Overflow system of thickener and mineral separation system

By designing a dense machine overflow system using sewage pumps and PE pipelines, the problem of transformation difficulty and waste in the prior art is solved, and lower investment and faster construction speed are achieved, adapting to water fluctuations and saving energy.

CN222804745UActive Publication Date: 2025-04-29MCC SHENKAN ENG TECH CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420549899.1
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-03-21
Publication Date
2025-04-29
Estimated Expiration
2034-03-21

AI Technical Summary

Technical Problem

The existing bushing overflow system needs to be modified when process changes, resulting in waste of pipeline pumps and pipelines and high construction difficulty, affecting production progress and causing economic losses.

Method used

Design a dense machine overflow system, using sewage pumps and PE pipelines, which are compact and can be placed directly in the water tank. The PE pipes can be purchased in a disk and quickly connected, reducing construction difficulty and time.

Benefits of technology

Reduced renovation investment and construction time, improved construction efficiency and energy utilization, adapted to water fluctuations in process debugging, and saved energy.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222804745U_ABST
    Figure CN222804745U_ABST
Patent Text Reader

Abstract

The utility model relates to the technical field of mineral separation, in particular to a thickener overflow system and a mineral separation system.The thickener overflow system comprises a thickener body, an overflow weir is arranged above the thickener body, a first overflow port and a second overflow port are formed in the overflow weir, the first overflow port is communicated with a first pipeline pump through a first overflow pipe, and the second overflow port is communicated with a second pipeline pump through a second overflow pipe. The second overflow opening is communicated with the water tank through a second overflow pipe, and a sewage pump is arranged in the water tank. Compared with the prior art, an original pipeline pump and an original pipeline are kept unchanged, a set of overflow water system is additionally laid, and the sewage pump and the PE pipeline are adopted. Therefore, the additionally arranged overflow water system is lower in investment and higher in construction speed, water quantity fluctuation in the flow debugging process can be better used, and meanwhile energy can be better saved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of ore dressing, in particular to a thickener overflow system and an ore dressing system. Background Art

[0002] The function of the thickener is to thicken the ore pulp. The thickened high-concentration ore pulp flows out from the bottom discharge pipe, and the clean water overflows from the top of the thickener. Under most conditions, this overflow water will be pumped to the high-level water tank for reuse through the pipeline pump. In the early stage of construction, the pipeline pump and the supporting pipelines are determined after calculation. If the front-end process changes, resulting in an increase in the amount of ore and water entering the thickener, then the pipeline pump and the pipeline overflow water system need to be modified.

[0003] In the past, the renovation method was to directly replace the pipeline pump and pipeline. After the pipeline pump was replaced, the original pump and pipeline were basically abandoned, resulting in waste. In addition, the pipeline laying project is very large, requiring a lot of manpower, material and financial resources, especially for sites with poor construction environment, the construction is more difficult, and the construction period is naturally increased. For on-site production, time is very important. The time for the renovation of the overflow water system will delay the progress of the new process and bring certain economic losses.

[0004] In view of this, the present utility model is proposed. Utility Model Content

[0005] In view of the above-mentioned deficiencies in the prior art, the utility model provides a thickener overflow system and a mineral processing system to solve the problems raised in the above-mentioned background technology.

[0006] In order to achieve one of the above purposes, the utility model provides the following technical solutions:

[0007] A thickener overflow system comprises a thickener body, an overflow weir is arranged above the thickener body, a first overflow port and a second overflow port are respectively opened on the overflow weir, the first overflow port is connected to a first pipeline pump through a first overflow pipe, the second overflow port is connected to a water tank through a second overflow pipe, and a sewage pump is arranged in the water tank.

[0008] Preferably, a check valve is provided on the outlet pipe of the sewage pump.

[0009] Preferably, the number of the sewage pumps is three.

[0010] Preferably, a float switch is provided in the water tank.

[0011] Preferably, the floating switch includes a first switch position and a second switch position, and the first switch position is located below the second switch position;

[0012] The first switch position controls the on and off of a sewage pump;

[0013] The second switch position controls the opening and closing of another sewage pump.

[0014] Preferably, the diameters of the outlet pipe of the sewage pump and the second overflow pipe are 110 mm.

[0015] Preferably, the water tank has a size of 3×1.5×1.5 meters.

[0016] Preferably, the first switch position is 1 m away from the bottom of the water tank; the second switch position is 1.3 m away from the bottom of the water tank.

[0017] In order to achieve the second purpose above, the utility model provides the following technical solutions:

[0018] A mineral processing system comprises a thickener overflow system as described above.

[0019] Preferably, the water tank is a shaft sealing water tank or a cooling water tank.

[0020] Compared with the prior art, the thickener overflow system and ore dressing system proposed by the utility model have the following advantages:

[0021] 1. In the thickener overflow system and mineral processing system proposed by the utility model, the original pipeline pump and pipeline are maintained unchanged, and an overflow water system is laid, which adopts a sewage pump and a PE pipeline. The sewage pump is small in size and does not require a separate foundation, and can be placed directly in the water tank. PE pipes can be purchased in reels, each reel is several dozen meters. It can be constructed faster with quick connectors, and its advantages can be more prominent in complex terrain conditions compared with flange connection or welding. The newly added overflow water system has lower investment, faster construction speed, and can better use the water volume fluctuations during process debugging, and can also better save energy.

[0022] 2. The thickener overflow system and mineral processing system proposed by the utility model can also utilize the existing water tanks in the workshop and solve some production problems. By using the original shaft seal water tank, the water replenishment problem of the water tank can be solved; by using the original cooling water tank, the flowing water can solve the heat dissipation problem of the water tank.

[0023] 3. In the thickener overflow system and mineral processing system proposed by the utility model, the working characteristics of the sewage pump need to be completely under the water surface to ensure its heat dissipation. Therefore, two working positions are set by using a floating switch. Position 1 is at 1m, which is the lowest pump start water level. Only when the water level is higher than this level can one sewage pump be started; when the liquid level reaches position 2, that is, 1.3m, the second sewage pump is started.

[0024] In order to make the above-mentioned objects, features and advantages of the present invention more obvious and easy to understand, preferred embodiments are given below and described in detail with reference to the accompanying drawings. BRIEF DESCRIPTION OF THE DRAWINGS

[0025] In order to more clearly illustrate the technical solutions of the embodiments of the utility model, the drawings required for use in the embodiments will be briefly introduced below. It should be understood that the following drawings only show certain embodiments of the utility model and therefore should not be regarded as limiting the scope. For ordinary technicians in this field, other relevant drawings can be obtained based on these drawings without paying creative work.

[0026] Figure 1 A schematic structural diagram of a thickener overflow system provided in an embodiment of the utility model.

[0027] Figure 2 A schematic structural diagram of a water tank in a thickener overflow system provided in an embodiment of the utility model.

[0028] The diagram is as follows:

[0029] 100, thickener body; 200, overflow weir; 300, first pipeline pump; 400, first overflow pipe; 500, second overflow pipe; 600, water tank;

[0030] 610, sewage pump; 620, check valve; 630, float switch; 640, first switch position; 650, second switch position. DETAILED DESCRIPTION

[0031] The following will be combined with the drawings in the embodiments of the utility model to clearly and completely describe the technical solutions in the embodiments of the utility model. Obviously, the described embodiments are only a part of the embodiments of the utility model, rather than all the embodiments. The components of the embodiments of the utility model generally described and shown in the drawings here can be arranged and designed in various different configurations. Therefore, the following detailed description of the embodiments of the utility model provided in the drawings is not intended to limit the scope of the utility model claimed for protection, but merely represents the selected embodiments of the utility model. Based on the embodiments of the utility model, all other embodiments obtained by those skilled in the art without making creative work belong to the scope of protection of the utility model.

[0032] like Figure 1As shown, an embodiment of the utility model provides a thickener overflow system, including a thickener body 100, an overflow weir 200 is arranged above the thickener body 100, a first overflow port and a second overflow port are respectively opened on the overflow weir 200, the first overflow port is connected to the first pipeline pump 300 through a first overflow pipe 400, and the second overflow port is connected to the water tank 600 through a second overflow pipe 500, and a sewage pump 610 is arranged in the water tank 600.

[0033] In the thickener overflow system proposed by the utility model, the original pipeline pump and pipeline are maintained unchanged, and an overflow water system is laid, using a sewage pump 610 and a PE pipeline. The sewage pump 610 is small in size and does not need to be separately made into a foundation, and can be directly placed in the water tank 600. In this way, the newly added overflow water system has a lower investment, a faster construction speed, and can better use the water volume fluctuation during the process debugging process, and can also better save energy.

[0034] In addition, in the preferred embodiments of the above embodiments, quick connectors are used to connect the second overflow port and the second overflow pipe 500, the second overflow pipe 500 and the water tank 600, the sewage pump 610 and its outlet pipe, etc., so that the use of quick connectors in the utility model can enable faster construction, and its advantages can be more prominent under complex terrain conditions compared to flange connections or welding.

[0035] like Figure 2 As shown, the embodiment of the utility model provides a thickener overflow system. The working characteristics of the sewage pump 610 require it to be completely under the water surface to ensure its heat dissipation. Therefore, a check valve 620 is provided on the outlet pipe of the sewage pump 610, so that the water in the outlet pipe can flow back to the water tank 600 when the pump is stopped, thereby ensuring that there is always water in the water tank 600.

[0036] The embodiment of the utility model provides a thickener overflow system, wherein the number of the sewage pumps 610 is three, two in use and one in reserve.

[0037] In addition, as mentioned above, the working characteristics of the sewage pump 610 require that it be completely under the water surface to ensure its heat dissipation; therefore, a floating switch 630 is provided in the water tank 600; the floating switch 630 includes a first switch position 640 and a second switch position 650, the first switch position 640 is located below the second switch position 650; the first switch position 640 controls the opening and closing of one sewage pump 610; the second switch position 650 controls the opening and closing of another sewage pump 610. In this way, the first switch position 640 is the lowest pump start water level, and only one sewage pump 610 can be started above this water level; when the liquid level reaches the second switch position 650, the second sewage pump 610 is started.

[0038] The embodiment of the utility model provides a thickener overflow system, the sewage pump 610 and the pipe diameter of the connected pipe are selected to be 110 mm, and the PE pipe under this pipe diameter can be coiled into 50m or 30m coils, which is convenient for transportation and installation, and the transformation efficiency is greatly increased.

[0039] The following is the specific transformation method of the applicant on site: adding 200m 3 Taking overflow water as an example, the flow rate or quantity of the sewage pump 610 can be adjusted according to the specific situation. First, a hole with a diameter of 200mm is opened from the overflow weir 200 of the thickener, and a water pipe with an inner diameter of 200mm is connected to allow the overflow water to flow to the water tank 600 below. Since the thickener has a certain height and a certain degree of construction difficulty, the overflow water pipe is made of PE material. The size of the water tank 600 is 3×1.5×1.5 meters (length×width×height), so a 6-meter steel plate is just enough to make a water tank 600. Three flow rates of 100m 3 / h sewage pump 610, 2 for 1 standby, a check valve 620 is set at the pump outlet to prevent the water in the pipeline from flowing back to the water tank 600 when the pump is stopped. The pipe diameter of the sewage pump 610 is selected to be 110mm. The PE pipe under this pipe diameter can be coiled into 50m or 30m coils, which is convenient for transportation and installation, and the transformation efficiency is greatly increased. Due to the working characteristics of the sewage pump 610, it needs to be completely under the water surface to ensure its heat dissipation. Therefore, two working positions are set using the floating switch 630. Position 1 is at 1m, which is the lowest pump start water level. Only when the water level is higher than this level can one sewage pump 610 be started; when the liquid level reaches position 2, that is, 1.3m, the second sewage pump 610 is started.

[0040] The utility model embodiment also provides a mineral processing system, comprising a thickener overflow system as described above, the thickener overflow system comprises a thickener body 100, an overflow weir 200 is arranged above the thickener body 100, a first overflow port and a second overflow port are respectively opened on the overflow weir 200, the first overflow port is connected to the first pipeline pump 300 through the first overflow pipe 400, the second overflow port is connected to the water tank 600 through the second overflow pipe 500, and a sewage pump 610 is arranged in the water tank 600.

[0041] In the mineral processing system provided by the above embodiment, the water tank 600 can also use the existing water tanks in the workshop of the mineral processing system, and can solve some production problems. For example, by using the shaft sealing water tank, the water replenishment problem of the water tank 600 can be solved; by using the cooling water tank, the flowing water can solve the heat dissipation problem of the water tank 600.

[0042] In the description of the present utility model, it should be noted that the terms "center", "upper", "lower", "left", "right", "vertical", "horizontal", "inside", "outside", etc. indicate the orientation or position relationship based on the orientation or position relationship shown in the accompanying drawings, or the orientation or position relationship in which the utility model product is usually placed when in use, which is only for the convenience of describing the utility model and simplifying the description, and does not indicate or imply that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore cannot be understood as a limitation on the present utility model. In addition, the terms "first", "second", "third", etc. are only used to distinguish the description, and cannot be understood as indicating or implying relative importance.

[0043] In addition, the terms "horizontal", "vertical", "overhanging" and the like do not mean that the components are required to be absolutely horizontal or overhanging, but can be slightly tilted. For example, "horizontal" only means that its direction is more horizontal than "vertical", and does not mean that the structure must be completely horizontal, but can be slightly tilted.

[0044] In the description of the present invention, it is also necessary to explain that, unless otherwise clearly specified and limited, the terms "set", "install", "connect", and "connect" should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection, or it can be indirectly connected through an intermediate medium, or it can be the internal communication of two components. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.

[0045] The above description is only a preferred embodiment of the utility model and is not intended to limit the utility model. For those skilled in the art, the utility model may have various modifications and changes. Any modifications, equivalent substitutions, improvements, etc. made within the spirit and principles of the utility model should be included in the protection scope of the utility model. It should be noted that similar numbers and letters represent similar items in the following drawings. Therefore, once an item is defined in one drawing, it does not need to be further defined and explained in the subsequent drawings.

Claims

1. A thickener overflow system, characterized in that: It includes a thickener body, an overflow weir is arranged above the thickener body, a first overflow port and a second overflow port are respectively opened on the overflow weir, the first overflow port is connected to the first pipeline pump through a first overflow pipe, the second overflow port is connected to the water tank through a second overflow pipe, and a sewage pump is arranged in the water tank.

2. A thickener overflow system according to claim 1, characterized in that: A check valve is arranged on the outlet pipe of the sewage pump.

3. A thickener overflow system according to claim 2, characterized in that: The number of the sewage pumps is three.

4. A thickener overflow system according to claim 3, characterized in that: A float switch is arranged in the water tank.

5. A thickener overflow system according to claim 4, characterized in that: The floating switch includes a first switch position and a second switch position, wherein the first switch position is located below the second switch position; The first switch position controls the on and off of a sewage pump; The second switch position controls the opening and closing of another sewage pump.

6. A thickener overflow system according to claim 5, characterized in that: The diameters of the outlet pipe of the sewage pump and the second overflow pipe are 110 mm.

7. A thickener overflow system according to claim 6, characterized in that: The water tank has dimensions of 3 x 1.5 x 1.5 m.

8. A thickener overflow system according to claim 7, characterized in that: The first switch position is 1m away from the bottom of the water tank; the second switch position is 1.3m away from the bottom of the water tank.

9. A mineral processing system, characterized in that: It comprises a thickener overflow system as described in any one of claims 1-8.

10. A mineral processing system according to claim 9, characterized in that: The water tank is a shaft sealing water tank or a cooling water tank.