Steel pipe pile lifting device
By setting through holes and rope components on the steel pipe piles, the problems of hanging ear interference and deformation are solved, and efficient and safe steel pipe pile lifting and pile cutting operations are achieved.
Patent Information
- Application Number
- CN202422793002.2
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-11-15
- Publication Date
- 2025-08-22
- Estimated Expiration
- 2034-11-15
AI Technical Summary
During the lifting of steel pipe piles, the lifting ears often interfere with the outer hoop equipment, and the convex lifting ears are easily affected by collision and deformation during transportation, increasing the risk of lifting.
A steel pipe pile lifting device is adopted. By setting a plurality of through holes on the steel pipe and using the first and second rope components, the installation of hanging lugs on the outside of the steel pipe is avoided. The different lifting speeds or synchronous lifting methods of the rope components are used to make the steel pipe turn from horizontal to vertical, and the lifting hook is hung through the through hole when cutting piles.
It effectively avoids interference and collision deformation problems between the hoisting lugs and outer hoist equipment, improves the lifting efficiency and the service life of the hoisting rope, and is suitable for lifting and cutting steel pipe piles.
Smart Images

Figure CN223254699U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of steel pipe pile lifting construction, in particular to a steel pipe pile lifting device. Background Art
[0002] At present, during the construction of high-pile docks, steel pipe piles need to be constructed. That is, the two ends of the steel pipe placed horizontally on the ground are connected to the steel wire rope of the hoist respectively, and then the hoist is lifted by a crane to make the steel pipe pile vertical. After that, it is lifted to the construction site and placed vertically on the piling equipment (pile driver or pile driving ship), and the piling equipment clamps it from the outside and impacts it downward.
[0003] The patent (publication number: CN113336073A) discloses a method for lifting offshore steel pipe piles. The method includes the following steps: during the actual lifting process, the offshore steel pipe pile lifting assembly can be first installed on the steel pipe so that the side wall of the steel pipe is inserted into the receiving groove; then the auxiliary lifting vessel is controlled to apply a lifting force to the offshore steel pipe pile lifting assembly through the second lifting part, so that the offshore steel pipe pile lifting assembly and the steel pipe are kept stable; then the main lifting vessel is controlled to lift the main lifting lug in the middle of the steel pipe through the first lifting part, and at the same time, the auxiliary lifting vessel is controlled to make the offshore steel pipe pile lifting assembly and the main lifting lug rise synchronously; then, after the steel pipe is lifted to the specified position, the main lifting vessel is controlled to drive the main lifting vessel to lift the steel pipe pile. The lifting lug rises, so that the offshore steel pipe pile lifting assembly is separated from the steel pipe; finally, after the main lifting lug rises until the steel pipe pile is vertical, the first lifting part is removed from the main lifting lug; during the lifting process, the offshore steel pipe pile lifting assembly can apply auxiliary lifting force to the steel pipe through the accommodating groove, so that the steel pipe is stably moved during the lifting process. After the steel pipe is lifted and placed in the specified position, the main crane ship is controlled to drive the main lifting lug to rise. At this time, the steel pipe is tilted, and the offshore steel pipe pile lifting assembly slides out from the lower end of the steel pipe pile under the action of gravity, so that the offshore steel pipe pile lifting assembly is separated from the steel pipe. Compared with the existing lifting method, there is no need to manually cut and remove the lifting lugs and lifting ropes separately, which effectively increases the lifting efficiency.
[0004] In the above process, since the piling equipment clamps the steel pipe piles, the lifting ears often interfere with the outer clamp equipment. Moreover, during transportation, the lifting ears on the outer side of the steel pipe sometimes collide with adjacent steel pipe piles or lifting ears, causing the lifting ears to deform, reducing the bearing capacity, and thus increasing the lifting risk. Utility Model Content
[0005] The purpose of the utility model is to overcome the problems existing in the background technology that the lifting lugs often interfere with the outer hoop equipment during the lifting process of the steel pipe pile, and the protruding lifting lugs are easily deformed by collision during the transportation of the steel pipe pile, and to provide a steel pipe pile lifting device.
[0006] In a first aspect, the utility model provides a steel pipe pile lifting device, comprising a steel pipe to be lifted, a first lifting rope assembly and a second lifting rope assembly, wherein:
[0007] The first lifting rope assembly includes a first lifting rope and a second lifting rope, wherein the upper ends of the first lifting rope and the second lifting rope are connected;
[0008] The second lifting rope assembly includes a third lifting rope, a fourth lifting rope and a fifth lifting rope, and the upper end of the third lifting rope is connected to the fourth lifting rope and the fifth lifting rope respectively;
[0009] At least three through holes are provided on the steel pipe to be hung, wherein the three through holes are a first through hole, a second through hole and a third through hole, the third lifting rope extends into the first through hole, the fourth lifting rope extends into the second through hole, the fifth lifting rope extends into the third through hole, the part of the third lifting rope extending into the first through hole is connected to the fourth lifting rope and the fifth lifting rope, and the first through hole, the second through hole and the third through hole are all located on the same side of the center of gravity of the steel pipe to be hung.
[0010] The steel pipe pile lifting device described in the present application is characterized in that, during construction, the third lifting rope is first extended into the first through hole, the fourth lifting rope is extended into the second through hole, and the fifth lifting rope is extended into the third through hole. Then, the part of the third lifting rope extended into the first through hole is connected to the fourth lifting rope and the fifth lifting rope, and the first lifting rope assembly is connected to the part of the steel pipe to be lifted which is located at a position where the center of gravity is far away from the first through hole. Then, the first lifting rope assembly and the second lifting rope assembly are used to change the steel pipe to be lifted from a horizontal state to a vertical state by first lifting the second lifting rope assembly and then lifting the first lifting rope assembly, or by lifting the second lifting rope assembly faster than the first lifting rope assembly, so that the steel pipe to be lifted can be placed on the piling equipment.
[0011] During the above process, no lifting lugs were set on the outside of the steel pipe to be lifted, thereby fundamentally avoiding the interference between the lifting lugs and the outer clamp equipment, and the problem of the lifting lugs being easily deformed by collision.
[0012] Preferably, it also includes a steel pipe to be hung, the first lifting rope assembly and the second lifting rope assembly are both connected to the steel pipe to be hung, and the center of gravity of the steel pipe to be hung is located between the first lifting rope assembly and the second lifting rope assembly.
[0013] Preferably, the first lifting rope assembly is connected to one end of the steel pipe to be lifted, and the second lifting rope assembly is connected to the other end of the steel pipe to be lifted.
[0014] Preferably, the first lifting rope and the second lifting rope are both wound around the steel pipe to be lifted, and the winding directions of the first lifting rope and the second lifting rope are opposite.
[0015] Preferably, all the through holes are arranged along the circumference of the steel pipe to be hung.
[0016] Preferably, the free end of the third suspension rope is connected to a first suspension hook, the free end of the fourth suspension rope is connected to a second suspension hook, and the free end of the fifth suspension rope is connected to a third suspension hook, wherein:
[0017] The first hook extends into the first through hole, the second hook extends into the second through hole, and the third hook extends into the third through hole;
[0018] The first hook, the second hook and the third hook are connected to each other.
[0019] The steel pipe pile lifting device described in the present application is characterized in that, during construction, the third lifting rope is first extended into the first through hole, the fourth lifting rope is extended into the second through hole, and the fifth lifting rope is extended into the third through hole. Then, the first hook, the second hook and the third hook are hung to each other in the steel pipe to be lifted, and the first lifting rope assembly is connected to the part of the steel pipe to be lifted that is located at a position where the center of gravity is away from the first through hole. Then, the first lifting rope assembly and the second lifting rope assembly are used to change the steel pipe to be lifted from a horizontal state to a vertical state by first lifting the second lifting rope assembly and then lifting the first lifting rope assembly, or by lifting the second lifting rope assembly faster than the first lifting rope assembly, so that the steel pipe to be lifted can be placed on the piling equipment.
[0020] Moreover, in the later pile cutting process, the third lifting rope, the fourth lifting rope and the fifth lifting rope are pulled from the bottom of the steel pipe to be lifted, and the first lifting hook is reversely hung at the first through hole, the second lifting hook is reversely hung at the second through hole, and the third lifting hook is reversely hung at the third through hole, so that the construction personnel can pull out the corresponding lifting hooks through the first through hole, the second through hole and the third through hole to lift the cut part of the steel pipe to be lifted, so that the steel pipe pile lifting device described in the present application can not only be used for the lifting operation of the steel pipe to be lifted, but also can take into account the lifting and moving operation of the cut part when cutting the pile, thereby making the second lifting rope assembly described in the present application more universal.
[0021] Preferably, the first through hole and the third through hole are provided correspondingly, so that during the process of suspending the steel pipe, friction between the portions of the third and fifth suspension ropes located outside the steel pipe and the outer wall of the steel pipe can be reduced or avoided, thereby effectively extending the service life of the third and fifth suspension ropes.
[0022] Preferably, the first through holes, the second through holes and the third through holes are evenly distributed along the circumference of the steel pipe to be hung.
[0023] Preferably, the first lifting rope assembly further includes a first main rope, and the first lifting rope and the second lifting rope are both connected to the first main rope.
[0024] Preferably, the second lifting rope assembly further includes a second main rope, and the third lifting rope, the fourth lifting rope and the fifth lifting rope are all connected to the second main rope.
[0025] Compared with the prior art, the present invention has the following beneficial effects:
[0026] The steel pipe pile lifting device described in the present application is configured such that during construction, the third lifting rope is first inserted into the first through hole, the fourth lifting rope is inserted into the second through hole, and the fifth lifting rope is inserted into the third through hole. The portion of the third lifting rope inserted into the first through hole is then connected to the fourth and fifth lifting ropes. The first lifting rope assembly is then connected to the portion of the steel pipe to be lifted, where the center of gravity is away from the first through hole. The first and second lifting rope assemblies are then used to lift the second lifting rope assembly first and then the first lifting rope assembly, or the lifting speed of the second lifting rope assembly is faster than that of the first lifting rope assembly, so that the steel pipe to be lifted can be placed on the piling equipment. In the above process, no lifting lugs are set on the outside of the steel pipe to be lifted, thereby fundamentally avoiding interference between the lifting lugs and the outer hoop equipment, and the problem of the lifting lugs being easily deformed by collision. BRIEF DESCRIPTION OF THE DRAWINGS
[0027] Figure 1 This is a three-dimensional schematic diagram of the structure of a steel pipe pile lifting device in this application (one angle).
[0028] Figure 2 This is a three-dimensional schematic diagram of the structure of a steel pipe pile lifting device in this application (from another angle).
[0029] Figure 3 This is a schematic diagram of the main structure of a steel pipe pile lifting device of the present application.
[0030] Figure 4 This is a schematic diagram of the mechanism of the second hanging rope assembly of the present application.
[0031] Figure 5 This is a schematic diagram of the hoisting of the second hoisting rope assembly of the present application when cutting piles.
[0032] Markings in the figure: 1-first lifting rope assembly, 10-first main rope, 11-first lifting rope, 12-second lifting rope, 2-second lifting rope assembly, 20-second main rope, 21-third lifting rope, 22-fourth lifting rope, 23-fifth lifting rope, 24-first hook, 25-second hook, 26-third hook, 3-steel pipe to be lifted, 31-first through hole, 32-second through hole, 33-third through hole. DETAILED DESCRIPTION
[0033] The present invention will be further described in detail below with reference to specific embodiments. However, this should not be construed as limiting the scope of the present invention to the following embodiments. All technologies implemented based on the present invention fall within the scope of the present invention.
[0034] Unless otherwise specified, in the description of the specific embodiments of the present invention, the terms indicating orientation or positional relationships, such as "upper," "lower," "left," "right," "center," "inside," and "outside," are based on the orientation or positional relationships shown in the accompanying drawings, or are the orientation or positional relationships in which the product / device / apparatus of the present invention is typically placed when in use. These terms indicating orientation or positional relationships are merely for the purpose of facilitating the description of the present invention or simplifying the description of the specific embodiments to facilitate a quick understanding of the solutions by technicians. They do not indicate or imply that a particular device / component / element must have a specific orientation or be constructed and operated in a specific positional relationship, and therefore should not be construed as limiting the present invention.
[0035] In addition, if the terms "horizontal", "vertical", "overhanging", "parallel" and the like appear, it does not mean that the corresponding devices / components / elements are required to be absolutely horizontal or vertical or overhanging or parallel, but may be slightly tilted or have deviations. For example, "horizontal" only means that its direction is more horizontal relative to "vertical", and does not mean that the structure must be completely horizontal, but may be slightly tilted. Alternatively, it can be simply understood that the corresponding devices / components / elements are set in directions such as "horizontal", "vertical", "overhanging", and "parallel", and can have an error / deviation of ±10% relative to the corresponding direction setting, more preferably an error / deviation within ±8%, more preferably an error / deviation within ±6%, more preferably an error / deviation within ±5%, and more preferably an error / deviation within ±4%. As long as the corresponding device / component / element is within the error / deviation range, it can still achieve its role in the solution of the present utility model.
[0036] In addition, the expressions "first", "second", "third", etc. that appear in the terms are merely descriptions used to distinguish the same or similar components and should not be understood as emphasizing or implying the relative importance of specific components.
[0037] In addition, in the description of the embodiments of the present invention, "several", "a plurality", and "a number" represent at least 2. It can be any number such as 2, 3, 4, 5, 6, 7, 8, 9, and even more than 9.
[0038] Furthermore, in the description of the technical solutions of this utility model, unless otherwise expressly specified / defined / restricted, the terms "disposed," "installed," "connected," "connected," "provided with," "laid," and "arranged" should be understood in a broad sense. For example, they may refer to fixed connections, detachable connections, or integral connections. They may be welding, riveting, bolting, threading, or other commonly used connection methods in the art. Such connections may be mechanical, electrical, or communication connections; they may be direct connections, indirect connections through an intermediate medium, or internal connections between two components.
[0039] Example 1
[0040] like Figures 1-4 As shown, this embodiment provides a steel pipe pile lifting device, including a steel pipe 3 to be lifted, wherein the steel pipe 3 to be lifted is provided with at least three through holes, wherein the three through holes are a first through hole 31 , a second through hole 32 and a third through hole 33 .
[0041] In a preferred embodiment, this embodiment provides a steel pipe pile lifting device including a steel pipe 3 to be lifted, and also including a first lifting rope assembly 1, the first lifting rope assembly 1 including a first lifting rope 11 and a second lifting rope 12, the upper ends of the first lifting rope 11 and the second lifting rope 12 are connected.
[0042] In a preferred embodiment, this embodiment provides a steel pipe pile lifting device which also includes a second lifting rope assembly 2, wherein the second lifting rope assembly 2 includes a third lifting rope 21, a fourth lifting rope 22 and a fifth lifting rope 23, and the upper end of the third lifting rope 21 is connected to the fourth lifting rope 22 and the fifth lifting rope 23 respectively.
[0043] In a further preferred embodiment, the third lifting rope 21 extends into the first through hole 31, the fourth lifting rope 22 extends into the second through hole 32, and the fifth lifting rope 23 extends into the third through hole 33. The part of the third lifting rope 21 extending into the first through hole 31 is connected to the fourth lifting rope 22 and the fifth lifting rope 23. The first through hole 31, the second through hole 32 and the third through hole 33 are all located on the same side of the center of gravity of the steel pipe 3 to be lifted.
[0044] The steel pipe pile lifting device described in this application is configured such that, during construction, the third lifting rope 21 is first inserted into the first through hole 31, the fourth lifting rope 22 is inserted into the second through hole 32, and the fifth lifting rope 23 is inserted into the third through hole 33. The portion of the third lifting rope 21 inserted into the first through hole 31 is then connected to the fourth and fifth lifting ropes 22 and 23. Furthermore, the first lifting rope assembly 1 is connected to the portion of the steel pipe 3 to be lifted, where its center of gravity is away from the first through hole 31. The first and second lifting rope assemblies 1 and 2 are then used to lift the steel pipe 3 from a horizontal position to a vertical position, either by lifting the second lifting rope assembly 2 first and then the first lifting rope assembly 1, or by lifting the second lifting rope assembly 2 faster than the first lifting rope assembly 1, so that the steel pipe 3 to be lifted can be placed on the piling equipment. During the above process, no lifting lugs are provided on the outside of the steel pipe 3 to be lifted, thereby fundamentally avoiding interference between the lifting lugs and the outer hoisting equipment, as well as the problem of the lifting lugs being easily deformed by collision.
[0045] In a preferred embodiment, the first lifting rope assembly 1 and the second lifting rope assembly 2 are both connected to the steel pipe 3 to be lifted, and the center of gravity of the steel pipe 3 to be lifted is located between the first lifting rope assembly 1 and the second lifting rope assembly 2.
[0046] In a preferred embodiment, the first lifting rope assembly 1 is connected to one end of the steel pipe 3 to be lifted, and the second lifting rope assembly 2 is connected to the other end of the steel pipe 3 to be lifted.
[0047] In a preferred embodiment, the first lifting rope 11 and the second lifting rope 12 are both wound around the steel pipe 3 to be hung, and the winding directions of the first lifting rope 11 and the second lifting rope 12 are opposite.
[0048] In a preferred embodiment, all the through holes are arranged along the circumference of the steel pipe 3 to be suspended.
[0049] Preferably, the first through hole 31 and the third through hole 33 are provided correspondingly, so that during the process of suspending the steel pipe 3, friction between the portions of the third suspension rope 21 and the fifth suspension rope 23 located outside the steel pipe 3 and the outer wall of the steel pipe 3 can be reduced or avoided, thereby effectively extending the service life of the third suspension rope 21 and the fifth suspension rope 23.
[0050] In a preferred embodiment, the first through holes 31 , the second through holes 32 and the third through holes 33 are evenly distributed along the circumference of the steel pipe 3 to be suspended.
[0051] In a preferred embodiment, the first lifting rope assembly 1 further includes a first main rope 10 , and the first lifting rope 11 and the second lifting rope 12 are both connected to the first main rope 10 .
[0052] In a preferred embodiment, the second suspension rope assembly 2 further includes a second main rope 20 , and the third suspension rope 21 , the fourth suspension rope 22 and the fifth suspension rope 23 are all connected to the second main rope 20 .
[0053] Example 2
[0054] like Figures 1-4 As shown, this embodiment provides a steel pipe pile lifting device, which is different from Example 1 in that: the free end of the third lifting rope 21 is connected to the first hook 24, the free end of the fourth lifting rope 22 is connected to the second hook 25, and the free end of the fifth lifting rope 23 is connected to the third hook 26, wherein the first hook 24 extends into the first through hole 31, the second hook 25 extends into the second through hole 32, and the third hook 26 extends into the third through hole 33; the first hook 24, the second hook 25 and the third hook 26 are connected to each other.
[0055] The steel pipe pile lifting device described in this embodiment, during construction, first extends the third lifting rope 21 into the first through hole 31, the fourth lifting rope 22 into the second through hole 32, and the fifth lifting rope 23 into the third through hole 33, then the first lifting hook 24, the second lifting hook 25 and the third lifting hook 26 are hung with each other in the steel pipe 3 to be lifted, and the first lifting rope assembly 1 is connected to the part of the steel pipe 3 to be lifted that is located at the center of gravity away from the first through hole 31, and then the first lifting rope assembly 1 and the second lifting rope assembly 2 are used to change the steel pipe 3 to be lifted from a horizontal state to a vertical state by first lifting the second lifting rope assembly 2 and then lifting the first lifting rope assembly 1, or by lifting the second lifting rope assembly 2 faster than the first lifting rope assembly 1, so that the steel pipe 3 to be lifted can be placed on the piling equipment.
[0056] like Figure 5 As shown, in the later pile cutting process, the third lifting rope 21, the fourth lifting rope 22 and the fifth lifting rope 23 are lowered from the steel pipe 3 to be lifted, and the first lifting hook 24 is reversely hung at the first through hole 31, the second lifting hook 25 is reversely hung at the second through hole 32, and the third lifting hook 26 is reversely hung at the third through hole 33, so that the construction personnel can pull out the corresponding lifting hooks through the first through hole 31, the second through hole 32 and the third through hole 33 to lift the cut part of the steel pipe 3 to be lifted, so that the steel pipe pile lifting device described in the present application can not only be used for the lifting operation of the steel pipe 3 to be lifted, but also can take into account the lifting and moving operation of the cut part when cutting the pile, thereby making the second lifting rope assembly 2 of the present application more universal.
[0057] The above description is only a preferred embodiment of the present invention and is not intended to limit the present invention. Any modifications, equivalent replacements and improvements made within the spirit and principles of the present invention should be included in the scope of protection of the present invention.
Claims
1. A steel pipe pile lifting device, characterized in that: It comprises a steel pipe to be hoisted (3), a first hoisting rope assembly (1) and a second hoisting rope assembly (2), wherein: The first lifting rope assembly (1) comprises a first lifting rope (11) and a second lifting rope (12), wherein the upper ends of the first lifting rope (11) and the second lifting rope (12) are connected; The second lifting rope assembly (2) comprises a third lifting rope (21), a fourth lifting rope (22) and a fifth lifting rope (23), wherein the upper end of the third lifting rope (21) is connected to the fourth lifting rope (22) and the fifth lifting rope (23), respectively; At least three through holes are provided on the steel pipe to be suspended (3), wherein the three through holes are a first through hole (31), a second through hole (32) and a third through hole (33); the third suspension rope (21) extends into the first through hole (31); the fourth suspension rope (22) extends into the second through hole (32); the fifth suspension rope (23) extends into the third through hole (33); the portion of the third suspension rope (21) extending into the first through hole (31) is connected to the fourth suspension rope (22) and the fifth suspension rope (23); the first through hole (31), the second through hole (32) and the third through hole (33) are all located on the same side of the center of gravity of the steel pipe to be suspended (3).
2. A steel pipe pile lifting device according to claim 1, characterized in that: The first lifting rope assembly (1) and the second lifting rope assembly (2) are both connected to the steel pipe (3) to be lifted, and the center of gravity of the steel pipe (3) to be lifted is located between the first lifting rope assembly (1) and the second lifting rope assembly (2).
3. A steel pipe pile lifting device according to claim 2, characterized in that: The first lifting rope assembly (1) is connected to one end of the steel pipe (3) to be lifted, and the second lifting rope assembly (2) is connected to the other end of the steel pipe (3) to be lifted.
4. A steel pipe pile lifting device according to claim 2, characterized in that: The first lifting rope (11) and the second lifting rope (12) are both wound around the steel pipe (3) to be lifted, and the winding directions of the first lifting rope (11) and the second lifting rope (12) are opposite.
5. The steel pipe pile lifting device according to claim 1, characterized in that: All the through holes are arranged along the circumference of the steel pipe (3) to be suspended.
6. The steel pipe pile lifting device according to claim 5, characterized in that: The free end of the third lifting rope (21) is connected to a first lifting hook (24), the free end of the fourth lifting rope (22) is connected to a second lifting hook (25), and the free end of the fifth lifting rope (23) is connected to a third lifting hook (26), wherein: The first hook (24) extends into the first through hole (31), the second hook (25) extends into the second through hole (32), and the third hook (26) extends into the third through hole (33); The first hook (24), the second hook (25) and the third hook (26) are connected to each other.
7. The steel pipe pile lifting device according to claim 5, characterized in that: The first through hole (31) and the third through hole (33) are arranged correspondingly.
8. The steel pipe pile lifting device according to claim 5, characterized in that: The first through hole (31), the second through hole (32) and the third through hole (33) are evenly distributed along the circumference of the steel pipe (3) to be suspended.
9. A steel pipe pile lifting device according to any one of claims 1 to 8, characterized in that: The first lifting rope assembly (1) further comprises a first main rope (10), and the first lifting rope (11) and the second lifting rope (12) are both connected to the first main rope (10).
10. A steel pipe pile lifting device according to any one of claims 1 to 8, characterized in that: The second lifting rope assembly (2) further comprises a second main rope (20), and the third lifting rope (21), the fourth lifting rope (22) and the fifth lifting rope (23) are all connected to the second main rope (20).
Citation Information
Patent Citations
Offshore steel pipe pile hoisting method
CN113336073A