Liftable elevator shaft construction operation platform

By designing an elevator shaft construction operation platform, the frame structure is combined with support, and the casing is connected to the operating frame vertical pole, the efficient and safe operation of elevator shaft construction is achieved, and the problems of inefficiency and poor safety in traditional construction are solved.

CN223151612UActive Publication Date: 2025-07-25中交四航局第六工程有限公司
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202421674432.6
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-07-16
Publication Date
2025-07-25
Estimated Expiration
2034-07-16

AI Technical Summary

Technical Problem

During the construction of traditional elevator shafts, the installation and demolition of the scaffolding operating platform is complicated, resulting in low construction efficiency and reduced safety, and the difficulty increases as the floor rises.

Method used

The liftable elevator shaft construction operation platform is adopted. The frame structure consists of the main beam and the secondary beam. It is fixed to the elevator shaft wall through support. The casing is connected to the vertical pole of the operating frame and is fixed by pins. The platform plate can be adjusted in size. The hook is used for platform lifting and lowering. The support and connectors can be detached and reused.

Benefits of technology

It improves construction efficiency and safety, reduces building materials waste, simplifies the installation and demolition process of the operating platform, and adapts to different elevator shaft size requirements.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN223151612U_ABST
    Figure CN223151612U_ABST
Patent Text Reader

Abstract

The utility model discloses a liftable elevator shaft construction operation platform and relates to the technical field of constructional engineering, the liftable elevator shaft construction operation platform is integrally erected on four supporting pieces and has good stability and supporting performance, channel steel serves as a main beam, one end of I-shaped steel is welded with a steel plate to serve as a supporting piece, and the other end of the I-shaped steel is welded with a steel plate to serve as a supporting piece. The connecting piece composed of the two U-shaped clamps and the iron block is used for connecting the main beam and the supporting piece, and it is ensured that the platform is fixed in the horizontal direction. In the vertical direction, the operating frame vertical rods and the sleeves are inserted in a one-to-one correspondence mode and are connected and fixed through pins. The supporting pieces and the connecting pieces can be detached and reused, safety and stability are guaranteed, meanwhile, erecting of the construction operation platform is more efficient, and waste of building materials is reduced. A certain distance is reserved between the operation platform and the inner wall of the elevator shaft. The size of the operation platform can be adjusted timely according to the size required by actual construction of the elevator shaft.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of construction engineering, in particular to a liftable construction operation platform for elevator shafts. Background Technique

[0002] With the springing up of more and more high-rise buildings, the car elevator, as an indispensable vertical means of transportation, its erection has become increasingly important, and the pouring of the elevator shaft for installing the elevator is the basis for all this. In traditional building construction, the formwork installation for elevator shaft pouring requires the erection of a scaffolding operation platform. The erection height of the scaffolding operation platform increases with the increase of the elevator shaft height. The dismantling of the scaffolding operation platform needs to be carried out from top to bottom after the elevator shaft construction reaches the preset height. The process of assembling and disassembling the scaffolding operation platform for the elevator shaft is very cumbersome, resulting in low construction efficiency. As the floor height increases, the construction difficulty gradually increases and the safety also decreases accordingly. Content of the Utility Model

[0003] One of the purposes of the utility model is at least to provide a liftable construction operation platform for elevator shafts, which can improve construction efficiency and ensure construction safety at the same time, aiming at how to overcome the problems existing in the above-mentioned prior art.

[0004] In order to achieve the above purpose, the technical solutions adopted by the utility model include the following aspects.

[0005] A liftable construction operation platform for elevator shafts, comprising: a frame structure, a platform board is arranged on the frame structure, the frame structure is arranged in the elevator shaft, and a detachable support is arranged on the wall of the elevator shaft, and the frame structure is arranged on the support.

[0006] Preferably, the frame structure is composed of a first main beam, a second main beam, a third main beam, a fourth main beam, a first secondary beam, a second secondary beam, a third secondary beam, a fourth secondary beam and a fifth secondary beam; at least two reserved holes are respectively arranged on the walls on both sides of the wellhead of the elevator shaft, the reserved holes penetrate through the walls, the support is detachably arranged on the wall through the reserved holes, the first main beam is connected with the support, and the second main beam is connected with the support; thus, the disassembly, assembly and erection of the operation platform are efficient and convenient.

[0007] Preferably, the first main beam, the second main beam, the third main beam and the fourth main beam are connected end to end to form a rectangular frame, the first main beam is parallel to the third main beam, and the second main beam is parallel to the fourth main beam.

[0008] Preferably, the first secondary beam is connected to the first main beam and the third main beam, and the first secondary beam is perpendicular to the first main beam; the second secondary beam is connected to the first main beam and the third main beam, and the second secondary beam is perpendicular to the first main beam; the third secondary beam is connected to the second main beam and the first secondary beam, and the connection position is at the middle of the second main beam, and the third secondary beam is perpendicular to the second main beam; the fourth secondary beam is connected to the first secondary beam and the second secondary beam; the fifth secondary beam is connected to the first main beam and the second secondary beam; the third secondary beam, the fourth secondary beam, and the fifth secondary beam are coaxial; the connection relationship is close and the connection structure is reasonable, ensuring the stability of the operation platform and guaranteeing construction safety.

[0009] Preferably, the size of the platform board is the same as that of the rectangular frame, and the platform board is connected above the frame structure; the size of the platform board can be adjusted according to actual construction requirements, making the operation platform more practical.

[0010] Preferably, cylindrical sleeves are respectively arranged above the first secondary beam and the second secondary beam. The platform board is provided with through holes, and the first secondary beam and the second secondary beam are provided with installation holes. The sleeves pass through the through holes of the platform board and are respectively vertically inserted into the installation holes on the first secondary beam and the second secondary beam. The connection parts of the sleeves and the first secondary beam are welded, and the connection parts of the sleeves and the second secondary beam are welded; the upper parts of the sleeves are inserted into the vertical rods of the operation frame.

[0011] Preferably, the support member is composed of a steel plate and an I-beam. The steel plate is arranged at one end of the I-beam, and the I-beam passes through the wall, and the steel plate is arranged on the outer side of the wall.

[0012] Preferably, the reserved hole is a rectangular through hole, and the gap reserved between the inner side of the wall and the edge of the frame structure is ≤100 mm.

[0013] Preferably, hooks are arranged above the first secondary beam and the second secondary beam. The hooks pass through the platform board and are connected to the first secondary beam; the hooks pass through the platform board and are connected to the second secondary beam.

[0014] Preferably, the sleeve and the vertical rod of the operation frame are connected and fixed by one or more pins. The distance between the pins is 200 mm, the distance between the pin and the first secondary beam is 200 mm, and the distance between the pin and the second secondary beam is 200 mm.

[0015] In summary, due to the adoption of the above technical solutions, the present utility model has at least the following beneficial effects:

[0016] The frame structure of the lift shaft platform construction operation platform is erected on four support members, with good stability and support. The main beam and the support member are fixed by connecting members to ensure the fixation of the operation platform in the horizontal direction. Vertically, the operation frame vertical pole is inserted into the sleeve and fixed by pins. The support members and connecting members used are all detachable and reusable, which not only ensures safety and stability but also makes the erection of the construction operation platform more efficient and reduces the waste of building materials. Hooks are welded above the platform board for connecting the hook ropes to facilitate the lifting of the platform. A certain distance is reserved between the operation platform and the inner wall of the lift shaft, and the size of the platform can be adjusted in a timely manner according to the actual construction requirements of the lift shaft. Description of the Drawings

[0017] Figure 1 is a top view of the operation platform of an exemplary embodiment of the present utility model.

[0018] Figure 2 is a front view of the operation platform of an exemplary embodiment of the present utility model.

[0019] Figure 3 is a perspective view of the operation platform of an exemplary embodiment of the present utility model.

[0020] Figure 4 is a schematic sectional view of the lift shaft operation frame of an exemplary embodiment of the present utility model.

[0021] Figure 5 is a schematic diagram of the connection between the sleeve and the secondary beam of an exemplary embodiment of the present utility model.

[0022] Figure 6 is a schematic diagram of the operation frame vertical pole inserted into the sleeve of an exemplary embodiment of the present utility model.

[0023] Figure 7 is a schematic diagram of the support member of an exemplary embodiment of the present utility model.

[0024] Figure 8 is a schematic diagram of the connecting member of an exemplary embodiment of the present utility model.

[0025] Reference numerals in the figures: 1 - Main beam one, 2 - Main beam two, 3 - Main beam three, 4 - Main beam four, 5 - Secondary beam one, 6 - Secondary beam two, 7 - Secondary beam three, 8 - Secondary beam four, 9 - Secondary beam five, 10 - Sleeve, 11 - Hook, 12 - Support member, 13 - Wall, 14 - Reserved hole, 15 - Operation frame vertical pole, 16 - Construction formwork, 17 - Connecting member, 18 - Steel plate, 19 - I-beam, 20 - Pin, 21 - U-shaped clamp, 22 - Iron block, 23 - Platform board, 24 - Operation frame. Detailed Embodiments

[0026] The present utility model will be further described in detail below in conjunction with the accompanying drawings and embodiments, so as to make the purpose, technical solution and advantages of the present utility model clearer and more understandable. It should be understood that the specific embodiments described herein are only used to explain the present utility model and are not used to limit the present utility model.

[0027] Figure 3 Fig. shows the liftable construction operation platform for the elevator shaft in this embodiment. The operation platform includes a frame structure, on which a platform board 23 is arranged. The frame structure is arranged in the elevator shaft, and a detachable and washable support member 12 is arranged on the wall 13 of the elevator shaft, and the frame structure is arranged on the support member 12.

[0028] During the construction of the elevator shaft, the operation frame can be installed on the operation platform, and the construction formwork for pouring the wall of the elevator shaft can be installed through the operation frame. When continuing the construction at the top of the already constructed elevator shaft, the operation frame and the operation platform can be lifted to a preset position and then the construction formwork can be set through the operation frame. Compared with the construction method of erecting the operation frame from the bottom of the elevator shaft, the method of cooperating the operation platform and the operation frame saves a large amount of rod erection operations and does not need to remove the operation frame after the construction of the elevator shaft is completed, effectively reducing the construction difficulty of the elevator shaft and improving the construction efficiency and construction safety.

[0029] Refer to Figure 1 、 Figure 2 Fig., the frame structure includes main beam one 1, main beam two 2, main beam three 3 and main beam four 4. The main beam one 1, main beam two 2, main beam three 3 and main beam four 4 are connected end to end to form a rectangular frame. The main beam one 1 is parallel to the main beam three 3, the main beam two 2 is parallel to the main beam four 4, and the main beam one 1 is perpendicular to the main beam two 2. Between the main beam two 2 and the main beam four 4, secondary beams five 5 and six 6 are arranged. The secondary beams five 5 and six 6 are both parallel to the main beam 2. The secondary beam one 5 is connected to the main beam one 1 and the main beam three 3, and the secondary beam two 6 is connected to the main beam one 1 and the main beam three 3. Between the main beam two 2 and the secondary beam one 5, a secondary beam three 7 is arranged. The secondary beam three 7 is perpendicularly connected to the main beam two 2, and the connection position is the middle of the secondary beam three 7. Between the secondary beam one 5 and the secondary beam two 6, a secondary beam four 8 is arranged. Between the secondary beam two 6 and the main beam four 4, a secondary beam five 9 is arranged. The secondary beam three 7, the secondary beam four 8 and the secondary beam five 9 are coaxial. All the main beams use channel steel; all the secondary beams use channel steel.

[0030] Refer to Figure 3 Fig., the platform board 23 is located above the frame structure. The shape and size of the platform board 23 are the same as the rectangular frame surrounded by the main beams. The contact part between the platform board 23 and the frame structure is welded to ensure the stability of the connection between the platform board 23 and the frame structure. The distance between the inner side surface of the wall 13 and the outer edge of the frame structure should be ≤ 100 mm.

[0031] Refer to Figure 1 、 Figure 3 、Figure 5 There are also four sleeves 10 provided on the operating platform, and the four sleeves 10 are arranged in a rectangle. The sleeve 10 can be connected to the platform plate 23 or the frame structure. When the sleeve 10 is connected to the platform plate 23, the bottom of the sleeve 10 is welded to the platform plate 23. When the sleeve 10 is connected to the frame structure, two sleeves 10 are respectively vertically connected to the first secondary beam 5, and the other two sleeves 10 are respectively vertically connected to the second secondary beam 6. Installation holes are respectively provided on the first secondary beam 5 and the second secondary beam 6. The positions of the installation holes correspond to the positions of the sleeves 10, and the sizes of the installation holes are adapted to the sizes of the sleeves 10. Correspondingly, through holes are provided at the contact parts of the platform plate 23 and the sleeves 10. After the sleeves 10 pass through the through holes of the platform plate 23, they are vertically inserted into the installation holes. After the sleeves 10 are inserted into the installation holes, the sleeves 10 and the first secondary beam 5 can also be welded respectively, and the sleeves 10 and the second secondary beam 6 can be welded to ensure the stability of the connection of the sleeves 10.

[0032] When the sleeve 10 is connected to the platform plate 23, two channel steels can also be welded on the platform plate 23. The two channel steels are parallel to each other. In the vertical direction, one channel steel corresponds to be above the first secondary beam 5, and the other channel steel corresponds to be above the second secondary beam 6. Two installation holes are provided on each channel steel. After the sleeve 10 is inserted into the installation hole, it is welded to the channel steel.

[0033] The sleeve 10 is used to connect with the operating frame 24 to ensure the stable installation of the operating frame 24 on the operating platform and ensure construction safety. Refer to Figure 6 When the sleeve 10 is connected to the operating frame 24, the bottoms of the four operating frame vertical rods 15 of the operating frame 24 are inserted into the corresponding four sleeves 10. Refer to Figure 5 The operating frame vertical rod 15 and the sleeve 10 are detachably connected by one or more pins 20. The distance between the pins 20 and the pins 20 is 200 mm, the distance between the pin 20 and the first secondary beam 5 is 200 m, and the distance between the pin 20 and the second secondary beam 6 is 200 mm. While having a certain supporting property, the pin 20 can also accurately position the operating frame 24. The construction formwork 16 is erected on the operating frame 24 to ensure the safety of construction operations.

[0034] Refer to Figure 7 One end of the I-beam 19 is fully welded to the steel plate 18 to form the support member 12. Refer to Figure 3 、 Figure 4 、 Figure 7, reserved holes 14 are respectively provided on the walls 13 on both sides of the wellhead of the elevator shaft. The reserved holes 14 on both sides of the wellhead are set at the same height on the wall 13 (on the same height of each side wall of the wellhead, the number of reserved holes is not less than two, and the specific number is determined according to the construction requirements). The support member 12 passes through the corresponding reserved hole 14 through the I-beam 19, and the I-beam 19 partially extends out of the wall 13 (the extended part ≥ 300 mm), and the steel plate 18 is attached to the outer side of the wall 13; the left and right sides of the frame structure are respectively supported above the I-beam 19 to ensure meeting the load-bearing requirements.

[0035] The I-beam 19 is connected to the main beam 1 through the connecting member 17, and the I-beam 19 is connected to the main beam 3 through the connecting member 17. Refer to Figure 8 , the connecting member 17 is composed of two U-shaped clips 21 and an iron block 22. When the I-beam 19 is connected to the main beam 1, the iron block 22 is located between the main beam 1 and the I-beam 19. Rectangular connecting holes with the same size are left on the flange plates on both sides of the webs of the main beam 1, the I-beam 19, and the iron block 22. The vertical part of each U-shaped clip 21 sequentially passes through the main beam 1, the iron block 22, and the I-beam 19. The U-shaped clip 21 forms a right angle with the I-beam 19, and the two are respectively located on both sides of the web of the I-beam 19, or the two vertical parts of each U-shaped clip 21 are respectively located on both sides of the web of the I-beam 19. The vertical part of the U-shaped clip 21 is detachably connected to the flange plate of the I-beam 19 through a nut, firmly fixing the frame structure and the support member. The connection method between the I-beam 19 and the main beam 3 is the same as the connection method between the I-beam 19 and the main beam 1.

[0036] Hook 11 is also provided on the platform plate 23. The hook 11 is semi-circular, and four hooks 11 are arranged in a rectangle. After the four hooks 11 pass through the platform plate 23, they are respectively welded above the secondary beam 1 5 and above the secondary beam 2 6. An operation frame 24 and a construction formwork 16 are erected above the operation platform, and specific construction operations are carried out on the construction formwork 16. When the operation height needs to be adjusted, a hook rope is used to connect the hook 11 on the platform plate 23, and then a crane or tower crane is used to lift the platform to a height slightly higher than the reserved hole 14. After inserting the support member 12 into the reserved hole 14, the operation platform is placed on the support member 12, and then the operation platform and the support member 12 are fixed using the connecting member 17.

[0037] As described above, it is only a detailed description of the specific implementation manner of the present utility model, rather than a limitation to the present utility model. Those skilled in the relevant technical fields shall include all kinds of substitutions, variations, and improvements made without departing from the principles and scopes of the present utility model within the protection scope of the present utility model.

Claims

1. An elevating construction operation platform for elevator shaft, characterized in that, Comprising: A frame structure, on which a platform plate (23) is provided. The frame structure is arranged in an elevator shaft, and a detachable support (12) is provided on the wall (13) of the elevator shaft. The frame structure is arranged on the support (12); the support (12) is composed of a steel plate (18) and an I-beam (19). The steel plate (18) is arranged at one end of the I-beam (19), the I-beam (19) passes through the wall (13), and the steel plate (18) is arranged on the outer side surface of the wall (13).

2. The liftable elevator shaft construction operation platform according to claim 1, wherein The frame structure is composed of a first main beam (1), a second main beam (2), a third main beam (3), a fourth main beam (4), a first secondary beam (5), a second secondary beam (6), a third secondary beam (7), a fourth secondary beam (8), and a fifth secondary beam (9); at least two reserved holes (14) are respectively provided on the walls (13) on both sides of the wellhead of the elevator shaft. The reserved holes (14) penetrate through the wall (13), and the support (12) is detachably arranged on the wall (13) through the reserved holes (14). The first main beam (1) is connected to the support (12), and the second main beam (2) is connected to the support (12).

3. The liftable elevator shaft construction operation platform according to claim 2, wherein The first main beam (1), the second main beam (2), the third main beam (3), and the fourth main beam (4) are connected end to end to form a rectangular frame. The first main beam (1) is parallel to the third main beam (3), and the second main beam (2) is parallel to the fourth main beam (4).

4. The liftable elevator shaft construction operation platform according to claim 2, characterized in that, The first secondary beam (5) is connected to the first main beam (1) and the third main beam (3), and the first secondary beam (5) is perpendicular to the first main beam (1); the second secondary beam (6) is connected to the first main beam (1) and the third main beam (3), and the second secondary beam (6) is perpendicular to the first main beam (1); the third secondary beam (7) is connected to the second main beam (2) and the first secondary beam (5), and the connection position is the middle of the second main beam (2). The third secondary beam (7) is perpendicular to the second main beam (2); the fourth secondary beam (8) is connected to the first secondary beam (5) and the second secondary beam (6); the fifth secondary beam (9) is connected to the first main beam (1) and the second secondary beam (6); the third secondary beam (7), the fourth secondary beam (8), and the fifth secondary beam (9) are coaxial.

5. The liftable elevator shaft construction operation platform according to claim 3, wherein The size of the platform plate (23) is the same as that of the rectangular frame, and the platform plate (23) is connected above the frame structure.

6. The liftable construction operation platform for elevator shafts according to claim 4, characterized in that, Cylindrical sleeves (10) are respectively provided above the first secondary beam (5) and the second secondary beam (6). The platform plate (23) is provided with through holes, and the first secondary beam (5) and the second secondary beam (6) are provided with mounting holes. The sleeves (10) pass through the through holes of the platform plate (23), and then are respectively vertically inserted into the mounting holes on the first secondary beam (5) and the second secondary beam (6). The connection parts of the sleeves (10) and the first secondary beam (5) are welded, and the connection parts of the sleeves (10) and the second secondary beam (6) are welded; the upper parts of the sleeves (10) are inserted into the operation rack vertical rods (15).

7. The liftable elevator shaft construction operation platform according to claim 2, characterized in that, The reserved holes (14) are rectangular through holes, and a certain gap is reserved between the inner side surface of the wall (13) and the edge of the frame structure.

8. The liftable construction operation platform for elevator shaft according to claim 2, wherein, Hook (11) is provided above each of secondary beam one (5) and secondary beam two (6). The hook (11) passes through the platform slab (23) and is connected to the secondary beam one (5), and the hook (11) also passes through the platform slab (23) and is connected to the secondary beam two (6).

9. The liftable elevator shaft construction operation platform according to claim 6, characterized in that, The casing (10) and the operation frame vertical rod (15) are fixedly connected by one or more pins (20). There is a spacing between the pins (20), a spacing between the pin (20) and the secondary beam one (5), and a spacing between the pin (20) and the secondary beam two (6).