Working platform for concrete pouring

By designing a working platform for concrete pouring, including hydraulic cylinders and wire mesh, the problems of inconvenient table adjustment and difficulty in cleaning concrete in the prior art are solved, and higher practicality and operational convenience are achieved.

CN222936373UActive Publication Date: 2025-06-03CHINA STATE CONSTR PORT ENG GRP
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202421560595.1
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-07-03
Publication Date
2025-06-03
Estimated Expiration
2034-07-03

AI Technical Summary

Technical Problem

The concrete pouring workbench for existing houses is not convenient to adjust according to different use scenarios, and is insufficient in practicality. At the same time, it is difficult to clean the concrete and moisture on the work platform during the construction process.

Method used

A working platform for concrete pouring is designed, including a base plate, a second hydraulic cylinder, a lift plate, a working plate and a wire mesh frame. The extension length of the working plate is adjusted by the first hydraulic cylinder and a wire mesh frame is installed on the working plate. During the pouring process, the concrete will pass through the steel mesh frame and fall to the ground to prevent the concrete from sprinkling on the workbench.

Benefits of technology

The height of the workbench and the extension length of the workbench are adjusted according to different usage scenarios, which improves the practicality of the workbench, and solves the problem of difficulty in cleaning the concrete on the workbench through a wire mesh.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222936373U_ABST
    Figure CN222936373U_ABST
Patent Text Reader

Abstract

The utility model relates to the technical field of building construction, in particular to a working platform for concrete pouring, which comprises a bottom plate, a second hydraulic cylinder is mounted in the center of the upper portion of the bottom plate, a lifting plate is arranged at the upper end of the second hydraulic cylinder, a groove is arranged on one side of the lifting plate, and a working plate is slidably connected in the groove. A steel wire net frame is installed in the middle of the working plate. The house building concrete pouring workbench solves the problems that an existing house building concrete pouring workbench is not convenient to adjust according to use scenes, practicability is insufficient, and meanwhile the problem that concrete sprayed on the workbench is not changed to be cleaned is solved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of building construction, in particular to a working platform for concrete pouring. Background Art

[0002] When building houses, it is usually necessary to pour concrete. During construction, construction workers need to use a concrete pouring platform to pour concrete. For the existing concrete pouring workbench for building construction, when used by construction workers, it is not convenient to adjust the workbench according to different usage scenarios, and its practicability is insufficient. At the same time, during the construction process, concrete and water will spill on the working platform, making it difficult to clean. Summary of the Utility Model

[0003] In order to solve the problems of the above-mentioned existing technologies, the utility model provides a working platform for concrete pouring, which solves the problems that the existing concrete pouring workbench for building construction is not convenient to adjust according to the usage scenario and has insufficient practicability, and at the same time solves the problem that it is inconvenient to clean the concrete spilled on the working platform.

[0004] To achieve the above object, the utility model provides the following technical solution: A working platform for concrete pouring, including a bottom plate, a second hydraulic cylinder is installed at the central position of the upper part of the bottom plate, a lifting plate is arranged at the upper end of the second hydraulic cylinder, a groove is formed on one side of the lifting plate, a working plate is slidably connected in the groove, and a steel wire mesh frame is installed in the middle of the working plate.

[0005] With the above structural design, the staff can adjust the extending length of the working plate according to the work needs, which is convenient for the pouring work. At the same time, a steel wire mesh frame is installed on the working plate, and the concrete spilled on the working plate during the pouring process will directly pass through the steel wire mesh frame and fall to the ground, preventing the problem of difficult cleaning of the concrete spilled on the working platform.

[0006] Preferably, a support block is fixedly connected to the side edge of the working plate away from the lifting plate, a first hydraulic cylinder is installed at the bottom of the lifting plate, and the piston rod of the first hydraulic cylinder is fixedly connected to the support block.

[0007] With the above structural design, the extending length of the working plate is controlled by controlling the length of the piston rod of the first hydraulic cylinder, and the structure is simple and the operation is convenient.

[0008] Preferably, several first columns are arranged on the lifting plate, a sleeve rod is fixedly connected to the upper end of the first column, several second columns are arranged on the working plate, a U-shaped central rod is fixedly connected to the upper end of the second column, and both ends of the central rod extend into the sleeve rod.

[0009] With the above structural design, the upright column, the sleeve rod and the central rod form a telescopic guardrail, which protects the safety of construction workers. The length of the guardrail can be adjusted according to the extended length of the working board, and it has strong practicability.

[0010] Preferably, a ladder is installed on one side of the lifting board.

[0011] With the above structural design, setting up the ladder facilitates the construction workers to get on and off the lifting board.

[0012] Preferably, the bottom plate and the lifting board are connected by multiple groups of limit telescopic rods.

[0013] With the above structural design, setting up multiple groups of limit telescopic rods ensures the stability of the lifting board during the moving process.

[0014] Compared with the prior art, the beneficial effects of the present utility model are as follows:

[0015] 1. The staff adjusts the extended length of the working board through the first hydraulic cylinder to facilitate the pouring work. At the same time, a steel wire mesh frame is installed on the working board, and the concrete spilled on the working board during the pouring process will directly pass through the steel wire mesh frame and fall to the ground, preventing the problem of difficult cleaning caused by the concrete spilled on the working table.

[0016] 2. The height of the working platform is adjusted through the second hydraulic cylinder, which is convenient for adjusting the building concrete pouring working platform according to different usage scenarios, and it has strong practicability. BRIEF DESCRIPTION OF THE DRAWINGS

[0017] Figure 1 is a structural schematic diagram of the present utility model;

[0018] Figure 2 is a side view of the present utility model. DETAILED DESCRIPTION OF THE EMBODIMENTS

[0019] The technical solutions in the embodiments of the present utility model will be clearly and completely described below with reference to the accompanying drawings in the embodiments of the present utility model. Obviously, the described embodiments are only a part of the embodiments of the present utility model, rather than all of the embodiments. Based on the embodiments of the present utility model, all other embodiments obtained by those of ordinary skill in the art without creative efforts shall fall within the protection scope of the present utility model.

[0020] Please refer to Figure 1-2, the present utility model provides a technical solution: a working platform for concrete pouring, including a bottom plate 11. At the central position of the upper part of the bottom plate 11, a second hydraulic cylinder 10 is installed. At the upper end of the second hydraulic cylinder 10, there is a lifting plate 1. Both the bottom plate 11 and the lifting plate 1 are rectangular structures. A groove is provided on one side of the lifting plate 1, and a working plate 6 is slidably connected in the groove. A wire mesh frame 7 is installed in the middle of the working plate 6. Workers can adjust the extending length of the working plate 6 according to the working needs, which facilitates the pouring work. At the same time, the wire mesh frame 7 is installed on the working plate. During the pouring process, the concrete spilled on the working plate will directly pass through the wire mesh frame 7 and fall to the ground, preventing the problem of difficult cleaning of the concrete spilled on the working platform.

[0021] A support block 5 is fixedly connected to the side edge of the working plate 6 away from the lifting plate 1. A first hydraulic cylinder 8 is installed at the bottom of the lifting plate 1, and the piston rod of the first hydraulic cylinder 8 is fixedly connected to the support block 5. By controlling the length of the piston rod of the first hydraulic cylinder 8, the extending length of the working plate 6 is controlled, with a simple structure and convenient operation.

[0022] Several first columns 2 are provided on the lifting plate 1. A sleeve rod 4 is fixedly connected to the upper ends of the first columns 2. The sleeve rod 4 is in the shape of a straight bar and is installed at the positions of the two side edges of the lifting plate 1. Several second columns 14 are provided on the working plate 6. A U-shaped center rod 3 is fixedly connected to the upper ends of the second columns 14. The two ends of the center rod 3 extend into the sleeve rod 4. The columns, the sleeve rod 4 and the center rod 3 form a telescopic guardrail, which protects the safety of construction workers and can adjust the length of the guardrail according to the extending length of the working plate, with strong practicability.

[0023] A ladder 9 is installed on one side of the lifting plate 1. The installation of the ladder 9 facilitates the construction workers to get on and off the lifting plate.

[0024] The bottom plate 11 and the lifting plate 1 are connected by four groups of limit telescopic rods 12. The limit telescopic rods 12 are installed at the four corners of the bottom plate 11 and the lifting plate 1. The setting of multiple groups of limit telescopic rods 12 ensures the stability of the lifting plate 1 during the moving process. A moving wheel 13 with a locking mechanism is installed at the bottom end of the bottom plate 11, which facilitates the construction workers to transfer the device.

[0025] Working principle: The construction workers first push the working platform to the designated position through the moving wheels 13, then stand on the lifting plate 1 through the ladder 9. Subsequently, start the second hydraulic cylinder 10 to lift the lifting plate 1 to an appropriate position, and start the first hydraulic cylinder 8 to push the working plate 6 out of the lifting plate 1. The construction workers can carry out the pouring operation while standing on the wire mesh frame 7 of the working plate 6. The staff adjusts the extending length of the working plate 6 through the first hydraulic cylinder 8 to facilitate the pouring work. At the same time, a wire mesh frame 7 is installed on the working plate 6. During the pouring process, the concrete spilled on the working plate 6 will directly pass through the wire mesh frame 7 and fall to the ground, preventing the problem of difficult cleaning caused by concrete spilling on the working platform.

[0026] The content not described in detail in this specification belongs to the prior art well-known to those skilled in the art. Although the present invention has been described in detail with reference to the foregoing embodiments, those skilled in the art can still modify the technical solutions described in the foregoing embodiments, or perform equivalent replacements for some of the technical features. Any modifications, equivalent replacements, improvements, etc. made within the spirit and principle of the present invention shall be included within the protection scope of the present invention.

Claims

1. A working platform for concrete pouring, comprising a bottom plate (11), characterized in that: A second hydraulic cylinder (10) is installed at the center of the upper part of the base plate (11), and a lifting plate (1) is arranged at the upper end of the second hydraulic cylinder (10). A groove is provided on one side of the lifting plate (1), and a working plate (6) is slidably connected in the groove. A wire mesh frame (7) is installed in the middle of the working plate (6).

2. A working platform for concrete pouring according to claim 1, characterized in that: A support block (5) is fixedly connected to the side of the working plate (6) away from the lifting plate (1), and a first hydraulic cylinder (8) is installed at the bottom of the lifting plate (1), and the piston rod of the first hydraulic cylinder (8) is fixedly connected to the support block (5).

3. A working platform for concrete pouring according to claim 1, characterized in that: The lifting plate (1) is provided with a plurality of first columns (2), the upper ends of which are fixedly connected to sleeve rods (4); the working plate (6) is provided with a plurality of second columns (14), the upper ends of which are fixedly connected to U-shaped center rods (3), and the two ends of the center rod (3) extend into the sleeve rods (4).

4. A working platform for concrete pouring according to claim 1, characterized in that: A ladder (9) is installed on one side of the lifting plate (1).

5. A working platform for concrete pouring according to claim 1, characterized in that: The bottom plate (11) and the lifting plate (1) are connected via a plurality of groups of position-limiting telescopic rods (12).