A dust suppression guardrail structure for the periphery of a construction site

By designing a reasonable structure and waterway layout of the peripheral dust reduction railings on the construction site, the existing dust removal devices have been solved, and the stability and recyclability of the structure have been achieved, while reducing waste of water resources.

CN222701683UActive Publication Date: 2025-04-01HEBEI XIONGAN WEIJIESI ENVIRONMENTAL PROTECTION ENG CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202421325676.3
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-06-12
Publication Date
2025-04-01
Estimated Expiration
2034-06-12

AI Technical Summary

Technical Problem

The existing construction site dust removal device is installed on the enclosure, resulting in small limitations, poor stability and inability to recycle.

Method used

A dust-reducing railing structure on the periphery of the construction site is designed, including the railing structure and the dust-reducing water spray structure located at the upper end of the railing structure. A reasonable waterway structure layout and detachable connection method are adopted to ensure the stability and recyclability of the structure.

Benefits of technology

The structure has great limitations, strong stability, recyclable use, and the waterway structure is reasonable and easy to install, reducing the waste of construction water.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222701683U_ABST
    Figure CN222701683U_ABST
Patent Text Reader

Abstract

The utility model is a dust reduction guardrail structure for the periphery of a construction site, including a guardrail structure and a dust reduction water mist spray structure. A connecting section structure is arranged between the guardrail structure and another guardrail structure. The guardrail structure includes a guardrail body and a bottom connecting seat structure. The guardrail body is composed of a guardrail inner support frame, an inner support frame structure, and a sealing plate. The dust reduction water mist spray structure is provided with a top water mist pipeline inside each guardrail structure and a water mist manufacturing nozzle structure evenly arranged on the top water mist pipeline. The lower part of the top water mist pipeline is connected to a branch water supply pipeline arranged in the guardrail structure, and a branch water supply node is connected to the main water supply pipeline structure. Beneficial effects of the utility model: the dust reduction guardrail structure for the periphery of the construction site has the advantages of being very limited, having strong stability, and being recyclable. The waterway structure of the structure is reasonably laid out, easy to install, and the construction water used at the construction site reduces the waste of water resources.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to an injection mold, in particular to a dust reduction guardrail structure at the periphery of a construction site. Background Art

[0002] Dust pollution caused by construction refers to the pollution of the atmosphere caused by dust particles generated during production activities such as house construction, road and pipeline construction, house demolition, material transportation, material stacking, road cleaning, and exposed mud. Dust pollution has a serious impact on the lives of residents in residential areas and other places with a large population of surrounding people. In order to prevent dust pollution and protect and improve the quality of the atmospheric environment, effective measures need to be taken to minimize and control the adverse effects of dust generated by construction on the environment.

[0003] However, the existing dust removal devices at construction sites are all installed with water pipes and spray heads on the fence, which makes them very limited, poor in stability, and cannot be used next time. To this end, we propose a dust reduction fence structure for the periphery of the construction site. Utility Model Content

[0004] The utility model aims to provide a dust reduction fence structure at the periphery of a construction site, solving the problem that a spray head is installed on the dust removal structure of the fence; the limitation is very small, the stability is poor, and the problem that the structure cannot be used next time is solved.

[0005] The technical solution adopted by the utility model to solve its technical problems is: a dust reduction guardrail structure at the periphery of a construction site, comprising a guardrail structure and a dust reduction water mist spraying structure arranged at the upper end of the guardrail structure, a connecting section structure is arranged between the guardrail structure and another guardrail structure, the guardrail structure comprises a guardrail body and a bottom connecting seat structure arranged at the lower part of the guardrail body, the guardrail body is composed of a guardrail inner support frame, an inner support frame structure arranged in the guardrail inner support frame, and a sealing plate arranged outside the guardrail inner support frame, the dust reduction water mist spraying structure is provided with a top water mist pipeline inside each guardrail structure and a water mist manufacturing nozzle structure evenly distributed on the top water mist pipeline, the lower part of the top water mist pipeline is connected to a branch water supply pipeline arranged in the guardrail structure, the two connected branch water supply pipelines are connected to a branch water supply node arranged between the connecting section structures, and the branch water supply node is connected to the main water supply pipeline structure.

[0006] The bottom connecting seat structure comprises a main seat body, a bottom clamping body arranged at the upper end of the middle part of the main seat body, and a foundation pile fixing hole arranged in the middle part of the main seat body.

[0007] The top water mist pipeline is arranged into two groups in the guardrail structure, one end of the two top water mist pipelines is connected to the double three-way pipe body, a plug is arranged at the other end of each top water mist pipeline, and an automatic flow controller is arranged in the top water mist pipeline.

[0008] A collecting partition groove is arranged at the lower part of the top water mist pipeline.

[0009] The total water supply pipeline structure comprises a main water supply pipeline connected to a construction site water reservoir provided with a multi-stage filtering structure, and a booster water pump arranged in the main water supply pipeline.

[0010] A shielding sleeve is also arranged on the upper part of the guardrail structure.

[0011] The beneficial effects of the utility model are as follows: the dust suppression guardrail structure at the periphery of the construction site has the advantages of very small limitations, strong stability, and recyclability; the water channel structure of the structure is reasonably laid out, easy to install, and the construction water used at the construction site can be used at the same time to reduce the waste of water resources.

[0012] The present invention will be described in more detail below with reference to the accompanying drawings and embodiments. BRIEF DESCRIPTION OF THE DRAWINGS

[0013] Figure 1 It is a schematic diagram of the structure of the utility model.

[0014] Figure 2 for Figure 1 Internal structure diagram.

[0015] Figure 3 for Figure 1 Top view of the .

[0016] Figure 4 It is a schematic diagram of the connection state of the utility model.

[0017] Figure 5 for Figure 4 Top view of the .

[0018] Figure 6 This is a state diagram of the waterway layout constructed for the utility model.

[0019] In the figure: 1. Support frame inside the guardrail, 2. Internal support frame structure, 3. Closing plate, 4. Top water mist pipeline, 5. Water mist manufacturing nozzle structure, 6. Branch water supply pipeline, 7. Branch water supply node, 8. Main water supply pipeline, 9. Booster pump, 10. Main seat body, 11. Bottom clamping body, 12. Foundation pile fixing hole, 13. Double three-way pipe body, 14. Plug, 15. Automatic flow controller, 16. Collecting partition groove, 17. Shielding sleeve, 18. Combined connector 19 Clamping connection groove, 20. Construction site water tank. DETAILED DESCRIPTION

[0020] The directions or positional relationships indicated by the terms "upper", "lower", "inner", "outer", "front end", "rear end", "two ends", "one end", "the other end" and the like in the application text are based on the directions or positional relationships shown in the drawings, and are only for the convenience of describing the present invention and simplifying the description, and do not indicate or imply that the devices or elements referred to must have a specific direction, be constructed and operate in a specific direction, and therefore cannot be understood as limiting the present invention. In addition, the terms "first" and "second" are used for descriptive purposes only, and cannot be understood as indicating or implying relative importance.

[0021] In the description of the present invention, it should be noted that, unless otherwise clearly specified and limited, the terms "installed", "provided with", "connected", etc. should be understood in a broad sense. For example, "connected" can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection, or it can be an indirect connection through an intermediate medium, or it can be the internal communication of two components. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.

[0022] Embodiment 1, as Figure 1-6 As shown, a dust reduction guardrail structure at the periphery of a construction site comprises a guardrail structure and a dust reduction water mist spray structure arranged at the upper end of the guardrail structure, a connecting section structure is arranged between the guardrail structure and another guardrail structure, the guardrail structure comprises a guardrail body and a bottom connecting seat structure arranged at the lower part of the guardrail body, the guardrail body is composed of a guardrail inner support frame 1, an inner support frame structure 2 arranged in the guardrail inner support frame, and a sealing plate 3 arranged outside the guardrail inner support frame, the dust reduction water mist spray structure is provided with a top water mist pipeline 4 inside each guardrail structure and a water mist manufacturing nozzle structure 5 evenly distributed on the top water mist pipeline, the lower part of the top water mist pipeline is connected to a branch water supply pipeline 6 arranged in the guardrail structure, the two connected branch water supply pipelines are connected to a branch water supply node 7 arranged between the connecting section structures, and the branch water supply node is connected to the main water supply pipeline structure. The main water supply pipeline structure includes a main water supply pipeline 8 connected to a construction site water reservoir 20 with a multi-stage filtering structure, and a booster pump 9 arranged in the main water supply pipeline. The connecting section structure includes a connecting body 18 and a clamping connection groove 19 arranged at the side end of the connecting body.

[0023] The bottom connecting seat structure comprises a main seat body 10, a bottom clamping body 11 arranged at the upper end of the middle part of the main seat body, and a foundation pile fixing hole 12 arranged in the middle part of the main seat body.

[0024] The top water mist pipeline is arranged in two groups in the guardrail structure, one end of the two top water mist pipelines is connected to the double three-way pipe body 13, a plug 14 is arranged at the other end of each top water mist pipeline, and an automatic flow controller 15 is arranged in the top water mist pipeline.

[0025] A collecting partition groove 16 is provided at the lower part of the top water mist pipeline.

[0026] A shielding sleeve 17 is also provided on the upper part of the guardrail structure.

[0027] The dust suppression guardrail structure at the periphery of the construction site has the advantages of very small limitations, strong stability, and recyclability. The water channel structure of the structure has a reasonable layout and is easy to install. At the same time, it can reduce the waste of water resources by using the construction water of the construction site.

[0028] The above embodiments are merely descriptions of the preferred implementation modes of the present invention, and are not intended to limit the scope of the present invention. Without departing from the design spirit of the present invention, various modifications and improvements made to the technical solutions of the present invention by ordinary engineering and technical personnel in the field shall fall within the protection scope determined by the claims of the present invention.

[0029] The parts not involved in the present invention are the same as the prior art or can be implemented by using the prior art.

Claims

1. A dust suppression guardrail structure around a construction site, characterized in that: It includes a guardrail structure and a dust reduction water mist spray structure arranged at the upper end of the guardrail structure. A connecting section structure is arranged between the guardrail structure and another guardrail structure. The guardrail structure includes a guardrail body and a bottom connecting seat structure arranged at the lower part of the guardrail body. The guardrail body is composed of a guardrail inner support frame, an inner support frame structure arranged in the guardrail inner support frame, and a sealing plate arranged outside the guardrail inner support frame. The dust reduction water mist spray structure is provided with a top water mist pipeline inside each guardrail structure and a water mist manufacturing nozzle structure evenly distributed on the top water mist pipeline. The lower part of the top water mist pipeline is connected to a branch water supply pipeline arranged in the guardrail structure, and the two connected branch water supply pipelines are connected to a branch water supply node arranged between the connecting section structures, and the branch water supply node is connected to the main water supply pipeline structure.

2. The dust suppression guardrail structure around the construction site as claimed in claim 1, characterized in that: The bottom connecting seat structure comprises a main seat body, a bottom clamping body arranged at the upper end of the middle part of the main seat body, and a foundation pile fixing hole arranged in the middle part of the main seat body.

3. The dust suppression guardrail structure around the construction site as claimed in claim 1, characterized in that: The top water mist pipeline is arranged in two groups in the guardrail structure, one end of the two top water mist pipelines is connected to the double three-way pipe body, a plug is arranged at the other end of each top water mist pipeline, and an automatic flow controller is arranged in the top water mist pipeline.

4. The dust suppression guardrail structure at the periphery of the construction site as claimed in claim 3, characterized in that: A collecting partition groove is arranged at the lower part of the top water mist pipeline.

5. The dust suppression guardrail structure at the periphery of a construction site as claimed in claim 1, characterized in that: The total water supply pipeline structure comprises a main water supply pipeline connected to a construction site water reservoir provided with a multi-stage filtering structure, and a booster water pump arranged in the main water supply pipeline.

6. The dust suppression guardrail structure around the construction site as claimed in claim 1, characterized in that: A shielding sleeve is also arranged on the upper part of the guardrail structure.