Channel platform between construction elevator and entrance floor

By designing a channel platform for guiding components, moving components and limiting components between the construction elevator and the incoming floor, the existing construction methods are solved, and rapid installation and removal are achieved, construction efficiency is improved and costs are reduced.

CN223227021UActive Publication Date: 2025-08-15CHINA CONSTR SCI & IND CORP LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202421678982.5
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-07-15
Publication Date
2025-08-15
Estimated Expiration
2034-07-15

AI Technical Summary

Technical Problem

The existing construction methods lead to low construction efficiency through the establishment of scaffolding, and there are safety hazards during high-rise construction.

Method used

A channel platform between the construction elevator and the entry floor is designed, including guide components, mobile components and limiting components. The guide components are installed on the concrete floor. The moving components slide under the action of external force and are connected to the construction elevator. The limiting components are used for clamping to achieve rapid installation and removal.

Benefits of technology

It improves construction efficiency, reduces construction costs, and can quickly install the passage between the construction elevator and the floor when the floor edges are not unified.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN223227021U_ABST
    Figure CN223227021U_ABST
Patent Text Reader

Abstract

The channel platform between the construction elevator and the entering floor comprises a guiding assembly, a moving assembly and a limiting assembly, and the guiding assembly is arranged on a concrete floor slab and detachably connected with the concrete floor slab; the moving assembly is arranged on the guide assembly, the moving assembly slides on the guide assembly under the action of external force, and one end of the moving assembly is connected with a construction elevator; the limiting assembly is arranged on the guiding assembly and connected with the moving assembly in a clamped mode. By means of the structure, the channel between the construction elevator and the entering floor can be installed and used more conveniently, construction efficiency is further improved, and meanwhile the channel between the construction elevator and the entering floor can be installed more effectively and rapidly under the condition that side lines of all floors are not uniform.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of elevator passages, in particular to a passage platform between a construction elevator and an entrance floor. Background Art

[0002] During the construction of high-rise buildings, it is usually necessary to transport construction workers or construction materials to the construction site, and thus a construction elevator is required. However, there is a gap between the construction elevator and the floors, and a passage structure needs to be set up. Due to the diversity of current building structures, the edge lines of each floor are not uniform, and thus the distance between each floor and the construction elevator is inconsistent. The existing solution is to install a passage between the construction elevator and the entrance floor by setting up scaffolding, but this method is cumbersome to operate, thereby reducing construction efficiency. In addition, if the floors are high, setting up scaffolding can easily pose a threat to the life safety of construction workers. Utility Model Content

[0003] Therefore, the technical problem to be solved by the present invention is to overcome the defect in the prior art that the existing construction method is to set up a scaffold, thereby reducing the construction efficiency.

[0004] To this end, the utility model provides a passage platform between a construction elevator and an access floor, comprising:

[0005] A guide assembly is provided on the concrete floor slab and is detachably connected to the concrete floor slab;

[0006] A moving assembly is provided on the guide assembly, and under the action of an external force, the moving assembly slides on the guide assembly, and one end of the moving assembly is connected to the construction elevator;

[0007] The limiting assembly is arranged on the guide assembly, and the limiting assembly is engaged with the moving assembly.

[0008] Optionally, the guide assembly is composed of two rails, the rails are provided with grooves, and the grooves are suitable for installing the moving assembly.

[0009] Optionally, a head plate is provided at one end of the track away from the construction elevator, and the head plate is suitable for restricting the moving component.

[0010] Optionally, the track gradually rises along the direction in which the moving component extends out of the concrete floor.

[0011] Optionally, the moving component includes:

[0012] a horizontal channel, arranged on the track;

[0013] an inclined channel connected to the horizontal channel;

[0014] a support member, one end of which is connected to the horizontal channel and the inclined channel respectively;

[0015] A pulley is arranged in the groove, and the pulley is connected to the other end of the support member.

[0016] Optionally, a hook is provided at one end of the horizontal channel close to the construction elevator, and the hook is suitable for being engaged with the construction elevator.

[0017] Optionally, the limiting component includes:

[0018] A rotating rod is mounted on the track, and the rotating rod rotates under the action of an external force;

[0019] A connecting plate, arranged on the rotating rod;

[0020] A spring, one end of which is connected to the connecting plate, and the other end of which is connected to the bottom of the groove.

[0021] Optionally, the access platform between the construction elevator and the floor further includes:

[0022] A driving member is connected to the hook and ring, and drives the moving assembly to slide. Optionally, a protective plate is provided at the edge of the concrete floor slab to prevent construction workers from falling.

[0023] Optionally, a protective door is provided on the protective plate, and the protective door is suitable for construction workers to enter and exit.

[0024] The technical solution of this utility model has the following advantages:

[0025] 1. The utility model provides a passage platform between a construction elevator and an entrance floor, comprising a guide assembly, a moving assembly and a limit assembly, wherein the guide assembly is arranged on a concrete floor slab and is detachably connected to the concrete floor slab; the moving assembly is arranged on the guide assembly, and under the action of an external force, the moving assembly slides on the guide assembly, and one end of the moving assembly is connected to the construction elevator; the limit assembly is arranged on the guide assembly, and the limit assembly is engaged with the moving assembly.

[0026] The existing approach is to install the passage between the construction elevator and the floor entrance by erecting scaffolding. However, this approach is cumbersome and reduces construction efficiency. In addition, if the floor is high, erecting scaffolding can easily pose a threat to the safety of construction workers. In the embodiment of the utility model, by placing the mobile assembly on the concrete floor and then connecting the mobile assembly to the construction elevator through external force, the installation of the passage between the construction elevator and the floor entrance can be made more convenient, thereby improving construction efficiency. At the same time, even if the floor boundaries are not uniform, the passage between the construction elevator and the floor entrance can be installed more efficiently and quickly.

[0027] 2. The utility model provides a passage platform between a construction elevator and an entrance floor. The guide assembly is detachably connected to the concrete floor slab. Through the detachable setting, the passage platform can be reused, thereby reducing construction costs. BRIEF DESCRIPTION OF THE DRAWINGS

[0028] In order to more clearly illustrate the specific implementation methods of the utility model or the technical solutions in the prior art, the drawings required for use in the specific implementation methods or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are some implementation methods of the utility model. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying any creative work.

[0029] Figure 1 It is a schematic diagram of the overall three-dimensional structure of the utility model;

[0030] Figure 2 This is a front view structural diagram of the utility model;

[0031] Figure 3 This is a schematic diagram of the structure of the mobile component of the utility model;

[0032] Figure 4 This is a schematic diagram of the guide assembly structure of the utility model;

[0033] Figure 5 This is a schematic diagram of the structure of the limit assembly of the utility model.

[0034] Description of the accompanying drawings in the embodiments:

[0035] 1. Guide assembly; 2. Moving assembly; 3. Limit assembly; 100. Concrete floor; 200. Construction elevator; 300. Protective plate; 400. Protective door;

[0036] 11. Track; 12. Groove; 13. Head plate;

[0037] 21. Horizontal channel; 22. Inclined channel; 23. Support member; 24. Pulley; 25. Hook;

[0038] 31. Rotating rod; 32. Connecting plate; 33. Spring. DETAILED DESCRIPTION

[0039] The following is a clear and complete description of the technical solution of the present invention in conjunction with the accompanying drawings. Obviously, the embodiments described are only some of the embodiments of the present invention, not all of them. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without making any creative efforts are within the scope of protection of the present invention.

[0040] In the description of this utility model, it should be noted that the terms "center," "upper," "lower," "left," "right," "vertical," "horizontal," "inner," and "outer," etc., indicating positions or relationships, are based on the positions or relationships shown in the accompanying drawings and are intended solely to facilitate the description of this utility model and simplify the description. They do not indicate or imply that the devices or components referred to must have a specific orientation, be constructed, or operate in a specific orientation. Therefore, they should not be construed as limitations on this utility model. Furthermore, the terms "first," "second," and "third" are used for descriptive purposes only and should not be construed as indicating or implying relative importance.

[0041] In the description of this utility model, it should be noted that, unless otherwise expressly specified or limited, the terms "mounted," "connected," and "connected" should be understood in a broad sense. For example, they can refer to fixed connections, detachable connections, or integral connections; mechanical connections, electrical connections; direct connections, indirect connections through an intermediate medium, and internal communication between two components. Those skilled in the art will understand the specific meanings of the above terms in this utility model based on the specific circumstances.

[0042] In addition, the technical features involved in the different embodiments of the present invention described below can be combined with each other as long as they do not conflict with each other.

[0043] Example

[0044] like Figures 1 to 5As shown, this embodiment provides a passage platform between a construction elevator and an entrance floor, including a guide assembly 1, a moving assembly 2 and a limiting assembly 3. The guide assembly 1 is arranged on a concrete floor 100 and is detachably connected to the concrete floor 100; the moving assembly 2 is arranged on the guide assembly 1, and under the action of external force, the moving assembly 2 slides on the guide assembly 1, and one end of the moving assembly 2 is connected to the construction elevator 200; the limiting assembly 3 is arranged on the guide assembly 1, and the limiting assembly 3 is engaged with the moving assembly 2.

[0045] In an embodiment of the present utility model, the guide assembly 1 is first installed on the concrete floor 100, and then the movable assembly 2 is placed on the guide assembly 1. When the construction elevator 200 rises to the corresponding floor, the movable assembly 2 is pulled onto the construction elevator 200 by external force, and then the movable assembly 2 is connected to the construction elevator 200 to complete the installation of the passage platform between the construction elevator 200 and the entrance floor.

[0046] The existing approach is to install the passage between the construction elevator and the floor entrance by erecting scaffolding. However, this approach is cumbersome and reduces construction efficiency. In addition, if the floor is high, erecting scaffolding can easily pose a threat to the safety of construction workers. In the embodiment of the present invention, by placing the mobile assembly 2 on the concrete floor 100 and then connecting the mobile assembly 2 to the construction elevator 200 through external force, the installation of the passage between the construction elevator and the floor entrance can be made more convenient, thereby improving construction efficiency. At the same time, even if the floor boundaries are not uniform, the passage between the construction elevator and the floor entrance can be installed more efficiently and quickly.

[0047] In an embodiment of the present invention, the guide assembly 1 and the concrete floor 100 are connected by bolts. Of course, the guide assembly 1 and the concrete floor 100 can also be connected by other detachable methods. This embodiment does not limit the connection method between the guide assembly 1 and the concrete floor 100. Technical personnel in this field can change the connection method between the guide assembly 1 and the concrete floor 100 according to actual conditions, as long as the same technical effect can be achieved.

[0048] Furthermore, if Figure 4As shown, the guide assembly 1 is composed of two rails 11, each of which is provided with a groove 12 suitable for mounting the moving assembly 2. In the embodiment of the present utility model, the groove 12 is configured to be U-shaped, and the rails 11 are configured to be steel beams, that is, the rails 11 are configured to be U-shaped steel beams. Of course, the rails 11 may also be configured in other forms. This embodiment does not limit the configuration of the rails 11. Those skilled in the art may change the configuration of the rails 11 according to actual conditions, as long as the same technical effect can be achieved.

[0049] Furthermore, a head plate 13 is provided at one end of the track 11 away from the construction elevator 200. The head plate 13 is adapted to restrict the moving assembly 2. By placing the head plate 13 at the end away from the construction elevator 200, the moving assembly 2 can be prevented from sliding off the track 11 during the fallback process, thereby affecting the installation and use of the access platform.

[0050] Furthermore, the track 11 gradually rises along the direction in which the moving assembly 2 extends from the concrete floor 100. By setting the track 11 in an inclined shape, the moving assembly 2 can naturally return to its initial position under the action of its own gravity, thereby making the access platform more convenient and quick to use.

[0051] Further, if Figure 3 As shown, the moving assembly 2 includes a horizontal channel 21, an inclined channel 22, a support member 23, and a pulley 24. The horizontal channel 21 is provided on the track 11; the inclined channel 22 is connected to the horizontal channel 21; one end of the support member 23 is connected to the horizontal channel 21 and the inclined channel 22 respectively; the pulley 24 is provided in the groove 12, and the pulley 24 is connected to the other end of the support member 23. In the embodiment of the present invention, the horizontal channel 21 and the inclined channel 22 are welded by a steel keel and a steel plate. At the same time, four support members 23 are provided at the lower end of the horizontal channel 21, and two support members 23 are provided at the lower end of the inclined channel 22. Of course, this embodiment does not limit the number of support members 23 provided at the lower ends of the horizontal channel 21 and the inclined channel 22. Those skilled in the art can change the number of support members 23 provided at the lower ends of the horizontal channel 21 and the inclined channel 22 according to actual conditions, as long as the same technical effect can be achieved.

[0052] Furthermore, a hook 25 is provided at one end of the horizontal passage 21, near the construction elevator 200, and is adapted to engage with the construction elevator 200. When the construction elevator 200 ascends to the corresponding floor, the hook 25 is pulled by an external force, connecting it to the construction elevator 200, completing the passage installation and enabling construction workers and materials to enter the corresponding floor for construction work.

[0053] Further, if Figure 5 As shown, the limiting assembly 3 includes a rotating rod 31, a connecting plate 32, and a spring 33. The rotating rod 31 is mounted on the track 11 and rotates under the action of an external force. The connecting plate 32 is disposed on the rotating rod 31. One end of the spring 33 is connected to the connecting plate 32, and the other end is connected to the bottom of the groove 12. When the moving assembly 2 needs to be connected to the construction elevator 200, the hook 25 is pulled to move the horizontal channel 21 and the inclined channel 22 until the pulley 24 at the lower end of the inclined channel 22 passes over the connecting plate 32. The connecting plate 32 engages the pulley 24 at the lower end of the inclined channel 22 through the elastic force of the spring 33, preventing the moving assembly 2 from falling back. When construction is completed and the track is no longer needed, the rotating rod 31 is rotated to make the connecting plate 32 flush with the bottom of the groove 12. The moving assembly 2 then falls back to its initial position under its own weight.

[0054] Furthermore, the passage platform between the construction elevator and the entrance floor also includes a driving member, which is connected to the hook ring 25 and drives the moving assembly 2 to slide. In the embodiment of the present invention, the driving member can be configured as a hook rod, which is composed of a long rod and a hook. Of course, the driving member can also be configured as other hook-shaped rods. This embodiment does not limit the configuration type of the driving member. Those skilled in the art can change the configuration type of the driving member according to actual conditions, as long as the same technical effect can be achieved.

[0055] Further, if Figure 1 and Figure 2 As shown, a protective plate 300 is installed at the edge of the concrete floor 100 to prevent construction workers from falling. A protective door 400 is installed on the protective plate 300 to allow construction workers to enter and exit. A gap is provided between the bottom of the protective door 400 and the concrete floor 100, which is suitable for the mobile assembly 2 to pass through.

[0056] The specific working process of the construction elevator provided by the utility model and the passage platform between the floors is as follows:

[0057] First, the track 11 is fixed to the concrete floor 100 by bolts, and then the moving assembly 2 is installed on the track 11. When the construction elevator 200 rises to the corresponding floor, the construction personnel connect the hook 25 through the driving member, and then pull the hook 25 to drive the horizontal channel 21 and the inclined channel 22 to move until the pulley 24 at the lower end of the inclined channel 22 passes over the connecting plate 32, and the connecting plate 32 restricts the pulley 24. At the same time, the hook 25 is connected to the construction elevator 200, and then the protective door 400 is opened. The construction personnel and construction materials are transported to the floor to carry out construction on the building, completing the installation and use of the channel. When the construction is completed and the channel needs to be dismantled, the rotating rod 31 is rotated so that the connecting plate 32 is flush with the bottom of the groove 12. The moving assembly 2 returns to its original position under the action of its own gravity, and then the track 11 is removed to complete the dismantling of the channel.

[0058] Obviously, the above embodiments are merely examples for clarity of explanation and are not intended to limit the implementation methods. Those skilled in the art will readily appreciate that other variations or modifications based on the above descriptions are possible. It is not necessary and impossible to enumerate all implementation methods here. Obvious variations or modifications arising therefrom remain within the scope of protection of the present invention.

Claims

1. A passage platform between a construction elevator and an entrance floor, characterized in that: include: A guide assembly (1) is arranged on a concrete floor slab (100) and is detachably connected to the concrete floor slab (100); A moving assembly (2) is arranged on the guide assembly (1), and under the action of an external force, the moving assembly (2) slides on the guide assembly (1), and one end of the moving assembly (2) is connected to the construction elevator (200); A limiting assembly (3) is arranged on the guide assembly (1), and the limiting assembly (3) is engaged with the moving assembly (2); The guide assembly (1) is composed of two rails (11), the rails (11) are provided with grooves (12), and the grooves (12) are suitable for installing the moving assembly (2); The mobile component (2) comprises: A horizontal channel (21) is provided on the track (11); an inclined channel (22) connected to the horizontal channel (21); A support member (23), one end of which is connected to the horizontal channel (21) and the inclined channel (22); A pulley (24) is arranged in the groove (12), and the pulley (24) is connected to the other end of the support member (23).

2. The passage platform between the construction elevator and the floor according to claim 1 is characterized in that: A head plate (13) is provided at one end of the track (11) away from the construction elevator (200), and the head plate (13) is suitable for limiting the moving component (2).

3. The passage platform between the construction elevator and the floor according to claim 2 is characterized in that: Along the direction in which the moving component (2) extends out of the concrete floor (100), the track (11) gradually rises.

4. The passage platform between the construction elevator and the floor according to claim 1 is characterized in that: A hook ring (25) is provided at one end of the horizontal channel (21) close to the construction elevator (200), and the hook ring (25) is suitable for being engaged with the construction elevator (200).

5. The passage platform between the construction elevator and the floor according to any one of claims 1 to 4, characterized in that: The limiting component (3) comprises: A rotating rod (31) is mounted on the track (11), and the rotating rod (31) rotates under the action of an external force; A connecting plate (32) is provided on the rotating rod (31); A spring (33), one end of the spring (33) is connected to the connecting plate (32), and the other end is connected to the bottom of the groove (12).

6. The passage platform between the construction elevator and the floor according to claim 4 is characterized in that: Also includes: A driving member is connected to the hook ring (25) and drives the moving assembly (2) to slide.

7. The passage platform between the construction elevator and the floor according to claim 5, characterized in that: A protective plate (300) is provided at the edge of the concrete floor slab (100), and the protective plate (300) prevents construction workers from falling.

8. The passage platform between the construction elevator and the floor according to claim 7 is characterized in that: A protective door (400) is provided on the protective plate (300), and the protective door (400) is suitable for construction workers to enter and exit.