Guardrail for safety construction of expressway
By installing counterweight components on the guardrail pole to inject water to increase weight, using hinges and locking components to fold the railing plate, and connecting the insertion rod to the insertion sleeve, the problems of poor stability and inconvenient transportation of the guardrail are solved, and stable use and convenient transportation are achieved in strong windy weather.
Patent Information
- Application Number
- CN202422604132.7
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-10-28
- Publication Date
- 2025-08-26
- Estimated Expiration
- 2034-10-28
AI Technical Summary
The existing highway construction guardrails are lightweight, poor stability, easy to be blown down, and the structure is fixed and cannot be flexibly adjusted, making it inconvenient to transport.
Installing the counterweight assembly on the vertical pole increases weight by injecting water, using hinges and locking components to achieve folding of the railings, and connecting the insert rods to the insert sleeves to achieve assembly, ensuring stability and convenient transportation.
Keep the guardrail stable in windy weather, and can fold and reduce the volume according to the size of the space, making it easier to transport.
Smart Images

Figure CN223269732U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of protective devices, in particular to a guardrail used for safe construction of expressways. Background Art
[0002] During highway construction, safety fences are set up at the edge of the construction area to prevent non-construction workers from accidentally entering and causing injuries.
[0003] At present, the guardrail for highway installation and construction mainly consists of two hollow vertical poles and an integrated guardrail body welded between the two vertical poles. Although the guardrail for highway installation and construction of this structure can prevent non-construction personnel from accidentally entering when in use, since the overall weight of the guardrail for highway installation and construction of this structure is relatively light and it is directly placed at the construction site when in use, the guardrail for highway installation and construction of this structure is less stable when in use and is easily blown down in windy weather, which is not convenient for the stable use of the guardrail for highway installation and construction. At the same time, since the overall structure of the guardrail for highway installation and construction of this structure is fixed, it cannot be flexibly adjusted according to the size of the actual transfer space, which makes the transfer of the guardrail for highway installation and construction of this structure more inconvenient. Utility Model Content
[0004] (1) Technical issues to be resolved
[0005] The technical problem to be solved by the present invention is to provide a guardrail for safe construction of highways, which can realize the stable placement and use of the guardrail as a whole and prevent the guardrail from being blown down in strong winds, and can be conveniently folded according to the size of the actual transfer space for easy transportation.
[0006] (2) Technical solution
[0007] The present invention is realized through the following technical scheme: The present invention proposes a guardrail for highway safety construction, comprising a vertical pole, a guardrail plate 1 welded on one side wall of the vertical pole, a guardrail plate 2 connected to one side of the guardrail plate by a hinge, a vertical pole 2 welded on the side of the guardrail plate 2 facing away from the guardrail plate 1, a counterweight assembly installed in each of the vertical pole 1 and the vertical pole 2, the counterweight assembly comprising a water storage box installed in the middle of the vertical pole 1, a one-way water inlet bucket installed on the top of the water storage box, and a drain pipe with a self-plug installed at the drain outlet of the water storage box, a locking assembly installed on the side walls of the guardrail plate 1 and the guardrail plate 2 facing away from the hinge, the locking assembly comprising a short shaft installed on the guardrail plate 2, a rotating block installed at one end of the short shaft, a screw head installed on the guardrail plate 1, a groove provided on the rotating block and cooperating with the screw head, and a butterfly nut screwed on the screw head.
[0008] Furthermore, a bent plug rod is welded to the side of the first vertical pole facing away from the first guardrail, and a socket is welded to the side wall of the second vertical pole facing away from the second guardrail.
[0009] By adopting the above technical solution, after the insertion rod of one guardrail is plugged into the insertion sleeve on another guardrail, a convenient assembly connection between the guardrails of this structure can be achieved to meet the reliable blocking requirements at the edge of the highway construction site.
[0010] Furthermore, the size of the insertion rod matches the size of the insertion sleeve, and the height of the insertion rod is higher than the height of the insertion sleeve.
[0011] By adopting the above technical solution, it is possible to ensure that the insertion rod can be easily inserted into the insertion sleeve, and at the same time ensure that after the insertion rod on one guardrail is inserted into the insertion sleeve on another guardrail, the heights of the two guardrails are consistent.
[0012] Furthermore, the one-way water inlet bucket is welded to the vertical pole, and the one-way water inlet bucket is provided with a one-way water inlet valve.
[0013] By adopting the above technical solution, external water can be conveniently poured into the water storage box with the help of the one-way water inlet bucket, so as to increase the overall weight of the guardrail and ensure the overall stable placement of the guardrail.
[0014] Furthermore, the drain pipe is connected to the drain outlet of the water storage box, and the water storage box is a plastic box made of PVC material.
[0015] By adopting the above technical solution, it is possible to ensure that water is reliably stored in the first vertical pole and the second vertical pole, and to avoid corrosion of the first vertical pole and the second vertical pole.
[0016] Furthermore, one end of the short shaft is rotatably connected to the second guardrail, and the other end of the short shaft is welded to the rotating block.
[0017] By adopting the above technical solution, the rotating block can be conveniently rotated and adjusted relative to the second fence under the action of the short shaft.
[0018] Furthermore, the size of the lap groove matches the size of the screw head, the screw head is welded to the guardrail, and the screw head extends out of the lap groove, and the butterfly nut is located outside the lap groove.
[0019] By adopting the above technical solution, when the groove on the rotating block is placed on the nut head, it is only necessary to tighten the butterfly nut to achieve the relative locking and limiting of the first and second railings after they are stretched out.
[0020] (3) Beneficial effects
[0021] Compared with the prior art, the present invention has the following beneficial effects:
[0022] In order to solve the problem that the current highway installation and construction guardrail is mainly composed of two hollow structure uprights and an integrated guardrail body welded between the two uprights, although the highway installation and construction guardrail of this structure can prevent non-construction personnel from entering by mistake when in use, due to the overall weight of the highway installation and construction guardrail of this structure is relatively light and it is directly placed on the construction site when in use, resulting in the highway installation and construction guardrail of this structure having poor stability when in use and being easily blown down in strong winds, which is not convenient for the stable use of the highway installation and construction guardrail. At the same time, due to the overall fixed structure of the highway installation and construction guardrail of this structure, it cannot be flexibly adjusted according to the size of the actual transfer space, resulting in the highway installation and construction guardrail of this structure having poor stability when in use and being easily blown down in strong winds. The problem of inconvenience in transporting the guardrail is solved. On the one hand, the present invention installs a counterweight assembly on the first and second uprights respectively, so that when the guardrail is in use, water can be injected into the water storage box through the one-way water inlet hopper to increase the overall weight of the guardrail, ensure the stable placement of the guardrail when in use, and avoid the disadvantage of the guardrail being blown down in windy weather. On the other hand, hinges are installed on one side of the first and second guardrails, and locking assemblies are installed on the sides of the first and second guardrails facing away from the hinges. When transporting the guardrail, the butterfly nut on the locking assembly can be removed according to the size of the transport space, and the turning block can be separated from the nut head, so that the first and second guardrails can be conveniently folded, so as to reduce the overall space occupied by the guardrail and facilitate the convenient transport and use of the guardrail. BRIEF DESCRIPTION OF THE DRAWINGS
[0023] Figure 1 This is a schematic structural diagram of a guardrail for safe construction on a highway according to the present utility model;
[0024] Figure 2 This is a back view of a guardrail for highway safety construction according to the present invention;
[0025] Figure 3 This is a kind of guardrail used for highway safety construction described in this utility model. Figure 1 Enlarged view of point A in the middle;
[0026] Figure 4 It is a sectional view of two sides of a central pole used for highway safety construction according to the utility model.
[0027] The following are the descriptions of the reference numerals:
[0028] 1. Guardrail 1; 2. Vertical pole 1; 3. Insert rod; 4. Insert sleeve; 5. Vertical pole 2; 6. Guardrail 2; 7. Locking assembly; 701. Turn block; 702. Screw head; 703. Butterfly nut; 704. Slot; 705. Short shaft; 8. Counterweight assembly; 801. One-way water inlet hopper; 802. Water storage box; 803. Drain pipe; 9. Hinge. DETAILED DESCRIPTION
[0029] In order to make the purpose, technical solutions and advantages of the present invention more clearly understood, the present invention is further described in detail below with reference to the accompanying drawings and embodiments. It should be understood that the specific embodiments described herein are only used to explain the present invention and are not intended to limit the present invention.
[0030] like Figures 1-4 As shown, a guardrail for highway safety construction in this embodiment includes a vertical pole 2, a guardrail 1 is welded to one side wall of the vertical pole 2, a guardrail 2 is connected to one side of the guardrail 1 by a hinge 9, and a vertical pole 2 5 is welded to the side of the guardrail 2 6 facing away from the guardrail 1. A counterweight assembly 8 is installed in each of the vertical pole 2 and the vertical pole 2 5. The counterweight assembly 8 includes a water storage box 802 installed in the middle of the vertical pole 2 5, a one-way water inlet bucket 801 installed at the top of the water storage box 802, and a drain pipe 803 with a built-in pipe plug installed at the drain outlet of the water storage box 802. With the help of the one-way water inlet bucket 801, external water can be conveniently poured into the water storage box 802 to increase the overall weight of the guardrail and ensure that the The guardrail is placed stably as a whole, and the drain pipe 803 can realize the convenient discharge of water in the water storage box 802 when transporting after use. A locking assembly 7 is installed on the side wall of the guardrail 1 and the guardrail 2 6 facing away from the hinge 9. The locking assembly 7 includes a short shaft 705 installed on the guardrail 2 6, a rotating block 701 installed at one end of the short shaft 705, a screw head 702 installed on the guardrail 1, a groove 704 on the rotating block 701 that cooperates with the screw head 702, and a butterfly nut 703 screwed on the screw head 702. When the groove 704 on the rotating block 701 is placed on the screw head 702, it is only necessary to lock the butterfly nut 703 to achieve the relative locking limit of the guardrail 1 and the guardrail 2 6 after they are stretched out.
[0031] like Figures 1-4As shown, in this embodiment, a bent plug rod 3 is welded on the side of the vertical pole 2 facing away from the guardrail 1, and a sleeve 4 is welded on the side wall of the vertical pole 2 5 facing away from the guardrail 2 6. After the plug rod 3 of one guardrail is plugged into the sleeve 4 on the other guardrail, a convenient assembly connection between the guardrails of this structure can be achieved to meet the reliable blocking requirements at the edge of the highway construction site. The size of the plug rod 3 matches the size of the sleeve 4, and the height of the plug rod 3 is higher than the height of the sleeve 4, which can ensure the convenient insertion of the plug rod 3 into the sleeve 4, and at the same time ensure that after the plug rod 3 on one guardrail is inserted into the sleeve 4 on the other guardrail, the heights of the two guardrails are consistent.
[0032] like Figures 1-4 As shown, in this embodiment, the one-way water inlet bucket 801 is welded to the vertical pole 2 5, and the one-way water inlet bucket 801 is equipped with a one-way water inlet valve, the drain pipe 803 is connected to the drain outlet of the water storage box 802, and the water storage box 802 is a plastic box made of PVC material, which can ensure the reliable storage of water in the vertical pole 1 2 and the vertical pole 2 5, and avoid causing corrosion of the vertical pole 1 2 and the vertical pole 2 5. One end of the short shaft 705 is rotatably connected to the guardrail 2 6, and the other end of the short shaft 705 is welded to the rotating block 701. Under the action of the short shaft 705, the rotating block 701 can be conveniently rotated and adjusted relative to the guardrail 2 6. The size of the groove 704 matches the size of the screw head 702. The screw head 702 is welded to the guardrail 1, and the screw head 702 extends out of the groove 704, and the butterfly nut 703 is located outside the groove 704.
[0033] The specific implementation process of this embodiment is as follows: when in use, first open the guardrail 1 and the guardrail 2 6, and use the locking component 7 to limit and fix them, then just connect the two adjacent guardrails with each other through the plug rod 3 and the plug sleeve 4, and pour water into the water storage box 802 through the one-way water inlet bucket 801, so that the highway safety construction guardrail can be put into use. During use, by installing a counterweight component 8 on the vertical pole 1 2 and the vertical pole 2 5 respectively, the guardrail can be used by injecting water into the water storage box 802 through the one-way water inlet bucket 801 to achieve the overall The increase in weight ensures that the guardrail can be placed stably when in use, and avoids the disadvantage of being blown down in windy weather. At the same time, by installing hinges 9 on one side of guardrail 1 and guardrail 2 6, and installing locking components 7 on the side of guardrail 1 and guardrail 2 6 facing away from hinges 9, the guardrail can be transported by removing the butterfly nut 703 on the locking component 7 according to the size of the transport space, and separating the turning block 701 from the screw head 702, thereby realizing convenient folding of guardrail 1 and guardrail 2 6, thereby reducing the overall space occupied by the guardrail and facilitating convenient transportation and use of the guardrail.
[0034] The above description of the disclosed embodiments will enable one skilled in the art to implement or use the present invention. Various modifications to these embodiments will be readily apparent to one skilled in the art, and the general principles defined herein may be implemented in other embodiments without departing from the spirit or scope of the present invention. Therefore, the present invention is not limited to the embodiments shown herein but is intended to conform to the widest scope consistent with the principles and novel features disclosed herein.
Claims
1. A guardrail for highway safety construction, characterized by: The invention comprises a vertical pole (2), a guard plate (1) is welded on one side wall of the vertical pole (2), a guard plate (6) is connected to one side of the guard plate (1) via a hinge (9), a vertical pole (5) is welded on the side of the guard plate (6) facing away from the guard plate (1), a counterweight assembly (8) is installed in each of the vertical pole (2) and the vertical pole (5), and the counterweight assembly (8) comprises a water storage box (802) installed in the middle of the vertical pole (2), a one-way water inlet hopper (801) installed at the top of the water storage box (802), and a water inlet hopper (801) installed in the water storage box (802). A drain pipe (803) with a built-in pipe plug at the drain outlet, a locking assembly (7) is installed on the side wall of the first guardrail (1) and the second guardrail (6) facing away from the hinge (9), and the locking assembly (7) includes a short shaft (705) installed on the second guardrail (6), a rotating block (701) installed at one end of the short shaft (705), a screw head (702) installed on the first guardrail (1), a groove (704) provided on the rotating block (701) and cooperating with the screw head (702), and a butterfly nut (703) screwed on the screw head (702).
2. A guardrail for highway safety construction according to claim 1, characterized in that: A bent insert rod (3) is welded to the side of the first vertical pole (2) facing away from the first guardrail (1), and a sleeve (4) is welded to the side wall of the second vertical pole (5) facing away from the second guardrail (6).
3. A guardrail for highway safety construction according to claim 2, characterized in that: The size of the insertion rod (3) matches the size of the insertion sleeve (4), and the height of the insertion rod (3) is higher than the height of the insertion sleeve (4).
4. The guardrail for highway safety construction according to claim 1, characterized in that: The one-way water inlet hopper (801) is welded to the vertical pole (2), and the one-way water inlet hopper (801) is provided with a one-way water inlet valve.
5. The guardrail for highway safety construction according to claim 1, characterized in that: The drainage pipe (803) is connected to the drainage port of the water storage box (802), and the water storage box (802) is a plastic box made of PVC material.
6. The guardrail for highway safety construction according to claim 1, characterized in that: One end of the short shaft (705) is rotatably connected to the second fence (6), and the other end of the short shaft (705) is welded to the rotating block (701).
7. The guardrail for highway safety construction according to claim 1, characterized in that: The size of the groove (704) matches the size of the screw head (702).
8. The guardrail for highway safety construction according to claim 7, characterized in that: The screw head (702) is welded to the guardrail (1), and the screw head (702) extends out of the lap groove (704), and the butterfly nut (703) is located outside the lap groove (704).