Building construction discharging platform

By setting up protective measures such as protective nets, reinforcement pads and guardrails on the construction unloading platform, the problems of material drop and safety hazards are solved, and the safety and stability of the construction process are achieved.

CN222924133UActive Publication Date: 2025-05-30DALIAN KAIPENG WATER CONSERVANCY ENGINEERING CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202421098072.X
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-05-20
Publication Date
2025-05-30
Estimated Expiration
2034-05-20

AI Technical Summary

Technical Problem

During construction, the unloading platform is prone to falling off due to the large weight of the material, high platform and lack of protection measures, which poses safety hazards.

Method used

A construction unloading platform was designed, including a base frame, mounting frame, protective net, I-beam, platform main body, guardrail, baffle, movable plate and reinforcement pad. By setting up protective measures such as protective nets, reinforcement pads and guardrails, prevent materials from falling and provide buffering effects.

Benefits of technology

Effectively prevent materials from falling to the ground, reduce safety hazards, and ensure the safety and stability of the construction process.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222924133U_ABST
    Figure CN222924133U_ABST
Patent Text Reader

Abstract

The utility model discloses a building construction discharging platform, which belongs to the technical field of building construction and comprises a bottom frame, a first mounting frame is mounted above the bottom frame, a second mounting frame is arranged on one side of the first mounting frame, and a first protective net and a second protective net are mounted on the inner side of the first mounting frame and the inner side of the second mounting frame. An I-shaped beam is mounted right above the bottom frame, a platform main body is arranged above the I-shaped beam, and a guardrail is mounted above the platform main body; according to the unloading platform, the first mounting frame and the second mounting frame are mounted above the bottom frame, when the unloading platform is used, materials are hoisted to the platform body through an external crane, the falling materials can directly fall onto the bottom frame, and the first protective net and the second protective net arranged on the periphery can prevent the materials from falling onto the ground; the two sets of symmetrical reinforcing pads are used for buffering fallen materials, protection measures are taken around the discharging platform, the materials cannot fall off, and potential safety hazards do not exist.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of building construction, and more specifically, to a building construction unloading platform. Background Art

[0002] The unloading platform is various temporary operating platforms and operating frames often built at the construction site, generally used for the turnover of materials. The unloading platform is divided into mobile unloading platforms, floor-mounted unloading platforms, cantilevered unloading platforms, etc.

[0003] Based on the above, the inventor found that: currently, when using the unloading platform, a crane is usually used to hoist materials into the platform. However, the weight of the materials is often relatively heavy, the platform is at a relatively high position, and there is a lack of protective measures around the unloading platform, resulting in the materials being prone to falling and posing a safety hazard. Therefore, in view of this, the existing structure is studied and improved to provide a building construction unloading platform, in order to achieve a more practical value. Summary of the Utility Model

[0004] 1. Technical Problems to be Solved

[0005] Aiming at the problems existing in the prior art, the purpose of the utility model is to provide a building construction unloading platform, which can prevent the problems of easy falling of materials and potential safety hazards caused by the relatively heavy weight of the materials, the relatively high position of the platform, and the lack of protective measures around the unloading platform.

[0006] 2. Technical Solutions

[0007] To solve the above problems, the utility model adopts the following technical solutions.

[0008] A building construction unloading platform includes a chassis. Above the chassis, a first mounting frame is installed. On one side of the first mounting frame, a second mounting frame is provided. Inside the first mounting frame and the second mounting frame, a first protective net and a second protective net are installed. Above the chassis, an I-beam is installed. Above the I-beam, a platform main body is provided. Above the platform main body, a guardrail is installed. On one side of the guardrail, a baffle is provided. On one side of the platform main body, a movable plate is installed. At the connection between the movable plate and the platform main body, a mounting sleeve is provided. On the side of the I-beam, a reinforcing pad is provided.

[0009] Further, there are two groups of the first mounting frames, symmetrically arranged on both sides above the chassis.

[0010] Further, there are two groups of I-beams, and the lengths of the two groups of I-beams are the same.

[0011] Further, there are two groups of reinforcing pads, symmetrically arranged on both sides of the platform main body, and the structural composition of each group of the platform main body is the same.

[0012] Further, buffer balls are arranged equidistantly above the reinforcement pad, and threaded grooves are formed at the four corner positions of the reinforcement pad. An installation bolt is threadedly connected to the inner side of the threaded groove, and the installation bolt passes through the reinforcement pad and is threadedly connected to the chassis.

[0013] Further, there are two groups of guardrails, symmetrically arranged on both sides above the platform main body.

[0014] Further, a movable shaft is movably connected to the inner side of the installation sleeve, and both ends of the movable shaft are respectively connected to the movable plate.

[0015] 3. Beneficial effects

[0016] Compared with the prior art, the advantages of the present utility model are as follows:

[0017] In this solution, two groups of mounting brackets I and II are installed above the chassis. When using the unloading platform, an external crane hoists the materials onto the platform main body. The dropped materials will directly fall onto the chassis, and the protective nets I and II arranged around can prevent the materials from falling to the ground. Two groups of symmetrical reinforcement pads are used to buffer the dropped materials. The unloading platform is equipped with protective measures around, and the materials will not fall, eliminating potential safety hazards. Brief description of the drawings

[0018] Figure 1 is a three-dimensional schematic diagram of the present utility model;

[0019] Figure 2 is a schematic diagram of the protection component of the present utility model;

[0020] Figure 3 is a schematic diagram of the platform main body of the present utility model;

[0021] Figure 4 is a schematic diagram of the reinforcement pad of the present utility model.

[0022] Description of the reference numerals in the drawings:

[0023] 1, chassis; 2, mounting bracket I; 3, protective net I; 4, mounting bracket II; 5, protective net II; 6, I-beam; 7, platform main body; 8, reinforcement pad; 81, buffer ball; 82, threaded groove; 83, installation bolt; 9, guardrail; 10, baffle; 11, movable plate; 12, installation sleeve. Specific embodiments

[0024] The following will clearly and completely describe the technical solutions in the embodiments of the present utility model in conjunction with the accompanying drawings in the embodiments of the present utility model; obviously, the described embodiments are only a part of the embodiments of the present utility model, rather than all the embodiments. Based on the embodiments of the present utility model, all other embodiments obtained by those of ordinary skill in the art without creative efforts shall fall within the protection scope of the present utility model.

[0025] Embodiment:

[0026] Please refer to Figures 1-4 , a construction material unloading platform, including a bottom frame 1, an installation frame 1 is installed above the bottom frame 1, an installation frame 2 is arranged on one side of the installation frame 1, and a protective net 3 and a protective net 5 are installed inside the installation frame 1 and the installation frame 2. The protective net 3 and the protective net 5 protect the outside of the platform main body 7. An I-beam 6 is installed directly above the bottom frame 1. The I-beam 6 is used for the movement of the platform main body 7. A platform main body 7 is arranged above the I-beam 6. A guardrail 9 is installed above the platform main body 7. A baffle 10 is arranged on one side of the guardrail 9. The guardrail 9 and the baffle 10 protect the outside of the platform main body 7. A movable plate 11 is installed on one side of the platform main body 7. An installation sleeve 12 is arranged at the connection between the movable plate 11 and the platform main body 7. The movable plate 11 and the installation sleeve 12 facilitate material unloading. A reinforcement pad 8 is arranged on the side of the I-beam 6. The reinforcement pad 8 is used to buffer the falling materials.

[0027] Refer to Figure 1 and Figure 2 , there are two groups of installation frames 1, symmetrically arranged on both sides above the bottom frame 1. By setting the installation frame 1, the two sides of the platform main body 7 can be protected.

[0028] Refer to Figure 1 and Figure 3 , there are two groups of I-beams 6, and the lengths of the two groups of I-beams 6 are the same. By setting the I-beam 6, the movement of the platform main body 7 can be facilitated.

[0029] Refer to Figure 2 and Figure 4 , there are two groups of reinforcement pads 8, symmetrically arranged on both sides of the platform main body 7. The structural composition of each group of platform main bodies 7 is the same. By setting the reinforcement pad 8, the falling materials can be buffered.

[0030] Refer to Figure 2 and Figure 4 , buffer balls 81 are arranged at equal intervals above the reinforcement pad 8, and threaded grooves 82 are opened at the four corner positions of the reinforcement pad 8. An installation bolt 83 is threadedly connected inside the threaded groove 82. The installation bolt 83 passes through the reinforcement pad 8 and is threadedly connected to the bottom frame 1. By setting the installation bolt 83, the reinforcement pad 8 can be installed.

[0031] Refer toFigure 1 and Figure 3 The guardrail 9 is provided with two groups, symmetrically arranged on both sides above the platform main body 7. By providing the guardrail 9 and the baffle 10, the outside of the platform main body 7 can be protected.

[0032] Refer to Figure 1 and Figure 3 Inside the mounting sleeve 12, a movable shaft is movably connected. Both ends of the movable shaft are respectively connected to the movable plate 11. By providing the mounting sleeve 12 and the movable shaft, the movement of the movable plate 11 can be facilitated.

[0033] During use: First, install the two groups of mounting frames I 2 and mounting frames II 4 above the chassis 1. When using the unloading platform, an external crane hoists the materials onto the platform main body 7. The dropped materials will directly fall onto the chassis 1, and the protective nets I 3 and protective nets II 5 arranged around can prevent the materials from falling to the ground. The two groups of symmetrically arranged reinforcing pads 8 are used to buffer the dropped materials. The unloading platform is surrounded by protective measures, so the materials will not fall, and there are no safety hazards.

[0034] Finally, it should be noted that in the description of the present invention, it should be noted that the orientation or positional relationship indicated by the terms "vertical", "upper", "lower", "horizontal", etc. is based on the orientation or positional relationship shown in the drawings. It is only for the convenience of describing the present invention and simplifying the description, rather than indicating or implying that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore should not be construed as a limitation to the present invention.

[0035] In the description of the present invention, it should also be noted that unless otherwise clearly specified and defined, the terms "set", "installed", "connected", "connected" should be understood in a broad sense. For example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection, or an electrical connection; it can be directly connected, or indirectly connected through an intermediate medium, and it can be the communication inside two elements. For those of ordinary skill in the art, the specific meanings of the above terms in the present invention can be understood according to specific situations.

[0036] The above are only the preferred embodiments of the present invention and are not used to limit the present invention. Although the present invention has been described in detail with reference to the foregoing embodiments, for those skilled in the art, they can still modify the technical solutions recorded in the foregoing embodiments, or perform equivalent replacements for some of the technical features. Any modifications, equivalent replacements, improvements, etc. made within the spirit and principle of the present invention shall be included within the protection scope of the present invention.

Claims

1. A construction unloading platform, comprising a base frame (1), a mounting frame 1 (2) being mounted above the base frame (1), a mounting frame 2 (4) being disposed on one side of the mounting frame 1 (2), and a protective net 1 (3) and a protective net 2 (5) being mounted on the inner sides of the mounting frame 1 (2) and the mounting frame 2 (4), characterized in that: An I-beam (6) is installed directly above the base frame (1), a platform body (7) is arranged above the I-beam (6), a guardrail (9) is installed above the platform body (7), a baffle (10) is arranged on one side of the guardrail (9), a movable plate (11) is installed on one side of the platform body (7), a mounting sleeve (12) is arranged at the connection between the movable plate (11) and the platform body (7), and a reinforcing pad (8) is arranged on the side of the I-beam (6).

2. A construction unloading platform according to claim 1, characterized in that: The first mounting frame (2) is provided with two groups, which are symmetrically arranged on both sides above the base frame (1).

3. A construction unloading platform according to claim 1, characterized in that: The I-beams (6) are provided in two groups, and the lengths of the two groups of I-beams (6) are the same.

4. A construction unloading platform according to claim 1, characterized in that: The reinforcement pads (8) are provided in two groups, symmetrically arranged on both sides of the platform body (7), and the structural composition of each group of platform bodies (7) is consistent.

5. A construction unloading platform according to claim 1, characterized in that: Buffer balls (81) are arranged at equal intervals above the reinforcement pad (8), and thread grooves (82) are provided at four corners of the reinforcement pad (8). The inner side of the thread groove (82) is threadedly connected with a mounting bolt (83), and the mounting bolt (83) passes through the reinforcement pad (8) and is threadedly connected to the base frame (1).

6. A construction unloading platform according to claim 1, characterized in that: The guardrails (9) are provided in two groups and are symmetrically arranged on both sides above the platform body (7).

7. A construction unloading platform according to claim 1, characterized in that: A movable shaft is movably connected to the inner side of the installation sleeve (12), and both ends of the movable shaft are respectively connected to the movable plate (11).