Building pile mounting device
By designing a building pile installation device, using clamping and adjusting fixing mechanisms and moving components, the shaking problem of building piles during lifting and transportation is solved, and crane damage and labor costs are reduced.
Patent Information
- Application Number
- CN202422265968.9
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-09-18
- Publication Date
- 2025-08-29
- Estimated Expiration
- 2034-09-18
AI Technical Summary
Building piles are prone to shake during lifting and transportation, causing damage to the crane, and the installation process requires the cooperation of multiple staff members to increase labor costs.
A building pile installation device is designed, including a bracket plate, a clamping and adjusting fixing mechanism, abutment assembly and a moving assembly. The building piles are fixed by clamping and adjusting fixing mechanism, and the moving assembly is used to avoid shaking and reduce the occupation of human resources.
It avoids damage to the crane during the movement of building piles, reduces the demand for human resources, and achieves a safe and efficient installation process.
Smart Images

Figure CN223280487U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of construction pile installation, in particular to a construction pile installation device. Background Art
[0002] In the construction field, building piles usually refer to the pile body part of the pile foundation. They are cylindrical load-bearing components that penetrate deep into the soil layer. Their main function is to bear and transfer the load of the upper building.
[0003] At present, due to the heavy weight of construction piles, heavy lifting equipment such as cranes are needed to assist in their installation. The crane lifts the construction piles and safely transports them to the predetermined installation location. Subsequently, under manual control of the staff, the construction piles are positioned at the installation site, thus successfully completing the installation operation.
[0004] However, although cranes and other lifting equipment have demonstrated excellent capabilities in lifting and transporting construction piles, some problems still exist. First, during transportation, the construction piles are prone to swinging due to the shaking caused by the crane's movement, increasing the risk of collision between the construction piles and the crane, which in turn causes damage to the crane. Second, when positioning the construction piles, workers need to do it manually. Given the large size and weight of the construction piles, this process requires the cooperation of multiple workers, which takes up additional human resources and increases labor costs. Utility Model Content
[0005] The utility model aims to solve one of the technical problems in the related art at least to a certain extent.
[0006] To this end, one purpose of the present invention is to propose a construction pile installation device to avoid damage to the crane caused by the shaking of the construction piles during the movement of the construction piles, while avoiding the occupation of additional human resources to achieve the effect of reducing labor costs.
[0007] To achieve the above-mentioned purpose, the utility model proposes a construction pile installation device, including a bracket plate, a clamping and adjusting fixing mechanism, an abutment assembly, a lifting ring and a movable assembly, wherein a positioning hole is opened through the middle portion of the bracket plate, and the clamping and adjusting fixing mechanism is installed on the top of the bracket plate, and the clamping and adjusting fixing mechanism includes a clamping assembly, a fixing assembly and an adjusting assembly, wherein the clamping assembly is installed on the top of the bracket plate, the fixing assembly is installed on one side of the clamping assembly, the adjusting assembly is installed on the bottom of one end of the clamping assembly, and the clamping assembly is slidably installed on the top of the bracket plate through the adjusting assembly; the abutment assembly is installed at one end of the bracket plate, and one end of the abutment assembly penetrates into the interior of the bracket plate and abuts against the adjusting assembly; the lifting ring is installed on the top of the clamping assembly; and the movable assembly is installed at the four corners of the bottom end of the bracket plate.
[0008] The construction pile installation device of the present invention completes the fixation of the construction pile under the action of the clamping, adjusting and fixing mechanism, and achieves the effect of moving the construction pile under the action of the moving component, avoiding the situation where the crane is damaged due to the shaking of the construction pile during the movement of the construction pile, and avoids occupying additional human resources, thereby achieving the effect of reducing labor costs.
[0009] In addition, the construction pile installation device proposed in the application may also have the following additional technical features:
[0010] Specifically, the clamping assembly includes a lower clamping plate, an upper clamping plate and a hinge, wherein the lower clamping plate is connected to the adjustment assembly, and the hinge and the lower clamping plate are hinged through the hinge.
[0011] Specifically, the fixing assembly includes a fixing plate, a rocking wheel and a screw, wherein the fixing plates are provided in two groups, and the two groups of rocking wheels are respectively connected to the lower splint and the upper splint, the screw is fixedly connected to the rocking wheel, and the end of the screw away from the rocking wheel is threaded through the two groups of fixing plates.
[0012] Specifically, the adjustment assembly includes a wheel frame and a pulley, wherein the wheel frame is connected to the lower clamping plate, the pulley is rotatably installed on one side of the wheel frame, and the top of the bracket plate is provided with a sliding groove for the pulley to slide.
[0013] Specifically, the abutment assembly includes a rotating wheel, a screw and a rocker, wherein the rotating wheel is connected to the screw, one end of the screw is threaded into the interior of the bracket plate and abuts against the pulley, and the rocker is connected to one end of the rotating wheel.
[0014] Additional aspects and advantages of the present invention will be given in part in the following description and in part will become apparent from the following description or learned through practice of the present invention. BRIEF DESCRIPTION OF THE DRAWINGS
[0015] The above and / or additional aspects and advantages of the present invention will become apparent and readily understood from the following description of the embodiments in conjunction with the accompanying drawings, in which:
[0016] Figure 1 This is a schematic structural diagram of a construction pile installation device according to one embodiment of the present utility model;
[0017] Figure 2 This is a structural schematic diagram of a construction pile installation device according to another embodiment of the present invention;
[0018] Figure 3 This is a schematic diagram of the structure of the clamping assembly of the utility model.
[0019] As shown in the figure: 1. Bracket plate; 2. Clamping, adjusting and fixing mechanism; 21. Clamping assembly; 211. Lower clamping plate; 212. Upper clamping plate; 213. Hinge; 22. Fixing assembly; 221. Fixing plate; 222. Rocker; 223. Screw; 23. Adjusting assembly; 231. Wheel frame; 232. Pulley; 233. Slide; 3. Abutment assembly; 31. Rotating wheel; 32. Lead screw; 33. Rocker; 4. Lifting ring; 5. Moving assembly; 6. Positioning hole. DETAILED DESCRIPTION
[0020] The following describes in detail embodiments of the present invention, examples of which are shown in the accompanying drawings, wherein the same or similar reference numerals throughout represent the same or similar elements or elements having the same or similar functions. The embodiments described below with reference to the accompanying drawings are exemplary and are intended to be used to explain the present invention, and should not be construed as limiting the present invention. On the contrary, the embodiments of the present invention include all variations, modifications, and equivalents that fall within the spirit and scope of the appended claims.
[0021] The following describes the construction pile installation device according to an embodiment of the present invention in conjunction with the accompanying drawings.
[0022] The construction pile installation device provided in the embodiment of the utility model can be used for the installation of construction piles, avoiding the situation where the construction piles shake and cause damage to the crane during the movement of the construction piles, and at the same time avoids occupying additional human resources, thereby achieving the effect of reducing labor costs.
[0023] like Figure 1-Figure 3 As shown, the construction pile installation device of the embodiment of the present invention may include a bracket plate 1 , a clamping and adjusting fixing mechanism 2 , an abutting component 3 , a lifting ring 4 and a moving component 5 .
[0024] It should be noted that the support plate 1 described in the above embodiment plays the role of supporting the building piles.
[0025] A positioning hole 6 is formed through the middle of the bracket plate 1 .
[0026] It can be understood that, under the action of the positioning holes 6 described in the above embodiment, the construction piles are positioned and lowered.
[0027] The clamping, adjusting, and fixing mechanism 2 is installed on the top of the bracket plate 1 . The clamping, adjusting, and fixing mechanism 2 may include a clamping component 21 , a fixing component 22 , and an adjusting component 23 .
[0028] It should be noted that the clamping assembly 21 described in the above embodiment achieves the effect of fixing the building pile under the action of the fixing assembly 22.
[0029] Among them, the clamping component 21 is installed at the top of the bracket plate 1, the fixing component 22 is installed on one side of the clamping component 21, the adjusting component 23 is installed at the bottom of one end of the clamping component 21, and the clamping component 21 is slidably installed on the top of the bracket plate 1 through the adjusting component 23.
[0030] It can be understood that the building pile is fixed under the action of the clamping component 21, and then the building pile is fixed in the clamping component 21 under the action of the fixing component 22, and the position of the building pile on the bracket plate 1 is adjusted by the adjusting component 23.
[0031] The abutting component 3 is installed at one end of the bracket plate 1 , and one end of the abutting component 3 penetrates into the interior of the bracket plate 1 and abuts against the adjusting component 23 .
[0032] It should be noted that, under the action of the abutting component 3 , the adjusted position of the adjusting component 23 can be fixed, thereby preventing the building pile from sliding on the bracket plate 1 .
[0033] The lifting ring 4 is mounted on the top of the clamping assembly 21 .
[0034] It can be understood that the lifting ring 4 facilitates the crane to move the support plate 1 and the clamped building pile.
[0035] The moving components 5 are installed at the four corners of the bottom end of the bracket plate 1.
[0036] It should be noted that the moving component 5 described in the above embodiment may be a universal wheel.
[0037] It can be understood that the movement of the bracket plate 1 is completed under the action of the moving component 5.
[0038] Specifically, during the actual operation, when installing the building pile, the relevant personnel use a crane to place the building pile in the clamping assembly 21. Then, with the assistance of the fixing assembly 22, the clamping assembly 21 completes the fixation of the fixing assembly 22. Then, the lifting ring 4 is connected to the crane. Under the push of the crane, the building pile is moved on the bracket plate 1 through the moving assembly 5 to avoid shaking when the building pile is lifted. At the same time, after the building pile arrives at the installation site, the building pile is adjusted under the action of the adjusting assembly 23 and moved to the top of the positioning hole 6. Then, the abutment component 3 is rotated to limit the adjustment component 23. Then, with the assistance of the crane, the building pile is lifted from the bracket plate 1, and the bottom of the building pile is aligned with the positioning hole 6. The clamping component 21 is opened by the adjustment component 23, and the building pile in the clamping component 21 falls to the installation location. Finally, the bracket plate 1 is taken out, thereby completing the installation of the building pile, avoiding the situation where the crane is damaged due to the shaking of the building pile during the movement of the building pile, and avoiding taking up extra human resources, thereby achieving the effect of reducing labor costs.
[0039] In one embodiment of the present invention, Figure 1-Figure 3 As shown, the clamping assembly 21 may include a lower clamping plate 211 , an upper clamping plate 212 and a hinge 213 .
[0040] It should be noted that rubber plates are installed on opposite sides of the lower clamping plate 211 and the upper clamping plate 212 described in the above embodiment to increase the friction between the lower clamping plate 211 and the upper clamping plate 212 and the building piles.
[0041] The lower clamping plate 211 is connected to the adjustment assembly 23 , and the hinge 213 and the lower clamping plate 211 are hingedly connected via the hinge 213 .
[0042] Specifically, under the action of the lower clamping plate 211 and the upper clamping plate 212, the construction pile achieves a fixing effect.
[0043] In one embodiment of the present invention, Figure 1-Figure 3 As shown, the fixing assembly 22 may include a fixing plate 221 , a rocking wheel 222 and a screw 223 .
[0044] As a possible scenario, a crank handle may be installed on the top of the rocking wheel 222 described in the above embodiment to facilitate the rotation of the rocking wheel 222 .
[0045] Among them, there are two groups of fixed plates 221, and the two groups of rocking wheels 222 are respectively connected to the lower clamping plate 211 and the upper clamping plate 212, the screw 223 is fixedly connected to the rocking wheel 222, and the end of the screw 223 away from the rocking wheel 222 is threaded through the two groups of fixed plates 221.
[0046] Specifically, under the rotation of the rocking wheel 222 , the driving screw 223 rotates downward, and then the screw 223 passes through the two sets of fixing plates 221 to complete the fixation of the lower clamping plate 211 and the upper clamping plate 212 .
[0047] In one embodiment of the present invention, Figure 1-Figure 3 As shown, the adjustment assembly 23 may include a wheel frame 231 and a pulley 232 .
[0048] It should be noted that the wheel frame 231 and the pulley 232 described in the above embodiment are both provided in two groups.
[0049] The wheel frame 231 is connected to the lower clamping plate 211 , the pulley 232 is rotatably mounted on one side of the wheel frame 231 , and a sliding groove 233 for the pulley 232 to slide is provided at the top of the bracket plate 1 .
[0050] Specifically, the wheel frame 231 is moved under the action of the pulley 232 , and the pulley 232 is connected under the action of the wheel frame 231 , and the wheel frame 231 is installed through the sliding groove 233 .
[0051] In one embodiment of the present invention, Figure 1-Figure 3 As shown, the abutment assembly 3 may include a rotating wheel 31 , a lead screw 32 and a rocker 33 .
[0052] The rotating wheel 31 is connected to the lead screw 32 , one end of the lead screw 32 is threaded into the interior of the bracket plate 1 and abuts against the pulley 232 , and the rocker 33 is connected to one end of the rotating wheel 31 .
[0053] Specifically, under the rotation of the rotating wheel 31 , the lead screw 32 rotates and penetrates into the sliding groove 233 , and the pulley 232 is fixed according to the position of the pulley 232 .
[0054] In summary, the construction pile installation device of the embodiment of the utility model completes the fixation of the construction pile under the action of the clamping, adjusting and fixing mechanism, and achieves the effect of moving the construction pile under the action of the moving component, thereby avoiding the situation where the crane is damaged due to the shaking of the construction pile during the movement of the construction pile, and at the same time avoids occupying additional human resources, thereby achieving the effect of reducing labor costs.
[0055] In this specification, the terms "first" and "second" are used for descriptive purposes only and should not be understood to indicate or imply relative importance or implicitly specify the number of technical features indicated. Therefore, a feature specified as "first" or "second" may explicitly or implicitly include at least one of such features. In the description of this utility model, "plurality" means at least two, for example, two, three, etc., unless otherwise specifically defined.
[0056] In the description of this specification, the description with reference to the terms "one embodiment", "some embodiments", "example", "specific example", or "some examples" means that the specific features, structures, materials or characteristics described in conjunction with the embodiment or example are included in at least one embodiment or example of the present invention. In this specification, the schematic representations of the above terms do not necessarily refer to the same embodiment or example. Moreover, the specific features, structures, materials or characteristics described can be combined in any one or more embodiments or examples in a suitable manner. In addition, those skilled in the art can combine and combine different embodiments or examples and features of different embodiments or examples described in this specification without contradiction.
[0057] Although the embodiments of the present invention have been shown and described above, it can be understood that the above embodiments are illustrative and cannot be understood as limitations on the present invention. Ordinary technicians in this field can change, modify, replace and deform the above embodiments within the scope of the present invention.
Claims
1. A construction pile installation device, characterized in that: It includes a bracket plate, a clamping and adjusting fixing mechanism, an abutment component, a lifting ring and a moving component, wherein: A positioning hole is provided in the middle of the bracket plate. The clamping, adjusting and fixing mechanism is installed on the top of the bracket plate, and the clamping, adjusting and fixing mechanism includes a clamping component, a fixing component and an adjusting component, wherein: The clamping assembly is mounted on the top of the bracket plate, the fixing assembly is mounted on one side of the clamping assembly, the adjusting assembly is mounted on the bottom of one end of the clamping assembly, and the clamping assembly is slidably mounted on the top of the bracket plate through the adjusting assembly; The abutment assembly is mounted on one end of the bracket plate, and one end of the abutment assembly penetrates into the interior of the bracket plate and abuts against the adjustment assembly; The lifting ring is installed on the top of the clamping assembly; The moving components are installed at the four corners of the bottom end of the bracket plate.
2. The construction pile installation device according to claim 1, characterized in that The clamping assembly includes a lower clamping plate, an upper clamping plate and a hinge, wherein: The lower clamping plate is connected to the adjusting assembly, and the hinge and the lower clamping plate are hinged via the hinge.
3. The construction pile installation device according to claim 2, characterized in that: The fixing assembly includes a fixing plate, a rocking wheel and a screw, wherein: There are two groups of fixed plates, and the two groups of rocking wheels are respectively connected to the lower clamping plate and the upper clamping plate. The screw is fixedly connected to the rocking wheel, and the end of the screw away from the rocking wheel is threaded through the two groups of fixed plates.
4. The construction pile installation device according to claim 3, characterized in that: The adjustment assembly includes a wheel frame and a pulley, wherein: The wheel frame is connected to the lower clamping plate, the pulley is rotatably mounted on one side of the wheel frame, and a sliding groove for the pulley to slide is provided on the top of the bracket plate.
5. The construction pile installation device according to claim 4, characterized in that: The abutment assembly includes a rotating wheel, a lead screw and a rocker, wherein: The rotating wheel is connected to the lead screw, one end of the lead screw is threadedly inserted into the interior of the bracket plate and abuts against the pulley, and the rocker is connected to one end of the rotating wheel.