Building central air conditioner air pipe hanging bracket

By adopting a rectangular frame structure and buffer in the central air conditioner air duct hanger, combined with the design of loose locking and ceiling seat, the problem of air duct clamping and installation effect is solved, and the stable clamping and buffering and shock absorption and quiet effect of different types of air ducts is achieved.

CN222669180UActive Publication Date: 2025-03-25WUHAN XINNONGKEN AIR CONDITIONING EQUIPMENT CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202421323295.1
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-06-12
Publication Date
2025-03-25
Estimated Expiration
2034-06-12

AI Technical Summary

Technical Problem

The existing central air conditioner duct hanger is difficult to clamp different types of air ducts after installation, and lacks shock absorption and silent wear resistance installation effects, resulting in a decrease in the cooling effect of the air conditioner.

Method used

Two clamp beams and two buffers are connected to form a rectangular frame structure. The sliding of the screw is loosened by the locking female adjustment, the installation height and spacing of the buffer are adjusted, and the air ducts of different models are clamped, and shock absorption and silence effects are achieved through the ceiling seat limit installation and cushioning.

Benefits of technology

It realizes stable clamping of different types of air ducts, has the installation effect of buffering, shock absorption and silent wear resistance, and improves the refrigeration performance of the air conditioner.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222669180U_ABST
    Figure CN222669180U_ABST
Patent Text Reader

Abstract

The utility model discloses a building central air conditioner air pipe hanging bracket, and belongs to the technical field of air pipe hanging brackets. Comprising two buffers, each buffer comprises a bottom column and an upper column, guide grooves are formed in the ends, away from each other, of the bottom column and the upper column, a piston rod is fixedly arranged at the bottom end of the upper column, two clamping beams and the two buffers are connected to form a rectangular frame structure, and a screw slides in a strip-shaped through groove by loosening a lock nut. The installation height of the buffers can be adjusted, the distance between the two buffers can be adjusted by rotating the adjusting threaded rod, then air pipes of different models can be clamped, the ceiling base is installed on the top of a building wall in a limited mode through expansion bolts to achieve air pipe suspension installation, and the buffers achieve air pipe installation and have the buffering and damping effects. And the four inner walls of the rectangular frame structure are each provided with one buffering pad in an inserted connection mode, so that the air pipe can achieve the wear-resisting and mute installation effects.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present application relates to the technical field of air duct hangers, and more specifically, to an air duct hanger for a building central air conditioner. Background Art

[0002] The construction of high-rise buildings requires the installation of large central air-conditioning equipment so that each floor of the building can achieve the cooling effect of central air-conditioning. The air duct of the central air-conditioning is composed of air ducts. When the air ducts are installed along the floors, they need to be suspended and installed on the roof of each floor of the building using a hanger. The traditional hanger includes hanging wires, expansion bolts and supporting steel. The structure is simple and the construction is convenient. However, after installation, it does not have the purpose of shock absorption and buffering of the air duct and silent and wear-resistant installation. The existing public technology number CN218178099U proposes a central air-conditioning air duct hanger. The device can be installed without disassembling the hanging chain. By directly disassembling the hanger, the suspension state of the hanger can be quickly released, or the hanging state of the hanger can be quickly formed. The disassembly and assembly are simple, fast and convenient, which improves the efficiency of air duct diversion, cleaning, maintenance or replacement. Regarding the above-mentioned related technologies, the utility model inventor believes that the following defects still exist: after installation, the hanger in the comparative literature is difficult to clamp and limit air ducts of different models, and the air duct still does not have the purpose of shock absorption and buffering and silent and wear-resistant installation after installation. In addition, the thermal insulation cotton wrapped around the outside of the air duct is easily worn, resulting in a decrease in the air conditioning cooling effect. In view of this, we propose a building central air conditioning duct hanger. Utility Model Content

[0003] 1. Technical issues to be solved

[0004] The purpose of the present application is to provide a building central air-conditioning duct hanger, which solves the technical problems that the hangers in the comparative literature in the above-mentioned background technology are difficult to clamp and limit air ducts of different models after installation, and the air ducts still do not have the purpose of shock absorption and buffering and silent and wear-resistant installation after installation, and the heat insulation cotton wrapped around the air duct is easily worn out, resulting in a decrease in the air conditioning refrigeration effect. The application realizes a rectangular frame structure connected by two clamping beams and two buffers, and the installation height of the buffer can be adjusted by loosening the lock nut to make the screw slide along the strip groove. The distance between the two buffers can be adjusted by rotating the adjusting threaded rod, and then different types of air ducts can be clamped. The ceiling seat is installed on the top of the building wall by expansion bolts to realize the suspension installation of the air duct. The buffer realizes the installation of the air duct with buffering and shock absorption effect, and a buffer pad is inserted and installed on the four inner walls of the rectangular frame structure, so that the air duct can achieve the technical effect of wear-resistant and silent installation effect.

[0005] 2. Technical solution

[0006] The technical solution of the present application provides a building central air-conditioning duct hanger, comprising: a buffer, the number of the buffers is two, the buffer comprises a bottom column and an upper column, the ends of the bottom column and the upper column that are away from each other are provided with a guide groove, a piston rod is fixedly provided at the bottom end of the upper column, the piston rod is slidably sleeved with the bottom column, the bottom column and the upper column are respectively slidably sleeved with a clamping beam through the guide groove, the two clamping beams are arranged in parallel, the clamping beam and the buffer are connected to form a rectangular structure, and a buffer pad is inserted and installed at the inner wall of the rectangular structure, a ceiling seat is installed on the upper column, a U-shaped seat is fixedly provided on the bottom surface of the bottom column and the upper surface of the upper column, the two buffers are threadedly installed with two threaded rods through the U-shaped seat, and are respectively arranged at the bottom of the bottom column and the upper part of the upper column.

[0007] By adopting the above technical scheme, when the central air-conditioning duct of a building is suspended and installed, the duct can be clamped by a rectangular frame structure formed by connecting two clamping beams and two buffers, and then the suspended installation is realized by installing the ceiling seat at the top of the building wall. Each buffer is composed of a bottom column and an upper column. The upper column is slidably installed along the bottom column by a piston rod, so as to realize the buffering and shock-absorbing effect. The bottom column and the upper column can be slidably installed along the two clamping beams through the guide grooves respectively, and the two clamping beams elastically slide along the bottom column by the piston rod, and the two threaded rods can be adjusted to realize the rectangular frame structure formed by connecting two clamping beams and two buffers to adjust the size of the rectangular frame, so as to clamp ducts of different types, and a buffer pad is inserted and installed on the four inner walls of the rectangular frame structure to realize the wear-resistant and silent effects.

[0008] Optionally, an inner cavity is opened in the bottom column, a spring is fixedly provided between the bottom end of the inner cavity and the bottom end of the piston rod, and plug-in grooves are opened on the sides of the bottom column and the upper column, and a buffer pad is inserted and installed in the plug-in grooves.

[0009] By adopting the above technical solution, the piston rod slides along the inner cavity, and the air pressure in the inner cavity changes, cooperating with the spring to form a buffering and shock-absorbing effect. The buffer pad can be slidably installed along the plug-in grooves opened on the bottom column and the upper column.

[0010] Optionally, a convex sliding groove is provided on the upper and lower surfaces of the clamping beam, and the clamping beam is plugged into the installation buffer pad through the convex sliding groove, and the clamping beam is slidably plugged into the guide groove.

[0011] By adopting the above technical solution, the clamping beam can be installed by inserting into the guide grooves provided in the bottom column and the upper column, and under the action of the spring, the two clamping beams can elastically clamp the air duct.

[0012] Optionally, the buffer pad is a rubber pad, and the cross-section of the buffer pad is an I-shaped structure.

[0013] By adopting the above technical solution, the buffer pad is closely attached to the air duct, thereby achieving wear-resistant and silent effects.

[0014] Optionally, two expansion bolts are threadedly installed on the ceiling mount, and the ceiling mount is installed on the top of the building wall through the expansion bolts. Two parallel screws are threadedly installed on the ceiling mount, and a strip through groove is opened on the upper column. The screw is slidably arranged in the strip through groove. Lock nuts are threadedly sleeved on the screws, and the lock nuts rotate along the screws and press the surface of the ceiling mount.

[0015] By adopting the above technical solution, the ceiling mount is installed on the top surface of the building wall through expansion bolts, and the bottom end of the ceiling mount is inserted into the outside of the upper column. By loosening the lock nut, the screw rod slides along the strip groove, and the installation height of the buffer can be adjusted, thereby adjusting the installation height of the air duct.

[0016] 3. Beneficial effects

[0017] One or more technical solutions provided in the technical solution of the present application have at least the following technical effects or advantages: a rectangular frame structure is connected by two clamping beams and two buffers, and the installation height of the buffer can be adjusted by loosening the lock nut to make the screw slide along the strip-shaped through groove, and the spacing between the two buffers can be adjusted by rotating the adjusting threaded rod, so that air ducts of different types can be clamped, and the ceiling mount is installed on the top of the building wall by means of expansion bolts to realize the suspension installation of the air duct, and the buffer realizes the installation of the air duct with buffering and shock-absorbing effect, and a buffer pad is inserted and installed on each of the four inner walls of the rectangular frame structure, so that the air duct can achieve wear-resistant and silent installation effect. BRIEF DESCRIPTION OF THE DRAWINGS

[0018] Figure 1 This is a schematic diagram of the overall structure of a building central air conditioning duct hanger disclosed in a preferred embodiment of the present application;

[0019] Figure 2 This is a schematic diagram of the overall exploded structure of a building central air conditioning duct hanger disclosed in a preferred embodiment of the present application;

[0020] Figure 3 A preferred embodiment of the present application discloses a central air conditioning duct hanger for a building Figure 2 The enlarged structural diagram at A in the middle;

[0021] Explanation of the numbers in the figure: 1. Buffer; 11. Bottom column; 111. Inner cavity; 12. Upper column; 121. Bar-shaped through groove; 13. Piston rod; 14. Plug-in groove; 15. Guide groove; 16. Spring; 17. U-shaped seat; 18. Threaded rod; 2. Buffer pad; 3. Clamping beam; 31. Convex slide groove; 4. Ceiling seat; 41. Expansion bolt; 42. Screw rod; 43. Lock nut. DETAILED DESCRIPTION

[0022] The present application is further described in detail below in conjunction with the accompanying drawings.

[0023] Reference Figures 1 to 3 The embodiment of the present application provides a building central air conditioning duct hanger, comprising: a buffer 1, the number of buffers 1 is two, the buffer 1 includes a bottom column 11 and an upper column 12, the ends of the bottom column 11 and the upper column 12 away from each other are provided with a guide groove 15, a piston rod 13 is fixedly provided at the bottom end of the upper column 12, the piston rod 13 is slidably sleeved with the bottom column 11, the bottom column 11 and the upper column 12 are respectively slidably sleeved with a clamping beam 3 through the guide groove 15, the two clamping beams 3 are arranged in parallel, the clamping beam 3 and the buffer 1 are connected to form a rectangular structure, and a buffer pad 2 is plugged and installed at the inner wall of the rectangular structure, a ceiling seat 4 is installed on the upper column 12, a U-shaped seat 17 is fixedly provided on the bottom surface of the bottom column 11 and the upper surface of the upper column 12, two threaded rods 18 are threadedly installed on the two buffers 1 through the U-shaped seat 17, and are respectively arranged at the bottom of the bottom column 11 and the upper column 1 2 upper position, when the central air-conditioning duct of the building is suspended and installed, the duct can be clamped by a rectangular frame structure formed by connecting two clamping beams 3 and two buffers 1, and then the ceiling seat 4 is limited to install the top of the building wall to realize the suspension installation. Each buffer 1 is composed of a bottom column 11 and an upper column 12. The upper column 12 is slidably installed along the bottom column 11 through a piston rod 13, which can achieve a buffering and shock-absorbing effect. The bottom column 11 and the upper column 12 can be slidably installed along the two clamping beams 3 through a guide groove 15 respectively, and the two clamping beams 3 elastically slide along the bottom column 11 through the piston rod 13, and the two threaded rods 18 can be adjusted to realize the rectangular frame structure formed by connecting two clamping beams 3 and two buffers 1. The size of the rectangular frame can be adjusted, so as to clamp ducts of different types, and a buffer pad 2 is inserted and installed on the four inner walls of the rectangular frame structure to achieve wear-resistant and silent effects.

[0024] Reference Figure 2 and Figure 3 An inner cavity 111 is opened in the bottom column 11, and a spring 16 is fixed between the bottom end of the inner cavity 111 and the bottom end of the piston rod 13. Insertion grooves 14 are opened on the sides of the bottom column 11 and the upper column 12. The buffer pad 2 is inserted and installed in the insertion groove 14. The piston rod 13 slides along the inner cavity 111. The air pressure in the inner cavity 111 changes and the spring 16 form a buffering and shock-absorbing effect. The buffer pad 2 can be slidably installed along the insertion grooves 14 opened in the bottom column 11 and the upper column 12.

[0025] Reference Figure 2 and Figure 3 A convex groove 31 is provided on the upper and lower surfaces of the clamping beam 3. The clamping beam 3 is inserted and installed with the buffer pad 2 through a convex groove 31. The clamping beam 3 is slidably inserted in the guide groove 15. The clamping beam 3 can be inserted and installed in the guide groove 15 opened by the bottom column 11 and the upper column 12. Under the action of the spring 16, the two clamping beams 3 can elastically clamp the air duct.

[0026] Reference Figure 2and Figure 3 The buffer pad 2 is a rubber pad, and the cross section of the buffer pad 2 is an I-shaped structure. The buffer pad 2 is closely attached to the air duct, thereby achieving wear resistance and quietness effects.

[0027] Reference Figure 1 and Figure 2 Two expansion bolts 41 are threadedly installed on the ceiling seat 4, and the ceiling seat 4 is installed on the top of the building wall through the expansion bolts 41. Two parallel screws 42 are threadedly installed on the ceiling seat 4. A strip through groove 121 is opened on the upper column 12. The screw 42 is slidably arranged in the strip through groove 121. A lock nut 43 is threadedly sleeved on the screw 42. The lock nut 43 rotates along the screw 42 and presses the surface of the ceiling seat 4. The ceiling seat 4 is installed on the top surface of the building wall through the expansion bolts 41. The bottom end of the ceiling seat 4 is inserted into the outside of the upper column 12. By loosening the lock nut 43, the screw 42 slides along the strip through groove 121, and the installation height of the buffer 1 can be adjusted, thereby adjusting the installation height of the air duct.

[0028] Working principle: When the central air-conditioning duct of a building is suspended and installed, the duct can be clamped by a rectangular frame structure formed by connecting two clamping beams 3 and two buffers 1, and then the duct can be suspended and installed at the top of the building wall through two expansion bolts 41 through the ceiling seat 4. By loosening the lock nut 43, the screw rod 42 slides along the strip groove 121, and the installation height of the buffer 1 can be adjusted, and then the installation height of the duct can be adjusted. Each buffer 1 consists of a bottom column 11 and an upper column 12. The upper column 12 is installed by sliding along the bottom column 11 through the piston rod 13, and the inner cavity The air pressure changes in 111 cooperate with the spring 16 to form a buffering and shock-absorbing effect, which can achieve a buffering and shock-absorbing effect. The bottom column 11 and the upper column 12 can be slidably installed along the two clamping beams 3 through the guide groove 15 respectively, and the two clamping beams 3 elastically slide along the bottom column 11 through the piston rod 13, and the two threaded rods 18 are adjusted to achieve a rectangular frame structure formed by connecting the two clamping beams 3 and the two buffers 1 to adjust the size of the rectangular frame, so as to clamp different types of air ducts for processing, and a buffer pad 2 is inserted and installed on the four inner walls of the rectangular frame structure to achieve wear-resistant and silent effects.

Claims

1. A building central air conditioning duct hanger, characterized in that: The invention comprises: a buffer (1), wherein the number of the buffers (1) is two, the buffer (1) comprises a bottom column (11) and an upper column (12), the ends of the bottom column (11) and the upper column (12) being separated from each other are each provided with a guide groove (15), a piston rod (13) is fixedly provided at the bottom end of the upper column (12), the piston rod (13) is slidably sleeved with the bottom column (11), the bottom column (11) and the upper column (12) are respectively slidably sleeved with a clamping beam (3) through the guide groove (15), and the two clamping beams (3) are connected to each other. ) are arranged in parallel, the clamping beam (3) and the buffer (1) are connected to form a rectangular structure, and a buffer pad (2) is inserted and installed on the inner wall of the rectangular structure, and a ceiling seat (4) is installed on each of the upper columns (12), and a U-shaped seat (17) is fixedly provided on the bottom surface of the bottom column (11) and the upper surface of the upper column (12), and two threaded rods (18) are threadedly installed on the two buffers (1) through the U-shaped seat (17), and are respectively arranged at the bottom of the bottom column (11) and the upper part of the upper column (12).

2. A building central air conditioning duct hanger according to claim 1, characterized in that: An inner cavity (111) is provided in the bottom column (11), a spring (16) is fixedly provided between the bottom end of the inner cavity (111) and the bottom end of the piston rod (13), and plug-in grooves (14) are provided on the sides of the bottom column (11) and the upper column (12), and a buffer pad (2) is inserted and installed in the plug-in groove (14).

3. A building central air conditioning duct hanger according to claim 2, characterized in that: The upper and lower surfaces of the clamping beam (3) are each provided with a convex sliding groove (31), the clamping beam (3) is plugged into the mounting buffer pad (2) through the convex sliding groove (31), and the clamping beam (3) is slidably plugged into the guide groove (15).

4. A building central air conditioning duct hanger according to claim 1, characterized in that: The buffer pad (2) is a rubber pad, and the cross section of the buffer pad (2) is an I-shaped structure.

5. The central air conditioning duct hanger for a building according to claim 1, characterized in that: Two expansion bolts (41) are threadedly mounted on the ceiling seat (4), and the ceiling seat (4) is ceiling-mounted on the top of a building wall through the expansion bolts (41). Two parallel screw rods (42) are threadedly mounted on the ceiling seat (4), and a strip-shaped through groove (121) is provided on the upper column (12). The screw rod (42) is slidably arranged in the strip-shaped through groove (121). Lock nuts (43) are threadedly sleeved on the screw rods (42), and the lock nuts (43) rotate along the screw rods (42) and press the surface of the ceiling seat (4).