Cable installation adjusting frame for electric power engineering construction

By designing a combination of clamping components and pushing components in the cable installation adjustment frame, the cable is easily removed, and the problem of inconvenient cable installation and removal in the prior art is solved.

CN222763491UActive Publication Date: 2025-04-15YUNNAN ZHENGDA SIYUAN IND DEV CO LTD
View PDF 1 Cites 0 Cited by

Patent Information

Application Number
CN202421469646.X
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-06-26
Publication Date
2025-04-15
Estimated Expiration
2034-06-26

AI Technical Summary

Technical Problem

After the existing cable installation adjustment frame is loosened, the cable is still in the clamping clamp, affecting the installation and removal of the cable.

Method used

A cable installation adjustment frame for power engineering construction is designed, using a combination of clamping components and pushing components. The connecting strips and swing strips are driven by hydraulic push rods to achieve clamping and loosening of the clamping components. The cable can be easily removed from the clamping components and support components.

Benefits of technology

It realizes convenient cable removal, avoids the impact of clamping clamps on cable installation, and improves the efficiency of cable installation and removal.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222763491U_ABST
    Figure CN222763491U_ABST
Patent Text Reader

Abstract

The utility model discloses a cable installation adjusting frame for electric power engineering construction, and relates to the technical field of electric power engineering. The cable installation adjusting frame for electric power engineering construction comprises a bottom plate, a lifting plate is arranged above the bottom plate, clamping assemblies are arranged on the left side of the lifting plate, each clamping assembly comprises a swing strip, the upper end of each swing strip is fixedly connected with a clamping plate, the lower end of each swing strip is hinged to a connecting strip, the number of the clamping assemblies is two, and the clamping plates are fixedly connected with the clamping plates. The two clamping assemblies are arranged on the left side of the lifting plate in a crossed mode, and supporting assemblies are arranged on the left sides of the clamping assemblies. According to the cable installation adjusting frame for electric power engineering construction, the clamping assemblies are pushed through the pushing assembly, so that the two clamping assemblies clamp or loosen a cable, when the two clamping assemblies loosen the cable, the cable can be directly taken down from the upper portions of the two clamping assemblies and the supporting assembly, and the cable installation adjusting frame has the effect of conveniently disassembling the cable.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of electric power engineering, in particular to a cable installation and adjustment frame for electric power engineering construction. Background Art

[0002] Communication engineering (also known as telecommunication engineering, formerly known as long-distance communication engineering and weak-current engineering) is an important branch of electronic engineering, a sub-major of electronic information, and also one of the basic disciplines. This discipline focuses on the principles and applications of information transmission and signal processing in the communication process. This major studies knowledge in communication technology, communication systems, and communication networks. It can engage in research, design, manufacturing, and operation in the communication field, as well as development and application of communication technology and equipment in various sectors of the national economy and the defense industry. In the current common communication engineering construction, cable installation adjustment frames are required to support the cable lines during installation.

[0003] For example, the Chinese patent publication number CN220156097U, "A cable installation and adjustment frame for power engineering construction", discloses a cable installation and adjustment frame for power engineering construction, which relates to the technical field of power engineering construction, and includes a cable installation and adjustment frame main body, a transport movable bottom plate is arranged at the bottom of the cable installation and adjustment frame main body, a height adjustment frame mechanism is arranged above the transport movable bottom plate, and a cable clamping frame mechanism is arranged at the front end of the height adjustment frame mechanism.

[0004] However, in actual use, it is inconvenient to loosen the cable. The cable is clamped by a clamp. However, after the clamp releases the cable, the cable is still in the clamp. At this time, the clamp may affect the installation of the cable, and it is inconvenient to remove the cable after loosening the cable. Therefore, a cable installation and adjustment frame for power engineering construction is proposed to solve the above-mentioned problems. Utility Model Content

[0005] In view of the deficiencies of the prior art, the utility model provides a cable installation and adjustment frame for power engineering construction, which solves the problems raised in the above background technology. To achieve the above purpose, the utility model is implemented through the following technical scheme: a cable installation and adjustment frame for power engineering construction, including a bottom plate, a lifting plate is arranged above the bottom plate, a clamping assembly is arranged on the left side of the lifting plate, the clamping assembly includes a swing bar, a clamping plate is fixedly connected to the upper end of the swing bar, a connecting bar is hinged at the lower end of the swing bar, the number of the clamping assemblies is two groups, and the two groups of the clamping assemblies are respectively cross-arranged on the left side of the lifting plate, a supporting assembly is arranged on the left side of the clamping assembly, a pushing assembly is arranged below the clamping assembly, a lifting assembly is arranged on the right side of the lifting plate, and a limit assembly is arranged on the front and rear sides of the lifting plate, the number of the limit assembly is two groups, and a universal wheel is rotatably connected below the bottom plate.

[0006] Preferably, the support assembly includes a support column, the support column is fixedly connected to the left side of the lifting plate, the support column is movably connected to the swing bars in the two groups of clamping assemblies, and the left end of the support column is fixedly connected to the first support frame.

[0007] Preferably, the support assembly further comprises a second support frame, the second support frame is fixedly connected to the top of the lifting plate, and slots for supporting cables are arranged on the tops of the first support frame and the second support frame.

[0008] Preferably, the pushing assembly includes a support plate, which is fixedly connected to the left side of the lifting plate, and a first hydraulic push rod is fixedly connected above the support plate, and the upper end of the first hydraulic push rod is hinged to the lower end of the connecting strip in the two groups of the clamping assemblies.

[0009] Preferably, the lifting assembly includes a second hydraulic push rod, the second hydraulic push rod is fixedly connected to the top of the bottom plate, the upper end of the second hydraulic push rod is fixedly connected to a top plate, and the top plate is fixedly connected to the right side of the lifting plate.

[0010] Preferably, the limiting assembly includes a sliding rod, the sliding rod is fixedly connected to the top of the bottom plate, a sliding sleeve is movable on the outer surface of the sliding rod, and the sliding sleeve is fixedly connected to the lifting plate.

[0011] The utility model provides a cable installation and adjustment frame for electric power engineering construction, which has the following beneficial effects:

[0012] (1) A cable installation and adjustment frame for electric power engineering construction, wherein the pushing assembly pushes the clamping assembly so that the two sets of clamping assemblies clamp or release the cable. When the two sets of clamping assemblies release the cable, the cable can be directly removed from above the two sets of clamping assemblies and the supporting assembly, which facilitates the removal of the cable.

[0013] (2) The cable installation and adjustment frame for electric power engineering construction uses a lifting assembly to lift a lifting plate to change the height of a clamping assembly and a supporting assembly, thereby facilitating the installation of cables at different heights. BRIEF DESCRIPTION OF THE DRAWINGS

[0014] Figure 1 It is a schematic diagram of the overall structure of the utility model;

[0015] Figure 2 This is a left view of the overall structure of the utility model;

[0016] Figure 3 It is the right view of the overall structure of the utility model.

[0017] In the figure: 1. bottom plate; 2. lifting plate; 3. clamping assembly; 301. swing bar; 302. clamping plate; 303. connecting bar; 4. supporting assembly; 401. supporting column; 402. first supporting frame; 403. second supporting frame; 5. pushing assembly; 501. supporting plate; 502. first hydraulic push rod; 6. lifting assembly; 601. second hydraulic push rod; 602. top plate; 7. limiting assembly; 701. sliding rod; 702. sliding sleeve; 8. universal wheel. DETAILED DESCRIPTION

[0018] The technical solutions in the embodiments of the present invention will be described clearly and completely below in conjunction with the drawings in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, rather than all of the embodiments. Embodiment 1

[0019] See also Figure 1-3A cable installation and adjustment frame for electric power engineering construction includes a bottom plate 1, a lifting plate 2 is arranged above the bottom plate 1, a clamping assembly 3 is arranged on the left side of the lifting plate 2, the clamping assembly 3 includes a swing bar 301, a clamping plate 302 is fixedly connected to the upper end of the swing bar 301, a connecting bar 303 is hinged at the lower end of the swing bar 301, the number of the clamping assembly 3 is two groups, the two groups of clamping assemblies 3 are cross-arranged on the left side of the lifting plate 2, a support assembly 4 is arranged on the left side of the clamping assembly 3, the support assembly 4 includes a support column 401, the support column 401 is fixedly connected to the left side of the lifting plate 2, the support column 401 and the swing bars 301 in the two groups of clamping assemblies 3 are movably penetrated, the left end of the support column 401 is fixedly connected to the first support frame 402, the support assembly 4 It also includes a second support frame 403, which is fixedly connected to the top of the lifting plate 2, and grooves for supporting cables are arranged on the top of the first support frame 402 and the second support frame 403. A pushing assembly 5 is arranged below the clamping assembly 3, and the pushing assembly 5 includes a supporting plate 501, and the supporting plate 501 is fixedly connected to the left side of the lifting plate 2. A first hydraulic push rod 502 is fixedly connected to the top of the supporting plate 501, and the upper end of the first hydraulic push rod 502 is hinged to the lower end of the connecting strip 303 in the two groups of clamping assemblies 3. A lifting assembly 6 is arranged on the right side of the lifting plate 2, and limit assemblies 7 are arranged on the front and rear surfaces of the lifting plate 2. The number of limit assemblies 7 is two groups, and universal wheels 8 are rotatably connected to the bottom of the base plate 1, and the number of universal wheels 8 is four.

[0020] When in use, first place the cable in the slot above the first support frame 402 and the second support frame 403, then move the base plate 1 through the universal wheel 8 to transport the cable to the place where it needs to be installed, then start the first hydraulic push rod 502, and pull the connecting bar 303 through the contraction of the first hydraulic push rod 502, the connecting bar 303 will pull the lower end of the swing bar 301 downward, the two swing bars 301 will rotate on the support column 401, and the clamping plates 302 at their upper ends will approach each other to clamp the cable, at this time, the lifting plate 2 is driven to rise and fall through the lifting assembly 6, so that the cable is sent to a suitable height, at this time, start the first hydraulic push rod 502 to extend it, and then the clamping plate 302 releases the cable, and the cable can be directly removed from above the first support frame 402 and the second support frame 403, which is convenient for removing the cable. Embodiment 2

[0021] See also Figure 1-3 On the basis of the first embodiment, the lifting assembly 6 includes a second hydraulic push rod 601, which is fixedly connected to the top of the bottom plate 1, and a top plate 602 is fixedly connected to the upper end of the second hydraulic push rod 601, and the top plate 602 is fixedly connected to the right side of the lifting plate 2. The limiting assembly 7 includes a sliding rod 701, which is fixedly connected to the top of the bottom plate 1, and a sliding sleeve 702 is movably provided on the outer surface of the sliding rod 701, and the sliding sleeve 702 is fixedly connected to the lifting plate 2.

[0022] During use, based on the first embodiment, when the cable needs to be sent to a high place, the second hydraulic push rod 601 is first started, and the second hydraulic push rod 601 will push the top plate 602 to rise, thereby driving the lifting plate 2 to make the sliding sleeve 702 on the lifting plate 2 slide and rise on the outer surface of the sliding rod 701. The rise of the lifting plate 2 will drive the first support frame 402 and the second support frame 403 to rise, so that the cable is sent to a high place. At this time, the cable is installed at a high place, and the second hydraulic push rod 601 is started to contract to drive the lifting plate 2 to descend, and the first support frame 402 and the second support frame 403 will descend and leave the cable, thereby facilitating the installation of the cable.

[0023] The above description is only a preferred specific implementation manner of the present invention, but the protection scope of the present invention is not limited thereto. Any technician familiar with the technical field can make equivalent replacements or changes within the technical scope disclosed by the present invention according to the technical scheme and the utility model concept of the present invention, which should be covered by the protection scope of the present invention.

Claims

1. A cable installation and adjustment frame for electric power engineering construction, comprising a base plate (1), characterized in that: A lifting plate (2) is arranged above the bottom plate (1), a clamping assembly (3) is arranged on the left side of the lifting plate (2), the clamping assembly (3) comprises a swing bar (301), the upper end of the swing bar (301) is fixedly connected to a clamping plate (302), the lower end of the swing bar (301) is hinged to a connecting bar (303), the number of the clamping assemblies (3) is two groups, the two groups of the clamping assemblies (3) are respectively arranged crosswise on the left side of the lifting plate (2), a supporting assembly (4) is arranged on the left side of the clamping assembly (3), a pushing assembly (5) is arranged below the clamping assembly (3), a lifting assembly (6) is arranged on the right side of the lifting plate (2), and limit assemblies (7) are arranged on the front and rear surfaces of the lifting plate (2), and a universal wheel (8) is rotatably connected below the bottom plate (1).

2. A cable installation and adjustment frame for electric power engineering construction according to claim 1, characterized in that: The support assembly (4) comprises a support column (401), the support column (401) being fixedly connected to the left side of the lifting plate (2), the support column (401) being movably connected to the swing bars (301) in the two groups of clamping assemblies (3), and the left end of the support column (401) being fixedly connected to a first support frame (402).

3. A cable installation and adjustment frame for electric power engineering construction according to claim 2, characterized in that: The support assembly (4) further comprises a second support frame (403), wherein the second support frame (403) is fixedly connected to the top of the lifting plate (2).

4. A cable installation and adjustment frame for electric power engineering construction according to claim 3, characterized in that: The pushing assembly (5) comprises a supporting plate (501), wherein the supporting plate (501) is fixedly connected to the left side of the lifting plate (2), and a first hydraulic push rod (502) is fixedly connected above the supporting plate (501), wherein the upper end of the first hydraulic push rod (502) is hinged to the lower end of the connecting strips (303) in the two groups of the clamping assemblies (3).

5. A cable installation and adjustment frame for electric power engineering construction according to claim 4, characterized in that: The lifting assembly (6) comprises a second hydraulic push rod (601), the second hydraulic push rod (601) is fixedly connected to the top of the bottom plate (1), the upper end of the second hydraulic push rod (601) is fixedly connected to a top plate (602), and the top plate (602) is fixedly connected to the right side of the lifting plate (2).

6. A cable installation and adjustment frame for electric power engineering construction according to claim 5, characterized in that: The limiting assembly (7) comprises a sliding rod (701), the sliding rod (701) being fixedly connected to the top of the bottom plate (1), a sliding sleeve (702) being movably sleeved on the outer surface of the sliding rod (701), and the sliding sleeve (702) being fixedly connected to the lifting plate (2).

Citation Information

Patent Citations

  • Cable installation adjusting frame for electric power engineering construction

    CN220156097U