Pile driver for water conservancy construction

By designing and cleaning components in the pile driver, including pulling holes, positioning columns, pulling plates, limit frames, threaded rods and brushes, the problems of wet soil adhesion and rust on the surface of the spiral blade are solved, achieving more efficient pile driving effects and longer service life.

CN222847355UActive Publication Date: 2025-05-09SICHUAN HONGSEN IND CO LTD
View PDF 1 Cites 0 Cited by

Patent Information

Application Number
CN202421464194.6
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-06-25
Publication Date
2025-05-09
Estimated Expiration
2034-06-25

AI Technical Summary

Technical Problem

After the existing pile drivers drive the pile body into the soil, wet soil adheres to the surface of the spiral blade, resulting in stickiness problems and rust, affecting the subsequent pile driving effect.

Method used

A pile driver for water conservancy construction is designed, which includes cleaning components, including pulling holes, positioning columns, pulling plates, limiting frames, threaded rods and brushes. Through the combination of these components, wet soil on the surface of the spiral blade can be cleaned and corrosion can be prevented.

Benefits of technology

It effectively prevents wet soil from adhesion and rust on the surface of the spiral blade, and improves the service life and pile driving efficiency of the pile driver.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222847355U_ABST
    Figure CN222847355U_ABST
Patent Text Reader

Abstract

According to the technical scheme, the pile driver for water conservancy construction is characterized in that the pile driver comprises a pile driver body, and two mounting plates are fixedly mounted on one side of a pile driver body support; and the cleaning assemblies are arranged on one sides of the two mounting plates correspondingly and used for cleaning soil, each cleaning assembly comprises two drawing holes, the two drawing holes are formed in one sides of the two mounting plates correspondingly, positioning columns are fixedly mounted in the drawing holes, drawing plates are movably connected in the drawing holes in a sleeved mode, and the positioning columns are fixedly mounted in the drawing holes. And a positioning hole is formed in the top surface of the drawing plate, and under the mutual cooperation action of the pile driver body, the mounting plate, the drawing hole, the positioning column, the drawing plate, the positioning hole, a limiting frame, a positioning block, a threaded hole, a threaded rod and a brush, wet soil attached to the surface of a spiral blade of the pile driver body after piling is difficult to clean by workers; the surface of the spiral blade is prevented from being rusted after a long time.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of pile drivers, in particular to a pile driver for water conservancy construction. Background Art

[0002] A pile driver consists of a pile hammer, a pile frame and ancillary equipment. The pile hammer is attached between two parallel vertical guide rods (commonly known as gantry) at the front of the pile frame and is lifted by a lifting hook. The pile frame is a steel structure tower with a winch at the rear to lift the pile and the pile hammer. There is a guide frame composed of two guide rods in front of the pile frame to control the direction of piling so that the pile can be accurately penetrated into the formation according to the designed direction. The basic technical parameters of a pile driver are the weight of the impact part, the impact kinetic energy and the impact frequency. Pile hammers can be divided into drop hammers, steam hammers, diesel hammers, hydraulic hammers, etc. according to the power source of the movement.

[0003] For example, the Chinese patent with publication number CN204982887U proposes a pile driver. The patent has a guide rail forward tilting mechanism and a guide rail swinging mechanism. The guide rail forward tilting mechanism can drive the guide rail to tilt forward and backward, so as to adjust the forward and backward tilting angle of the pile hammer; the guide rail swinging mechanism can drive the guide rail to swing freely left and right and move the guide rail up and down as a whole, so as to adjust the pile driving angle of the pile hammer and facilitate driving, and the pile driving efficiency is high. However, in this scheme, after the pile driver drives the pile body into the soil, the spiral blade rises and wet soil is attached to its surface after leaving the pile hole. The wet soil is sticky, and the wet soil may adhere to the surface of the spiral blade, which may cause the spiral blade to rust, thereby affecting the subsequent piling effect of the spiral blade. Utility Model Content

[0004] In view of the deficiencies in the prior art, the utility model provides a pile driver for water conservancy construction, which solves the problem that after the pile driver drives the pile body into the soil, the spiral blade rises and after leaving the pile hole, wet soil adheres to the surface of the spiral blade, and the wet soil is sticky, so the wet soil may adhere to the surface of the spiral blade, which may cause the spiral blade to rust, thereby affecting the subsequent piling effect of the spiral blade.

[0005] The above technical objectives of the utility model are achieved through the following technical solutions:

[0006] 4. The repairing kit for automotive dents, according to claim 1, wherein the two bosses are designed to be closely connected to the base frame, and the bosses are configured to be closely connected to the base frame, and the bosses are configured to be closely connected to the base frame.

[0007] In order to move the pile driver body, as a pile driver for water conservancy construction of the utility model, it is preferred that two fixing plates are fixedly installed on one side of the pile driver body bracket, and mounting holes are respectively opened on the sides of the two fixing plates close to each other, and the inner circular wall surface of the mounting hole is fixedly sleeved with a bearing, the inner ring of the bearing is fixedly sleeved with a positioning rod, and the outer circular wall surface of the positioning rod is fixedly sleeved with two wheels.

[0008] In order to make the pile driver body placed on the ground more stably, as a pile driver for water conservancy construction of the utility model, preferably, a plurality of gaskets are fixedly installed on the bottom surface of the pile driver body bracket, and a positioning cone is fixedly installed on the bottom surface of the gasket.

[0009] In order to facilitate the staff to push the pile driver body, as a pile driver for water conservancy construction of the utility model, preferably, two positioning plates are fixedly installed on one side of the pile driver body bracket, and a gripping rod is fixedly installed between the two positioning plates.

[0010] In order to facilitate the staff to rotate the threaded rod, as a pile driver for water conservancy construction of the utility model, preferably, a handle is fixedly installed on the top surface of the threaded rod.

[0011] In order to prevent the surfaces of the positioning columns, pull-out plates, limit frames, threaded rods and positioning cones from rusting after long-term use and affecting their service life, as a pile driver for water conservancy construction in the utility model, it is preferred that the surfaces of the mounting plate, the positioning columns, the pull-out plates, the limit frames, the threaded rods and the positioning cones are respectively coated with anti-corrosion paint.

[0012] In summary, the utility model mainly has the following beneficial effects:

[0013] Through the mutual cooperation of the pile driver body, mounting plate, pull-out hole, positioning column, pull-out plate, positioning hole, limit frame, positioning block, threaded hole, threaded rod and brush, it is possible to make it difficult for workers to clean the wet soil attached to the surface of the spiral blade of the pile driver body after piling, thereby preventing the surface of the spiral blade from rusting after a long time. BRIEF DESCRIPTION OF THE DRAWINGS

[0014] Figure 1 It is a three-dimensional structural schematic diagram of the utility model;

[0015] Figure 2 yes Figure 1 A partial schematic diagram of the middle part;

[0016] Figure 3 yes Figure 1 A partial schematic diagram of B in the middle;

[0017] Figure 4 It is a front view schematic diagram of the main structure of the pile driver of the utility model.

[0018] Figure numerals: 1. pile driver body; 2. mounting plate; 3. pull-out hole; 4. positioning column; 5. pull-out plate; 6. positioning hole; 7. limit frame; 8. positioning block; 9. threaded hole; 10. threaded rod; 11. brush; 12. fixing plate; 13. mounting hole; 14. bearing; 15. positioning rod; 16. wheel; 17. gasket; 18. positioning cone; 19. positioning plate; 20. grip; 21. handle. DETAILED DESCRIPTION

[0019] The following will be combined with the drawings in the embodiments of the utility model to clearly and completely describe the technical solutions in the embodiments of the utility model. Obviously, the described embodiments are only part of the embodiments of the utility model, not all of the embodiments. Based on the embodiments in the utility model, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the utility model.

[0020] Embodiment 1

[0021] refer to Figure 1 , Figure 2 , Figure 3 and Figure 4A pile driver for water conservancy construction comprises a pile driver body 1, one side of the bracket of the pile driver body 1 is fixedly installed with two mounting plates 2, the pile driver body 1 is an existing structure, one side of the two mounting plates 2 is respectively provided with a cleaning component for cleaning the soil, the cleaning component comprises two pulling holes 3, the two pulling holes 3 are respectively opened on one side of the two mounting plates 2, the inside of the pulling holes 3 is fixedly installed with a positioning column 4, the inside of the pulling holes 3 is movably sleeved with a pulling plate 5, the top surface of the pulling plate 5 is provided with a positioning hole 6, the inside of the positioning hole 6 is movably sleeved with the outer circular wall surface of the positioning column 4, one side of the pulling plate 5 is fixedly installed with a limiting frame 7, one side of the mounting plate 2 is fixedly installed with a positioning block 8, the top surface of the positioning block 8 is provided with a threaded hole 9, the inner circular wall surface of the threaded hole 9 is threadedly connected with a threaded rod 10, the threaded rod 10 is movably sleeved with the inside of the limiting frame 7, and one side of the pulling plate 5 is fixedly installed with a rough The brush 11 is provided, and when the staff operates the pile driver body 1 to drive piles on the ground, the staff stands up the pile driver body 1 and then operates the spiral blade to drive piles on the ground, and then the spiral blade takes out a part of the soil when it rises from the pile hole after driving the pile. At this time, the staff rotates the threaded rod 10 so that the threaded rod 10 rotates and moves downward in the threaded hole 9 so that the height of the threaded rod 10 is lower than the limit frame 7, and then the staff pulls the limit frame 7 to drive the pull-out plate 5 to slide in the pull-out hole 3, so that the brush 11 is close to the spiral blade. At this time, the staff swings the limit frame 7 to make the pull-out plate 5 swing left and right and drive the brush 11 to swing to wipe and clean the soil attached to the surface of the spiral blade, so as to achieve the goal of making it difficult for the staff to clean the wet soil attached to the surface of the spiral blade of the pile driver body 1 after piling, thereby preventing the surface of the spiral blade from rusting after a long time.

[0022] Embodiment 2

[0023] Based on the above embodiment 1, reference Figure 1 , Figure 2 , Figure 3 and Figure 4Two fixing plates 12 are fixedly installed on one side of the bracket of the pile driver body 1. The two fixing plates 12 are respectively provided with mounting holes 13 on the sides close to each other. The inner circumferential wall surface of the mounting hole 13 is fixedly sleeved with a bearing 14. The inner ring of the bearing 14 is fixedly sleeved with a positioning rod 15. The outer circumferential wall surface of the positioning rod 15 is fixedly sleeved with two wheels 16. Through the provided wheels 16, when the staff operates the pile driver body 1 to drive piles on the ground, the staff swings the pile driver body 1 to tilt the pile driver body 1 and place the wheels 16 on the ground, and then the staff pushes the pile driver body 1 to move the pile driver body 1. A plurality of gaskets 17 are fixedly installed on the bottom surface of the bracket of the pile driver body 1, and a positioning cone 18 is fixedly installed on the bottom surface of the gasket 17. When the staff erects the pile driver body 1 and performs piling, the positioning cone 18 is inserted into the soil on the ground, so that the pile driver body 1 is placed on the ground more stably. Two positioning plates 19 are fixedly installed on one side of the bracket of the pile driver body 1, and a grip rod 20 is fixedly installed between the two positioning plates 19. A handle 21 is fixedly installed on the top surface of the threaded rod 10. The surfaces of the mounting plate 2, the positioning column 4, the pull-out plate 5, the limit frame 7, the threaded rod 10 and the positioning cone 18 are respectively coated with anti-corrosion paint.

[0024] Working principle: Please refer to Figure 1-Figure 4 As shown, through the provided brush 11, when the staff operates the pile driver body 1 to drive piles into the ground, the staff will stand up the pile driver body 1 and then operate the spiral blade to drive piles into the ground, and then the spiral blade will take out a part of the soil when it rises from the pile hole after driving the pile. At this time, the staff rotates the threaded rod 10 so that the threaded rod 10 rotates and moves downward in the threaded hole 9 so that the height of the threaded rod 10 is lower than the limit frame 7, and then the staff pulls the limit frame 7 to drive the pull-out plate 5 to slide in the pull-out hole 3, so that the brush 11 is close to the spiral blade. At this time, the staff swings the limit frame 7 to make the pull-out plate 5 swing left and right and drive the brush 11 to swing to wipe and clean the soil attached to the surface of the spiral blade, so as to achieve the goal of making it difficult for the staff to clean the wet soil attached to the surface of the spiral blade of the pile driver body 1 after piling, thereby preventing the surface of the spiral blade from rusting after a long time.

[0025] By means of the provided wheels 16, when the worker operates the pile driver body 1 to drive piles into the ground, the worker swings the pile driver body 1 to tilt the pile driver body 1 and places the wheels 16 on the ground, and then pushes the pile driver body 1 to move the pile driver body 1. When the worker stands up the pile driver body 1 to drive piles, the positioning cone 18 is inserted into the soil on the ground, so that the pile driver body 1 is placed on the ground more stably.

[0026] Although the embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that various changes, modifications, substitutions and variations may be made to the embodiments without departing from the principles and spirit of the present invention, and that the scope of the present invention is defined by the appended claims and their equivalents.

Claims

1. A pile driver for water conservancy construction, characterized in that: include: A pile driver body (1), wherein two mounting plates (2) are fixedly mounted on one side of a bracket of the pile driver body (1); A cleaning component, the cleaning component is respectively arranged on one side of two mounting plates (2) and is used for cleaning soil. The cleaning component comprises: two pull-out holes (3), the two pull-out holes (3) are respectively opened on one side of the two mounting plates (2), a positioning column (4) is fixedly installed inside the pull-out hole (3), a pull-out plate (5) is movably sleeved inside the pull-out hole (3), a positioning hole (6) is opened on the top surface of the pull-out plate (5), the interior of the positioning hole (6) is movably sleeved with the outer circular wall surface of the positioning column (4), a limiting frame (7) is fixedly installed on one side of the pull-out plate (5), a positioning block (8) is fixedly installed on one side of the mounting plate (2), a threaded hole (9) is opened on the top surface of the positioning block (8), a threaded rod (10) is threadedly connected to the inner circular wall surface of the threaded hole (9), the threaded rod (10) is movably sleeved with the interior of the limiting frame (7), and a brush (11) is fixedly installed on one side of the pull-out plate (5).

2. A pile driver for water conservancy construction according to claim 1, characterized in that: Two fixing plates (12) are fixedly mounted on one side of the bracket of the pile driver body (1), and mounting holes (13) are respectively provided on the sides of the two fixing plates (12) close to each other, and a bearing (14) is fixedly sleeved on the inner circular wall surface of the mounting hole (13), and a positioning rod (15) is fixedly sleeved on the inner ring of the bearing (14), and two wheels (16) are fixedly sleeved on the outer circular wall surface of the positioning rod (15).

3. A pile driver for water conservancy construction according to claim 1, characterized in that: A plurality of gaskets (17) are fixedly mounted on the bottom surface of the bracket of the pile driver body (1), and a positioning cone (18) is fixedly mounted on the bottom surface of the gasket (17).

4. A pile driver for water conservancy construction according to claim 1, characterized in that: Two positioning plates (19) are fixedly mounted on one side of the bracket of the pile driver body (1), and a gripping rod (20) is fixedly mounted between the two positioning plates (19).

5. A pile driver for water conservancy construction according to claim 1, characterized in that: A handle (21) is fixedly mounted on the top surface of the threaded rod (10).

6. A pile driver for water conservancy construction according to claim 3, characterized in that: The surfaces of the mounting plate (2), the positioning column (4), the pull-out plate (5), the limiting frame (7), the threaded rod (10) and the positioning cone (18) are respectively coated with anti-corrosion paint.

Citation Information

Patent Citations

  • Pile driver

    CN204982887U