Tool lifting frame for hoisting large structure

By designing a tool lifting frame for large structures, using pile foundations to fix the lifting frame body, and using hydraulic jacks and lifting ropes to lift the arch ribs, the difficulty of lifting the arch ribs with high height and heavy weight is solved, and efficient and convenient lifting effect is achieved.

CN223118030UActive Publication Date: 2025-07-18HEAVY EQUIP ENG CO LTD OF WUCHANG SHIPBUILDING IND
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202422399527.8
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-09-30
Publication Date
2025-07-18
Estimated Expiration
2034-09-30

AI Technical Summary

Technical Problem

The prior art cannot efficiently lift the high height and heavy arch ribs, which leads to expensive cranes and difficult to build the pier, and conventional lifting cannot be completed.

Method used

Design a large-scale structure lifting tool lifting frame, including mounting frame, lifting components and hydraulic jacks, fix the lifting frame body through pile foundation, use hydraulic lifting jacks and lifting ropes for arch rib lifting, and combine cable and air steel ropes and tension jacks to improve stability.

Benefits of technology

It realizes efficient and convenient lifting of arch ribs, reduces crane costs and trest production costs, and improves the stability and safety of lifting.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN223118030U_ABST
    Figure CN223118030U_ABST
Patent Text Reader

Abstract

The utility model is suitable for the technical field of bridge installation, and provides a tool hoisting frame for hoisting a large structure, which comprises an installation frame, the lifting assemblies are symmetrically and fixedly mounted on the mounting frame and used for lifting the arch rib; the lifting assembly comprises three lifting frame main bodies, a cross beam and four hydraulic jacks, and the lifting frame main bodies play a supporting role in the arch rib lifting process; the cross beam is fixedly mounted at the top ends of the three hoisting frame main bodies and is used for mounting a hydraulic jack; the four hydraulic lifting jacks are fixedly installed on the top of the cross beam, and lifting ropes are arranged on the hydraulic lifting jacks and used for lifting arch ribs. The tool hoisting frame for hoisting the large-scale structure, provided by the scheme, can be used for hoisting an arch rib, and compared with a traditional crane hoisting mode, hoisting is relatively convenient.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model belongs to the technical field of bridge installation, and particularly relates to a tool lifting frame for hoisting large structures. Background Technique

[0002] The width of the Yulin River at the bridge site is 137 meters. The height of the main beam directly above the Yulin River from the water surface is about 46 meters, and the height of the highest point of the arch rib from the water surface is about 109 meters. The maximum designed weight of the main beam segment directly above the Yulin River is 50.8 tons, and the heaviest arch rib is 43.1 tons. In order to protect the bridge main beam and be consistent with the designed force calculation model, the design principle requires that the arch rib be hoisted first, and then the main beam be hoisted, and the tensioning starts under the condition that the main beam is not stressed. Due to the too high hoisting height and large weight of the arch rib, using an extra-large crane not only incurs high crane costs, but also the trestle has to bear the ballast under the hoisting condition of the extra-large crane. Fabricating such a trestle is time-consuming and laborious, and the cost is even greater. Therefore, conventional hoisting cannot be completed. Content of the Utility Model

[0003] The utility model provides a tool lifting frame for hoisting large structures, aiming to solve the problem of inconvenient hoisting of arch ribs at present.

[0004] The utility model is realized as follows. A tool lifting frame for hoisting large structures includes: an installation frame; a group of lifting components symmetrically and fixedly installed on the installation frame for lifting the arch rib; the lifting components include three lifting frame bodies, a cross beam, and four hydraulic jacks. The lifting frame bodies play a supporting role during the lifting of the arch rib; the cross beam is fixedly installed at the top of the three lifting frame bodies, and the cross beam is used for installing hydraulic jacks; the four hydraulic lifting jacks are fixedly installed on the top of the cross beam, and lifting ropes are arranged on the hydraulic lifting jacks, and the lifting ropes are used for hoisting and lifting the arch rib.

[0005] Preferably, pile foundations are arranged at the bottom of the installation frame, and the pile foundations are used for installing and fixing the installation frame.

[0006] Preferably, a plurality of guy steel ropes are arranged on the lifting frame body. One end of the guy steel rope is connected to the ground where the installation frame is installed. A plurality of tensioning jacks are arranged on the lifting frame body, and the tensioning jacks are communicated with one end of the guy steel rope. The tensioning jacks are used for tensioning the guy steel ropes.

[0007] Preferably, an anchor pile is arranged on one side of the installation frame. A jack rope is arranged on the anchor pile. A connection box is arranged at one end of the jack rope, and the connection box is connected to one end of the guy steel rope.

[0008] Preferably, a steel pin is provided on the connection box. One end of the steel pin is connected to the gin pole rope. A fixed-end anchor is provided on the connection box, and the fixed-end anchor is used to fixedly connect the connection box and the guy steel rope.

[0009] Preferably, the anchor pile includes: concrete, seamless steel pipe, spiral reinforcement and anchor ring. The concrete is arranged on the ground where the mounting frame is installed. The seamless steel pipe is assembled on the concrete. The spiral reinforcement is arranged on the seamless steel pipe. The anchor ring is assembled on the concrete.

[0010] Preferably, the mounting frame, the main body of the lifting frame and the cross beam are all made of steel.

[0011] Preferably, a tool anchor plate is provided on the tension jack, and tool wedge grips are provided on the tool anchor plate.

[0012] Compared with the related art, the large-structure hoisting tooling lifting frame provided by the present utility model has the following beneficial effects:

[0013] The mounting frame and the main body of the lifting frame can be stably installed through the pile foundation. The main body of the lifting frame is installed on the mounting frame. The arch rib is integrally in an X shape. When using multiple main bodies of the lifting frame to hoist the arch rib, the lifting ropes on multiple hydraulic lifting jacks are connected to the arch rib. The lifting ropes are lifted by the hydraulic lifting jacks, so as to drive the arch rib to be lifted. When the arch rib is lifted to the corresponding position, finally, the construction workers can adjust and weld at high altitude. The arch rib can be lifted through the entire tooling lifting frame. Compared with the traditional crane hoisting method, the hoisting is more convenient. BRIEF DESCRIPTION OF THE DRAWINGS

[0014] Figure 1 is the front view structural schematic diagram of a large-structure hoisting tooling lifting frame provided by the present utility model;

[0015] Figure 2 is the top view structural schematic diagram of the main body of the lifting frame and the hydraulic lifting jack in the present utility model;

[0016] Figure 3 is the top view structural schematic diagram of the present utility model;

[0017] Figure 4 is the side view structural schematic diagram of the main body of the lifting frame and the hydraulic lifting jack in the present utility model;

[0018] Figure 5 is Figure 1 the enlarged structural schematic diagram of part A shown in;

[0019] Figure 6 is Figure 4 the enlarged structural schematic diagram of part B shown in;

[0020] Figure 7 This is a schematic structural diagram of the anchor pile, hoisting rope, connection box, steel pin and guy steel rope in the present utility model;

[0021] Figure 8 This is a schematic structural diagram of the concrete, seamless steel pipe, spiral reinforcement and anchor ring in the present utility model;

[0022] Figure 9 This is a partial front view structural diagram of the present utility model;

[0023] Figure 10 This is a partial front view structural diagram of the tensioning jack, tool anchor plate and tool wedge in the present utility model.

[0024] Reference numerals: 1, mounting frame; 2, main body of lifting frame; 3, cross beam; 4, hydraulic lifting jack; 5, pile foundation; 6, guy steel rope; 7, tensioning jack; 701, tool anchor plate; 702, tool wedge; 8, anchor pile; 801, concrete; 802, seamless steel pipe; 803, spiral reinforcement; 804, anchor ring; 9, hoisting rope; 10, connection box; 11, steel pin; 12, fixed end anchor. Detailed implementation manners

[0025] Unless otherwise defined, all technical and scientific terms used herein have the same meaning as commonly understood by one of ordinary skill in the technical field to which this application belongs; the terms used in the specification of this application are only for the purpose of describing specific embodiments and are not intended to limit this application; the terms "including" and "having" and any variations thereof in the specification and claims of this application and the above accompanying drawings are intended to cover non-exclusive inclusion. The terms "first", "second", etc. in the specification and claims of this application or the above accompanying drawings are used to distinguish different objects and not to describe a specific order.

[0026] Reference to "embodiment" herein means that a particular feature, structure or characteristic described in connection with the embodiment can be included in at least one embodiment of this application. The phrase does not necessarily refer to the same embodiment at every occurrence in the specification, nor is it an independent or alternative embodiment mutually exclusive with other embodiments. Those skilled in the art will explicitly and implicitly understand that the embodiments described herein can be combined with other embodiments.

[0027] The embodiment of the present utility model provides a tool lifting frame for hoisting large structures, as Figure 1-10As shown in the figure, the tooling lifting frame for large-scale structure hoisting includes: a mounting frame 1; a set of lifting components symmetrically and fixedly mounted on the mounting frame 1 for lifting the arch rib; the lifting components include three lifting frame bodies 2, a cross beam 3 and four hydraulic jacks 4, and the lifting frame bodies 2 play a supporting role during the process of lifting the arch rib; the cross beam 3 is fixedly mounted on the tops of the three lifting frame bodies 2, and the cross beam 3 is used for mounting the hydraulic jacks 4; the four hydraulic lifting jacks 4 are fixedly mounted on the top of the cross beam 3, and lifting ropes are arranged on the hydraulic lifting jacks 4, and the lifting ropes are used for hoisting and lifting the arch rib.

[0028] It should be noted that there are a total of 6 lifting frame bodies 2 at the top of the mounting frame 1, and there is a cross beam 3 at the top of 3 lifting frame bodies 2. In order to protect the main bridge girder and be consistent with the designed force calculation model, the design principle requires that the arch rib be hoisted first and then the main girder be hoisted, and the tensioning starts under the condition that the main girder is not stressed. Since the hoisting height of the arch rib is too high and the weight is not small, using an extra-large crane not only incurs high crane costs, but also the trestle has to bear the ballast under the hoisting condition of the extra-large crane. Making such a trestle is time-consuming and laborious, and the cost is even huge. Therefore, conventional hoisting cannot be completed;

[0029] In this embodiment, at the position where the lifting frame body 2 is installed, steel pipes of 630×10 are first driven into the Yulin River. The length of the steel pipe is about 34 meters, of which the depth of the driven pile into the rock is not less than 10 meters, and it is poured with concrete with a height not less than 5 meters, thus forming a pile foundation 5. Through the pile foundation 5, the mounting frame 1 and the lifting frame body 2 can be stably installed. The lifting frame body 2 can be provided with 6 in total, and the 6 lifting frame bodies 2 are symmetrically arranged on the mounting frame 1. The overall arch rib is in an X shape. When using multiple lifting frame bodies 2 to hoist the arch rib, the lifting ropes on the multiple hydraulic lifting jacks 4 are connected to the arch rib, and the lifting ropes are lifted by the hydraulic lifting jacks 4, thereby driving the arch rib to be lifted. When the arch rib is lifted to the corresponding position, finally the construction workers can adjust and weld at high altitude. Through the entire tooling lifting frame, the arch rib can be lifted, which is more convenient compared with the traditional crane hoisting method.

[0030] In a further preferred embodiment of the present invention, a pile foundation 5 is provided at the bottom of the mounting frame 1, and the pile foundation 5 is used for installing and fixing the mounting frame 1.

[0031] In this embodiment, through the pile foundation 5, the mounting frame 1 and the lifting frame body 2 can be stably installed, improving the stability of the lifting frame body 2 during use.

[0032] In a further preferred embodiment of the present utility model, a plurality of guy steel ropes 6 are provided on the main body 2 of the lifting frame. One end of the guy steel rope 6 is connected to the ground where the mounting frame 1 is installed. A plurality of tensioning jacks 7 are provided on the main body 2 of the lifting frame. The tensioning jack 7 is communicated with one end of the guy steel rope 6. The tensioning jack 7 is used to tension the guy steel rope 6.

[0033] In this embodiment, the main body 2 of the lifting frame can be pulled by the guy steel rope 6 to prevent the main body 2 of the lifting frame from tipping over, improving the overall stability of the main body 2 of the lifting frame. The tensioning jack 7 is used to tension the guy steel rope 6 to adjust the overall tension of the guy steel rope 6 and improve the stability of the use of the guy steel rope 6.

[0034] In a further preferred embodiment of the present utility model, an anchor pile 8 is provided on one side of the mounting frame 1. A hoisting rope 9 is provided on the anchor pile 8. A connection box 10 is provided at one end of the hoisting rope 9, and the connection box 10 is connected to one end of the guy steel rope 6.

[0035] In this embodiment, the installation of the guy steel rope 6 is facilitated by the anchor pile 8, the hoisting rope 9 and the connection box 10.

[0036] In a further preferred embodiment of the present utility model, a steel pin 11 is provided on the connection box 10. The steel pin 11 is connected to one end of the hoisting rope 9. A fixed-end anchor 12 is provided on the connection box 10. The fixed-end anchor 12 is used to fixedly connect the connection box 10 and the guy steel rope 6.

[0037] In this embodiment, the connection between the hoisting rope 9 and the connection box 10 is facilitated by the steel pin 11, and the connection box 10 and the guy steel rope 6 are fixedly connected by the fixed-end anchor 12.

[0038] In a further preferred embodiment of the present utility model, the anchor pile 8 includes: concrete 801, seamless steel pipe 802, spiral reinforcement 803 and anchor ring 804. The concrete 801 is provided on the ground where the mounting frame 1 is installed. The seamless steel pipe 802 is assembled on the concrete 801. The spiral reinforcement 803 is provided on the seamless steel pipe 802. The anchor ring 804 is assembled on the concrete 801.

[0039] In this embodiment, the anchor pile 8 is formed by the concrete 801, the seamless steel pipe 802, the spiral reinforcement 803 and the anchor ring 804, and the installation of the guy steel rope 6 is facilitated by the anchor pile 8.

[0040] In a further preferred embodiment of the present utility model, the mounting frame 1, the main body 2 of the lifting frame and the cross beam 3 are all made of steel.

[0041] In this embodiment, by setting the steel material, the overall hardness can be improved, thereby enhancing the stability of the overall use.

[0042] In a further preferred embodiment of the present utility model, a tool anchor plate 701 is provided on the tensioning jack 7, and tool wedges 702 are provided on the tool anchor plate 701.

[0043] In this embodiment, the tool anchor plate 701 can bear the tensile force of the tensioning jack 7 on the guy steel rope 6, and the tool wedges 702 can firmly clamp the guy steel rope 6 to prevent it from slipping or loosening during the tensioning process, ensuring the stability and reliability of the tensioning effect.

[0044] In summary, compared with the related art, the mounting frame 1 and the main body 2 of the lifting frame can be stably installed through the pile foundation 5. The main body 2 of the lifting frame is installed on the mounting frame 1. A total of 6 main bodies 2 of the lifting frame can be provided as a whole, and the 6 main bodies 2 of the lifting frame are symmetrically arranged on the mounting frame 1. The arch rib is in an X shape as a whole. When using multiple main bodies 2 of the lifting frame to hoist the arch rib, the lifting ropes on the multiple hydraulic lifting jacks 4 are connected to the arch rib, and the lifting ropes are lifted by the hydraulic lifting jacks 4, thereby driving the arch rib to be lifted. When the arch rib is lifted to the corresponding position, finally, the construction workers can adjust and weld at high altitude. The arch rib can be lifted through the entire tooling lifting frame, which is more convenient for hoisting compared with the traditional crane hoisting method.

[0045] It should be noted that the circuits, electronic components, and modules involved in the present utility model are all prior arts, which can be fully realized by those skilled in the art without further elaboration. The content protected by the present utility model does not involve improvements to software and methods.

[0046] In several embodiments provided by the present application, it should be understood that the disclosed device can be implemented in other ways.

[0047] The above embodiments are only used to illustrate the technical solutions of the present utility model, rather than to limit the protection scope of the utility model. Obviously, the described embodiments are only some embodiments of the present utility model, rather than all embodiments. Based on these embodiments, all other embodiments obtained by those of ordinary skill in the art without creative work fall within the scope of protection of the present utility model. Although the present utility model has been described in detail with reference to the above embodiments, those of ordinary skill in the art can still, without conflict, make combinations, additions, deletions, or other adjustments to the features in the various embodiments of the present utility model without creative work according to the situation, so as to obtain different technical solutions that are essentially not divorced from the concept of the present utility model, and these technical solutions also fall within the scope of protection of the present utility model.

Claims

1. An industrial lifting frame for hoisting large structures, characterized in that, Including: Mounting frame (1); A set of lifting components symmetrically and fixedly mounted on the mounting frame (1) for lifting the arch rib; The lifting component includes three lifting frame bodies (2), a cross beam (3) and four hydraulic lifting jacks (4). The lifting frame body (2) plays a supporting role during the process of lifting the arch rib; The cross beam (3) is fixedly mounted on the tops of the three lifting frame bodies (2). The cross beam (3) is used for mounting the hydraulic lifting jacks (4); The four hydraulic lifting jacks (4) are fixedly mounted on the top of the cross beam (3). A lifting rope is arranged on the hydraulic lifting jack (4), and the lifting rope is used for hoisting and lifting the arch rib.

2. The tooling lifting frame for large-scale structure hoisting according to claim 1, characterized in that, Pile foundations (5) are arranged at the bottom of the mounting frame (1), and the pile foundations (5) are used for installing and fixing the mounting frame (1).

3. The lifting frame of the tooling for hoisting large structures according to claim 1, characterized in that, A plurality of guy steel ropes (6) are arranged on the lifting frame body (2). One end of the guy steel rope (6) is connected to the ground where the mounting frame (1) is installed. A plurality of tensioning jacks (7) are arranged on the lifting frame body (2), and the tensioning jack (7) is communicated with one end of the guy steel rope (6). The tensioning jack (7) is used for tensioning the guy steel rope (6).

4. The lifting frame for large-scale structure hoisting according to claim 3, wherein An anchor pile (8) is arranged on one side of the mounting frame (1). A jack rope (9) is arranged on the anchor pile (8). A connection box (10) is arranged at one end of the jack rope (9), and the connection box (10) is connected to one end of the guy steel rope (6).

5. The tooling lifting frame for large-scale structure hoisting according to claim 4, characterized in that, A steel pin (11) is arranged on the connection box (10), and the steel pin (11) is connected to one end of the jack rope (9). A fixed end anchor (12) is arranged on the connection box (10), and the fixed end anchor (12) is used for fixedly connecting the connection box (10) and the guy steel rope (6).

6. The lifting frame for large-scale structure hoisting according to claim 4, characterized in that, The anchor pile (8) includes: concrete (801), seamless steel pipe (802), spiral reinforcement (803) and anchor ring (804). The concrete (801) is arranged on the ground where the mounting frame (1) is installed. The seamless steel pipe (802) is assembled on the concrete (801). The spiral reinforcement (803) is arranged on the seamless steel pipe (802). The anchor ring (804) is assembled on the concrete (801).

7. The tooling lifting frame for large-scale structure hoisting according to claim 1, characterized in that, The mounting frame (1), the lifting frame body (2) and the cross beam (3) are all made of steel.