A kind of assembled foundation of collector line iron tower

By adopting prefabricated foundation technology of concrete pipe piles and prefabricated foundation plates, the problems of slow construction speed and great environmental impact of overhead collecting line tower foundations are solved, and rapid and mechanized construction is achieved, reducing costs and environmental impacts.

CN222745094UActive Publication Date: 2025-04-11CHINA POWER CONSTR ENG CONSULTING CORP
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420589532.2
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-03-26
Publication Date
2025-04-11
Estimated Expiration
2034-03-26

Smart Images

  • Figure CN222745094U_ABST
    Figure CN222745094U_ABST
Patent Text Reader

Abstract

The utility model relates to the technical field of electric wire tower installation, and discloses an assembled foundation for a collector line tower, comprising a concrete pipe pile and a prefabricated foundation plate, wherein a pile end connection support plate is slidably connected inside the concrete pipe pile, a plurality of anchor bars are fixedly connected to the top of the pile end connection support plate, a plurality of the anchor bars are fixedly connected by a plurality of transverse stirrups, and a plurality of holes slidably connected to the anchor bars are provided on the prefabricated foundation plate. The assembled foundation for the collector line tower adopts an assembled new energy overhead collector line pull-out tower foundation, which saves construction time compared with conventional cast-in-place reinforced concrete foundation methods, especially in rainy season and winter, reduces construction complexity and construction costs, speeds up construction progress, adopts an assembled new energy overhead collector line pull-out tower foundation, is manufactured in a factory, and can use high-strength concrete, which can save reinforced concrete materials compared with conventional cast-in-place reinforced concrete foundations, and indirectly reduces energy consumption.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of electric wire tower installation, in particular to an assembled foundation of a collector line tower. Background Art

[0002] With the development of green and low-carbon economy currently advocated, new energy is developing rapidly. With the increase in the number of new energy projects, the length of overhead collection lines built to support new energy projects is getting longer and longer, and the corresponding overhead collection line tower foundations are also increasing.

[0003] The overhead collector line is long, and the construction location of the tower foundation supporting the conductor is scattered. The foundation usually adopts a concrete foundation. The collector lines of new energy projects are usually located in remote areas, and it is inconvenient to mix concrete on site and transport commercial concrete. For overhead collector lines, the conductors are supported on the tower, and the tower is supported on the concrete foundation. Under the action of the tension wire, the tower legs will generate an upward pull force, which is transmitted to the foundation. The foundation often needs to resist pullout. In areas with poor geological conditions, pile foundations are required. The foundation of the conventional overhead collector line tower adopts a cast-in-place reinforced concrete slab foundation. The site requires formwork support, reinforcement, and concrete pouring. Most of these links are completed manually, and the construction progress is slow. The foundation of the overhead collector line is generally excavated mechanically. When a cast-in-place reinforced concrete foundation is used, due to the slow construction speed, when it encounters the rainy season, rainwater will accumulate in the foundation pit, causing disturbance to the foundation soil, making construction difficult and affecting the construction period. In addition, there are wet operations on the construction site, and the level of civilized construction on site is not high, which has a great impact on the environment. The use of cast-in-place reinforced concrete foundations, due to the scattered location of the foundations, it is difficult for the concrete mixed on site to achieve high strength, and the foundation size is relatively large, which increases the amount of reinforced concrete materials used, indirectly increasing energy consumption. At the same time, due to progress reasons, when winter construction is required, cast-in-place reinforced concrete structures are used, which have high requirements for ambient temperature. When the temperature is below a certain level, winter construction measures need to be adopted, and the construction cost is high. In addition, it is inconvenient to construct, the construction progress is slow, and the construction difficulty is high. It can be seen that the use of cast-in-place reinforced concrete foundations will consume a large amount of reinforced concrete materials and labor costs due to the large number of overhead collector line tower foundations and their scattered locations. The construction is difficult and slow, and the project cost is high. Therefore, a prefabricated foundation for collector line towers is proposed to solve the above problems. Utility Model Content

[0004] The utility model aims to provide an assembled foundation for a collector line iron tower to solve the problems in the above-mentioned background technology.

[0005] The purpose of the utility model can be achieved through the following technical solutions:

[0006] A prefabricated foundation for a collector line tower comprises a concrete pipe pile and a prefabricated foundation plate, wherein a pile end connection support plate is slidably connected inside the concrete pipe pile, a plurality of anchor bars are fixedly connected to the top of the pile end connection support plate, the plurality of anchor bars are fixedly connected to each other by a plurality of transverse stirrups, a plurality of holes slidably connected to the anchor bars are formed on the prefabricated foundation plate, high-strength cement slurry is poured between the outer surface of the anchor bars and the holes, a steel anchor plate fixedly welded to the anchor bars is slidably connected to the top of the prefabricated foundation plate, a plurality of anchor bolts are arranged on the prefabricated foundation plate, and the anchor bolts are fixedly connected to the tower foot bottom plate at the bottom of the tower by installing nuts.

[0007] As a further solution of the utility model: the prefabricated foundation plate includes prefabricated foundation short column longitudinal reinforcement and prefabricated foundation short column stirrups, and the prefabricated foundation short column longitudinal reinforcement and the prefabricated foundation short column stirrups are fixed by steel wire binding. The prefabricated foundation is formed by placing the bracket bound between the prefabricated foundation short column longitudinal reinforcement and the prefabricated foundation short column stirrups into the template, and holes and installation grooves are reserved at the same time, and then the molded concrete is poured in and out.

[0008] As a further solution of the utility model: core concrete is poured inside the concrete pipe pile, and a concrete cushion layer connected to the ground is poured on the outer surface of the concrete pipe pile.

[0009] As a further solution of the utility model: a concrete protective layer is poured on the top of the prefabricated foundation plate, and the concrete protective layer wraps the steel anchor plate and the anchor bar.

[0010] As a further solution of the utility model: a cement grouting layer fixedly connected to the prefabricated foundation plate is poured on the top of the tower foot bottom plate.

[0011] Beneficial effects of the utility model:

[0012] (1) The use of assembled new energy overhead collector line anti-pullout tower foundation saves construction time, especially in the rainy season and winter, reduces construction complexity and construction costs, and speeds up construction progress compared to conventional cast-in-place reinforced concrete foundation methods.

[0013] (2) Compared with conventional cast-in-place concrete foundations, prefabricated foundations are basically mechanized in construction, without the need for formwork, reinforcement and concrete pouring, which are basically completed manually, thus reducing labor costs. The prefabricated foundation and prefabricated reinforced concrete piles are connected by anchor bars and high-pressure cement slurry, which is convenient for construction, requires less wet work, is fast in construction, and is less affected by the construction environment.

[0014] (3) Prefabricated foundations can be miniaturized and standardized, with simple production, convenient transportation, construction and installation. Concrete prefabricated components are uniformly prefabricated by the factory, with good component quality, beautiful appearance, water and material saving, and in line with energy-saving and environmentally friendly green building materials.

[0015] (4) The assembled new energy overhead collector line anti-pullout tower foundation is manufactured in the factory and can use high-strength concrete. Compared with the conventional cast-in-place reinforced concrete foundation, it can save reinforced concrete materials and indirectly reduce energy consumption. BRIEF DESCRIPTION OF THE DRAWINGS

[0016] The utility model is further described below in conjunction with the accompanying drawings.

[0017] Figure 1 This is the foundation plan of the utility model assembled new energy collection line anti-pulling iron tower;

[0018] Figure 2 This is a cross-sectional view of the foundation of the utility model assembled new energy collection line anti-pulling iron tower;

[0019] Figure 3 It is a plan view of the connection between the pile anchor bar and the prefabricated foundation of the utility model;

[0020] Figure 4 This is a cross-sectional view of the connection between the pile anchor bar and the prefabricated foundation of the utility model;

[0021] Figure 5 It is a plan view of the pile anchor bar of the utility model;

[0022] Figure 6 It is a cross-sectional view of a prefabricated foundation short column of the utility model.

[0023] In the figure: 1. Concrete pipe piles; 2. Prefabricated foundation plate; 3. Connecting support plate; 4. Anchor bars; 5. Transverse stirrups; 6. Holes; 7. High-strength cement slurry; 8. Steel anchor plates; 9. Anchor bolts; 10. Iron tower; 11. Tower foot plate; 12. Mounting nuts; 13. Longitudinal bars of foundation short columns; 14. Stirrups of foundation short columns; 15. Mounting grooves; 16. Core pouring concrete; 17. Concrete cushion layer; 18. Concrete protective layer; 19. Cement grouting layer; 20. Formed concrete. DETAILED DESCRIPTION

[0024] The following will be combined with the drawings in the embodiments of the utility model to clearly and completely describe the technical solutions in the embodiments of the utility model. Obviously, the described embodiments are only part of the embodiments of the utility model, not all of the embodiments. Based on the embodiments of the utility model, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the utility model.

[0025] See also Figure 1-Figure 6As shown, the utility model is an assembled foundation for a collector line tower, comprising a concrete pipe pile 1 and a prefabricated foundation plate 2, wherein a pile end connection support plate 3 is slidably connected inside the concrete pipe pile 1, a plurality of anchor bars 4 are fixedly connected to the top of the pile end connection support plate 3, and the plurality of anchor bars 4 are fixedly connected by a plurality of transverse stirrups 5, a plurality of holes 6 slidably connected to the anchor bars 4 are opened on the prefabricated foundation plate 2, high-strength cement slurry 7 is poured between the outer surface of the anchor bars 4 and the holes 6, a steel anchor plate 8 fixedly welded to the anchor bars 4 is slidably connected to the top of the prefabricated foundation plate 2, a plurality of anchor bolts 9 are arranged on the prefabricated foundation plate 2, and the anchor bolts 9 are fixedly connected to the tower foot bottom plate 11 at the bottom of the iron tower 10 by installing nuts 12.

[0026] The prefabricated foundation plate 2 includes prefabricated foundation short column longitudinal reinforcement 13 and prefabricated foundation short column stirrups 14, which are fixed by steel wire bundling. The prefabricated foundation is formed by placing the bracket bundled between the prefabricated foundation short column longitudinal reinforcement 13 and the prefabricated foundation short column stirrups 14 into the template, and reserving holes 6 and installation grooves 15, and then pouring and molding concrete 20 to form the prefabricated foundation.

[0027] A core concrete 16 is poured inside the concrete pipe pile 1 , and a concrete cushion layer 17 connected to the ground is poured on the outer surface of the concrete pipe pile 1 .

[0028] A concrete protective layer 18 is poured on the top of the prefabricated foundation plate 2 , and the concrete protective layer 18 wraps between the steel anchor plate 9 and the anchor bar 4 .

[0029] A cement grouting layer 19 fixedly connected to the prefabricated foundation plate 2 is poured on the top of the tower foot bottom plate 11 .

[0030] First, use construction machinery to drive or press the prefabricated reinforced concrete pipe pile 1 to the designed depth at the designed position of the site. Tie the anchor bars 4 and transverse stirrups 5, weld them together with the pile end connection support plate 3 and place them inside the pipe pile 1, and then pour the core concrete 16 into the concrete pipe pile 1. Pour the concrete cushion layer 17 on the site to form a flat and solid plane. According to the design drawings, support the template in the factory, tie the prefabricated foundation bottom plate steel bars, prefabricated foundation short column longitudinal bars 13, and prefabricated foundation short column transverse stirrups 14, and fix the anchor bolts 9 at the designed position. At the same time, reserve the installation groove 15 for the pile head and the hole 6 for the anchor bar 4 to pass through. Pour the molded concrete 20 into the template and maintain it for a period of time to form the prefabricated foundation plate 2. Use construction machinery to hoist the prefabricated foundation plate 2 prefabricated in the factory onto the prefabricated reinforced concrete pipe pile 1, and the anchor bar 4 passes through the prefabricated foundation plate 2 through the hole 6 reserved on the prefabricated foundation. The pile head of the reinforced concrete pipe pile 1 is placed in the installation groove 15 reserved in the prefabricated foundation plate 2. Through the equipment, high-strength cement slurry 7 is injected into the hole 6 reserved in the prefabricated foundation under high pressure. Then the steel anchor plate 8 is welded to the anchor bar 4, and the concrete protective layer 18 is poured in the anchor bar 3 area on the bottom plate of the prefabricated foundation plate 2. In the processing plant, the legs of the iron tower 10 are welded to the tower leg bottom plate 11, and then the components of the iron tower are transported to the construction site and assembled together to form an iron tower. The iron tower is hoisted by mechanical equipment, and the anchor bolts 9 pass through the bolt holes reserved on the tower leg bottom plate 11. After adjusting the position and level, they are fixed and installed by installing the nuts 13, and then the secondary grouting layer 19 is poured under the tower leg bottom plate for protection. Through the above-mentioned construction of the iron tower, a simple structure, convenient connection and low construction difficulty are achieved. Compared with the conventional cast-in-place reinforced concrete foundation, the assembled new energy overhead power collection line anti-pulling tower foundation does not require formwork, reinforcement and concrete pouring on site, which reduces labor costs, has little impact on the site environment, and greatly improves the construction efficiency of the tower. At the same time, the prefabricated foundation plate and the prefabricated reinforced concrete piles are connected by anchor bars and high-pressure cement slurry, which is convenient for construction, with small wet work volume, fast construction speed and little impact on the construction environment.

[0031] Especially in the rainy season and winter, it reduces the complexity of construction, speeds up the construction progress, and reduces the cost of construction measures. Prefabricated reinforced concrete foundations are made in prefabrication plants with good production conditions and can use high-strength concrete. Compared with conventional foundations, they can save reinforced concrete materials and indirectly reduce energy consumption.

[0032] The above is a detailed description of an embodiment of the utility model, but the content is only a preferred embodiment of the utility model and cannot be considered to limit the scope of implementation of the utility model. All equivalent changes and improvements made within the scope of application of the utility model should still fall within the scope of the patent coverage of the utility model.

Claims

1. A prefabricated foundation for a collector line tower, comprising a concrete pipe pile (1) and a prefabricated foundation plate (2), characterized in that: A pile end connection support plate (3) is slidably connected inside the concrete pipe pile (1), a plurality of anchor bars (4) are fixedly connected to the top of the pile end connection support plate (3), and the plurality of anchor bars (4) are fixedly connected to each other via a plurality of transverse stirrups (5). A plurality of holes (6) slidably connected to the anchor bars (4) are provided on the prefabricated foundation plate (2), and high-strength cement slurry (7) is poured between the outer surface of the anchor bars (4) and the holes (6). A steel anchor plate (8) fixedly welded to the anchor bars (4) is slidably connected to the top of the prefabricated foundation plate (2), and a plurality of anchor bolts (9) are arranged on the prefabricated foundation plate (2), and the anchor bolts (9) are fixedly connected to the tower foot base plate (11) at the bottom of the iron tower (10) via mounting nuts (12).

2. The assembled foundation of a collector line tower according to claim 1, characterized in that: The prefabricated foundation plate (2) comprises prefabricated foundation short column longitudinal reinforcement (13) and prefabricated foundation short column stirrups (14), wherein the prefabricated foundation short column longitudinal reinforcement (13) and the prefabricated foundation short column stirrups (14) are bound and fixed by steel wires. The prefabricated foundation is formed by placing the bracket after the prefabricated foundation short column longitudinal reinforcement (13) and the prefabricated foundation short column stirrups (14) are bound into a template, and a hole (6) and an installation groove (15) are reserved at the same time, and then the prefabricated foundation is formed by pouring concrete (20).

3. The assembled foundation of a collector line tower according to claim 1, characterized in that: The concrete pipe pile (1) is poured with core concrete (16), and the outer surface of the concrete pipe pile (1) is poured with a concrete cushion layer (17) connected to the ground.

4. The assembled foundation of a collector line tower according to claim 1, characterized in that: A concrete protective layer (18) is poured on the top of the prefabricated foundation plate (2), and the concrete protective layer (18) wraps between the steel anchor plate (8) and the anchor bar (4).

5. The assembled foundation of a collector line tower according to claim 1, characterized in that: A cement grouting layer (19) is cast on the top of the tower footing plate (11) and is fixedly connected to the prefabricated foundation plate (2).