An anchor beam raft structure for slope reinforcement and vegetation restoration

By adopting an anchor beam-type raft structure on the slope, combined with the vegetation restoration system and drainage pipe, the problem of difficult to balance slope reinforcement and vegetation restoration in the existing technology is solved, and better protective effects and vegetation restoration capabilities are achieved.

CN222701012UActive Publication Date: 2025-04-01陕西省交通规划设计研究院有限公司
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420986769.4
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-05-08
Publication Date
2025-04-01
Estimated Expiration
2034-05-08

AI Technical Summary

Technical Problem

The existing slope protection measures are difficult to take into account both reinforcement and vegetation restoration. Skeleton protection has good effect on vegetation restoration but poor stability. Although closed protection has good stability, it cannot undergo later vegetation restoration.

Method used

The anchor beam-type raft structure is adopted, including raft plates, vegetation restoration system, frame beams, frame longitudinal beams, anchor rods and drain pipes. The raft plate is subject to loose soil pressure on the slope, and the anchor rods transmit the load to the slope. The vegetation restoration system realizes grass planting and greening in the block, and the drain pipe reduces hydrostatic pressure.

Benefits of technology

The double protection effect of the slope is achieved, which not only strengthens the stability of the slope, but also facilitates the recovery of later vegetation. It has a low cost and is easy to carry out construction.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222701012U_ABST
    Figure CN222701012U_ABST
Patent Text Reader

Abstract

The present application discloses an anchor beam raft structure for slope reinforcement and vegetation restoration. The raft is arranged on the slope surface; a plurality of frame cross beams and a plurality of frame longitudinal beams are arranged on the side of the raft away from the slope, and the plurality of frame cross beams are connected with the plurality of frame longitudinal beams to form a plurality of grids; the raft, the frame cross beams and the frame longitudinal beams are all cast-in-place concrete structures; the raft is provided with a plurality of first anchor holes and a plurality of drainage holes, and a plurality of second anchor holes corresponding to the plurality of first anchor holes are arranged at the connection between the frame cross beam and the frame longitudinal beam; one end of the plurality of anchor rods passes through the second anchor hole and the first anchor hole, and extends into the slope; the vegetation restoration system is arranged in each grid; a plurality of frame cross beams and a plurality of frame longitudinal beams are provided with drainage grooves on the side away from the raft; one end of the plurality of drainage pipes passes through the vegetation restoration system and the drainage hole, and extends into the slope. Therefore, the anchor beam raft structure has a better reinforcement and protection effect, is convenient for vegetation restoration on the slope surface, and is easy to construct.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present application relates to the technical field of protection, reinforcement, management and vegetation restoration, and in particular to an anchor beam raft structure for slope reinforcement and vegetation restoration. Background Art

[0002] Slope protection refers to the use of a series of engineering measures to protect the stability of soil or rock slopes to prevent geological disasters such as landslides and collapses caused by natural factors such as rainfall and earthquakes or human factors such as excavation and loading.

[0003] The existing slope protection measures mainly include skeleton protection and closed protection. Skeleton protection mainly includes arch skeleton slope protection, diamond skeleton slope protection, frame beam slope protection and window hole retaining wall. This type of protection structure has the advantages of small masonry protection area, large proportion of vegetation greening, and strong ability of vegetation recovery in the later stage. Its disadvantage is that the soft rock and soil in the skeleton or frame is prone to slippage, and the slope stability effect is poor. Closed protection mainly includes solid retaining wall, soil nail wall, retaining wall, shotcrete, etc. Although this type of protection structure has a good protection effect, it can effectively stabilize the slope for a long time. However, closed protection performs masonry protection on the entire slope surface, isolates the space for vegetation recovery, and cannot carry out later greening of the slope, resulting in extremely poor environmental protection and landscape effects. Utility Model Content

[0004] The embodiment of the present application solves the technical problem that the skeleton-type protection and closed-type protection in the prior art can only achieve good effects in slope reinforcement or vegetation restoration, but it is difficult to achieve the dual protection effects of slope reinforcement and vegetation restoration by providing an anchor beam raft structure for slope reinforcement and vegetation restoration.

[0005] The embodiment of the present application provides an anchor beam raft structure for slope reinforcement and vegetation restoration, comprising a raft, a vegetation restoration system, a plurality of frame cross beams, a plurality of frame longitudinal beams, a plurality of anchors and a plurality of drainage pipes; the raft is arranged on the slope surface; a plurality of the frame cross beams and a plurality of the frame longitudinal beams are all arranged on the side of the raft away from the slope, a plurality of the frame cross beams are arranged at intervals along the height direction of the raft, a plurality of the frame longitudinal beams are arranged at intervals along the length direction of the raft, a plurality of the frame cross beams are connected to a plurality of the frame longitudinal beams to form a plurality of barriers; the raft, the frame cross beams and the frame longitudinal beams are all It is a cast-in-place concrete structure; the raft is provided with a plurality of first anchor holes and a plurality of drainage holes, and a plurality of second anchor holes corresponding to the plurality of first anchor holes are provided at the connection between the frame cross beam and the frame longitudinal beam; one end of the plurality of anchor rods passes through the second anchor holes and the first anchor holes and extends into the slope; the vegetation restoration system is arranged in each of the blocks; a plurality of the frame cross beams and the plurality of the frame longitudinal beams are provided with drainage grooves on one side away from the raft; one end of the plurality of drainage pipes passes through the vegetation restoration system and the drainage holes and extends into the slope, and the drainage pipes are configured to flow water into the drainage grooves.

[0006] In a possible implementation, the vegetation restoration system includes a vegetation bag disposed in the barrier; one end of a plurality of drainage pipes passes through the vegetation bag and the drainage hole and extends into the slope.

[0007] In a possible implementation, at least two layers of steel mesh are arranged in the raft slab; the at least two layers of steel mesh are arranged at intervals along the thickness direction of the raft slab, and the angles between the at least two layers of steel mesh and the horizontal plane and the angle between the slope surface and the horizontal plane are the same.

[0008] In a possible implementation, a filter layer is provided at the water inlet of the drain pipe.

[0009] In a possible implementation, the length of the anchor rods is 8000-15000 mm.

[0010] In a possible implementation, the anchor rod is a Grade III threaded steel bar.

[0011] In a possible implementation, the distance between two adjacent frame longitudinal beams and the distance between two adjacent frame transverse beams are both 2.5-3 m.

[0012] In a possible implementation, one end of the drainage pipe extends out of the vegetation restoration system by no less than 50 mm; the other end of the drainage pipe extends into the slope by no less than 50 mm.

[0013] One or more technical solutions provided in the embodiments of the present application have at least the following technical effects:

[0014] The anchor beam raft structure for slope reinforcement and vegetation restoration provided by the embodiment of the present application includes a raft, a vegetation restoration system, a plurality of frame beams, a plurality of frame longitudinal beams, a plurality of anchors and a plurality of drainage pipes. The raft of the embodiment of the present application bears all the loose soil pressure of the slope and transfers it to the frame beams and the frame longitudinal beams, and finally the anchors at the connection between the frame beams and the frame longitudinal beams transfer all the loads to the inside of the slope. The present application utilizes the strength of the deep soil of the slope to stabilize the shallow soil of the slope. The vegetation restoration system of the present application is placed in the grid to achieve grass planting and greening. The drainage pipe of the present application can reduce and release the hydrostatic pressure and dynamic pressure of the slope, improve the stability of the slope, and the drainage trough drains the water. Therefore, the anchor beam raft structure for slope reinforcement and vegetation restoration has a better reinforcement and protection effect, is convenient for the later vegetation restoration of the slope surface, has a low cost, and is easy to construct. BRIEF DESCRIPTION OF THE DRAWINGS

[0015] In order to more clearly illustrate the technical solutions in the embodiments of the present application, the drawings required for use in the description of the embodiments of the present application will be briefly introduced below. Obviously, the drawings described below are some embodiments of the present application. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying any creative work.

[0016] Figure 1 A schematic structural diagram of an anchor beam raft structure for slope reinforcement and vegetation restoration provided in an embodiment of the present application;

[0017] Figure 2 A normal projection diagram of an anchor beam raft structure for slope reinforcement and vegetation restoration provided in an embodiment of the present application;

[0018] Figure 3 A schematic diagram of the structure of the frame cross beam and frame longitudinal beam provided in the embodiment of the present application;

[0019] Figure 4 A cross-sectional view of a frame longitudinal beam provided in an embodiment of the present application;

[0020] Figure 5 Structural diagram of the arrangement of drain pipes and anchor rods provided in the embodiment of the present application

[0021] Figure 6 A schematic diagram of the structure of a drain pipe provided in an embodiment of the present application;

[0022] Figure 7 A cross-sectional view of a frame beam provided in an embodiment of the present application;

[0023] Figure 8A cross-sectional view of a frame longitudinal beam provided in an embodiment of the present application;

[0024] Fig. 9 A schematic diagram of the structure of the anchor rod provided in an embodiment of the present application.

[0025] Icons: 1-raft; 11-steel mesh; 2-vegetation restoration system; 21-vegetation bag; 3-frame crossbeam; 4-frame longitudinal beam; 5-anchor rod; 6-sluice pipe; 7-drainage trough; 8-block. DETAILED DESCRIPTION

[0026] The following will be combined with the drawings in the embodiments of the present application to clearly and completely describe the technical solutions in the embodiments of the present application. Obviously, the described embodiments are part of the embodiments of the present application, not all of the embodiments. Based on the embodiments in the present application, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of this application.

[0027] In the description of the embodiments of the present application, it should be noted that the terms "center", "up", "down", "left", "right", "vertical", "horizontal", "inside", "outside", etc. indicate positions or positional relationships based on the positions or positional relationships shown in the accompanying drawings, which are only for the convenience of describing the embodiments of the present application and simplifying the description, and do not indicate or imply that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore cannot be understood as a limitation on the present application. The terms "first", "second", and "third" are used for descriptive purposes only and cannot be understood as indicating or implying relative importance. In addition, the terms "installed", "connected", and "connected" should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection, or it can be indirectly connected through an intermediate medium, or it can be a connection between the two elements. For those of ordinary skill in the art, the specific meanings of the above terms in the embodiments of the present application can be understood according to the specific circumstances.

[0028] The embodiment of the present application provides an anchor beam raft structure for slope reinforcement and vegetation restoration, such as Figures 1 to 9As shown. The anchor beam type raft structure for slope reinforcement and vegetation restoration includes a raft 1, a vegetation restoration system 2, a plurality of frame cross beams 3, a plurality of frame longitudinal beams 4, a plurality of anchor rods 5 and a plurality of drainage pipes 6. The raft 1 is arranged on the slope surface. The plurality of frame cross beams 3 and the plurality of frame longitudinal beams 4 are arranged on the side of the raft 1 away from the slope, the plurality of frame cross beams 3 are arranged at intervals along the height direction of the raft 1, the plurality of frame longitudinal beams 4 are arranged at intervals along the length direction of the raft 1, and the plurality of frame cross beams 3 are connected with the plurality of frame longitudinal beams 4 to form a plurality of grids 8. The raft 1, the frame cross beams 3 and the frame longitudinal beams 4 are all cast-in-place concrete structures. The raft 1 is provided with a plurality of first anchor holes and a plurality of drainage holes, and the connection between the frame cross beams 3 and the frame longitudinal beams 4 is provided with a plurality of second anchor holes corresponding to the plurality of first anchor holes. One end of the plurality of anchor rods 5 passes through the second anchor hole and the first anchor hole and extends into the slope. The vegetation restoration system 2 is arranged in each grid 8. A drainage ditch 7 is provided on one side of the plurality of frame cross beams 3 and the plurality of frame longitudinal beams 4 away from the raft 1. One end of the plurality of drainage pipes 6 passes through the vegetation restoration system 2 and the drainage hole and extends into the slope, and the drainage pipes 6 are configured to flow water into the drainage ditch 7. Specifically, the drainage pipes 6 of the embodiment of the present application are arranged obliquely.

[0029] Furthermore, the raft 1, the frame cross beam 3 and the frame longitudinal beam 4 are all cast-in-place C30 cement concrete. The drain pipe 6 is a PE pipe.

[0030] It should be noted that the raft 1 of the embodiment of the present application bears all the loose soil pressure of the slope, and transfers it to the frame crossbeam 3 and the frame longitudinal beam 4, and finally the anchor 5 at the connection between the frame crossbeam 3 and the frame longitudinal beam 4 transfers all the loads to the inside of the slope. The present application utilizes the strength of the deep soil of the slope to stabilize the shallow soil of the slope. The vegetation restoration system 2 of the present application is placed in the block 8 to achieve grass planting and greening. The drain pipe 6 of the present application can reduce and release the static water pressure and dynamic water pressure of the slope, improve the stability of the slope, and the drainage trough 7 drains the water. Therefore, the anchor beam type raft structure used for slope reinforcement and vegetation restoration has a better reinforcement and protection effect, is convenient for the later vegetation restoration of the slope surface, has a low cost, and is easy to construct.

[0031] In the embodiment of the present application, the vegetation restoration system 2 includes a vegetation bag 21 disposed in the barrier 8. One end of a plurality of drainage pipes 6 passes through the vegetation bag 21 and the drainage hole and extends into the slope. The filling thickness of the vegetation bag 21 of the present application is 30 cm.

[0032] In the embodiment of the present application, at least two layers of steel mesh 11 are arranged in the raft 1. The at least two layers of steel mesh 11 are arranged at intervals along the thickness direction of the raft 1, and the angles between the at least two layers of steel mesh 11 and the horizontal plane are the same as the angles between the slope surface and the horizontal plane.

[0033] In the embodiment of the present application, a filter layer is provided at the water inlet of the drain pipe 6. The filter layer is a permeable geotextile.

[0034] In the embodiments of the present application, the length of the anchor rod 5 is 8000-15000 mm.

[0035] In the embodiment of the present application, the anchor rod 5 is a grade III threaded steel bar.

[0036] In the embodiment of the present application, the distance between two adjacent frame longitudinal beams 4 and two adjacent frame cross beams 3 is 2.5-3m.

[0037] In the embodiment of the present application, one end of the drainage pipe 6 extends out of the vegetation restoration system 2 by no less than 50 mm, and the other end of the drainage pipe 6 extends into the slope by no less than 50 mm.

[0038] It should be noted that during the construction, the slope surface is cleaned, the steel mesh 11 and the drain pipe 6 of the raft 1 are tied on site, and the first anchor hole is reserved, and then the concrete is poured and cured;

[0039] After the cement concrete strength of the raft 1 reaches the required level, the steel bars of the frame cross beam 3 and the frame longitudinal beam 4 are tied on site, and the second anchor hole is reserved before pouring concrete and curing;

[0040] Drill a hole at the reserved first anchor hole, the depth of which is not less than 50 cm greater than the length of the anchor rod 5;

[0041] The manufactured anchor rod 5 is passed through the second anchor hole and the first anchor hole and extended into the drilled hole, and M35 cement mortar is poured through a grouting pipe with a grouting pressure of 0.6-1.2 MPa;

[0042] After the cement mortar solidifies and shrinks, fill the hole with grout;

[0043] The vegetation restoration system 2 is placed in the block 8 formed by the frame cross beam 3 and the frame longitudinal beam 4 to restore the vegetation and green the slope surface.

[0044] The various embodiments in this specification are described in a progressive manner, and the same or similar parts between the various embodiments can be referenced to each other. Each embodiment focuses on the differences from other embodiments.

[0045] The above embodiments are only used to illustrate the technical solutions of the present application, rather than to limit the present application. Although the present application has been described in detail with reference to the aforementioned embodiments, a person of ordinary skill in the art should understand that the technical solutions described in the aforementioned embodiments may still be modified, or some or all of the technical features thereof may be replaced by equivalents. However, these modifications or replacements do not cause the essence of the corresponding technical solutions to deviate from the scope of the technical solutions of the present application.

Claims

1. An anchor beam raft structure for slope reinforcement and vegetation restoration, characterized in that: It comprises a raft (1), a vegetation restoration system (2), a plurality of frame cross beams (3), a plurality of frame longitudinal beams (4), a plurality of anchor rods (5) and a plurality of drainage pipes (6); The raft (1) is arranged on the slope surface; The plurality of frame cross beams (3) and the plurality of frame longitudinal beams (4) are both arranged on a side of the raft (1) away from the slope, the plurality of frame cross beams (3) are arranged at intervals along the height direction of the raft (1), the plurality of frame longitudinal beams (4) are arranged at intervals along the length direction of the raft (1), and the plurality of frame cross beams (3) are connected to the plurality of frame longitudinal beams (4) to form a plurality of blocks (8); The raft slab (1), the frame cross beam (3) and the frame longitudinal beam (4) are all cast-in-place concrete structures; The raft (1) is provided with a plurality of first anchor holes and a plurality of drainage holes, and a plurality of second anchor holes corresponding to the plurality of first anchor holes are provided at the connection between the frame cross beam (3) and the frame longitudinal beam (4); One end of each of the plurality of anchor rods (5) passes through the second anchor hole and the first anchor hole and extends into the slope; The vegetation restoration system (2) is arranged in each of the barriers (8); A drainage groove (7) is provided on one side of the plurality of frame cross beams (3) and the plurality of frame longitudinal beams (4) away from the raft (1); One end of the plurality of drainage pipes (6) passes through the vegetation restoration system (2), the drainage hole, and extends into the slope, and the drainage pipes (6) are configured to flow water into the drainage trough (7).

2. The anchor beam raft structure for slope reinforcement and vegetation restoration according to claim 1, characterized in that: The vegetation restoration system (2) comprises a vegetation bag (21) arranged in the barrier (8); One end of the plurality of drainage pipes (6) passes through the vegetation bag (21), the drainage hole, and extends into the slope.

3. The anchor beam raft structure for slope reinforcement and vegetation restoration according to claim 1, characterized in that: At least two layers of steel mesh (11) are arranged in the raft (1); At least two layers of the steel mesh (11) are arranged at intervals along the thickness direction of the raft (1), and the angles between the at least two layers of the steel mesh (11) and the horizontal plane and the angles between the slope surface and the horizontal plane are the same.

4. The anchor beam raft structure for slope reinforcement and vegetation restoration according to claim 1, characterized in that: The water inlet of the drain pipe (6) is provided with a reverse filter layer.

5. The anchor beam raft structure for slope reinforcement and vegetation restoration according to claim 1, characterized in that: The length of the anchor rods (5) is 8000-15000 mm.

6. The anchor beam raft structure for slope reinforcement and vegetation restoration according to claim 5, characterized in that: The anchor rod (5) is a grade III threaded steel bar.

7. The anchor beam raft structure for slope reinforcement and vegetation restoration according to claim 1, characterized in that: The distance between two adjacent frame longitudinal beams (4) and two adjacent frame transverse beams (3) is 2.5-3 m.

8. The anchor beam raft structure for slope reinforcement and vegetation restoration according to claim 1, characterized in that: The length of one end of the drainage pipe (6) extending out of the vegetation restoration system (2) is not less than 50 mm; The other end of the drain pipe (6) extends into the slope by a length of not less than 50 mm.