Protective construction system for house transformation of existing building facade

By setting up scaffolding and protective fences on the facade of large shopping malls, combined with the fixing method of structural wall parts and curtain wall parts, the problem of the renovation of large shopping malls not affecting merchant operations is solved, and the transformation and operation are carried out simultaneously.

CN222759318UActive Publication Date: 2025-04-15BEIJING FOURTH CONSTR & ENG
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202421571969.X
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-07-04
Publication Date
2025-04-15
Estimated Expiration
2034-07-04

AI Technical Summary

Technical Problem

During the renovation and renovation of the facade of a large shopping mall, how to complete the renovation of the facade curtain wall without affecting the normal operation of the merchant, and ensure that the renovation and the business of the merchant are carried out simultaneously in space and time.

Method used

The scaffolding and protective fence system are adopted from the inside out. The scaffolding is fixed to the main structure and curtain wall through structural wall connections, curtain wall connections and ground wall connections to ensure stability of the frame, and the construction area and operation area are separated by protective fences, and a safe passage is set to ensure pedestrians' passage.

Benefits of technology

The facade curtain wall renovation and merchant business are realized simultaneously, avoiding the impact of construction on merchant operations, ensuring the normal progress of the project and cost control.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222759318U_ABST
    Figure CN222759318U_ABST
Patent Text Reader

Abstract

The utility model discloses a protective construction system for house-carrying reconstruction of an external facade of an existing building, which comprises a scaffold and a protective fence which are sequentially erected on the outer side of the external facade on one side to be reconstructed of the existing building from inside to outside, and the scaffold is a double-row floor open type frame body. The scaffold in the non-operation area is fixed to the main body structure through a structural wall connecting piece in a pulling mode, the scaffold in the commercial tenant operation area is fixed to a grating curtain wall on the outer side of the main body structure through a curtain wall connecting piece in a pulling mode, and the protective fence is erected on the outer side of the scaffold to separate the construction area from the outside and separate the non-operation area from the commercial tenant operation area. And a safety channel for communicating the outside with a merchant shop is also arranged along the outer facade transformation area. The external facade curtain wall is simple in structure and convenient to construct, the influence of external facade transformation operation on normal operation of merchants is avoided, and the purpose that external facade curtain wall transformation and merchant operation are carried out at the same time in space and time is achieved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of decoration and renovation construction of existing buildings, and in particular to a protective construction system for renovation of existing building facades with households. Background Art

[0002] With the continuous improvement of China's economic level, the continuous development of the construction industry, and the change of the public's aesthetic concept of buildings, more and more existing building facades can no longer meet the use requirements. Therefore, the number of existing building facade renovation projects has been growing rapidly in recent years.

[0003] Among them, the renovation of large shopping malls often involves the renovation of the facades. However, the single buildings corresponding to large shopping malls are usually shared by multiple property units, and some construction areas are the relocated merchant areas. Affected by the relocated merchant areas, the entire facade cannot be dismantled and renovated as a whole, and the demolition and renovation construction will inevitably affect the normal business of the merchants. At that time, the merchant claims and disputes will cause an increase in project costs and delays in the construction period to a certain extent, wasting a lot of manpower and financial resources. Therefore, how to complete the renovation of the facades of large shopping malls without affecting the normal operation of the merchants, ensure that the facade curtain wall renovation and the business of the merchants are carried out simultaneously in space and time, and realize the renovation construction with households has become a technical problem that needs to be solved urgently. Utility Model Content

[0004] The utility model aims to provide a protective construction system for the renovation of the existing building facade with households, so as to solve the technical problems described in the background technology.

[0005] In order to achieve the above technical purpose, the utility model adopts the following technical solutions:

[0006] A protective construction system for the renovation of the exterior facade of an existing building with households, comprising scaffolding and protective enclosures erected in sequence from the inside to the outside on the exterior facade of one side of the existing building to be renovated, the scaffolding being a double-row, ground-standing, open frame, the scaffolding in the non-operating area being fixed to the main structure by means of structural wall ties, the scaffolding in the merchant operating area being fixed to the grille curtain wall on the exterior side of the main structure by means of curtain wall ties, the protective enclosure being erected on the exterior side of the scaffolding to separate the construction area from the outside, and the non-operating area from the merchant operating area, and a safe passage connecting the outside and the merchant shops is also provided along the exterior facade renovation area.

[0007] Preferably, the first floor of the main structure is an overall concave structure, and the scaffolding is fixed to the ground by ground wall connecting members arranged in the open space between the safety passages.

[0008] Preferably, the ground wall connection member includes a ground anchor pole, a transverse tie rod and a diagonal brace. The ground anchor pole is vertically anchored in the open space between the safety passages. The transverse tie rod is horizontally arranged, one end of the rod body is fixed to the ground anchor pole, and the other end of the rod body is fixed to the vertical pole of the scaffolding. The diagonal brace is inclined, the bottom end of the rod body is fixed to the ground anchor pole, and the top end of the rod body is fixed to the vertical pole of the scaffolding.

[0009] Preferably, the curtain wall connecting member includes a through rod and a wall connecting rod, the through rod horizontally penetrates the grille curtain wall and is welded and fixed to the curtain wall transverse keel of the grille curtain wall, and the wall connecting rod is horizontally arranged, one end of the rod body is fixed on the through rod, and the other end of the rod body is fixed on the vertical pole of the scaffolding.

[0010] Preferably, the structural wall connecting member includes a through-plate vertical rod and a horizontal tie rod, the through-plate vertical rod vertically penetrates the structural floor of the main structure, the horizontal tie rod is arranged in pairs, and the two horizontal tie rods arranged in pairs are correspondingly arranged at positions above and below the structural floor, the horizontal tie rod is arranged horizontally, one end of the rod body is fixed on the through-plate vertical rod, and the other end of the rod body is fixed on the vertical rod of the scaffolding.

[0011] Preferably, a core-filling rod is fixedly provided on the wall tie rod, and the gap between the core-filling rod and the main structure on the side close to the main structure, the gap between the core-filling rods, and the gap between the core-filling rods and the scaffolding on the side close to the scaffolding are all less than 150 mm.

[0012] Preferably, a core-filling rod is fixedly provided on the horizontal pull rod, and the gap between the core-filling rod and the main structure on the side close to the main structure, the gap between the core-filling rods, and the gap between the core-filling rods and the scaffolding on the side close to the scaffolding are all less than 150 mm.

[0013] Compared with the prior art, the beneficial effects of the present invention are as follows: the present invention has a simple structure and is easy to construct. A reliable working platform is provided for the renovation of the facade curtain wall through the scaffolding. At the same time, according to the different positions of the frame, ground wall ties, curtain wall ties and structural wall ties are respectively used to ensure the stability of the frame and avoid the impact of the facade renovation work on the normal operation of the merchants. On this basis, the construction area is further separated from the operation area by protective fences, and the normal and safe passage of pedestrians is ensured by the layout of safety passages, thereby achieving the purpose of simultaneous renovation of the facade curtain wall and business operations in space and time. BRIEF DESCRIPTION OF THE DRAWINGS

[0014] The above and / or other aspects and advantages of the present invention will become clearer and easier to understand through the detailed description made in conjunction with the following drawings, which are only schematic and do not limit the present invention, wherein:

[0015] Figure 1 This is a schematic diagram of the main structure of a protective construction system for renovation of an existing building facade with households involved in the utility model;

[0016] Figure 2 for Figure 1 Schematic diagram of the structure after removing the steel enclosure and protective enclosure;

[0017] Figure 3 It is a structural schematic diagram of the scaffolding involved in the utility model at the ground wall connection parts and the curtain wall connection parts;

[0018] Figure 4 The utility model is a schematic diagram of the structure of the scaffolding at the structural wall connecting member.

[0019] Figure numerals: 1. Protective enclosure; 2. Safety passage; 3. Scaffolding; 301. Vertical pole; 302. Large cross bar; 303. Small cross bar; 304. Zigzag brace; 305. Steel enclosure; 4. Ground wall connection piece; 401. Ground anchor vertical pole; 402. Horizontal tie rod; 403. Diagonal brace; 5. Curtain wall connection piece; 501. Through-core rod; 502. Wall connection rod; 6. Structural wall connection piece; 601. Through-plate vertical pole; 602. Horizontal tie rod; 7. Grille curtain wall; 8. Main structure; 9. Diagonal steel plate; 10. Filling rod. DETAILED DESCRIPTION

[0020] In the following, an embodiment of a protective construction system for the renovation of an existing building facade with households of the utility model will be described with reference to the accompanying drawings. The embodiments recorded herein are specific embodiments of the utility model, which are used to illustrate the concept of the utility model, are explanatory and exemplary, and should not be interpreted as limitations on the implementation methods of the utility model and the scope of the utility model. In addition to the embodiments recorded herein, those skilled in the art can also adopt other obvious technical solutions based on the contents disclosed in the claims and the specification of this application, including technical solutions that adopt any obvious replacements and modifications to the embodiments recorded herein.

[0021] In the description of the present invention, it should be noted that the terms "front", "rear", "left", "right", "top", "bottom", "up", "down", "inside", "outside", "horizontal", "longitudinal", "vertical", "oblique" and the like indicate directions or positional relationships based on the directions or positional relationships shown in the accompanying drawings, and are only for the convenience of describing the present invention and simplifying the description, and do not indicate or imply that the device or element referred to must have a specific direction, be constructed and operated in a specific direction, and therefore cannot be understood as limiting the present invention. In addition, the terms "first", "second" and the like are only used for descriptive purposes and cannot be understood as indicating or implying relative importance.

[0022] The drawings of this specification are schematic diagrams, which assist in explaining the concept of the utility model and schematically show the shapes of various parts and their mutual relationships. Please note that in order to clearly show the structure of various components of the embodiments of the utility model, the drawings are not drawn according to the same scale. The same reference numerals are used to represent the same parts.

[0023] The principles and features of the present invention are described below in conjunction with the accompanying drawings. The embodiments are only used to explain the present invention and are not intended to limit the scope of the present invention. Figure 1-4 , the preferred embodiments of the utility model are further described in detail:

[0024] like Figure 1-2 As shown, the utility model preferably adopts a protective construction system for renovation of the facade of an existing building with households, including a scaffold 3 and a protective fence 1 which are sequentially erected from the inside to the outside on the outer side of the facade of the existing building to be renovated, wherein the scaffold 3 is a double-row, ground-standing, open frame, the scaffold 3 in the non-operating area is tied and fixed to the main structure 8 by a structural wall connecting member 6, and the scaffold 3 in the merchant operating area is tied and fixed to the grille curtain wall 7 on the outer side of the main structure 8 by a curtain wall connecting member 5, the protective fence 1 is erected on the outer side of the scaffold 3 to separate the construction area from the outside, and to separate the non-operating area from the merchant operating area, and a safety passage 2 connecting the outside and the merchant shops is also provided along the facade renovation area;

[0025] Usually, the decorative curtain wall of a large shopping mall will protrude outward for a distance. At this time, the first floor of the main structure 8 will be an overall concave structure. On this basis, combined with the original intention of not affecting the normal operation of the merchants, in order to ensure the stability of the ground-type scaffolding 3, the setting of its wall connecting parts meets the requirements of the specification, such as Figure 3 As shown, the bottom of the scaffolding 3 is tied and fixed to the ground through a ground wall connecting member 4 arranged in the open space between the safety passages 2. The ground wall connecting member 4 includes a ground anchor rod 401, a transverse tie rod 402 and a diagonal brace 403. The ground anchor rod 401 is vertically anchored in the open space between the safety passages 2. The transverse tie rod 402 is horizontally arranged, with one end of its rod body fixed to the ground anchor rod 401 and the other end of its rod body fixed to the vertical pole 301 of the scaffolding 3. The diagonal brace 403 is tiltedly arranged, with the bottom end of its rod body fixed to the ground anchor rod 401 and the top end of its rod body fixed to the vertical pole 301 of the scaffolding 3.

[0026] Since the merchants in the renovation area need to operate normally, the wall connecting parts in this area cannot be erected according to the conventional design form. On this basis, in order to ensure the stability of the scaffolding 3 within this range, Figure 3As shown, the scaffolding 3 in this area is fixed to the grille curtain wall 7 by means of curtain wall connecting pieces 5, the curtain wall connecting pieces 5 include a through rod 501 and a wall connecting rod 502, the through rod 501 horizontally penetrates the grille curtain wall 7 and is welded and fixed to the transverse curtain wall keel of the grille curtain wall 7, the wall connecting rod 502 is arranged horizontally, one end of the rod body is fixed to the through rod 501, and the other end of the rod body is fixed to the vertical pole 301 of the scaffolding 3, as the transformation proceeds, the outer decorative layer of the grille curtain wall 7 and part of the keel will be removed, at this time, the safe distance between the scaffolding 3 and the structure will become larger, in order to ensure the safety of construction, it is necessary to add a filling rod 10 to the wall connecting rod 502 in this area, and ensure that the gap between the filling rod 10 and the main structure 8 on the side close to the main structure 8, the gap between the filling rod 10 and the filling rod 10, and the gap between the filling rod 10 and the scaffolding 3 on the side close to the scaffolding 3 are all less than 150mm;

[0027] In the normal construction area where no business is operating, the scaffolding 3 is tied and fixed to the main structure 8 in the form of a standard layer, such as Figure 4 As shown, the structural wall connecting member 6 includes a through-plate upright 601 and a horizontal tie rod 602. The through-plate upright 601 vertically penetrates the structural floor of the main structure 8. The horizontal tie rod 602 is arranged in pairs. The two horizontal tie rods 602 arranged in pairs are correspondingly arranged at the upper and lower positions of the structural floor. The horizontal tie rod 602 is arranged horizontally, and one end of the rod body is fixed on the through-plate upright 601, and the other end of the rod body is fixed on the upright 301 of the scaffolding 3. Of course, whether to add a filling rod 10 between the scaffolding 3 and the main structure 8 in this area can be determined according to needs. When the filling rod 10 is added, it needs to be fixed on the horizontal tie rod 602, and ensure that the gap between the filling rod 10 and the main structure 8 on the side close to the main structure 8, the gap between the filling rod 10 and the filling rod 10, and the gap between the filling rod 10 and the scaffolding 3 on the side close to the scaffolding 3 are all less than 150mm.

[0028] Taking a specific construction project as an example, the specific construction process of the utility model is introduced below:

[0029] Step 1: Compare and select renovation plans, conduct a feasibility study on the in-depth design of the demolition and renovation plan with households, design a comprehensive demolition and renovation plan for the facades of the property unit area and the non-property unit area, and do not demolish the enclosure structure in other property unit areas. Use vertical aluminum plate molding on the outside of the curtain wall keel of the original grille curtain wall 7;

[0030] Step 2: Set up protective fence 1 and safety passage 2. Set up protective fence 1 to effectively separate the construction area from the business operation area, set up safety passage 2 along the facade renovation area, and set up safety passage 2 and head protection shed at the main entrance of the operating business to ensure the normal passage of pedestrians. Strong noise and light pollution operations are carried out in different time periods and sections to avoid affecting the operation of businesses;

[0031] Step 3: Scaffold 3 is set up. Scaffold 3 is a floor-standing double-row open scaffold 3, with a height of 39.9m. The step distance between the large crossbars 302 is 1.8m, the vertical distance between the vertical poles 301 is 1.5m, the horizontal distance between the inner and outer rows of vertical poles 301 is 1.0m, the distance between the inner row of vertical poles 301 and the decoration demolition surface layer is ≤0.3m, the outer side is a steel enclosure 305, and a zigzag support 304 is added at the opening of the scaffold 3;

[0032] Step 4: The wall connection in the household construction area needs to be set up. The facade renovation needs to set up double-row ground-to-ceiling and open scaffolding 3. The objective conditions for setting up are complicated, mainly manifested in the difficulty of setting up the wall connection parts, and the design needs to be carried out according to the actual situation on site;

[0033] 1. The ground wall connection member 4 of the first floor is set. Because the first floor of the main structure 8 is an overall concave area and the merchants are in normal business, vertical ground anchor poles 401 are set in the open space between the safety passages 2 according to the on-site conditions, and connected to the frame body poles 301 through transverse pull rods 402. The poles can be connected by fasteners or other methods that meet the requirements of the specifications. If the ground anchor pole 401 is set opposite to the pole 301, a longer steel pipe can be directly selected as the small cross bar 303 of the scaffolding 3, and the end of the small cross bar 303 can be extended to The ground anchor rod 401 is directly connected to the ground anchor rod 401 and used as a transverse tie rod 402. On this basis, an additional oblique brace 403 is required to be connected and fixed to the rod 301 at the height of the first large cross bar 302 of the frame to ensure that the height of the wall connection does not exceed the safety setting requirements of the scaffold 3. At the same time, in order to ensure the safety of the frame, the two rods 301 at the wall connection position are connected to form a zigzag brace 304 with a small oblique rod to ensure the safety of the frame. Of course, in order to avoid the risk of falling from a height, an oblique steel plate 9 needs to be added to the bottom of the grille curtain wall 7 as protection;

[0034] 2. Setting of the wall connecting parts on the first floor. Because the construction area of ​​the relocated merchants only removes the ceramic panels at the original curtain wall modeling position, without destroying the overall curtain wall system, in order to ensure the normal operation of the merchants, the merchant area on the first floor uses the original external curtain wall modeling keel system, and uses the scaffolding tube as the through-rod 501 to cross the modeling keel and weld and fix it with the horizontal keel of the curtain wall keel as the tie rod of the wall tie rod 502. The wall tie rod 502 is connected and fixed to the frame body upright 301 to ensure the stability of the frame. Of course, if the position of the wall tie rod 502 coincides with the small cross bar 303, the small cross bar 303 can also be extended to be used as the wall tie rod 502 and directly fixed to the through-rod 501;

[0035] 3. In the normal construction area where no business is operating, the scaffolding 3 is tied and fixed to the main structure 8 in the form of a standard layer, such as Figure 4As shown, the structural wall connecting member 6 includes a through-plate vertical rod 601 and a horizontal tie rod 602. The through-plate vertical rod 601 vertically penetrates the structural floor of the main structure 8. The horizontal tie rod 602 is arranged in pairs. The two horizontal tie rods 602 arranged in pairs are correspondingly arranged at the upper and lower positions of the structural floor. The horizontal tie rod 602 is arranged horizontally, and one end of the rod body is fixed to the through-plate vertical rod 601, and the other end of the rod body is fixed to the vertical rod 301 of the scaffold 3.

[0036] Step 5: Setting of the filling rod 10. After the curtain wall is removed, the distance between the frame and the structure and structural members will be greater than 300mm, which may cause safety hazards. To ensure construction safety, when the distance between the frame and the structure and structural members is greater than 300mm, a horizontal large crossbar 302 is set up between the wall connecting parts (depending on the increase in the distance, ensuring that the distance between the large crossbars 302 is less than 150mm), ensuring that the distance between the large crossbars 302 and between the large crossbars 302 and the structure is less than 150mm, commonly known as the filling rod 10;

[0037] Step 6: The curtain wall is dismantled and removed with the households, and the demolition and reconstruction work is carried out in the relocated commercial area. The construction waste is transported to the indoor demolition and reconstruction area on the same floor according to the designated route. After entering the room, it is transported to the designated location by vertical transportation equipment for the construction waste stacking and removal work;

[0038] Step seven: Curtain wall installation with households. The area for relocated businesses is mainly frame glass curtain walls, metal curtain walls, and artificial board (imitation ceramic panels) curtain walls. The installation is carried out using a truck crane and the lifting operation is carried out during the business’ non-business hours.

[0039] The above description is only a preferred embodiment of the present invention and is not intended to limit the present invention. Any modifications, equivalent substitutions, improvements, etc. made within the spirit and principles of the present invention should be included in the protection scope of the present invention.

Claims

1. A protective construction system for renovation of existing building facades with households, characterized by: The invention comprises a scaffold (3) and a protective fence (1) which are sequentially erected on the outer side of the facade of an existing building to be renovated from the inside to the outside. The scaffold (3) is a double-row, ground-standing, open frame. The scaffold (3) in the non-operating area is tied and fixed to the main structure (8) through a structural wall tie (6). The scaffold (3) in the business operation area is tied and fixed to the grille curtain wall (7) outside the main structure (8) through a curtain wall tie (5). The protective fence (1) is erected outside the scaffold (3) to separate the construction area from the outside and the non-operating area from the business operation area. A safety passage (2) connecting the outside and the business shops is also provided along the facade renovation area.

2. According to claim 1, a protective construction system for renovation of existing building facades with households, characterized in that: The first floor of the main structure (8) is an overall concave structure, and the scaffolding (3) is fixed to the ground through ground wall connecting pieces (4) arranged in the open space between the safety passages (2).

3. A protective construction system for renovation of existing building facades with households according to claim 2, characterized in that: The ground wall connection member (4) comprises a ground anchor pole (401), a transverse tie rod (402) and an oblique brace (403); the ground anchor pole (401) is vertically anchored in the open space between the safety passages (2); the transverse tie rod (402) is horizontally arranged, with one end of its rod body fixed to the ground anchor pole (401) and the other end of its rod body fixed to the pole (301) of the scaffold (3); the oblique brace (403) is inclinedly arranged, with the bottom end of its rod body fixed to the ground anchor pole (401) and the top end of its rod body fixed to the pole (301) of the scaffold (3).

4. According to claim 1, a protective construction system for renovation of existing building facades with households, characterized in that: The curtain wall connecting member (5) comprises a through rod (501) and a wall connecting rod (502); the through rod (501) horizontally penetrates the grid curtain wall (7) and is welded and fixed to the curtain wall transverse keel of the grid curtain wall (7); the wall connecting rod (502) is arranged horizontally, one end of the rod body is fixed to the through rod (501), and the other end of the rod body is fixed to the vertical rod (301) of the scaffolding (3).

5. According to claim 1, a protective construction system for renovation of existing building facades with households, characterized in that: The structural wall connecting member (6) comprises a through-plate vertical rod (601) and a horizontal tie rod (602), wherein the through-plate vertical rod (601) vertically penetrates the structural floor of the main structure (8), and the horizontal tie rod (602) is arranged in pairs, and the two horizontal tie rods (602) arranged in pairs are arranged at positions above and below the structural floor respectively, and the horizontal tie rod (602) is arranged horizontally, and one end of the rod body is fixed to the through-plate vertical rod (601), and the other end of the rod body is fixed to the vertical rod (301) of the scaffolding (3).

6. The protective construction system for renovation of existing building facades with households according to claim 4 is characterized by: A core-filling rod (10) is fixedly arranged on the wall tie rod (502), and the gap between the core-filling rod (10) and the main structure (8) on the side close to the main structure (8), the gap between the core-filling rod (10) and the core-filling rod (10), and the gap between the core-filling rod (10) and the scaffolding (3) on the side close to the scaffolding (3) are all less than 150 mm.

7. The protective construction system for renovation of existing building facades with households according to claim 5 is characterized by: A core-filling rod (10) is fixedly arranged on the horizontal pull rod (602), and the gap between the core-filling rod (10) and the main structure (8) on the side close to the main structure (8), the gap between the core-filling rod (10) and the core-filling rod (10), and the gap between the core-filling rod (10) and the scaffolding (3) on the side close to the scaffolding (3) are all less than 150 mm.