Assembling type hanging basket rapid maintenance construction platform

By splitting the bridge construction hanging basket into multiple assembled components and connecting it through anchors and booms, the instability and large footprint of the one-piece hanging basket structure is solved, and a more stable construction process and convenient transportation are achieved.

CN223281220UActive Publication Date: 2025-08-29SICHUAN ROAD & BRIDGE CONSTRUCTION GROUP CO LTD
View PDF 1 Cites 0 Cited by

Patent Information

Application Number
CN202422646387.X
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-10-31
Publication Date
2025-08-29
Estimated Expiration
2034-10-31

AI Technical Summary

Technical Problem

The one-piece hanging basket structure used in the existing bridge construction results in unstable lifting, large area of ​​land, and high overall lifting difficulty, which increases the unstable factors during the construction process.

Method used

The assembled hanging basket structure is adopted, and the hanging basket is divided into rear lower beam, front lower beam, bottom longitudinal beam and bottom formwork. It is connected by anchor rod and hanging rod to increase overall strength and stability, and the bottom formwork is spot welded on the bottom longitudinal beam to ensure the stability of construction workers.

Benefits of technology

It reduces the instability of the overall lifting, reduces the floor area of ​​the transportation process, improves the convenience and safety of construction, and ensures the safety of construction personnel.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN223281220U_ABST
    Figure CN223281220U_ABST
Patent Text Reader

Abstract

The utility model relates to an assembly type hanging basket rapid maintenance construction platform, which belongs to the technical field of bridge construction and comprises a bridge, a pier formwork is poured at the top of the bridge, two main trusses are arranged at one end of the top of the pier formwork, and a front upper cross beam is fixedly mounted between the tops of the two main trusses. The utility model has the beneficial effects that the front lower cross beam is arranged below the front upper cross beam by utilizing the front suspender, and the bottom longitudinal beams are arranged above the front lower cross beam and the rear lower cross beam, so that the stability between the rear lower cross beam and the front lower cross beam can be increased, the overall strength can be increased, and the bottom templates are spot-welded on the plurality of bottom longitudinal beams, so that the production efficiency is improved. Compared with a traditional one-piece hanging basket, according to the scheme, the whole hanging basket is divided into the rear lower cross beam, the front lower cross beam, the bottom longitudinal beam and the bottom formwork, the instability of overall hoisting can be reduced, meanwhile, the occupied area in the transportation process can be reduced, and consignment is more convenient and faster.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of bridge construction, in particular to an assembled hanging basket rapid maintenance construction platform. Background Art

[0002] The bridge construction hanging basket is a device used for cantilever casting of concrete bridges. The construction hanging baskets used in the cantilever casting construction of prestressed concrete continuous beams (rigid frame beams) in my country mostly adopt functional designs. As long as the strength, rigidity, stability and deadweight limit requirements of the structure are met, it is an open hanging basket, and safety protection is limited to conventional guardrails and protective nets. The removal of the hanging basket requires on-site dismantling of the entire structure.

[0003] After searching, a Chinese patent disclosed a hanging basket safety protection system device for bridge construction (authorization announcement number CN201071487Y), including a high-altitude falling object prevention device, which is a dense mesh steel wire mesh enclosed along the four sides of the hanging basket. The bottom and surrounding areas of the hanging basket are provided with an insulation device, the bottom of the hanging basket is provided with a waterproof device, and one end of the main beam of the hanging basket is provided with a lightning protection device. Although this patented technology adopts the hanging basket safety protection system device of this utility model, it can provide comprehensive safety protection for structures and construction personnel during bridge construction, effectively improving the construction progress.

[0004] However, the above device still has some shortcomings in actual use. The most obvious one is that most of the bridge construction currently uses a one-piece hanging basket, and the on-site construction is carried out as a whole. However, the one-piece hanging basket structure causes its entire skeleton to be larger, which increases the floor space occupied during the transportation process. In addition, the overall lifting method has a high difficulty coefficient and the lifting process is unstable, which greatly increases the unstable factors in the construction process. Utility Model Content

[0005] In view of the above problems existing in the prior art, the main purpose of the present invention is to provide an assembled hanging basket rapid maintenance construction platform.

[0006] The technical solution of the present utility model is as follows: an assembled hanging basket rapid maintenance construction platform, including a bridge, a pier formwork cast on the top of the bridge, two main trusses are provided at one end of the top of the pier formwork, a front upper cross beam is fixedly installed between the tops of the two main trusses, a rear lower cross beam is provided at the bottom end of the pier formwork, two third anchor rods are provided inside the rear lower cross beam, the rear lower cross beam and the pier formwork are connected by the third anchor rod, a front lower cross beam is provided at the bottom end of the front upper cross beam, a plurality of bottom longitudinal beams are built between the front lower cross beam and the top of the rear lower cross beam, both ends of the bottom longitudinal beam are first anchor rods, and the first anchor rods are connected to the rear lower cross beam and the front lower cross beam by the first anchor rod.

[0007] By adopting the above technical solution, the front lower crossbeam is installed below the front upper crossbeam using the front hoist rod, and the bottom longitudinal beams are arranged above the front lower crossbeam and the rear lower crossbeam to increase the stability between the rear lower crossbeam and the front lower crossbeam, thereby increasing the overall strength. The bottom formwork is spot-welded on multiple bottom longitudinal beams to ensure the stability of the contact surface of the construction workers' feet. Compared with the traditional one-piece hanging basket, this solution splits the entire hanging basket into: rear lower crossbeam, front lower crossbeam, bottom longitudinal beam and bottom formwork, which can reduce the instability of the overall lifting.

[0008] As a preferred embodiment, two front hangers are provided between the front upper crossbeam and the front lower crossbeam, the front upper crossbeam and the front lower crossbeam are connected through the front hangers, four rear hangers are provided on the top of the rear lower crossbeam, the rear lower crossbeam and the pier formwork are connected through two of the rear hangers, a transverse connecting truss is provided at the top end of the pier formwork, and the rear lower crossbeam and the transverse connecting truss are connected through another two rear hangers.

[0009] By adopting the above technical solution and setting the front suspension rod, the front lower crossbeam can be installed below the front upper crossbeam to increase the connection strength between the front upper crossbeam and the front lower crossbeam, and improve the stability of the front lower crossbeam during use.

[0010] As a preferred embodiment, tracks are provided at both ends of the top of the pier formwork, the bottom ends of the tracks are fixedly connected with pad beams at equal distances, second anchor rods are provided inside the pad beams, and the pier formwork and the pad beams are connected via the second anchor rods.

[0011] By adopting the above technical solution and setting the second anchor rod, multiple cushion beams can be installed above the pier formwork, and the track can be fixed thereto, thereby providing stronger support for the main truss.

[0012] As a preferred embodiment, a shear brace is welded between the two main trusses, and the shear brace includes two transverse beams, and the two transverse beams are in a cross structure.

[0013] By adopting the above technical solution and setting shear braces, the shear resistance of the two main trusses can be increased, thereby improving the stability of both.

[0014] As a preferred embodiment, the transverse connecting truss is fixedly installed between the two main trusses, a prestressed frame is provided on the outer side of the track, rear anchor rods are provided at both ends of the prestressed frame, and the prestressed frame is connected to the pier formwork through the rear anchor rods.

[0015] By adopting the above technical solution and setting up the prestressed frame, the prestress of the track can be increased to improve the longitudinal resistance of the track.

[0016] As a preferred embodiment, bottom templates are spot-welded between the tops of the plurality of bottom longitudinal beams, and the main trusses are fixedly mounted on the outsides of the corresponding rails.

[0017] By adopting the above technical solution and spot welding the bottom formwork on multiple bottom longitudinal beams, the smoothness of the contact surface of the construction workers' feet can be ensured.

[0018] As a preferred embodiment, a protective fence is provided between the top of the front lower cross beam and the rear lower cross beam, and the protective fence includes two side fences and a front fence. The side fences are installed at the top of one of the bottom longitudinal beams, and the front fence is installed between the tops of multiple bottom longitudinal beams.

[0019] By adopting the above technical solution and setting up a protective fence, safe construction at the hanging basket position can be ensured, and construction workers can be prevented from falling on the bottom formwork.

[0020] Compared with the prior art, the advantages and positive effects of the present invention are:

[0021] 1. In the present invention, when bridge construction is required, the third anchor rod can be used to install the rear lower cross beam under the pier formwork, and the rear hanger can be used to increase the overall stability and supporting performance of the rear lower cross beam. Subsequently, the front hanger can be used to install the front lower cross beam under the front upper cross beam, and the bottom longitudinal beams can be arranged above the front lower cross beam and the rear lower cross beam to increase the stability between the rear lower cross beam and the front lower cross beam, thereby increasing the overall strength. The bottom formwork is spot-welded on multiple bottom longitudinal beams to ensure the stability of the contact surface of the construction workers' feet. Compared with the traditional one-piece hanging basket, this solution splits the entire hanging basket into: rear lower cross beam, front lower cross beam, bottom longitudinal beam and bottom formwork, which can reduce the instability of the overall lifting, and at the same time can reduce the floor space occupied during transportation, making consignment more convenient.

[0022] 2. In the present invention, by setting the second anchor rod, multiple cushion beams can be installed above the pier formwork, and the track can be fixed thereto, thereby providing stronger support for the main truss. In the later construction process, the track and the cushion beam are detachable to facilitate subsequent bridge construction. BRIEF DESCRIPTION OF THE DRAWINGS

[0023] Figure 1 The utility model provides an overall three-dimensional diagram of an assembled hanging basket rapid maintenance construction platform;

[0024] Figure 2 The utility model provides a main view of an assembled hanging basket rapid maintenance construction platform;

[0025] Figure 3 This utility model provides a kind of assembled hanging basket rapid maintenance construction platform Figure 1 Enlarged view of point A in the middle.

[0026] Legend: 1. Bridge; 2. Pier formwork; 3. Track; 4. Pad beam; 5. Prestressed frame; 6. Main truss; 7. Shear brace; 8. Front upper crossbeam; 9. Transverse connecting truss; 10. Front hanger; 11. Front lower crossbeam; 12. Protective fence; 13. First anchor rod; 14. Rear lower crossbeam; 15. Rear hanger; 16. Bottom longitudinal beam; 17. Bottom formwork; 18. Second anchor rod; 19. Rear anchor rod. DETAILED DESCRIPTION

[0027] The technical solutions in the embodiments of the present application will be clearly and completely described below in conjunction with the drawings in the embodiments of the present application. Obviously, the described embodiments are only part of the embodiments of the present application, not all of the embodiments. Based on the embodiments in the present application, all other embodiments obtained by ordinary technicians in this field without making creative work are within the scope of protection of this application.

[0028] Reference Figure 1-3 , an assembled hanging basket rapid maintenance construction platform, including a bridge 1, the top of the bridge 1 is cast with a pier formwork 2, one end of the top of the pier formwork 2 is provided with two main girders 6, a front upper cross beam 8 is fixedly installed between the tops of the two main girders 6, the bottom end of the pier formwork 2 is provided with a rear lower cross beam 14, two third anchor rods are provided inside the rear lower cross beam 14, the rear lower cross beam 14 and the pier formwork 2 are connected by the third anchor rod, the bottom end of the front upper cross beam 8 is provided with a front lower cross beam 11, a plurality of bottom longitudinal beams 16 are built between the front lower cross beam 11 and the top of the rear lower cross beam 14, the two ends of the bottom longitudinal beam 16 are both first anchor rods 13, the first anchor rod 13 is connected to the rear lower cross beam 14 and the front lower cross beam 11 by the first anchor rod 13, when the bridge 1 needs to be constructed, the rear lower cross beam can be connected by the third anchor rod The beam 14 is installed below the pier formwork 2, and the rear hanger 15 is used to increase the overall stability and supporting performance of the rear lower cross beam 14. Subsequently, the front hanger 10 is used to install the front lower cross beam 11 below the front upper cross beam 8, and the bottom longitudinal beams 16 are arranged above the front lower cross beam 11 and the rear lower cross beam 14 to increase the stability between the rear lower cross beam 14 and the front lower cross beam 11, thereby increasing the overall strength, and spot welding the bottom formwork 17 on multiple bottom longitudinal beams 16 to ensure the stability of the contact surface of the construction workers' feet. Compared with the traditional one-piece hanging basket, this solution splits the entire hanging basket into: rear lower cross beam 14, front lower cross beam 11, bottom longitudinal beam 16 and bottom formwork 17, which can reduce the instability of the overall lifting, and at the same time can reduce the floor space occupied during transportation, making consignment more convenient.

[0029] Reference Figure 2Two front hangers 10 are provided between the front upper cross beam 8 and the front lower cross beam 11, and the front upper cross beam 8 and the front lower cross beam 11 are connected through the front hangers 10. Four rear hangers 15 are provided on the top of the rear lower cross beam 14. The rear lower cross beam 14 is connected to the pier formwork 2 through two of the rear hangers 15. A transverse connecting truss 9 is provided on the top of the pier formwork 2, and the rear lower cross beam 14 is connected to the transverse connecting truss 9 through another two rear hangers 15. Through the setting of the front hangers 10, the front lower cross beam 11 can be installed under the front upper cross beam 8 to increase the connection strength between the front upper cross beam 8 and the front lower cross beam 11, and improve the stability of the front lower cross beam 11 during use. The use of the rear hangers 15 can further improve the stability of the rear lower cross beam 14 on the basis of the third anchor connection, and increase the overall strength after assembly.

[0030] Reference Figure 2 , tracks 3 are provided at both ends of the top of the pier formwork 2, and the bottom ends of the tracks 3 are fixedly connected with cushion beams 4 at equal distances. The interior of the cushion beams 4 is provided with second anchor rods 18, and the pier formwork 2 and the cushion beams 4 are connected by the second anchor rods 18. Through the setting of the second anchor rods 18, multiple cushion beams 4 can be installed above the pier formwork 2, and thereby the tracks 3 can be fixed, thereby providing stronger support for the main truss 6. In the later construction process, the tracks 3 and the cushion beams 4 are detachable to facilitate the subsequent construction of the bridge 1.

[0031] Reference Figure 1 A shear brace 7 is welded between the two main trusses 6. The shear brace 7 includes two transverse beams. The two transverse beams are in a cross structure. By setting the shear brace 7, the shear resistance of the two main trusses 6 can be increased, thereby improving the stability of both.

[0032] Reference Figure 3 The transverse connecting truss 9 is fixedly installed between the two main trusses 6. A prestressed frame 5 is provided on the outside of the track 3. Rear anchor rods 19 are provided at both ends of the prestressed frame 5. The prestressed frame 5 is connected to the pier formwork 2 through the rear anchor rods 19. Bottom templates 17 are spot-welded between the tops of multiple bottom longitudinal beams 16. The main trusses 6 are fixedly installed on the outside of the corresponding track 3. By setting the prestressed frame 5, the prestress of the track 3 can be increased to improve the longitudinal resistance of the track 3.

[0033] Reference Figure 2 A protective fence 12 is provided between the top of the front lower cross beam 11 and the rear lower cross beam 14. The protective fence 12 includes two side fences and a front fence. The side fence is installed at the top of one of the bottom longitudinal beams 16, and the front fence is installed between the tops of multiple bottom longitudinal beams 16. The setting of the protective fence 12 can ensure safe construction at the hanging basket position and prevent construction workers from falling on the bottom formwork 17.

[0034] Working principle: First, clean the area above the bridge 1 and install the track 3. By setting the second anchor rod 18, multiple cushion beams 4 can be installed above the pier formwork 2 to fix the track 3, thereby providing strong support for the main trusses 6. Then, the main trusses 6 are installed above the corresponding tracks 3, and the transverse connecting trusses 9 and the front upper crossbeam 8 are welded between the two main trusses 6.

[0035] Then, the third anchor rod is used to install the rear lower cross beam 14 under the pier formwork 2, and the rear hanger 15 is used to increase the overall stability and support performance of the rear lower cross beam 14. At the same time, the rear hanger 15 is used to connect the rear lower cross beam 14 with the transverse connecting truss 9 and the pier formwork 2. Subsequently, the front hanger 10 is used to install the front lower cross beam 11 under the front upper cross beam 8, and the bottom longitudinal beam 16 is arranged above the front lower cross beam 11 and the rear lower cross beam 14 to increase the stability between the rear lower cross beam 14 and the front lower cross beam 11. The overall strength can be increased, and the bottom formwork 17 is spot-welded on multiple bottom longitudinal beams 16 to ensure the stability of the contact surface of the construction workers' feet. Compared with the traditional one-piece hanging basket, this solution splits the entire hanging basket into: the rear lower crossbeam 14, the front lower crossbeam 11, the bottom longitudinal beam 16 and the bottom formwork 17, which can reduce the instability of the overall hoisting and the floor space occupied during transportation, making consignment more convenient. The protective fence 12 is set to ensure safe construction at the hanging basket position and prevent construction workers from falling on the bottom formwork 17.

[0036] Finally, after the entire hanging basket is installed, the side formwork is installed and the hanger is inserted, and then the hanging basket pre-compression construction can be carried out, thereby achieving the construction purpose of Bridge 1.

[0037] In the description of the present invention, it should be noted that, unless otherwise clearly specified and limited, the terms "installed", "provided with", "connected", etc. should be understood in a broad sense. For example, "connection" can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection or an indirect connection through an intermediate medium, or it can be a connection between the internal parts of two components. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to the specific circumstances.

[0038] The above are only preferred embodiments of the present application and are not intended to limit the present application. Although the present application has been described in detail with reference to the aforementioned embodiments, those skilled in the art can still modify the technical solutions described in the aforementioned embodiments or make equivalent replacements for some of the technical features therein. Any modifications, equivalent replacements, improvements, etc. made within the spirit and principles of the present application should be included in the scope of protection of the present application.

Claims

1. An assembled hanging basket rapid maintenance construction platform, comprising a bridge (1), characterized in that: A pier formwork (2) is cast on the top of the bridge (1), two main girders (6) are provided at one end of the top of the pier formwork (2), a front upper crossbeam (8) is fixedly installed between the tops of the two main girders (6), a rear lower crossbeam (14) is provided at the bottom end of the pier formwork (2), two third anchor rods are provided inside the rear lower crossbeam (14), the rear lower crossbeam (14) and the pier formwork (2) are connected by the third anchor rods, a front lower crossbeam (11) is provided at the bottom end of the front upper crossbeam (8), a plurality of bottom longitudinal beams (16) are built between the front lower crossbeam (11) and the top of the rear lower crossbeam (14), both ends of the bottom longitudinal beam (16) are connected by first anchor rods (13), and the first anchor rod (13) is connected to the rear lower crossbeam (14) and the front lower crossbeam (11) by the first anchor rod (13).

2. The assembled hanging basket rapid maintenance construction platform according to claim 1, characterized in that: Two front suspension rods (10) are provided between the front upper crossbeam (8) and the front lower crossbeam (11), the front upper crossbeam (8) and the front lower crossbeam (11) are connected via the front suspension rods (10), four rear suspension rods (15) are provided on the top of the rear lower crossbeam (14), the rear lower crossbeam (14) and the pier formwork (2) are connected via two of the rear suspension rods (15), a transverse connecting truss (9) is provided at the top end of the pier formwork (2), and the rear lower crossbeam (14) and the transverse connecting truss (9) are connected via the other two rear suspension rods (15).

3. The assembled hanging basket rapid maintenance construction platform according to claim 2, characterized in that: Tracks (3) are provided at both ends of the top of the pier formwork (2), and cushion beams (4) are fixedly connected to the bottom ends of the tracks (3) at equal intervals. Second anchor rods (18) are provided inside the cushion beams (4), and the pier formwork (2) and the cushion beams (4) are connected via the second anchor rods (18).

4. The assembled hanging basket rapid maintenance construction platform according to claim 1, characterized in that: A shear brace (7) is welded between the two main trusses (6), and the shear brace (7) comprises two transverse beams, and the two transverse beams are in a cross structure.

5. The assembled hanging basket rapid maintenance construction platform according to claim 3 is characterized by: The transverse connecting truss (9) is fixedly installed between the two main trusses (6), a prestressed frame (5) is provided on the outside of the track (3), rear anchor rods (19) are provided at both ends of the interior of the prestressed frame (5), and the prestressed frame (5) is connected to the pier formwork (2) via the rear anchor rods (19).

6. The assembled hanging basket rapid maintenance construction platform according to claim 1, characterized in that: A bottom template (17) is spot-welded between the tops of the plurality of bottom longitudinal beams (16), and the main truss (6) is fixedly mounted on the outside of the corresponding track (3).

7. The assembled hanging basket rapid maintenance construction platform according to claim 1, characterized in that: A protective fence (12) is provided between the top of the front lower cross beam (11) and the top of the rear lower cross beam (14), and the protective fence (12) includes two side fences and a front fence, the side fences being installed at the top of one of the bottom longitudinal beams (16), and the front fence being installed between the tops of a plurality of bottom longitudinal beams (16).

Citation Information

Patent Citations

  • Suspension basket safety protection system device in bridge construction

    CN201071487Y