layer 31 on the upper part of the carbon fiber mesh layer 4 needs to be calculated and set according to the silt thickness required in the aquatic plant area.
[0185] The 30-50 thick sand layer 33 is not provided when there are aquatic plants.
[0186] This example is applicable to all stream / river / lake anti-seepage projects. In actual design and construction, the thickness of sub-clay on the mud-paste anti-seepage layer should be designed separately according to the actual surrounding conditions, mainly to solve the problem of water level pressure difference destroying the mud-paste anti-seepage layer.
[0187] Embodiment 11
[0188] like Fig.11 As shown, (based on Example 1,) the utility model also provides a mud paste underground engineering anti-seepage plugging structure, which is a raft / wall plugging structure;
[0189] The raft / wall plugging structure includes: the lower part of the raft plugging structure and the internal plugging structure of the wall;
[0190] The plugging structure of the lower part of the raft slab is, from bottom to top, the original soil layer 1, the high-pressure mud injection paste plugging layer 35, the plain concrete cushion layer 6, the coiled material anti-seepage layer 11 and the reinforced concrete raft slab 7;
[0191] The internal plugging structure of the wall is, from the inside to the outside, the original soil layer 1, the backfill soil compaction layer 13, the high-pressure mud injection plugging layer 35, the coiled material anti-seepage layer 11 and the reinforced concrete outer wall 14;
[0192] The high-pressure mud-injection paste plugging layer 35 is a post-injection structure, which is formed by the mud paste injected by the grouting pipe 19 arranged on the plugging structure at the bottom of the raft and the plugging structure inside the wall;
[0193] The front end of the grouting pipe 19 provided on the plugging structure at the lower part of the raft is provided between the original soil layer 1 and the plain concrete cushion layer 6;
[0194] The front end of the grouting pipe 19 arranged on the internal plugging structure of the wall is arranged between the backfill soil ramming layer 13 and the coiled material anti-seepage layer 11 .
[0195] This example is applicable to all basement raft slab / facade wall sealing technologies. In actual construction, continuous construction should be carried out at the same grouting point within a certain period of time to ensure the continuity of the grouting time at one point.
[0196] Example 12
[0197] like Fig.12 As shown, (based on Example 1,) the utility model also provides a mud paste underground engineering anti-seepage plugging structure, which is a cap / raft plugging structure;
[0198] The cap / raft plugging structure includes: a cap bottom plugging structure and a raft bottom plugging structure B;
[0199] The plugging structure at the bottom of the cap is, from bottom to top, the original soil layer 1, the high-pressure mud injection paste plugging layer 35, the plain concrete cushion layer 6, the coiled material anti-seepage layer 11 and the reinforced concrete cap 12;
[0200] The plugging structure B at the bottom of the raft slab is composed of, from bottom to top: original soil layer 1, high pressure mud injection paste plugging layer 35, plain concrete cushion layer 6, coiled material anti-seepage layer 11 and reinforced concrete raft slab 7;
[0201] The high-pressure mud injection plugging layer 35 is a post-injection structure, which is formed by the mud injected by the grouting pipe 19 arranged on the plugging structure at the bottom of the cap and the plugging structure B at the bottom of the raft;
[0202] The front end of the grouting pipe 19 is arranged between the original soil layer 1 and the plain concrete cushion layer 6 of the plugging structure at the bottom of the cap and the plugging structure B at the bottom of the raft.
[0203] This example is applicable to all basement raft slab / cap plugging technologies. In actual construction, continuous construction should be carried out at the same grouting point within a certain period of time to ensure the continuity of the grouting time at one point.
[0204] Finally, it should be noted that the above embodiments are only used to illustrate the technical solution of the utility model, rather than to limit it. Although the utility model has been described in detail with reference to the aforementioned embodiments, ordinary technicians in this field should understand that they can still modify the technical solutions recorded in the aforementioned embodiments, or replace some or all of the technical features therein with equivalents. However, these modifications or replacements do not make the essence of the corresponding technical solution deviate from the scope of the technical solution of the embodiments of the utility model.
Claims
1. A mud-paste underground engineering anti-seepage and plugging structure, characterized in that: The mud paste underground engineering anti-seepage and plugging structure includes: independent foundation anti-seepage structure, pedestal foundation anti-seepage structure, pool and well structure anti-seepage structure, raft / beam anti-seepage structure, raft / beam / wall anti-seepage structure, civil air defense basement roof engineering anti-seepage structure, stream / stream / river anti-seepage structure, raft / wall plugging structure and pedestal / raft plugging structure; the mud paste is a mud-like substance formed by a mixture of bentonite and water.
2. The anti-seepage and plugging structure of mud paste underground engineering according to claim 1 is characterized in that: The independent foundation anti-seepage structure includes: a basement reinforced concrete independent foundation raft slab mud plaster anti-seepage structure without coiled materials and a basement reinforced concrete independent foundation raft slab mud plaster anti-seepage structure with coiled materials; The overall structure of the reinforced concrete independent foundation raft slab mud plaster anti-seepage structure of the non-rolled basement is a concave structure, which is divided into: a central concave surface structure A, a side slope surface structure A and a top surface structure A; The central concave surface structure comprises, from bottom to top, an original soil layer (1), a reinforced concrete structure cushion layer (8), a mud slab anti-seepage bearing layer, a carbon fiber mesh layer (4), a 30mm thick cement mortar protective layer (5), a plain concrete cushion layer (6) and a reinforced concrete independent foundation (9); the mud slab anti-seepage bearing layer is formed by paving a 50mm thick mud paste anti-seepage layer (3) and a 50mm thick natural stone slab (10) at intervals; The side slope surface structure comprises, from bottom to top, an original soil layer (1), a 30mm thick cement mortar protective layer (5), a 50mm thick mud paste anti-seepage layer (3), a carbon fiber mesh layer (4), a 30mm thick cement mortar protective layer (5), a plain concrete cushion layer (6) and a reinforced concrete independent foundation (9); The top surface structure is composed of, from bottom to top: an original soil layer (1), a 100mm thick sub-clay rolling layer (2), a 50mm thick mud paste anti-seepage layer (3), a carbon fiber mesh layer (4), a 30mm thick cement mortar protective layer (5), a plain concrete cushion layer (6) and a reinforced concrete raft slab (7); The overall structure of the reinforced concrete independent foundation raft slab mud plaster anti-seepage structure with coiled basement is a concave structure, which is divided into: a central concave surface structure B, a side slope surface structure B and a top surface structure B; The central concave surface structure B comprises, from bottom to top, an original soil layer (1), a plain concrete cushion layer (6), a coiled material anti-seepage layer (11), a 30mm thick cement mortar protective layer (5) and a reinforced concrete independent foundation (9); The side slope structure B comprises, from bottom to top, an original soil layer (1), a plain concrete cushion layer (6), a coiled material anti-seepage layer (11), a 30mm thick cement mortar protective layer (5) and a reinforced concrete independent foundation (9); The top surface structure B comprises, from bottom to top, an original soil layer (1), a 100mm thick sub-clay rolling layer (2), a 50mm thick mud paste anti-seepage layer (3), a carbon fiber mesh layer (4), a 30mm thick cement mortar protective layer (5), a plain concrete cushion layer (6) and a reinforced concrete raft slab (7); the coiled material anti-seepage layer (11) is embedded more than 200mm inside the 50mm thick mud paste anti-seepage layer (3).
3. The anti-seepage and plugging structure of mud-paste underground engineering according to claim 1 is characterized by: The anti-seepage structure of the cap foundation includes: a basement reinforced concrete cap, a raft slab mud plaster anti-seepage structure and a basement outer wall reinforced concrete cap / raft slab / external wall mud plaster anti-seepage structure; The basement reinforced concrete cap and raft slab mud paste anti-seepage structure are generally concave structures, which are divided into: a central concave surface structure C, a side slope surface structure C and a top surface structure C; The central concave surface structure C comprises, from bottom to top, an original soil layer (1), a 100mm thick sub-clay rolling layer (2), a 50mm thick mud paste anti-seepage layer (3), a carbon fiber mesh layer (4), a 30mm thick cement mortar protective layer (5), a plain concrete cushion layer (6) and a reinforced concrete cap (12); The side slope surface structure C comprises, from bottom to top, an original soil layer (1), a 30mm thick cement mortar protective layer (5), a 50mm thick mud paste anti-seepage layer (3), a carbon fiber mesh layer (4), a 30mm thick cement mortar protective layer (5), and a reinforced concrete cap (12); The top surface structure C comprises, from bottom to top, an original soil layer (1), a 100mm thick sub-clay rolling layer (2), a 50mm thick mud paste anti-seepage layer (3), a carbon fiber mesh layer (4), a 30mm thick cement mortar protective layer (5), a plain concrete cushion layer (6) and a reinforced concrete raft slab (7); The basement exterior wall reinforced concrete cap / raft slab / exterior wall mud paste anti-seepage structure is a concave structure as a whole, which is divided into: a central concave surface structure D, a side slope surface structure D, a top surface structure D and a basement exterior wall structure; The central concave surface structure D comprises, from bottom to top, an original soil layer (1), a 100mm thick sub-clay rolling layer (2), a 50mm thick mud paste anti-seepage layer (3), a carbon fiber mesh layer (4), a 30mm thick cement mortar protective layer (5), a plain concrete cushion layer (6) and a reinforced concrete cap (12); The side slope surface structure D comprises, from bottom to top, an original soil layer (1), a 100mm thick sub-clay rolling layer (2), a 50mm thick mud paste anti-seepage layer (3), a carbon fiber mesh layer (4), a 30mm thick cement mortar protective layer (5), and a reinforced concrete cap (12); The top surface structure D comprises, from bottom to top, an original soil layer (1), a 100mm thick sub-clay rolling layer (2), a 50mm thick mud paste anti-seepage layer (3), a carbon fiber mesh layer (4), a 30mm thick cement mortar protective layer (5), a plain concrete cushion layer (6) and a reinforced concrete raft slab (7); The basement exterior wall structure comprises: an exterior wall underground part and an exterior wall ground part; The underground part of the outer wall is composed of, from the inside to the outside, an original soil layer (1), a 50mm thick mud plaster anti-seepage layer (3), a 60mm thick plain concrete prefabricated board (15) and a reinforced concrete cap (12); The outer wall ground part is composed of, from the inside to the outside, a backfill soil compaction layer (13), a 60mm thick plain concrete prefabricated board (15), a 50mm thick mud paste anti-seepage layer (3) and a reinforced concrete outer wall (14); The corner of the junction between the underground part of the outer wall and the ground part of the outer wall comprises, from bottom to top, a reinforced concrete cap (12), a 50mm thick mud paste anti-seepage layer (3), a 60mm thick plain concrete prefabricated board (15) and a backfill soil compaction layer (13).
4. The anti-seepage and plugging structure of mud paste underground engineering according to claim 1 is characterized in that: The anti-seepage structure of the pool and well structure includes: the anti-seepage structure of the pool and well firstly anti-seepage and then structure mud paste anti-seepage structure and the anti-seepage structure of the pool and well firstly structure and then mud paste; The anti-seepage structure of the pool and well first and then the structure of the mud paste anti-seepage structure includes: a pool and well bottom surface structure, a pool and well vertical wall structure and a pool and well top surface structure; The bottom surface structure of the well is, from bottom to top, composed of: an original soil layer (1), a reinforced concrete structure cushion layer (8), a mud plate anti-seepage bearing layer, a carbon fiber mesh layer (4), a 30mm thick cement mortar protective layer (5) and a well reinforced concrete bottom plate (16); The pool wall structure is composed of, from inside to outside, an original soil layer (1), a 50mm thick mud plaster anti-seepage layer (3), a 60mm thick plain concrete prefabricated board (15) and a pool wall reinforced concrete wall (17); The top surface structure of the pool well is, from bottom to top, the original soil layer (1), a 100mm thick sub-clay rolling layer (2), a 50mm thick mud paste anti-seepage layer (3), a carbon fiber mesh layer (4), a 30mm thick cement mortar protective layer (5), a plain concrete cushion layer (6) and a reinforced concrete raft slab (7); The anti-seepage structure of the pool well first and then the mud paste includes: the bottom surface structure of the pool well, the anti-seepage structure of the pool well vertical wall and the top surface structure of the pool well; The bottom surface structure of the well is, from bottom to top, composed of: an original soil layer (1), a reinforced concrete structure cushion layer (8), a mud plate anti-seepage bearing layer, a carbon fiber mesh layer (4), a 30mm thick cement mortar protective layer (5) and a well reinforced concrete bottom plate (16); The anti-seepage structure of the pool wall is composed of, from inside to outside: an original soil layer (1), a backfill soil tamping layer (13), a 50-100 thick polystyrene board isolation layer (18), a 50 thick mud paste anti-seepage layer (3) and a pool wall reinforced concrete wall (17); The top surface structure of the pool well is, from bottom to top, the following: an original soil layer (1), a 100-mm-thick sub-clay rolling layer (2), a 50-mm-thick mud paste anti-seepage layer (3), a carbon fiber mesh layer (4), a 30-mm-thick cement mortar protective layer (5), a plain concrete cushion layer (6), and a reinforced concrete raft slab (7).
5. The anti-seepage and plugging structure of mud paste underground engineering according to claim 1 is characterized by: The raft / beam anti-seepage structure comprises: a beam bottom surface structure A, a beam side elevation structure and a raft bottom surface structure; The beam bottom surface structure A comprises, from bottom to top, an original soil layer (1), a 100-mm thick sub-clay rolling layer (2), a 50-mm thick mud paste anti-seepage layer (3), a 60-mm thick plain concrete prefabricated board (15), a reinforced concrete beam (20) and a reinforced concrete raft slab (7); The beam side elevation structure is composed of, from inside to outside: an original soil layer (1), a 50mm thick mud plaster anti-seepage layer (3), a 60mm thick plain concrete prefabricated board (15) and a reinforced concrete beam (20); The bottom surface structure of the raft slab comprises, from bottom to top, an original soil layer (1), a 100-mm-thick sub-clay rolling layer (2), a 50-mm-thick mud paste anti-seepage layer (3), a carbon fiber mesh layer (4), a 30-mm-thick cement mortar protective layer (5), a plain concrete cushion layer (6), and a reinforced concrete raft slab (7).
6. The anti-seepage and plugging structure of mud paste underground engineering according to claim 1 is characterized by: The raft / beam / wall anti-seepage structure comprises: a beam bottom surface structure B, a beam side elevation structure, a beam side elevation structure under the wall, a wall side elevation structure and a raft bottom plugging structure A; The bottom surface structure B of the beam is composed of, from bottom to top: an original soil layer (1), a 100mm thick sub-clay rolling layer (2), a 50mm thick mud paste anti-seepage layer (3), a 60mm thick plain concrete prefabricated board (15) and a reinforced concrete beam (20); The beam side elevation structure is composed of, from inside to outside: an original soil layer (1), a 50mm thick mud plaster anti-seepage layer (3), a 60mm thick plain concrete prefabricated board (15) and a reinforced concrete beam (20); The side elevation structure of the wall beam is composed of, from the inside to the outside, an original soil layer (1), a 60mm thick plain concrete prefabricated board (15), a 50mm thick mud plaster anti-seepage layer (3), a 60mm thick plain concrete prefabricated board (15) and a reinforced concrete beam (20); The side elevation structure of the wall body is composed of, from the inside to the outside, a backfill soil compaction layer (13), a 60mm thick plain concrete prefabricated board (15), a 50mm thick mud plaster anti-seepage layer (3) and a reinforced concrete outer wall (14); Between the backfill soil ramming layer (13) and the reinforced concrete beam (20), from top to bottom, there are a 60mm thick plain concrete cover plate (21) and a 50mm thick mud paste anti-seepage layer (3) to prevent leakage at the connection between the beam and the wall; The bottom plugging structure A of the raft slab comprises, from bottom to top, an original soil layer (1), a 100-mm-thick sub-clay rolling layer (2), a 50-mm-thick mud paste anti-seepage layer (3), a carbon fiber mesh layer (4), a 30-mm-thick cement mortar protective layer (5), a plain concrete cushion layer (6), and a reinforced concrete raft slab (7).
7. The anti-seepage and plugging structure of mud plaster underground engineering according to claim 1 is characterized by: The anti-seepage structure of the civil air defense basement roof project includes: the basement outer ground structure, the basement outer wall side elevation structure and the basement outer water dispersion bottom surface structure; The outer ground structure of the basement is composed of, from bottom to top: a reinforced concrete structure top plate (22), a 50mm thick mud paste anti-seepage layer (3), a carbon fiber mesh layer (4), a plain concrete cushion layer (6), and a backfill soil compaction layer (13); A planting soil layer (23) may also be provided on the upper part of the backfill soil ramming layer (13) of the outer ground structure of the basement; The side elevation structure of the basement exterior wall is composed of a reinforced concrete wall panel (24), a 50mm thick mud plaster anti-seepage layer (3), a 50mm thick polystyrene board isolation layer (25) and a backfill soil compaction layer (13) from the inside to the outside. The bottom surface structure of the basement external water dispersion is, from bottom to top, composed of: a backfill soil compaction layer (13), a 400mm thick shaken sand layer (26), a 100mm thick polystyrene board insulation layer (27), a 100mm thick reinforced concrete base layer (28), and a 30mm thick cement mortar surface layer (29).
8. The anti-seepage and plugging structure of mud-paste underground engineering according to claim 1 is characterized by: The stream / stream / river anti-seepage structure is, from bottom to top, a plain soil compaction layer (30), a sub-clay rolling layer (31), a 50-100 thick mud paste anti-seepage layer (32), a carbon fiber mesh layer (4), a sub-clay rolling layer (31), a 30-50 thick sand layer (33), and water (34); The thickness of the sub-clay rolling layer (31) on the upper part of the carbon fiber mesh layer (4) needs to be calculated and set according to the silt thickness required for the aquatic plant area.
9. The anti-seepage and plugging structure of mud-paste underground engineering according to claim 8 is characterized by: The 30-50mm thick sand layer (33) is not provided when there are aquatic plants.
10. The anti-seepage and plugging structure of mud paste underground engineering according to claim 1, characterized in that: The raft / wall plugging structure comprises: a plugging structure at the bottom of the raft and a plugging structure inside the wall; The lower part of the raft slab leak-proof structure comprises, from bottom to top, an original soil layer (1), a high-pressure mud injection paste leak-proof layer (35), a plain concrete cushion layer (6), a coiled material anti-seepage layer (11) and a reinforced concrete raft slab (7); The wall internal leak-proof structure comprises, from the inside to the outside, an original soil layer (1), a backfill soil compaction layer (13), a high-pressure mud injection paste leak-proof layer (35), a coiled material anti-seepage layer (11), and a reinforced concrete outer wall (14); The high-pressure mud injection paste plugging layer (35) is a post-injection structure, formed by mud paste injected through a grouting pipe (19) arranged on the plugging structure at the bottom of the raft and the plugging structure inside the wall; The front end of the grouting pipe (19) provided on the lower leak-proof structure of the raft slab is provided between the original soil layer (1) and the plain concrete cushion layer (6); The front end of the grouting pipe (19) provided on the wall internal leak-proof structure is provided between the backfill soil compaction layer (13) and the coiled material anti-seepage layer (11).
11. The anti-seepage and plugging structure of mud underground engineering according to claim 1, characterized in that: The cap / raft plugging structure includes: a cap bottom plugging structure and a raft bottom plugging structure B; The bottom plugging structure of the capping platform comprises, from bottom to top, an original soil layer (1), a high-pressure mud injection plugging layer (35), a plain concrete cushion layer (6), a coiled material anti-seepage layer (11), and a reinforced concrete capping platform (12); The raft bottom plugging structure B comprises, from bottom to top, an original soil layer (1), a high-pressure mud injection plugging layer (35), a plain concrete cushion layer (6), a coiled material anti-seepage layer (11), and a reinforced concrete raft (7); The high-pressure mud injection paste plugging layer (35) is a post-injection structure, formed by mud paste injected through a grouting pipe (19) arranged on the plugging structure at the bottom of the cap and the plugging structure B at the bottom of the raft; The front end of the grouting pipe (19) is arranged between the original soil layer (1) and the plain concrete cushion layer (6) of the plugging structure at the bottom of the cap and the plugging structure B at the bottom of the raft.