By designing intelligent control devices in the tunnel lighting system, combining LED light groups, camera devices and detectors, time-lapse brightness adjustment and energy saving are achieved, solving the problems of high energy consumption and unstable operation of the existing tunnel lighting system, and ensuring safe and reliable tunnel lighting.
Patent Information
- Application Number
- CN202420776449.6
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-04-16
- Publication Date
- 2025-04-08
- Estimated Expiration
- 2034-04-16
AI Technical Summary
The existing tunnel lighting system is uninterrupted in high-speed tunnels for a long time, resulting in high energy consumption and unstable operation of energy-saving devices, which poses safety hazards.
A high-energy-saving control device for tunnel lighting is designed, using LED light group, camera device, main controller, backup controller and pulse control lamp control circuit. Combined with a brightness detector, vehicle detector and LED driver with unpole dimming, intelligent control is carried out through the main control center computer to achieve time-lapse brightness adjustment and energy saving.
It realizes the maximum energy saving while tunnel lighting, significantly improves the energy saving effect, and ensures the stable and reliable operation of the system through redundant design, avoiding the safety hazards of lighting power outage.
Smart Images

Figure CN222736342U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to a high energy-saving control device for tunnel lighting, belonging to the field of tunnel lighting tools. Background Art
[0002] Tunnel lighting is an indispensable tunnel facility in high-speed tunnels. Tunnel lighting can improve the road conditions in the tunnel, improve the visual enjoyment in the tunnel, reduce driver fatigue, and help improve the tunnel's traffic capacity to ensure traffic safety. The cost of tunnel lighting is a considerable expense in the tunnel operating costs.
[0003] However, in actual tunnel operation, tunnel lighting is usually on 24 hours a day, regardless of whether there are vehicles passing through the tunnel. From a low-carbon and environmental protection perspective, this does not meet the requirements of energy conservation and emission reduction.
[0004] Generally, high-speed tunnel lighting often uses the tunnel lights to work in a long-lasting manner. According to our on-site investigation and review of relevant information, we found that there are very few tunnels equipped with relevant energy-saving devices. The main reasons are: first, the existing energy-saving lighting control equipment is unstable, and the controller often crashes or is damaged, which increases the maintenance workload; second, the crash or damage of the controller will cause the tunnel lighting to lose power and the tunnel will lose lighting, posing a safety hazard to the passage of vehicles; at the same time, the energy-saving effect of the existing lighting devices is poor.
[0005] That is, there is a need for a tunnel lighting device that can ensure the tunnel lighting effect while also having a high energy-saving effect. Utility Model Content
[0006] In view of this, the purpose of the utility model is to provide a high energy-saving control device for tunnel lighting, which can ensure the tunnel lighting effect while also having a high energy-saving effect; and can overcome the shortcomings of the prior art.
[0007] The purpose of this utility model is achieved through the following technical solutions:
[0008] The utility model discloses a high energy-saving control device for tunnel lighting, which comprises LED lamp groups and camera devices which are arranged in sections in the tunnel, a main controller, a backup controller and a pulse-controlled lamp control circuit of the LED lamp group and the camera device are arranged in the tunnel, the main controller, the backup controller and the pulse-controlled lamp control circuit are connected in parallel with each other, a light brightness detector, a vehicle detector and an LED driver for stepless dimming corresponding to the LED lamp group are arranged on each tunnel section, the light brightness detector and the vehicle detector are connected to a computer of a master control center through a data transmission device, and data of the computer of the master control center and the LED driver are exchanged.
[0009] The computer in the above-mentioned master control center is provided with LED light group brightness adjustment values corresponding to the tunnel section brightness interval values and the vehicle flow interval values.
[0010] The above-mentioned master control center computer controls the LED driver through RS communication protocol technology.
[0011] The aforementioned vehicle detector is a millimeter-wave radar, and the millimeter-wave radar and camera device are both connected to a radar-vision fusion edge computing unit.
[0012] Compared with the prior art, the beneficial effects of the utility model are:
[0013] 1. The utility model can detect the brightness of each section of the tunnel and the size of the vehicle flow through the light brightness detector and the vehicle detector, and obtain data. Then, the LED driver is controlled by the computer of the master control center to perform stepless dimming and adjust the brightness. In this way, it can be adjusted at any time to ensure the lighting effect of the LED lamp group while saving energy to the greatest extent. The energy-saving effect is significant. At the same time, the main controller, backup controller and pulse control are redundantly designed to overcome the problem of unreliable operation of the existing energy-saving controller, and achieve the purpose of both energy saving in the tunnel and stable and reliable operation.
[0014] 2. The computer in the main control center is equipped with LED light group brightness adjustment values corresponding to the tunnel section brightness interval values and the traffic flow interval values. In this way, the brightness of the LED light group can be adjusted according to the brightness measured by the brightness detector, and the brightness of the LED light group can be adjusted according to the traffic flow detected by the vehicle detector.
[0015] 3. The computer in the master control center regulates the LED driver through RS communication protocol technology, which can realize remote or local automatic control, making the tunnel lighting system more intelligent and energy-saving.
[0016] Other advantages, objectives and features of the present invention will be described in the following description to some extent, and will be apparent to those skilled in the art based on the following examination and research, or can be taught from the practice of the present invention to some extent. The objectives and other advantages of the present invention can be achieved and obtained through the following description. BRIEF DESCRIPTION OF THE DRAWINGS
[0017] In order to make the purpose, technical solution and advantages of the utility model clearer, the utility model will be further described in detail below with reference to the accompanying drawings, in which:
[0018] Figure 1 It is a schematic diagram of the connection structure of the utility model.
[0019] Figure 2 It is a schematic diagram of the circuit structure of the utility model.
[0020] Among them, there are a tunnel 1; an LED light group 2; a camera device 3; a main controller 4; a backup controller 5; a pulse control 6; a light control circuit 7; a light brightness detector 8; a vehicle detector 9; and an LED driver 10. DETAILED DESCRIPTION
[0021] The preferred embodiments of the present invention will be described in detail below with reference to the accompanying drawings. It should be understood that the preferred embodiments are only for illustrating the present invention, rather than for limiting the protection scope of the present invention.
[0022] like Figure 1-Figure 2 As shown, the utility model discloses a high energy-saving control device for tunnel lighting, which includes LED lamp groups 2 and camera devices 3 arranged in sections in a tunnel 1, a main controller 4, a backup controller 5 and a light control circuit 7 of a pulse control 6 of the LED lamp groups 2 and the camera devices 3 are arranged in the tunnel 1, the main controller 4, the backup controller 5 and the light control circuit 7 of the pulse control 6 are connected in parallel with each other, a light brightness detector 8, a vehicle detector 9 and an LED driver 10 for stepless dimming corresponding to the LED lamp groups 2 are arranged on each section of the tunnel 1, the light brightness detector 8 and the vehicle detector 9 are connected to a computer of a master control center through a data transmission device, and the computer of the master control center is connected to The LED driver 10 data is mutually exchanged. Such a structure can detect the brightness of each section of the tunnel 1 and the size of the vehicle flow through the brightness detector 8 and the vehicle detector 9, and obtain data. Then, the LED driver 10 is controlled by the computer of the main control center to perform stepless dimming and adjust the brightness. In this way, it can be adjusted at any time to ensure the lighting effect of the LED lamp group 2 while saving energy to the greatest extent. The energy-saving effect is significant. At the same time, the main controller 4, the backup controller 5 and the pulse control 6 are redundantly designed to overcome the problem of unreliable operation of the existing energy-saving controller, and achieve the purpose of both realizing tunnel energy saving and stable and reliable operation.
[0023] The computer of the master control center is provided with the brightness adjustment value of the LED light group 2 corresponding to the brightness interval value and the traffic flow interval value of the tunnel 1, so that the brightness of the LED light group 2 can be adjusted according to the brightness measured by the brightness detector 8, and the brightness of the LED light group 2 can be adjusted according to the traffic flow detected by the vehicle detector 9. Furthermore, the computer of the master control center controls the LED driver 10 through the RS485 communication protocol technology, so that remote or local automatic control can be realized, making the tunnel lighting system more intelligent and energy-saving.
[0024] The vehicle detector 9 is a millimeter wave radar. The millimeter wave radar and the camera device 3 are both connected to the radar fusion edge computing unit. In this way, the microwave plus visual recognition sensor technology combined with the millimeter wave radar and the camera device 3 can sense the vehicle normally even when the vehicle is prohibited from moving. By making micro-innovations, developing and improving the microwave plus visual recognition sensor technology, the reliability of the energy-saving device is improved, the safety risks caused by the abnormal operation of the energy-saving device can be avoided when the energy-saving device is working abnormally, and the safety risks caused by the parking of the vehicle in the tunnel are reduced. More specifically, the specific model of the millimeter wave radar is RACO-RVC120, and the camera device 3 is a general tunnel camera. The device constituting the radar fusion edge computing unit and the data transmission and configuration unit includes the radar fusion edge computing unit: GPU, CPU memory, external storage, Ethernet card data transmission and configuration unit: router, Ethernet card and controller, and its specific working principle is as follows:
[0025] The camera collects on-site image data. The GPU filters and reduces noise on the data image, extracts edge information, performs object segmentation, and identifies target types. The recognition results are then sent to the CPU for target statistics, target parameter calculation, and other operations. The data is then sent to the router via Ethernet, and the controller obtains target information via Ethernet. At the same time, the controller can also send configuration information to the RayVision Fusion Edge Computing Unit via Ethernet for parameter configuration.
[0026] The above is only a preferred embodiment of the utility model, and does not limit the confidentiality of the utility model in any form. Any modification based on the technical essence of the utility model without departing from the technical solution of the utility model shall not be construed as a violation of the technical content of the utility model.
[0027] Any simple modifications, equivalent changes and modifications made to the above embodiments are still within the scope of the technical solution of the utility model.
Claims
1. A high energy-saving control device for tunnel lighting, comprising LED light groups (2) and camera devices (3) arranged in sections in a tunnel (1), a main controller (4), a backup controller (5) and a light control circuit (7) of a pulse control (6) of the LED light groups (2) and the camera devices (3) arranged in the tunnel (1), the main controller (4), the backup controller (5) and the light control circuit (7) of the pulse control (6) being connected in parallel with each other, characterized in that: A light brightness detector (8), a vehicle detector (9) and an LED driver (10) for stepless dimming are provided in each tunnel (1) segment corresponding to the LED light group (2). The light brightness detector (8) and the vehicle detector (9) are connected to a computer in a master control center via a data transmission device, and data is exchanged between the computer in the master control center and the LED driver (10).
2. The tunnel lighting high energy-saving control device according to claim 1 is characterized in that: The computer in the master control center is provided with brightness adjustment values of the LED light group (2) corresponding to the light brightness interval values of the tunnel (1) and the traffic flow interval values.
3. The tunnel lighting high energy-saving control device according to claim 1 is characterized in that: The computer in the master control center regulates the LED driver (10) through RS485 communication protocol technology.
4. The tunnel lighting high energy-saving control device according to claim 1 is characterized in that: The vehicle detector (9) is a millimeter wave radar, and the millimeter wave radar and the camera device (3) are both connected to a radar-vision fusion edge computing unit.