Foundation pit single-person excavation device
By designing a single-person excavation device for foundation pits, the combination of traction rope and tie rope is used to solve the problem of high earth transportation cost during foundation pit excavation, and efficient single-person transportation and cost reduction effects are achieved.
Patent Information
- Application Number
- CN202421639503.9
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-07-11
- Publication Date
- 2025-04-25
- Estimated Expiration
- 2034-07-11
AI Technical Summary
During the excavation of artificial foundation pits, workers or mechanical equipment need to be arranged on the top of the foundation pit to complete vertical and horizontal transportation of the earth, resulting in extremely high construction costs.
A single-person excavation device for foundation pits is designed, including a first support frame, a second support frame, a slide, a slide, a slide, a fixed pulley, a soil hopper, a traction rope and a tie rope. The traction rope is used to drive the soil hopper to move on the slide, and the opening and closing of the soil hopper is controlled to realize single-person excavation and transportation of the foundation pit.
It improves construction efficiency, reduces the construction cost of manual excavation of foundation pits, and reduces the number of workers and machinery and equipment required.
Smart Images

Figure CN222796570U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of foundation pit excavation equipment, in particular to a single-person foundation pit excavation device. Background Art
[0002] When excavating artificial foundation pits near important infrastructure such as subways, gas and high-voltage transmission lines, such as bridge abutments and pipeline trenches, it is generally necessary to conduct geophysical exploration and excavation at the same time, which is limited by the small foundation pit space. There are usually 1 to 2 workers excavating in the foundation pit, and 1 to 2 people or excavators, cranes and other mechanical equipment are deployed on the top of the foundation pit to assist in vertical lifting and horizontal transportation of earthwork. However, due to the large investment in labor and machinery, the cost of manual excavation of foundation pits is extremely high.
[0003] Currently, there are earth-moving lifting equipment such as jib cranes on the market, but jib cranes require an operator to be set up on the top of the foundation pit, and the excavation task cannot be completed by a single person. In addition, a power supply is required, and the construction efficiency is low and the construction cost is high. Utility Model Content
[0004] The utility model aims to provide a single-person foundation pit excavation device to solve the problem that when excavating a manual foundation pit, workers or mechanical equipment need to be deployed on the top of the foundation pit to complete vertical and horizontal transportation of earthwork, resulting in extremely high construction costs.
[0005] In order to solve the above technical problems, the technical solutions adopted by the present utility model are as follows:
[0006] A single-person foundation pit excavation device comprises a first support frame, a second support frame, a slideway, a sliding block, a fixed pulley, an earth hopper, a traction rope and a tying rope;
[0007] A first support frame is arranged in the foundation pit;
[0008] A second support frame is arranged outside the foundation pit;
[0009] A slideway is arranged obliquely, one end of which is connected to the first support frame, and the other end of which is connected to the second support frame;
[0010] A slider is slidably arranged on the slideway, and a hook is provided at the bottom of the slider;
[0011] The soil hopper is open at the top and bottom, and the top is connected to the hook by a triangular hanger;
[0012] A tying rope, one end of which is set in the foundation pit, and the other end is connected to the lower part of the soil hopper to complete the sealing of the lower part of the soil hopper;
[0013] A fixed pulley is arranged on a slideway outside the foundation pit;
[0014] One end of the traction rope is set in the foundation pit, and the other end is connected to the slider after passing through the fixed pulley, driving the slider to move on the slideway.
[0015] As a further technical solution of the above solution, a limit block is provided at the bottom of the slideway.
[0016] As a further technical solution of the above solution, the first support frame and the second support frame are triangular supports.
[0017] As a further technical solution of the above solution, the legs of the first support frame and the second support frame can be raised and lowered and adjusted.
[0018] Compared with the prior art, the utility model has the following advantages and beneficial effects: in the device of the utility model, the operator drives the soil bucket to move on the slideway through the traction rope, and uses the tie rope to control the opening and closing of the soil bucket, so as to complete the single-person excavation and transportation of the foundation pit, improve the construction efficiency, and greatly reduce the construction cost of manual excavation of the foundation pit. BRIEF DESCRIPTION OF THE DRAWINGS
[0019] Figure 1 It is a schematic diagram of the use state of the utility model.
[0020] The meanings of the numbers in the figure are: first support frame-1; second support frame-2; slideway-3; slider-4; fixed pulley-5; soil hopper-6; traction rope-7; tying rope-8; hook-9; triangular hanger-10; limit block-11. DETAILED DESCRIPTION
[0021] The following will clearly and completely describe the technical solutions in the embodiments of the utility model in conjunction with the accompanying drawings in the embodiments of the utility model, so as to have a further understanding of the concept of the utility model, the technical problems solved, the technical features constituting the technical solutions and the technical effects brought about.
[0022] like Figure 1 As shown, a single-person foundation pit excavation device includes a first support frame 1, a second support frame 2, a slideway 3, a slider 4, a fixed pulley 5, a soil hopper 6, a traction rope 7 and a tying rope 8;
[0023] A first support frame 1 is arranged in the foundation pit;
[0024] The second support frame 2 is arranged outside the foundation pit;
[0025] The slideway 3 is tilted, one end of which is connected to the first support frame 1 and the other end of which is connected to the second support frame 2;
[0026] A slider 4 is slidably disposed on the slideway 3, and a hook 9 is provided at the bottom of the slider 4;
[0027] The soil hopper 6 is open at the top and bottom, and the top is connected to the hook 9 through a triangular hanger 10;
[0028] A tying rope 8, one end of which is arranged in the foundation pit, and the other end is connected to the lower part of the soil hopper 6 to complete the sealing of the lower part of the soil hopper 6;
[0029] A fixed pulley 5 is arranged on the slideway 3 outside the foundation pit;
[0030] One end of the traction rope 7 is arranged in the foundation pit, and the other end is connected to the slider 4 after passing through the fixed pulley 5, so as to drive the slider 4 to move on the slideway 3.
[0031] When using the device, firstly, a first support frame 1 is set up in the foundation pit, and a second support frame 2 is set up outside the foundation pit. Due to the height difference between the inside and outside of the foundation pit, the slideway 3 arranged between the first support frame 1 and the second support frame 2 is arranged to be inclined. The operator stands in the foundation pit, and the soil hopper 6 slides down into the foundation pit along the slideway 3 through the slider 4 under the influence of gravity. The operator uses the tying rope 8 to tie and seal the bottom of the soil hopper 6. The operator puts the excavated waste soil into the soil hopper 6, pulls the traction rope 7, and After the fixed pulley 5 changes the direction of the force, it drives the sliding block 4 to rise upward along the slideway 3 to the outside of the foundation pit. The operator pulls the tie rope 8 to loosen it, the lower part of the soil hopper 6 opens, and the waste soil falls to the outside of the foundation pit to complete the transportation; after the operator loosens the traction rope 7, the soil hopper 6 falls back into the foundation pit, and the above operations are repeated to complete the excavation of the foundation pit and the transportation of waste soil, effectively reducing the number of excavation personnel for each foundation pit from 2 to 4 people to at least 1 person and zero mechanical equipment, without affecting the construction efficiency, thereby greatly reducing the cost of manual excavation of the foundation pit.
[0032] like Figure 1 As shown, as a preferred embodiment, a limit block 11 is provided at the bottom of the slide 3. In this embodiment, the limit block 11 is provided at the bottom of the slide 3, and when the slider 4 slides downward, it is pressed by the limit block 11 when it slides to the limit block 11 and no longer moves downward, so the operator does not need to pull the traction rope 7 to adjust the position of the soil hopper 6, and the soil hopper 6 is in a suitable position, which is convenient for the operator to load.
[0033] like Figure 1 As shown, as a preferred embodiment, the second support frame 2 is a tripod support. In this embodiment, in order to improve the stability of the device, the second support frame 2 is set as a tripod support.
[0034] like Figure 1 As shown, as a preferred embodiment, the legs of the first support frame 1 can be raised and lowered. In this embodiment, a plurality of adjustment holes are provided on the legs of the first support frame 1. When different heights are required, a cross bar is used to insert the adjustment holes of different heights, and different adjustment holes can be selected according to the height of the foundation pit.
[0035] The words “connection” and “fixation” appearing in the description of the present invention may refer to fixed connection, processing and forming, welding, or mechanical connection. The specific meanings of the above terms in the present invention shall be understood according to the specific circumstances.
[0036] In the description of the present invention, the terms "center", "upper", "lower", "horizontal", "inner", "outer", etc., which indicate the orientation or position relationship, are only for the convenience of describing the present invention and simplifying the description, rather than indicating or implying a specific orientation that the device or element referred to must have, and therefore cannot be understood as a limitation on the present invention.
[0037] Finally, it should be noted that the above embodiments are only used to illustrate the technical solution of the utility model, rather than to limit it. Although the utility model has been described in detail with reference to the aforementioned embodiments, ordinary technicians in the field should understand that they can still modify the technical solutions described in the aforementioned embodiments, or replace some or all of the technical features therein with equivalents. However, these modifications or replacements do not make the essence of the corresponding technical solutions deviate from the scope of the technical solutions of the embodiments of the utility model.
Claims
1. A single-person foundation pit excavation device, characterized in that: It comprises a first support frame (1), a second support frame (2), a slideway (3), a sliding block (4), a fixed pulley (5), an earth hopper (6), a traction rope (7) and a tying rope (8); A first support frame (1) is arranged in the foundation pit; A second support frame (2) is arranged outside the foundation pit; A slideway (3) is arranged obliquely, one end of which is connected to the first support frame (1) and the other end of which is connected to the second support frame (2); A slider (4) is slidably disposed on the slideway (3), and a hook (9) is provided at the bottom of the slider (4); A soil hopper (6) having openings at the top and bottom and a top connected to a hook (9) via a triangular hanger (10); A tying rope (8), one end of which is arranged in the foundation pit, and the other end of which is connected to the lower part of the soil hopper (6) to complete the sealing of the lower part of the soil hopper (6); A fixed pulley (5) is arranged on the slideway (3) outside the foundation pit; A traction rope (7) has one end disposed in the foundation pit and the other end connected to the slider (4) after passing through the fixed pulley (5), thereby driving the slider (4) to move on the slideway (3).
2. A single-person foundation pit excavation device as claimed in claim 1, characterized in that: A limiting block (11) is provided at the bottom of the slideway (3).
3. A single-person foundation pit excavation device as claimed in claim 1, characterized in that: The second support frame (2) is a tripod support frame.
4. A single-person foundation pit excavation device as claimed in claim 1, characterized in that: The legs of the first support frame (1) can be raised and lowered and adjusted.