Arched beam type hoisting equipment
By installing arch beam-type lifting equipment of multiple lifting trolleys on the arch frame, the problem of low pouring and lifting efficiency of concrete in hydropower station dams is solved, and more efficient pouring and lifting is achieved, suitable for large and complex construction areas.
Patent Information
- Application Number
- CN202421919616.4
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-09
- Publication Date
- 2025-06-10
- Estimated Expiration
- 2034-08-09
AI Technical Summary
The concrete pouring and hoisting of hydropower dams is low, which affects the progress of the project.
Design an arch beam-type lifting equipment to achieve more efficient concrete pouring and hoisting by installing multiple lifting trolleys on the arch frame.
It improves the pouring efficiency and lifting capacity, meets the needs of large and complex construction areas, and significantly shortens the production time of hydropower stations.
Smart Images

Figure CN222961005U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of hydropower station construction equipment, in particular to an arch-beam type lifting device. Background Art
[0002] Hydropower stations are mostly arranged in deep mountain valleys, and the concrete pouring volume of hydropower station dams is often very large. The pouring speed of mass concrete directly determines the commissioning time of the hydropower station. Each day of earlier commissioning will bring direct benefits in millions. The pouring means of such mass concrete are generally cable cranes or tower cranes arranged on the bays. Due to the lifting weight limitation and the non-continuous pouring of one working cycle for pouring one can of concrete, the lifting and pouring efficiency is low, which directly affects the project progress. Content of the Utility Model
[0003] The technical problem to be solved by the utility model is: to solve the problems existing in the above background art, and provide an arch-beam type lifting device, by installing a plurality of lifting trolleys on the arch frame, so as to solve the problem of relatively low concrete pouring and hoisting efficiency of the hydropower station dam.
[0004] In order to solve the above technical problem, the technical solution adopted by the utility model is: an arch-beam type lifting device, including a first track, an arch frame and a lifting trolley. The first track is used to be installed on the foundation platforms on both sides of the valley. Walking frames are respectively installed on the lower sides of the two ends of the two arch frames, and the walking frames on both sides are respectively used to be installed on the first tracks on both sides. A plurality of lifting trolleys are installed on the two arch frames.
[0005] A truss structure is arranged on the lower side of the arch frame.
[0006] The walking frame includes a machine base, a roller path wheel and a first motor. The roller path wheel is rotatably installed on the lower side of the machine base through a central shaft. The first motor is installed on the machine base, and the output shaft of the first motor is connected and transmitted with the central shaft of one of the roller path wheels; the two arch frames are installed on the machine base.
[0007] One walking frame is installed at each end of each arch frame, and the two walking frames on the same side are connected into a whole.
[0008] The lifting trolley includes a walking seat, a box body and a hoisting system. The walking seats are respectively installed on both sides of the box body, and the walking seats on both sides are respectively on the upper sides of the two arch frames. The hoisting system is installed in the box body, and the hook of the hoisting system extends downward between the two arch frames; at least two walking wheels are installed on the lower side of the walking seat, and the walking wheels roll on the upper side of the arch frame.
[0009] A rack is installed on the arch frame. A bracket is installed on the outer side of the traveling seat. A second motor is installed on the bracket. A first gear is installed on the output shaft of the second motor. The first gear meshes with the rack for transmission.
[0010] A second track is installed on the arch frame. The traveling wheels roll on the second track.
[0011] A trolley wire is also installed on the arch frame. A collector is installed on the traveling seat or the bracket. The collector elastically contacts the trolley wire for conduction. The collector is used to supply power to the hoisting system and the second motor.
[0012] An electric control cabinet is also installed in the box body. The electric control cabinet is electrically connected to the collector. The hoisting system and the second motor are electrically connected to the electric control cabinet. A remote control unit is provided in the electric control cabinet. The hoisting system and the second motor are started and stopped through remote control.
[0013] The arch frame is formed by assembling multiple sections into a whole.
[0014] The utility model has the following beneficial effects:
[0015] 1. Compared with the commonly used cable cranes and gantry tower cranes, because the arch beam form is adopted in this patent, the bearing capacity and the lifting capacity of the crane are greatly increased. Multiple hoisting trolleys on each arch beam type lifting equipment can separately carry out hoisting operations. The trolleys on the same or different arch beam type lifting equipment can also be combined to carry out corresponding double-trolley or multi-trolley lifting operations, meeting the hoisting requirements of multiple pouring positions and large lifting weights in dam construction, and can well meet the operation requirements of the construction area, especially suitable for large and complex construction areas.
[0016] 2. This patent solves the problem of low efficiency of existing pouring equipment well. Through a lighter structural weight compared with existing equipment such as cable cranes and gantry tower cranes, it realizes a larger lifting weight, more abundant functions, and the effect of multiple machines using the same track, thus effectively improving the pouring efficiency and generating considerable economic and social benefits. BRIEF DESCRIPTION OF THE DRAWINGS
[0017] In order to more clearly illustrate the specific embodiments of the utility model or the technical solutions in the prior art, the following will briefly introduce the drawings required for use in the description of the specific embodiments or the prior art. Obviously, the drawings in the following description are some embodiments of the utility model. For those of ordinary skill in the art, other drawings can be obtained based on these drawings without creative efforts.
[0018] Figure 1 It is the front view structural schematic diagram of the utility model.
[0019] Figure 2Schematic three-dimensional structure diagram of the present utility model.
[0020] Figure 3 Schematic top view structure diagram of the present utility model.
[0021] Figure 4 Schematic structure diagram of the traveling frame of the present utility model installed on the first track.
[0022] Figure 5 Schematic structure diagram of the connection between the arch frame and the traveling frame of the present utility model.
[0023] Figure 6 Schematic structure diagram of the installation of the hoisting trolley and the arch frame of the present utility model.
[0024] Figure 7 Schematic three-dimensional structure diagram of the hoisting trolley of the present utility model.
[0025] Figure 8 Schematic top view structure diagram of the hoisting trolley of the present utility model.
[0026] In the figure:
[0027] Foundation platform 100, first pier 101, first track 102;
[0028] Arch frame 200, truss structure 201, second track 202, trolley wire 203, first connecting rod 204, rack 205, traveling frame 210, machine base 211, roller track wheel 212, first motor 213;
[0029] Hoisting trolley 300, traveling seat 310, traveling wheel 311, support 312, second motor 313, first gear 314, hub 315, box body 320, hoisting system 330, hook 331, electric control cabinet 340;
[0030] Canyon 400, dam 401. Detailed implementation manners
[0031] Next, the technical solution of the present utility model will be clearly and completely described in conjunction with the accompanying drawings. Obviously, the described embodiments are some, but not all, of the embodiments of the present utility model. All other embodiments obtained by those of ordinary skill in the art based on the embodiments of the present utility model without creative efforts shall fall within the protection scope of the present utility model.
[0032] In the description of the present utility model, it should be noted that the orientation or positional relationship indicated by the terms "center", "upper", "lower", "left", "right", "vertical", "horizontal", "inner", "outer", etc. is based on the orientation or positional relationship shown in the drawings. It is only for the convenience of describing the present utility model and simplifying the description, rather than indicating or implying that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation. Therefore, it should not be construed as a limitation to the present utility model. In addition, the terms "first", "second", "third" are only used for descriptive purposes and cannot be construed as indicating or implying relative importance.
[0033] In the description of the present utility model, it should be noted that unless otherwise clearly specified and defined, the terms "installation", "connection", "coupling" should be understood in a broad sense. For example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be directly connected or indirectly connected through an intermediate medium, and it can be the communication inside two elements. For those of ordinary skill in the art, the specific meanings of the above terms in the present utility model can be understood according to specific situations.
[0034] In addition, the technical features involved in different embodiments of the present utility model described below can be combined with each other as long as they do not conflict with each other.
[0035] Embodiment 1:
[0036] See Figure 1-8 , an arch beam type lifting device, including a first track 102, an arch frame 200, and a lifting trolley 300. The first track 102 is used to be installed on the foundation platforms 100 on both sides of the canyon 400. The lower sides of the two ends of the two arch frames 200 are respectively installed with traveling carriages 210, and the traveling carriages 210 on both sides are respectively used to be installed on the first tracks 102 on both sides. A plurality of lifting trolleys 300 are installed on the two arch frames 200.
[0037] Compared with the commonly used cable cranes and gantry tower cranes, because of the adoption of the arch beam form, the bearing capacity and the lifting capacity of the crane are greatly increased. The multiple lifting trolleys 300 on each arch beam type lifting device can both perform hoisting operations separately, and the trolleys on the same or different arch beam type lifting devices can also be combined to perform corresponding double trolley or multi-trolley lifting operations, meeting the hoisting requirements of multiple pouring positions and large lifting weights in the construction of dams, concrete water conservancy facilities, large-volume buildings, etc., and can well meet the operation requirements of the construction area, and are particularly suitable for large and complex construction areas.
[0038] See Figure 1, a truss structure 201 is provided on the lower side of the arch frame 200, and the structural strength of the arch frame 200 is improved by providing the truss structure. The truss structure 201 includes transverse rods and longitudinal rods. The transverse rods are connected to both ends of the lower side of the arch frame 200, and multiple longitudinal rods connect the arch frame 200 and the transverse rods. Of course, diagonal braces can be further provided between the arch frame 200 and the transverse rods. The cross braces and vertical braces are both provided under the arch frame. In order not to interfere with the position of the rack, a staggered arrangement is made to further supplement the strength of the arch frame. The arch frame, cross braces, and vertical braces are all assembled into a whole by multiple sections and are connected by welding or local flange bolts to avoid interference with components such as the track and the rack.
[0039] See Figure 4 , 5 , the walking frame 210 includes a machine base 211, roller path wheels 212, and a first motor 213. The roller path wheels 212 are rotatably installed on the lower side of the machine base 211 through a central shaft. The first motor 213 is installed on the machine base 211, and the output shaft of the first motor 213 is connected to the central shaft of one of the roller path wheels 212 for transmission; the arch frame 200 is installed on the machine base 211. Through the above structure, the arch frame 200 moves on the first track 102 through the walking frame 210.
[0040] In one of the solutions, there can be one walking frame 210, and two arch frames 200 are installed on the same walking frame 210. In another solution, see Figure 5 , a walking frame 210 is installed at both ends of each arch frame 200, and the two walking frames 210 on the same side are connected into a whole. Specifically, flange plates can be provided on the opposite sides of the two walking frames 210, and the two walking frames 210 are bolted together through the flange plates. Of course, it can also be Figure 5 the structure welded into one body through connecting rods as shown in
[0041] During specific implementation, the walking frame 210 can be welded to the lower side of the arch frame 200, or it can be installed on the lower side of the arch frame 200 by bolts as shown in Figure 5 .
[0042] See Figure 6 , 7, the hoisting trolley 300 includes a traveling seat 310, a box body 320, and a hoisting system 330. The traveling seats 310 are respectively installed on both sides of the box body 320. The traveling seats 310 on both sides are respectively on the upper side of the two arch frames 200. The hoisting system 330 is installed in the box body 320, and the hook 331 of the hoisting system 330 extends downward between the two arch frames 200; at least two traveling wheels 311 are installed on the lower side of the traveling seat 310, and the traveling wheels 311 roll and travel on the upper side of the arch frame 200. A rack 205 is installed on the lower side of the arch frame 200. A bracket 312 is installed on the outer side of the traveling seat 310. A second motor 313 is installed on the bracket 312, and a first gear 314 is installed on the output shaft of the second motor 313. The first gear 314 meshes with the rack 205 for transmission. By meshing the first gear 314 with the rack 205 on the lower side of the arch frame 200, the traveling seat 310 is limited to travel and move on the arch frame 200.
[0043] Furthermore, a second track 202 is installed on the arch frame 200, and the traveling wheels 311 roll and travel on the second track 202. Setting the second track 202 can not only improve the structural strength of the arch frame 200, but also prevent the arch frame 200 from being worn by the traveling of the traveling wheels 311, and more importantly, ensure that the traveling wheels 311 travel along the longitudinal axis of the arch frame 200 to avoid deviation faults. In this solution, the traveling wheels 311 are track wheels.
[0044] It should be noted that when the second track 202 is not provided on the arch frame 200, the traveling wheels 311 are arc-shaped wheels that cooperate with the arch frame 200.
[0045] See Figure 5 、 6 , a trolley wire 203 is also installed on the arch frame 200. An insulating board is padded between the trolley wire 203 and the arch frame 200 to ensure that the arch frame 200 is not charged. A collector 315 is installed on the traveling seat 310 or the bracket 312. A spring is provided inside the collector 315 bracket to ensure that the collector 315 always elastically maintains contact with the trolley wire 203 for conduction under various influences such as vibration, shaking, and bouncing during the operation of the device in this patent. The collector 315 is used to supply power to the hoisting system 330 and the second motor 313. Through the above structure, the power supply for the hoisting system 330 and the second motor 313 is realized. When in use, the trolley wire 203 is laid on the arch frame 200 and connected to the power supply, and the collector 315 slides along the trolley wire 203 and can conduct electricity.
[0046] Furthermore, see Figure 8, an electric control cabinet 340 is also installed inside the box body 320. The electric control cabinet 340 is electrically connected to the hub 315. The hoisting system 330 and the second motor 313 are electrically connected to the electric control cabinet 340. The electric control cabinet 340 is provided with a remote control unit inside. The hoisting system 330 and the second motor 313 are started and stopped remotely through the remote control unit. Through the above structure, the remote control of the hoisting trolley 300 and the hoisting system 330 is realized. The remote control unit is a prior art. For example, a QA600 industrial crane wireless controller is adopted. The controller includes a controller host and a remote controller.
[0047] In one of the solutions, refer to Figure 5 , a first connecting rod 204 is fixedly connected between the two arch frames 200 at the end positions.
[0048] Embodiment 2:
[0049] The difference between this embodiment and Embodiment 1 is that if the width of the canyon is large, resulting in a large width of the pouring area of the dam 401 and a large length and weight of the arch frame 200, refer to Figure 1 、 2 , two half-width arch frames 200 can be respectively arranged on the foundation platforms 100 on the left and right banks of the canyon 400 according to the above structure. After the two half-width arch frames 200 are installed in place, bolts or welding connections are made at the docking joints by personnel.
[0050] The above embodiments are only the preferred technical solutions of the present invention and should not be regarded as limitations on the present invention. The protection scope of the present invention should be the technical solutions recorded in the claims, including the equivalent replacement solutions of the technical features in the technical solutions recorded in the claims. For those of ordinary skill in the art, other different forms of changes or modifications can be made on the basis of the above description. It is not necessary and impossible to enumerate all the implementation manners here. That is, the equivalent replacement improvements within this scope are also within the protection scope of the present invention.
Claims
1. An arch beam type lifting equipment, characterized in that: The invention comprises a first track (102), an arch frame (200) and a lifting trolley (300), wherein the first track (102) is used to be installed on a base platform (100) on both sides of a canyon (400), and a traveling frame (210) is respectively installed on the lower sides of both ends of the two arch frames (200), and the traveling frames (210) on both sides are respectively used to be installed on the first track (102) on both sides, and a plurality of lifting trolleys (300) are installed on the two arch frames (200).
2. The arch beam type lifting equipment according to claim 1, characterized in that: A truss structure (201) is provided on the lower side of the arch frame (200).
3. The arch beam type lifting equipment according to claim 1, characterized in that: The traveling frame (210) comprises a machine base (211), a roller wheel (212) and a first motor (213); the roller wheel (212) is rotatably mounted on the lower side of the machine base (211) via a central axis; the first motor (213) is mounted on the machine base (211); an output shaft of the first motor (213) is connected to the central axis of one of the roller wheels (212) for transmission; and two arch frames (200) are mounted on the machine base (211).
4. The arch beam type lifting equipment according to claim 3, characterized in that: A traveling frame (210) is installed at both ends of each arch frame (200), and two traveling frames (210) located on the same side are connected to form a whole.
5. The arch beam type lifting equipment according to claim 1, characterized in that: The lifting trolley (300) comprises a traveling seat (310), a box (320) and a hoisting system (330); the traveling seats (310) are respectively installed on both sides of the box (320); the traveling seats (310) on both sides are respectively located on the upper sides of two arch frames (200); the hoisting system (330) is installed in the box (320); the hook (331) of the hoisting system (330) extends downward from between the two arch frames (200); at least two traveling wheels (311) are installed on the lower side of the traveling seat (310); the traveling wheels (311) roll and travel on the upper sides of the arch frames (200).
6. The arch beam type lifting equipment according to claim 5, characterized in that: A rack (205) is mounted on the arch frame (200), a bracket (312) is mounted on the outer side of the traveling seat (310), a second motor (313) is mounted on the bracket (312), a first gear (314) is mounted on the output shaft of the second motor (313), and the first gear (314) is meshed with the rack (205) for transmission.
7. The arch beam type lifting equipment according to claim 5, characterized in that: A second track (202) is installed on the arch frame (200), and the running wheels (311) roll on the second track (202).
8. The arch beam type lifting equipment according to claim 6, characterized in that: A busbar (203) is also installed on the arch frame (200), and a hub (315) is installed on the traveling seat (310) or the bracket (312). The hub (315) elastically contacts the busbar (203) for electrical conduction, and the hub (315) is used to supply power to the hoisting system (330) and the second motor (313).
9. The arch beam type lifting equipment according to claim 8, characterized in that: An electric control cabinet (340) is also installed in the box body (320); the electric control cabinet (340) is electrically connected to the hub (315); the hoisting system (330) and the second motor (313) are electrically connected to the electric control cabinet (340); a remote control unit is provided in the electric control cabinet (340); and the hoisting system (330) and the second motor (313) are started and stopped by remote control.
10. The arch beam type lifting equipment according to claim 1, characterized in that: The arch frame (200) is composed of multiple sections assembled and connected to form a whole.