Steel guide beam for roadbed slab-pile wall construction
By designing a steel guide beam system including support beams, wide-directional calibration blocks and long-directional calibration blocks, the problem of inconvenience in the construction of roadbed pile panel walls is solved, and the convenient calibration and stable fixation of steel guide beams is achieved, and the construction efficiency is improved.
Patent Information
- Application Number
- CN202421643239.6
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-07-11
- Publication Date
- 2025-05-06
- Estimated Expiration
- 2034-07-11
AI Technical Summary
In the construction of roadbed pile panel walls, there is a lack of effective auxiliary tools in the erection and calibration process of steel guide beams, which leads to inconvenient installation and complex calibration operations, which affects construction efficiency.
A steel guide beam system including support beam, wide-directional calibration block and long-directional calibration block is designed. Through the combination of pallets, wide-directional calibration block and long-directional calibration block, the width and length of the steel guide beam segments are realized, and the erection and fixation of the steel guide beam is conveniently completed.
Through this system, the calibration process of steel guide beams can be significantly simplified, construction efficiency can be improved, the stability and straightness of steel guide beams can be ensured, and the requirements of pile driving operations can be met.
Smart Images

Figure CN222834895U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of roadbed construction, in particular to a steel guide beam for roadbed pile-sheet wall construction. Background Art
[0002] In the construction of roadbed pile-sheet walls, the construction site needs to be leveled first, and then the foundation is poured on both sides of the area where the steel sheet piles are to be driven as needed. Subsequently, steel guide beams need to be erected on the foundation before the steel sheet piles are driven. At present, the erection of steel guide beams is carried out by temporary on-site lifting and connection. In the actual operation process, the support of the steel guide beams and the connection between the two adjacent steel guide beam segments are all installed on-site, resulting in the need to repeatedly measure and inspect the erected steel guide beams after installation to ensure that the steel guide beams are straight and meet the requirements of the pile driving operation. Due to the lack of effective auxiliary tools during the alignment of the steel guide beams, the alignment of the steel guide beams is relatively inconvenient. Utility Model Content
[0003] In order to solve the above technical problems, the utility model provides a steel guide beam for roadbed pile-sheet wall construction.
[0004] The technical solution of the utility model is achieved in this way:
[0005] A steel guide beam for roadbed pile-sheet wall construction, comprising:
[0006] A support beam, the top of which is provided with a support plate for supporting the steel guide beam segment;
[0007] A widthwise alignment block is installed on the support plate in a lifting manner, and the widthwise alignment block centers the steel guide beam segment on the support plate by moving upward from the bottom of the support plate;
[0008] The lengthwise alignment block is elastically supported on the support plate, and the top end of the widthwise alignment block is arranged in a step shape, and the top surfaces of the two steps are respectively used to press down the butt ends of the two butt-jointed steel guide beam segments.
[0009] Furthermore, when the steel guide beam segment on the support plate is centered in the width direction, the inward side surface of the support plate is flush with the inner side surface of the steel guide beam segment.
[0010] Furthermore, the widthwise alignment block includes a first part and a second part which are distributed up and down, the first part is an isosceles trapezoidal structure, the second part is a rectangular structure, and the width of the second part is set to match the width of the inner cavity of the steel guide beam segment.
[0011] Furthermore, a height adjustment bolt is installed at the bottom of the widthwise calibration width, and the height adjustment bolt is threadedly installed on the support plate.
[0012] Furthermore, the support plate is provided with a first displacement groove and a second displacement groove for the up and down displacement of the widthwise calibration block and the lengthwise calibration block respectively. The widthwise calibration block is slidably arranged in the first displacement groove, and the lengthwise calibration block is slidably arranged in the second displacement groove.
[0013] Furthermore, a first supporting spring is connected to the bottom of the longitudinal alignment block, and the first supporting spring is used to keep the height of the top surfaces of the two steps of the longitudinal alignment block greater than the height of the support plate.
[0014] Furthermore, a retractable fixing bolt is arranged on the top of the widthwise alignment block, a through hole for the fixing screw to pass through is arranged on the steel guide beam segment, and when the steel guide beam segment is centrally distributed on the support plate, the top end of the fixing bolt passes through the through hole.
[0015] Furthermore, a telescopic groove for accommodating the fixing bolt is provided at the top of the widthwise alignment block, and a second spring for pushing up the fixing bolt is provided in the telescopic groove.
[0016] The utility model has the following beneficial effects:
[0017] 1. Fix the support beam at the end of the steel guide beam segment first, and then directly hoist the steel guide beam segment onto the pallet, so that the end of the steel guide beam segment is supported by the pallet. In the process of lowering the steel guide beam segment onto the pallet, use the lengthwise alignment block to directly calibrate the position of the steel guide beam segment in the length direction. Then, use each widthwise alignment block to calibrate the steel guide beam segment in the width direction in turn, so that the steel guide beam segment can be centered in the width direction, and the steel guide beam erection operation can be realized conveniently by alignment, thereby improving the efficiency of roadbed pile-sheet wall construction.
[0018] 2. When the steel guide beam segment is centered on the support plate, the top of the fixing bolt will automatically pass through the through hole and then be connected to the fixing bolt with a nut, thereby fixing the steel guide beam segment on the support plate and improving the stability of the steel guide beam segment. BRIEF DESCRIPTION OF THE DRAWINGS
[0019] Figure 1 It is a schematic diagram of the utility model when erecting a steel guide beam;
[0020] Figure 2 It is an overall schematic diagram of the support plate, the transverse alignment block and the longitudinal alignment block of the utility model;
[0021] Figure 3 This utility model Figure 2 A cross-sectional view of
[0022] Figure 4 It is an overall schematic diagram of the support plate of the utility model;
[0023] Figure 5 It is a schematic diagram of the widthwise alignment block of the utility model. DETAILED DESCRIPTION
[0024] The technical solutions in the embodiments of the present invention are described clearly and completely below. Obviously, the described embodiments are only a part of the embodiments of the present invention, not all of them. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0025] like Figures 1 to 5 As shown, a steel guide beam for roadbed pile-sheet wall construction comprises:
[0026] A support beam 1, the top of which is provided with a support plate 2 for supporting the steel guide beam segment;
[0027] A widthwise alignment block 3 is installed on the support plate 2 in a manner that it can be raised or lowered, and the widthwise alignment block 3 centers the steel guide beam segment on the support plate 2 by moving upward from the bottom of the support plate 2;
[0028] The lengthwise alignment block 4 is elastically supported on the support plate 2, and the top end of the widthwise alignment block 3 is arranged in a step shape, and the top surfaces of the two steps are respectively used to press down the butt ends of the two butt-jointed steel guide beam segments.
[0029] In the operation of erecting the steel guide beam, the support beam 1 is first arranged and fixed in sequence according to the segment length of the steel guide beam, and then the steel guide beam segment is directly hoisted onto the support plate 2 by using a crane. For the support plate 2 between the butt ends of the two steel guide beam segments, when placing the two steel guide beam segments one after another, the first steel guide beam segment to be lowered should be pressed on a step with a lower top surface height of the lengthwise alignment block 4. At this time, the side of a step with a higher height has a limiting effect on the end of the first steel guide beam segment to be lowered. The steel guide beam segment to be lowered later should be pressed on a step with a higher top surface height of the lengthwise alignment block 4. At this time, the end of the first steel guide beam to be lowered has a limiting effect on the end of the later steel guide beam to be lowered. Afterwards, the widthwise alignment block 3 is displaced upward on the support plate 2 to achieve alignment of the steel guide beam segment in the width direction.
[0030] When the steel guide beam segments on the support plate 2 are centered in the width direction, the inward side of the support plate 2 is flush with the inner side of the steel guide beam segments. At this time, it is ensured that there is enough gap between the two rows of steel guide beams for the steel sheet piles to be inserted.
[0031] The widthwise alignment block 3 includes a first part 3.1 and a second part 3.2 which are distributed up and down. The first part 3.1 is an isosceles trapezoidal structure, and the second part 3.2 is a rectangular structure. The width of the second part 3.2 is set to match the width of the inner cavity of the steel guide beam segment. During the upward displacement of the widthwise alignment block, the first part 3.1 compares the steel guide beam segment in the width direction through the inclined surfaces on both sides thereof. When the second part 3.2 moves into the bottom cavity of the steel guide beam segment, the alignment of the steel guide beam segment in the width direction can be achieved.
[0032] A height adjustment bolt 5 is installed at the bottom of the widthwise calibration block 2, and the height adjustment bolt 5 is threadedly installed on the support plate 2. By rotating the height adjustment bolt 5, the lifting and lowering of the widthwise calibration block 3 can be controlled.
[0033] The pallet 2 is provided with a first displacement groove 6 and a second displacement groove 7 for the up and down displacement of the widthwise alignment block 3 and the lengthwise alignment block 4, respectively. The widthwise alignment block 3 is slidably arranged in the first displacement groove 6, and the lengthwise alignment block 4 is slidably arranged in the second displacement groove 7. When the steel guide beam segment is placed on the pallet 2 in the initial state, the widthwise alignment block 3 is located below the pallet 2 to facilitate the lowering operation of the steel guide beam stage.
[0034] The bottom of the longitudinal alignment block 4 is connected to a first support spring 8, which is used to keep the height of the top surfaces of the two steps of the longitudinal alignment block 4 greater than the height of the support plate 2. In the initial state, the top of the longitudinal alignment block 4 extends to the area above the support plate 2. When the end of the steel guide beam segment is lowered, the end of the steel guide beam segment is aligned in the length direction using the step groove, so that the support plate 2 can be centrally supported below the butt ends of the two steel guide beam segments. A retractable fixing bolt 9 is provided at the top of the width alignment block 3, and a through hole for the fixing screw to pass through is provided on the steel guide beam segment, and when the steel guide beam segment is centrally distributed on the support plate 2, the top of the fixing bolt 9 passes through the through hole. A telescopic groove 10 for accommodating the fixing bolt 9 is provided at the top of the width alignment block 3, and a second spring 11 for pushing up the fixing bolt 9 is provided in the telescopic groove 10.
[0035] During the process of the widthwise calibration block 3 moving upward to calibrate the position of the steel guide beam segment in the width direction, the fixing bolt 9 is pressed down by the steel guide beam segment to be accommodated in the expansion slot 10. When the steel guide beam segment is centered, the through hole is aligned with the top end of the fixing bolt 9. At this time, the fixing bolt 9 passes through the through hole under the elastic action of the second spring 11, and then the fixing bolt 9 is connected with a nut, so that the steel guide beam segment can be fixed on the support plate 2.
[0036] The above description is only a preferred embodiment of the present invention and is not intended to limit the present invention. Any modifications, equivalent substitutions, improvements, etc. made within the spirit and principles of the present invention should be included in the protection scope of the present invention.
Claims
1. A steel guide beam for roadbed pile-sheet wall construction, characterized in that: include: A support beam (1) having a support plate (2) disposed at the top thereof for supporting the steel guide beam segment; A widthwise alignment block (3) which is installed on the support plate (2) in a manner that it can be raised or lowered, and the widthwise alignment block (3) is used to center and align the steel guide beam segment on the support plate (2) by moving upward from the bottom of the support plate (2); The longitudinal alignment block (4) is elastically supported on the support plate (2), and the top end of the widthwise alignment block (3) is arranged in a step shape, and the top surfaces of the two steps are respectively used to press down the butt ends of the two butt-jointed steel guide beam segments.
2. A steel guide beam for roadbed pile-sheet wall construction according to claim 1, characterized in that: When the steel guide beam segment on the support plate (2) is centered in the width direction, the inward side surface of the support plate (2) is flush with the inner side surface of the steel guide beam segment.
3. The steel guide beam for roadbed pile-sheet wall construction according to claim 1, characterized in that: The widthwise alignment block (3) comprises a first part (3.1) and a second part (3.2) which are distributed up and down, the first part (3.1) being an isosceles trapezoidal structure, the second part (3.2) being a rectangular structure, and the width of the second part (3.2) being arranged to match the width of the inner cavity of the steel guide beam segment.
4. The steel guide beam for roadbed pile-sheet wall construction according to claim 1, characterized in that: A height adjustment bolt (5) is installed at the bottom of the widthwise calibration width, and the height adjustment bolt (5) is threadedly installed on the support plate (2).
5. The steel guide beam for roadbed pile-sheet wall construction according to claim 1, characterized in that: The support plate (2) is provided with a first displacement groove (6) and a second displacement groove (7) for respectively displacing the widthwise alignment block (3) and the lengthwise alignment block (4) up and down; the widthwise alignment block (3) is slidably disposed in the first displacement groove (6), and the lengthwise alignment block (4) is slidably disposed in the second displacement groove (7).
6. The steel guide beam for roadbed pile-sheet wall construction according to claim 1, characterized in that: A first supporting spring (8) is connected to the bottom of the longitudinal alignment block (4), and the first supporting spring (8) is used to keep the height of the top surfaces of the two steps of the longitudinal alignment block (4) greater than the height of the support plate (2).
7. The steel guide beam for roadbed pile-sheet wall construction according to claim 1, characterized in that: A retractable fixing bolt (9) is arranged on the top of the widthwise alignment block (3), and a through hole for the fixing screw to pass through is arranged on the steel guide beam segment, and when the steel guide beam segment is centrally distributed on the support plate (2), the top end of the fixing bolt (9) passes through the through hole.
8. The steel guide beam for roadbed pile-sheet wall construction according to claim 7, characterized in that: A telescopic groove (10) for accommodating the fixing bolt (9) is arranged at the top of the widthwise alignment block (3), and a second spring (11) for pushing up the fixing bolt (9) is arranged in the telescopic groove (10).