Operating platform for seam splicing operation of laminated wall
By designing an operating platform suitable for narrow sites and using limit rollers and steel truss structures, the problem of inefficient construction caused by site restrictions in the prior art is solved, safe and efficient overlapping wall joint operations are achieved, and construction period and cost are reduced.
Patent Information
- Application Number
- CN202422234517.9
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-09-12
- Publication Date
- 2025-07-11
- Estimated Expiration
- 2034-09-12
AI Technical Summary
In the joint operation of prefabricated double-skin overlapping walls, existing climbing cars or scissors cars cannot be used effectively due to site restrictions, resulting in inefficient construction efficiency, extended construction period, and safety risks.
An operating platform is designed, including the first column, the second column and the beam, and the counterweight block. Through the limit roller and the steel truss structure, it is adapted to narrow sites to ensure the platform balance and safe lifting. The steel truss beam and limit roller are used to facilitate lifting and lowering, and avoid damage to the overlapping wall.
Achieve safe and reliable seam operations under narrow sites, shorten construction periods, reduce costs, improve construction efficiency, and reduce dependence on site conditions.
Smart Images

Figure CN223088870U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of operating platforms, in particular to an operating platform for the joint operation of laminated walls. Background Technique
[0002] In the joint operation between two adjacent wall panels of precast double-skin laminated walls, a scissor lift or a boom lift is usually used as the operating platform. The prerequisite for its use is that the reserved width from the outer wall of the precast double-skin laminated wall to the slope should reach more than 2.5 m. The conventional operation method is to consider reserving enough width from the outer wall to the toe line during the design of the foundation pit excavation, and then backfill the reserved width to the top of the raft foundation and harden the ground to form a freely movable passage. This method is the most widely used and common solution at present.
[0003] However, due to the influence of the land use scope and surrounding buildings, the width between the outer wall and the raft foundation is only 500 mm. The operability of using a scissor lift or a boom lift is restricted by the on-site basic conditions. The width from the outer wall of the laminated wall to the edge of the raft foundation is small, and there is not enough reserved width for the scissor lift or boom lift to construct, resulting in the inability to orderly connect the construction process and the difficulty in achieving the construction period target, which affects the construction efficiency of the laminated wall. Therefore, there is an urgent need for an operating platform for the joint operation of laminated walls to solve the above problems. Content of the Utility Model
[0004] In order to solve the above problems, the utility model provides an operating platform for the joint operation of laminated walls, including a first column, a second column, a cross beam and a counterweight. The heights of the first column and the second column are higher than the height of the laminated wall. The first column and the second column are connected by the cross beam, and the three enclose a receiving cavity for the laminated wall to pass through. The distance between the first column and the second column is greater than the thickness of the laminated wall. A plurality of construction platforms are arranged on the second column at intervals along the vertical direction. The distance between the topmost construction platform and the top of the laminated wall is not greater than 2 m. The counterweight is arranged on the first column.
[0005] Furthermore, limiting rollers are arranged on one side of the first column and the second column facing the receiving cavity, and the axial direction of the limiting rollers is parallel to the longitudinal direction.
[0006] Furthermore, the protruding length of the limiting rollers on the second column is less than the distance between the outer wall of the laminated wall and the edge of the raft foundation.
[0007] Furthermore, the cross beam is a steel truss cross beam, and the first column and the second column are respectively fixedly connected to the bottom of the steel truss cross beam.
[0008] Further, the cross beam includes two cross beam units, the first upright post and the second upright post are respectively connected to one of the cross beam units, and the two cross beam units are telescopically connected.
[0009] Further, a vertical channel is provided in the second upright post. The vertical channel is located on one side of the construction platform. A plurality of tread bars are arranged at intervals along the vertical direction in the vertical channel, and each tread bar is fixedly connected to the second upright post.
[0010] Further, the second upright post is a steel truss upright post, which includes a vertical support assembly and a plurality of horizontal support assemblies arranged at intervals along the vertical direction of the vertical support assembly. The vertical support assembly includes a plurality of vertical rods distributed in a square shape, and each vertical rod is connected to the horizontal support assembly layer by layer. The construction platform is arranged corresponding to the horizontal support assemblies of the second upright post one by one.
[0011] Further, a plurality of diagonal braces are provided between two adjacent vertical rods.
[0012] Further, a hoisting position for hoisting is provided on the cross beam.
[0013] Further, an anti-corrosion layer is provided on the first upright post, the second upright post and the cross beam.
[0014] Due to the adoption of the above technical solutions, the present utility model has the following beneficial effects compared with the prior art:
[0015] 1) The operation platform provided by the present utility model can be used when the distance between the outer wall of the composite wall and the edge of the raft foundation is small. The second upright post can be partially placed on the raft foundation and partially cantilevered, and the balance of the operation platform is realized through the counterweight on the first upright post. The required site is small, which solves the problem that the operation platform cannot be set due to limited site, reduces the influence of on-site conditions on the investment of the operation platform, increases the applicability of the operation platform, and thus shortens the construction period and cost investment.
[0016] 2) For the operation platform provided by the present utility model, limit rollers are provided on the first upright post and the second upright post, which is convenient for the operation platform to be lifted and lowered smoothly along the composite wall during the hoisting process without damaging the composite wall. Description of the Drawings
[0017] In order to more clearly illustrate the technical solutions in the embodiments of the present utility model or the prior art, the following will briefly introduce the drawings required for the description of the embodiments or the prior art. Obviously, the following drawings are only some embodiments of the present utility model. For those of ordinary skill in the art, other drawings can be obtained based on these drawings without creative efforts.
[0018] Figure 1Schematic structural diagram of the operation platform provided in Embodiment 1
[0019] Figure 2 Top view of the operation platform provided in Embodiment 1
[0020] Figure 3 Side view of the operation platform provided in Embodiment 1
[0021] 1 - Composite wall; 2 - Raft foundation; 3 - First column; 4 - Second column; 41 - Vertical channel; 42 - Standpipe; 43 - Transverse rod; 44 - Longitudinal rod; 45 - Brace; 46 - First guardrail; 47 - Second guardrail; 5 - Cross beam; 6 - Counterweight; 7 - Construction platform; 8 - Limit roller Detailed implementation manners
[0022] Next, the technical solutions in the embodiments of the present invention will be clearly and completely described in conjunction with the accompanying drawings in the embodiments of the present invention. Obviously, the described embodiments are only a part of the embodiments of the present invention, rather than all the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by those of ordinary skill in the art without creative efforts shall fall within the protection scope of the present invention. In the accompanying drawings, for clear visibility, the dimensions and relative dimensions of some parts may be enlarged
[0023] In the description of the present invention, unless otherwise clearly defined and limited, the terms "connected" and "coupled" shall be interpreted in a broad sense. For example, it may be a fixed connection, a detachable connection, or integrated; it may be a mechanical connection or an electrical connection; it may be a direct connection or an indirect connection through an intermediate medium, and it may be the internal communication of two components or the interaction relationship between two components. For those of ordinary skill in the art, the specific meanings of the above terms in the present invention can be understood according to specific circumstances
[0024] In the description of the present invention, the orientation or positional relationships such as "upper", "lower", "left", "right", "front", "rear", "center", "horizontal", "vertical", "top", "bottom", "inner", "outer", etc. are based on the orientation or positional relationships shown in the accompanying drawings. It is only for the convenience of description and simplifying the operation, rather than indicating or implying that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore cannot be construed as a limitation to the present invention
[0025] In addition, in the description of the present invention, the terms "first" and "second" are only used for descriptive distinction and cannot be understood as indicating or implying relative importance or implicitly indicating the quantity of the indicated technical features. In addition, the features defined with "first" and "second" may explicitly or implicitly include one or more of such features
[0026] Example 1
[0027] As shown in the attached drawings of the specification Figures 1-3 As shown, this embodiment provides an operating platform for the splicing operation of a composite wall, including a first column 3, a second column 4, a cross beam 5, and a counterweight 6. The heights of the first column 3 and the second column 4 are higher than the height of the composite wall 1. The first column 3 and the second column 4 are connected by the cross beam 5, and the three enclose a receiving cavity for the composite wall 1 to pass through. The distance between the first column 3 and the second column 4 is greater than the thickness of the composite wall 1. A plurality of construction platforms 7 are arranged on the second column 4 at intervals in the vertical direction. The distance between the uppermost construction platform 7 and the top of the composite wall 1 is not greater than 2 m. The counterweight 6 is arranged on the first column 3.
[0028] Specifically, the composite wall 1 is arranged on the raft foundation 2. The composite wall 1 can be a precast double-skin composite wall. The operating platform of the present application is suitable for operating on the outer joint of the composite wall 1. The distance between the outer side of the composite wall 1 and the edge of the raft foundation 2 is 500 mm. The distance between the composite wall and the slope is greater than the length of the second column 4. The first column 3 and the second column 4 are connected into a whole by the cross beam 5. The distance between the first column 3 and the second column 4 is greater than the thickness of the composite wall 1. The height of the cross beam 5 is greater than the height of the composite wall 1. During use, the operating platform straddles the composite wall 1. The first column 3 is located inside the composite wall 1 and is placed on the raft foundation 2. The second column 4 is located outside the composite wall 1, with part placed on the raft foundation 2 and the other part cantilevered. A counterweight 6 is arranged on the first column 3. The operating platform can achieve a balanced effect completely relying on its own structure, ensuring the operation safety of construction workers on the construction platform.
[0029] The operating platform is prefabricated in the factory, is adapted to the composite wall 1, and can be used only after passing the inspection. It is hoisted to the target position for the splicing operation of the composite wall 1. The operating platform occupies a small area, reduces the influence of on-site conditions on the use of the operating platform, and increases the applicability of the operating platform. The traditional method using a scissor lift or an aerial work platform requires backfilling and hardening the side of the raft foundation before use. This method has safety risks of mechanical use caused by uneven settlement, and also causes ineffective connection between processes, increased construction period, and cost waste. The operating platform of the present application can effectively solve the above problems. By using a customized finished operating platform matching the composite wall, the safety risk of erection and dismantling is reduced, and the overall structure is safe and reliable.
[0030] Preferably, a construction platform 7 is arranged on the second column 4 for the outer joint operation of the composite wall; multiple construction platforms can also be arranged on the first column 3 for the inner operation of the composite wall. The first column 3 can be supported on the raft foundation 2 without additional counterweight.
[0031] Optimized implementation manner. On one side of the first upright column 3 and the second upright column 4 facing the accommodating cavity, a limiting roller 8 is provided. The axial direction of the limiting roller 8 is parallel to the longitudinal direction. In this embodiment, the transverse direction is parallel to the thickness direction of the laminated wall, the longitudinal direction is parallel to the length direction of the laminated wall, and the vertical direction is parallel to the height direction of the laminated wall. In order to facilitate the operation platform to smoothly straddle the laminated wall during the hoisting process, limiting rollers 8 are provided on the inner sides of the first upright column 3 and the second upright column 4. The limiting rollers 8 face the laminated wall 1. During the lowering or taking-out process, the limiting rollers 8 can contact the laminated wall 1 and roll along the laminated wall 1, which is convenient for hoisting the operation platform. At the same time, it can also prevent the upright columns from hitting the laminated wall 1 and damaging the laminated wall 1.
[0032] Preferably, a rubber layer is provided on the outer side of the limiting roller 8, which plays a buffering role when the limiting roller 8 contacts the laminated wall 1, and at the same time can protect the laminated wall 1 from being impacted. At least two limiting rollers 8 are provided vertically on the first upright column 3 and the second upright column 4.
[0033] Optimized implementation manner. The distance between the limiting roller 8 of the first upright column 3 and the limiting roller 8 of the second upright column 4 is greater than the thickness of the laminated wall 1, which is convenient for the operation platform to have enough space for hoisting, while meeting the use requirements of the operation platform and reducing the requirements for hoisting accuracy.
[0034] Preferably, the protruding length of the limiting roller 8 on the second upright column 4 is less than the distance between the outer wall of the laminated wall 1 and the edge of the raft foundation 2, that is, the distance between the end of the limiting roller 8 far from the second upright column 4 and the side wall of the second upright column 4 facing the accommodating cavity is less than the distance between the outer wall of the laminated wall 1 and the edge of the raft foundation 2. During use, it can be ensured that at least part of the second upright column 4 is supported on the raft foundation 2. The limiting roller 8 on the second upright column 4 is in clearance fit with the laminated wall 1, and the clearance can be adjusted by the placement position of the operation platform.
[0035] Optimized implementation manner. The cross beam 5 is a steel truss cross beam. The first upright column 3 and the second upright column 4 are respectively fixedly connected to the bottom of the steel truss cross beam, and the steel truss cross beam is welded to the upright columns.
[0036] In some embodiments, the cross beam 5 can be a steel plate, and the steel plate is welded to the tops of the first upright column 3 and the second upright column 4.
[0037] Optimized implementation mode, the second column 4 is provided with a construction part and a vertical passage 41. The vertical passage 41 is located on one side of the construction part. Each construction platform 7 is arranged layer by layer on the construction part. A number of tread bars are arranged at intervals along the vertical direction in the vertical passage 41. Each tread bar is fixedly connected to the second column 4. The tread bar can be made of round steel or square steel. The adjacent tread bars are spaced 285 mm apart. During the operation, the construction personnel move to the target construction platform through the tread bars.
[0038] Optimized implementation mode, the second column 4 is preferably a steel truss column, including a vertical support component and a plurality of horizontal support components arranged at intervals along the vertical direction of the vertical support component. The vertical support component includes a plurality of vertical rods 42 distributed in a square shape. Each vertical rod 42 is connected to the horizontal support component layer by layer. Each vertical rod 42 is connected by the horizontal support component to form a steel truss column. The construction platform 7 is arranged corresponding to the horizontal support component of the second column 4 one by one.
[0039] Specifically, the horizontal support component includes a transverse rod 43 and a longitudinal rod 44. The horizontal support component can be a square frame formed by welding the transverse rod 43 and the longitudinal rod 44, and then the square frame is welded to the vertical rod 42. The number of vertical rods 42 is at least four, distributed at the four corners of the square. The horizontal support component can also be that the transverse rod 43 is welded to the vertical rods 42 in the transverse direction, and the longitudinal rod 44 is welded to the vertical rods 42 in the longitudinal direction to obtain the steel truss column.
[0040] Optimized implementation mode, in order to ensure the strength of the steel truss column, the second column 4 further includes a number of diagonal braces 45. Diagonal braces 45 are arranged layer by layer between two adjacent vertical rods 42 in the transverse direction. Of course, diagonal braces can also be arranged between two adjacent vertical rods in the longitudinal direction as needed.
[0041] Preferably, the first column 3 and the second column 4 have the same structure, both are steel truss structures built by steel structures. Of course, the first column 3 can also be other steel structure columns.
[0042] Optimized implementation mode, to ensure operation safety, the second column 4 further includes a number of first guardrails 46 and a number of second guardrails 47. The first guardrails 46 are arranged on the construction part and are arranged vertically along the vertical rods 42. A plurality of first guardrails 46 are arranged at intervals above each construction platform 7. The first guardrails 46 are welded to the vertical rods 42 and surround the vertical support component to ensure the personal safety of the construction personnel. The second guardrails 47 are welded to the vertical rods 42 and surround the vertical passage 41 to ensure the personal safety of the construction personnel. Of course, the first guardrails 46 and the second guardrails 47 can be integral guardrails.
[0043] The vertical rods, transverse rods, longitudinal rods, and guardrails can be made of steel members such as square steel or steel pipes.
[0044] The steel truss cross beam has the same structure as the second column 4. The steel truss cross beam is horizontally arranged, so its structure will not be described in detail here.
[0045] In this embodiment, the total height of the operation platform is 11.49 m, the size of the first column 3 is 1.2 m * 1.2 m * 10.7 m, the size of the second column 4 is 0.8 m * 2 m * 10.7 m, the size of the steel truss cross beam is 1.2 m * 3.75 m * 0.79 m, and the weight of the counterweight 6 is 280 kg. Of course, the size of the above steel truss can be adjusted according to actual needs, and the weight of the counterweight 6 can also be adjusted according to actual needs, which is not limited in this embodiment.
[0046] Preferably, the counterweight 6 is preferably a finished concrete counterweight. The counterweight 6 is arranged at the bottom of the first column 3, and the bottom of the first column 3 is reinforced.
[0047] In an optimized implementation mode, to facilitate the hoisting of the operation platform, a hoisting position for hoisting is provided on the cross beam 5, and a lifting ring can be arranged at the hoisting position. In this embodiment, by using a steel truss cross beam, hoisting can be directly carried out through the members on the steel truss cross beam.
[0048] In an optimized implementation mode, an anti-corrosion layer is provided on each member of the first column 3, the second column 4 and the steel truss cross beam. At the same time, an anti-corrosion layer is provided on each guardrail and the construction platform. The anti-corrosion layer can be realized by spraying anti-corrosion paint, which improves the service life of the operation platform.
[0049] Embodiment 2
[0050] This embodiment provides an operation platform for the splicing operation of laminated walls. The structures that are the same as those in Embodiment 1 will not be described in detail here. The cross beam 5 is a steel truss cross beam. The steel truss cross beam includes two cross beam units. The first column 3 and the second column 4 are respectively connected to one of the cross beam units. The longitudinal rods of the two cross beam units are made of sleeved steel pipes. By adjusting the insertion degree of the steel pipes, the distance between the first column 3 and the second column 4 can be adjusted to meet the use of laminated walls of different sizes.
[0051] At the same time, the content not described in detail in this specification belongs to the prior art well known to those skilled in the art.
[0052] Those skilled in the art of this technology should understand that the present utility model can be implemented in many other specific forms without departing from the spirit and scope of the present utility model. Although the embodiments of the present utility model have been described, it should be understood that the present utility model should not be limited to these embodiments. Those skilled in the art of this technology can make changes and modifications within the spirit and scope of the present utility model as defined in the appended claims.
Claims
1. An operating platform for the splicing operation of laminated walls, characterized in that, It includes a first upright column, a second upright column, a cross beam and a counterweight. The heights of the first upright column and the second upright column are higher than the height of the laminated wall. The first upright column and the second upright column are connected by the cross beam, and the three enclose a receiving cavity for the laminated wall to pass through. The distance between the first upright column and the second upright column is greater than the thickness of the laminated wall. A plurality of construction platforms are arranged on the second upright column at intervals in the vertical direction. The distance between the uppermost construction platform and the top end of the laminated wall is not greater than 2 m. The counterweight is arranged on the first upright column.
2. The operating platform for the splicing operation of the laminated wall according to claim 1, characterized in that, Limit rollers are provided on one side of the first upright column and the second upright column facing the receiving cavity. The axial direction of the limit rollers is parallel to the longitudinal direction.
3. The operating platform for the splicing operation of superposed walls according to claim 2, wherein The protruding length of the limit rollers on the second upright column is less than the distance between the outer wall of the laminated wall and the edge of the raft foundation.
4. The operating platform for the splicing operation of the laminated wall according to claim 1, characterized in that, The cross beam is a steel truss cross beam. The first upright column and the second upright column are respectively fixedly connected to the bottom of the steel truss cross beam.
5. The operating platform for the splicing operation of the laminated wall according to claim 1, characterized in that, The cross beam includes two cross beam units. The first upright column and the second upright column are respectively connected to one cross beam unit, and the two cross beam units are telescopically connected.
6. The operating platform for the splicing operation of the laminated wall according to claim 1, characterized in that, A vertical passage is provided on the second upright column. The vertical passage is located on one side of the construction platform. A number of tread bars are arranged in the vertical passage at intervals in the vertical direction. Each tread bar is fixedly connected to the second upright column.
7. The operating platform for the splicing operation of the laminated wall according to claim 1, characterized in that, The second upright column is a steel truss upright column, which includes a vertical support assembly and a plurality of horizontal support assemblies arranged at intervals in the vertical direction along the vertical support assembly. The vertical support assembly includes a plurality of upright bars distributed in a square shape. Each upright bar is connected to the horizontal support assembly layer by layer. The construction platforms are arranged corresponding to the horizontal support assemblies of the second upright column one by one.
8. The operating platform for the splicing operation of the laminated wall according to claim 7, characterized in that, A number of diagonal braces are provided between two adjacent upright bars.
9. The operating platform for the splicing operation of the laminated wall according to claim 1, characterized in that, Hoisting positions for hoisting are provided on the cross beam.
10. The operating platform for the splicing operation of the laminated wall according to claim 1, characterized in that, Anticorrosion layers are provided on the first upright column, the second upright column and the cross beam.