Jacking system for protecting building
By combining components such as wall clamping beams, wall lifting beams, and connecting beams, the problem of having to completely dismantle the jacking and support structure in existing technologies is solved. This achieves foundation reinforcement and construction quality improvement after building relocation, reduces the amount of demolition work, and provides concealed space and aesthetics for electromechanical pipelines.
Patent Information
- Application Number
- CN202422706471.6
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-11-07
- Publication Date
- 2025-11-04
- Estimated Expiration
- 2034-11-07
AI Technical Summary
The existing lifting and support structure needs to be completely dismantled after the protected building is moved into place, resulting in a large amount of work and material waste.
The building is constructed using wall-clamping beams, lifting beams, connecting beams, and reinforcement components. Jacks are used to lift and move the building. After the move, the wall-clamping beams and connecting beams are retained as the foundation, and only the lifting beams are removed, thus reducing the amount of demolition work.
It improves the integrity, stability and seismic resistance of the building foundation, reduces the amount of demolition work, and creates a cavity in the building for the installation of electromechanical pipelines, ensuring construction safety and aesthetics.
Smart Images

Figure CN223510653U_ABST
Abstract
Description
TECHNICAL FIELD
[0001] The utility model relates to the technical field of building engineering, especially relates to a protection building jacking system. BACKGROUND
[0002] The protection building is usually completed by a jacking system to achieve building translation jacking and underpinning construction, and the jacking system directly bears the building load and transmits the building load to the lower translation object. For example, the Chinese invention patent application CN115822315A discloses a shallow foundation protection building whole underpinning structure and construction method, the structure includes an underpinning platform composed of steel strand bundles synthesized by top pipes arranged in the soil below the shallow foundation protection building; the top pipe includes two side top pipes and a plurality of middle top pipes; the underpinning platform is provided with top pipe jacking shafts corresponding to the two edges of the two openings of all top pipes, and the lower sides of the two edges are provided with underpinning beams; a plurality of jacks are arranged between the underpinning beams and the corresponding edges; the soil above the two side top pipes is hollowed out to form a disconnection groove communicating the two top pipe jacking shafts; the soil of the top pipe jacking shafts and the disconnection groove arranged around the shallow foundation protection building is reinforced to form a soil reinforcement area.
[0003] The jacking and underpinning structure of the prior art is a temporary component, which needs to be completely removed after the protection building is translated and positioned, and the removal engineering quantity is large, and the waste quantity of the removed materials is also large. Therefore, it is necessary to provide a protection building jacking system, which can solve the problem that the jacking system of the prior art needs to be completely removed after the protection building is translated and positioned. SUMMARY
[0004] The utility model aims at providing a protection building jacking system, which can solve the problem that the jacking system of the prior art needs to be completely removed after the protection building is translated and positioned.
[0005] The utility model is realized as follows:
[0006] A protection building jacking system, comprising a wall clamping beam, a wall lifting beam, a jack and a reinforcing assembly; a pair of wall clamping beams are respectively attached to the inner wall and the outer wall of the protection building, and the pair of wall clamping beams form a closed loop structure along the bottom of the protection building; the wall lifting beam penetrates the wall of the protection building vertically, and a plurality of wall lifting beams are arranged at intervals along the circumference of the protection building; the bottom surface of each wall lifting beam is fixedly connected to the top surface of the pair of wall clamping beams, and the two ends of the wall lifting beam extend to the inner side and the outer side of a pair of reinforcing beams, respectively; a pair of jacks are arranged between the two ends of the wall lifting beam and the translation surface; a plurality of reinforcing assemblies are installed on the protection building.
[0007] The protection building is provided with a plurality of connecting beams at intervals, and each connecting beam is connected vertically between the two oppositely arranged surfaces of the wall clamping beam on the inner side of the protection building.
[0008] The reinforcing assembly comprises a scissors brace, a horizontal brace, an inner reinforcing rib, an outer reinforcing rib and a tie member; the inner reinforcing rib is vertically attached to the inner wall of the wall of the protected building, the outer reinforcing rib is vertically attached to the outer wall of the wall of the protected building, and the tie member penetrates the wall of the protected building and is fixedly connected with the inner reinforcing rib and the outer reinforcing rib; the scissors brace and the horizontal brace are arranged between the two oppositely arranged walls of the protected building and are installed between the two oppositely arranged inner reinforcing ribs.
[0009] The first-floor structural floor of the protected building is constructed on the wall-enclosing beams and the connecting beams located on the inner side of the protected building, and the mechanical and electrical pipelines of the protected building are arranged in the space enclosed by the first-floor structural floor, the basement roof and the wall-enclosing beams.
[0010] The ground ridge walls are arranged between the wall-enclosing beams located on the inner side of the protected building, and the ground ridge walls are vertically connected with the connecting beams and are arranged in a staggered manner with the mechanical and electrical pipelines.
[0011] The outer side of the protected building is provided with a waterproof layer, and the waterproof layer is arranged on the top surface of the basement roof, the outer side surface and the top surface of the wall-enclosing beams located on the outer side of the protected building and the outer wall of the wall of the protected building.
[0012] The outer side of the protected building is provided with earthwork, and the earthwork covers the waterproof layer.
[0013] When the backfill elevation of the earthwork is higher than the top surface of the wall-enclosing beams, the earthwork covers and wraps the wall-enclosing beams located on the outer side of the protected building; when the backfill elevation of the earthwork is lower than the top surface of the wall-enclosing beams, the decorative plate covers and wraps the wall-enclosing beams located on the outer side of the protected building.
[0014] Compared with the prior art, the utility model has the following beneficial effects:
[0015] 1、The utility model discloses a wall-enclosing beam, a wall-raising beam, a jack, a connecting beam and a reinforcing assembly, the wall-enclosing beam, the wall-raising beam and the connecting beam can form an integral whole for bearing the load of the protected building, and the integral translation of the protected building is realized by combining the jack, thereby guaranteeing the safety of the translation construction.
[0016] 2, The utility model discloses because being equipped with sandwich wall beam and connection beam, after the translation is completed, and the sandwich wall beam and connection beam are reserved, only need to remove the wall lifting beam, greatly reduce the demolition work quantity, and can take the sandwich wall beam and connection beam as the foundation of the protected building, can greatly enhance the integrity, stability and anti -seismic ability of the protected building foundation, simultaneously, the sandwich wall beam and connection beam can form the sandwich cavity below the first floor structural floor, be used for the construction of electromechanical pipeline etc. Hidden component has good water vapor isolation effect.
[0017] 3, The utility model discloses because being equipped with waterproof layer and earthwork, the waterproof layer is turned up to the sandwich wall beam of protected building outdoor and the wall surface outer wall of protected building, to guarantee the waterproof and anti -permeation performance of protected building, simultaneously, through backfilling earthwork or installing the way of decorative board covers the sandwich wall beam of protected building outdoor, avoids the sandwich wall beam exposure and influences the aesthetic property, also can satisfy the decoration requirement of afforestation planting. BRIEF DESCRIPTION OF DRAWINGS
[0018] Figure 1 It is the elevation view of the utility model protected building jacking system;
[0019] Figure 2 It is the partial reservation schematic drawing after the translation of the utility model protected building jacking system is completed;
[0020] Figure 3 It is the first floor structural floor and electromechanical construction schematic drawing after the translation of the utility model protected building jacking system is completed;
[0021] Figure 4 It is the waterproof construction schematic drawing after the translation of the utility model protected building jacking system is completed.
[0022] In the drawing, 1 sandwich wall beam, 2 wall lifting beam, 3 jack, 4 connection beam, 5 protected building, 501 first floor structural floor, 502 electromechanical pipeline, 503 basement roof, 504 ground ridge wall, 505 waterproof layer, 506 earthwork, 601 scissor brace, 602 horizontal support, 603 inner reinforcing beam, 604 outer reinforcing beam, 605 tie member. DETAILED DESCRIPTION
[0023] The utility model will be further explained below in connection with the drawings and specific embodiment.
[0024] Please refer to the attached Figure 1The utility model provides a kind of protective building jacking system, including sandwich wall beam 1, wall lifting beam 2, jack 3 and reinforcing assembly;A pair of sandwich wall beam 1 is respectively attached to the inner wall and outer wall of the wall of protective building 5, and a pair of sandwich wall beam 1 forms a closed loop structure along the bottom of protective building 5;Wall lifting beam 2 vertically penetrates the wall of protective building 5, and several wall lifting beams 2 are arranged along the circumference of protective building 5;The bottom surface of each wall lifting beam 2 is fixedly connected with the top surface of a pair of sandwich wall beam 1, and the two ends of wall lifting beam 2 extend to the inner side and outer side of a pair of reinforcing beam 1 respectively, and a pair of jack 3 is arranged between the two ends of wall lifting beam 2 and the translation plane such as basement roof 503 of protective building 5;Several groups of reinforcing assemblies are respectively installed on protective building 5 and can be respectively fixedly connected with several wall lifting beams 2.
[0025] Sandwich wall beam 1 and wall lifting beam 2 form a closed loop whole along the circumference at the bottom of the wall of protective building 5, for bearing the load of protective building 5, and form a jacking system in combination with jack 3, to realize the jacking, underpinning and translation of protective building 5.The translation procedure can adopt the whole building translation technology of prior art, which will not be described here.
[0026] The reinforcing assembly is used for reinforcing the whole of protective building 5, to improve the structural safety of protective building 5 during translation.
[0027] After translation, a pair of sandwich wall beam 1 can be retained as the foundation of protective building 5, to improve the integrity, stability and seismic capacity of the foundation of protective building 5, and only the part of wall lifting beam 2 located outside the wall of protective building 5 needs to be removed, greatly reducing the amount of demolition work.
[0028] Please refer to the accompanying drawings Figure 1 And the accompanying drawings Figure 2 A plurality of tie beams 4 are arranged at intervals in protective building 5, and each tie beam 4 is connected vertically between two oppositely arranged surfaces of sandwich wall beam 1 located on the inner side of protective building 5.
[0029] The tie beam 4 can be integrally cast with the sandwich wall beam 1, to further improve the structural strength and carrying capacity of the whole jacking system during the translation of protective building 5.
[0030] Meanwhile, the tie beam 4 is retained synchronously with the sandwich wall beam 1, and together serves as the foundation of protective building 5, and can serve as the support of the first-floor structural floor slab 501 of protective building 5, to further improve the integrity, stability and seismic capacity of the foundation of protective building 5.
[0031] Please refer to the accompanying drawings Figure 1Each of the reinforcing assemblies comprises a scissors brace 601, a horizontal brace 602, an inner reinforcing rib 603, an outer reinforcing rib 604 and a tie 605; the inner reinforcing rib 603 is vertically attached to the inner wall of the wall surface of the protected building 5, the outer reinforcing rib 604 is vertically attached to the outer wall of the wall surface of the protected building 5, and the tie 605 penetrates the wall surface of the protected building 5 and is fixedly connected with the inner reinforcing rib 603 and the outer reinforcing rib 604; the scissors brace 601 and the horizontal brace 602 are arranged between the two oppositely arranged wall surfaces of the protected building 5 and are fixedly connected between the two oppositely arranged inner reinforcing ribs 603 by means of angle codes or other fixing members.
[0032] Preferably, the reinforcing assemblies are made of steel structures, and the number and arrangement spacing of the reinforcing assemblies can be flexibly adjusted to form a roof support inside the protected building 5 to prevent the protected building 5 from deforming during the translation process. The reinforcing assemblies can be staggered with the wall-raising beams 2, or the bottom of the reinforcing assemblies can be fixed to the wall-raising beams 2 according to the construction requirements.
[0033] Through the arrangement of the scissors brace 601 and the horizontal brace 602, vertical and horizontal loads can be simultaneously borne, and through the arrangement of the inner reinforcing rib 603 and the outer reinforcing rib 604, the stress of the wall surface can be uniformly and stably borne, and the load transmission is facilitated.
[0034] Please refer to the accompanying drawings Figure 3 The first-floor structural floor 501 of the protected building 5 is constructed on the wall-clamping beams 1 and the connecting beams 4 located inside the protected building 5, and the mechanical and electrical pipelines 502 of the protected building 5 are arranged in the space enclosed by the first-floor structural floor 501, the basement roof 503 and the wall-clamping beams 1.
[0035] The wall-clamping beams 1 and the connecting beams 4 are used to construct the first-floor structural floor 501 of the protected building 5. Since the wall-clamping beams 1 and the connecting beams 4 have a certain height, a space is formed below the first-floor structural floor 501, forming a sandwich cavity, which can be used to arrange the mechanical and electrical pipelines 502 and other concealed works.
[0036] Please refer to the accompanying drawings Figure 3 The first-floor structural floor 501 and the basement roof 503 are provided with the ground ridge walls 504, a plurality of ground ridge walls 504 are arranged between the two oppositely arranged wall-clamping beams 1 located inside the protected building 5, and the ground ridge walls 504 are perpendicularly connected with the connecting beams 4 and are arranged staggered with the mechanical and electrical pipelines 502.
[0037] If the span of the first-floor structural floor 501 is large, the ground ridge walls 504 can be constructed in the direction perpendicular to the connecting beams 4, and the ground ridge walls 504, the connecting beams 4 and the wall-clamping beams 1 are used as the supports of the first-floor structural floor 501 to avoid the deflection and deformation of the first-floor structural floor 501 due to the large span.
[0038] The 504 foundation wall can be constructed using reinforced concrete, and should be built according to the drawings and process requirements, which will not be elaborated here. During the construction of the 504 foundation wall, care should be taken to avoid interference with the installation of electromechanical pipelines 502.
[0039] Please see the appendix Figure 4 The outer side of the protective building 5 is provided with a waterproof layer 505, which is laid on the top surface of the basement roof slab 503, the outer side and top surface of the wall beam 1 located on the outer side of the protective building 5, and the outer wall of the protective building 5.
[0040] Waterproof layer 505 can be constructed using conventional hot-melt overlapping technology with waterproof membrane, which will not be elaborated here. During construction, waterproof layer 505 should be extended to the wall beam 1 outside the protected building 5 and the outer wall of the protected building 5 to ensure the waterproof and seepage-proof performance of the protected building 5.
[0041] Please see the appendix Figure 4 The outer side of the protective building 5 is covered with earthwork 506, which covers the waterproof layer 505. When the backfill elevation of earthwork 506 is higher than the top surface of the wall beam 1, earthwork 506 covers and wraps the wall beam 1 located on the outer side of the protective building 5. When the backfill elevation of earthwork 506 is lower than the top surface of the wall beam 1, decorative panels (not shown in the figure) cover and wrap the wall beam 1 located on the outer side of the protective building 5.
[0042] When there are requirements for greening construction on the exterior of the protected building 5, soil 506 can be backfilled directly on the waterproof layer 505 for planting. When backfilling the soil 506, the external wall beam 1 of the protected building 5 should be covered to prevent it from being exposed and affecting the aesthetics. If the backfill height of the soil 506 is insufficient to cover the wall beam 1, the wall beam 1 of the protected building 5 can be wrapped with decorative panels such as stone curtain walls to prevent it from being exposed.
[0043] Please see the appendix Figure 1 To be continued Figure 4 The construction method of this utility model is as follows:
[0044] Construct wall-clamping beams 1 on the inner and outer walls of the protected building 5 respectively. A pair of wall-clamping beams 1 form a closed loop structure along the bottom circumference of the protected building 5, and use the friction between the wall-clamping beams 1 and the wall surface to bear part of the load of the protected building 5.
[0045] Drill holes at the bottom of the wall of the protected building 5 and construct a lifting beam 2. The lifting beam 2 vertically penetrates the wall of the protected building 5 and extends to the inner and outer sides of a pair of clamping beams 1. The bottom surface of the lifting beam 2 is attached to the top surface of the pair of clamping beams 1, connecting the lifting beam 2 and the pair of clamping beams 1 into a whole to jointly bear the load.
[0046] A connecting beam 4 is constructed between the two opposing surfaces of the wall beam 1 on the inner side of the protected building 5 to improve the integrity, structural strength and load-bearing capacity of the wall beam 1.
[0047] The wall beam 1, the lifting beam 2, and the connecting beam 4 can be made of reinforced concrete and cast in one piece, with high integrity and structural strength, and can bear the load of the protected building 5 as a whole.
[0048] Jacks 3 are installed between the two ends of the lifting beam 2 and the translational surfaces such as the basement roof slab 503 of the protected building 5. The lifting beam 2 and the two jacks 3 are set up in groups, and the number of groups can be adjusted according to the load and process requirements.
[0049] Internal reinforcing ribs 603 are installed on the inner wall of the protected building 5, and external reinforcing ribs 604 are installed on the outer wall. Both internal and external reinforcing ribs 603 and 604 can be made of channel steel. Tie bolts 605 can be used as tie rods. The tie bolts penetrate the wall of the protected building 5 and connect and fix the internal and external reinforcing ribs 603 and 604. The number and spacing of the tie bolts between the internal and external reinforcing ribs 603 and 604 can be adjusted according to their height. The internal and external reinforcing ribs 603 and 604, and the tie bolts 605 are arranged in groups, and the number of groups can be adjusted according to load requirements.
[0050] A horizontal brace 602 is installed on the upper part of the two internal reinforcing ribs 603 that are set opposite to each other. The two ends of the horizontal brace 602 are fixed to the internal reinforcing ribs 603 by bolts through angle brackets. The horizontal brace 602 can be made of I-beams.
[0051] A scissor brace 601 is installed between two opposing inner reinforcing ribs 603. The top two ends of the scissor brace 601 share angle brackets with the horizontal brace 602 and are fixed to the two opposing inner reinforcing ribs 603. The bottom two ends of the scissor brace 601 are fixed to the two opposing inner reinforcing ribs 603 by bolts using angle brackets. The scissor brace 602 can be formed by three I-beams intersecting and connected by connectors to form an X-shaped structure.
[0052] The protective building 5 was moved as a whole using a lifting system formed by the wall beam 1, the lifting beam 2, the jack 3, and the connecting beam 4. The moving process adopted the existing technology of building whole-building moving process, which will not be described in detail here.
[0053] After the relocation is completed, remove the lifting beam 2 and jack 3, and retain a pair of clamping beams 1 and connecting beam 4 to reduce the amount of demolition work. The retention of the pair of clamping beams 1 will significantly enhance the stability, integrity, and seismic resistance of the foundation of the protected building 5. The lifting beam 2 can be cut and removed using conventional techniques such as water drilling and wire sawing, which will not be described in detail here.
[0054] Because of the retention of a pair of wall beams 1, the elevation of the first floor of the protected building 5 is raised. After the translation is completed, the first floor slab 501 is directly constructed on the wall beams 1 and the connecting beams 4 inside the protected building 5. If the span of the first floor slab 501 is large, a ground joist wall 504 is constructed between the opposite sides of the wall beams 1. The ground joist wall 504 intersects the connecting beams 4 perpendicularly, and the wall beams 1, the connecting beams 4, and the ground joist wall 504 are used as supports for the first floor slab 501.
[0055] A cavity is formed between the basement roof slab 503, the wall beam 1 within the protected building 5, and the first-floor structural slab 501. This cavity provides a certain degree of moisture isolation, improving the living experience of the protected building 5. Simultaneously, concealed works such as mechanical and electrical pipelines 502, typically located within the ceiling, can be moved to this cavity, increasing the first-floor ceiling height and ensuring the first-floor height. During construction, holes can be drilled in the connecting beam 4 using a water drill for the installation of mechanical and electrical pipelines 502. The layout of the mechanical and electrical pipelines 502 can be constructed according to the detailed mechanical and electrical design requirements, which will not be elaborated here.
[0056] For the outdoor waterproofing construction of protected building 5, the waterproof membrane can be laid along the top surface of the basement roof slab 503, the outer side and top surface of the wall beam 1 located on the outside of protected building 5, and the outer wall of protected building 5 to form a waterproof layer 505, ensuring the waterproof and seepage-proof performance of protected building 5. The waterproof membrane should be installed according to the drawings and specifications, which will not be elaborated here.
[0057] Backfill soil 506 on the top of the basement outside the protected building 5. Soil 506 covers and wraps the wall beam 1 outside the protected building 5. If the elevation of soil 506 is low, decorative panels such as stone curtain walls can be used to cover and wrap the wall beam 1 to hide the wall beam 1 and ensure aesthetics.
[0058] The above are merely preferred embodiments of the present utility model and are not intended to limit the scope of protection of the present utility model. Therefore, any modifications, equivalent substitutions, improvements, etc., made within the spirit and principles of the present utility model should be included within the scope of protection of the present utility model.
Claims
1. A protective building lifting system, characterized by: It includes a wall-clamping beam (1), a wall-lifting beam (2), jacks (3), and reinforcement components; a pair of wall-clamping beams (1) are respectively attached to the inner and outer walls of the protective building (5), and the pair of wall-clamping beams (1) form a closed loop structure along the bottom circumference of the protective building (5); the wall-lifting beam (2) penetrates vertically through the wall of the protective building (5), and several wall-lifting beams (2) are arranged at intervals along the circumference of the protective building (5); the bottom surface of each wall-lifting beam (2) is fixedly connected to the top surface of a pair of wall-clamping beams (1), and the two ends of the wall-lifting beam (2) extend to the inner and outer sides of a pair of reinforcing beams (1), respectively; a pair of jacks (3) are respectively set between the two ends of the wall-lifting beam (2) and the translation surface; several sets of reinforcement components are respectively installed on the protective building (5).
2. The protective building lifting system according to claim 1, characterized in that: The protective building (5) is provided with several connecting beams (4) at intervals. Each connecting beam (4) is vertically connected between two opposite surfaces of the wall beam (1) located inside the protective building (5).
3. The protective building lifting system according to claim 1, characterized in that: Each set of reinforcement components includes a scissor brace (601), a horizontal brace (602), an inner reinforcing rib (603), an outer reinforcing rib (604), and a tie rod (605); the inner reinforcing rib (603) is vertically attached to the inner wall of the protective building (5), the outer reinforcing rib (604) is vertically attached to the outer wall of the protective building (5), and the tie rod (605) penetrates the wall of the protective building (5) and is tied and fixed to the inner reinforcing rib (603) and the outer reinforcing rib (604); the scissor brace (601) and the horizontal brace (602) are both set between the two oppositely arranged walls of the protective building (5) and installed between the two oppositely arranged inner reinforcing ribs (603).
4. The protective building lifting system according to claim 2, characterized in that: The first floor slab (501) of the protected building (5) is constructed on the wall beam (1) and connecting beam (4) located inside the protected building (5). The electromechanical pipelines (502) of the protected building (5) are laid in the space enclosed by the first floor slab (501), the basement roof slab (503) and the wall beam (1).
5. The protective building lifting system according to claim 4, characterized in that: A ground ridge wall (504) is provided between the first floor slab (501) and the basement roof slab (503). Several ground ridge walls (504) are respectively set between two opposite sides of the wall beam (1) located inside the protected building (5). The ground ridge wall (504) is vertically connected to the connecting beam (4) and staggered from the electromechanical pipeline (502).
6. The protective building lifting system according to any one of claims 1-5, characterized in that: The protective building (5) is provided with a waterproof layer (505) on the outside. The waterproof layer (505) is laid on the top surface of the basement roof slab (503), the outer side and top surface of the wall beam (1) located on the outside of the protective building (5), and the outer wall of the protective building (5).
7. The protective building lifting system according to claim 6, characterized in that: The outer side of the protective building (5) is covered with earthwork (506), which is covered with a waterproof layer (505).
8. The protective building lifting system according to claim 7, characterized in that: When the backfill elevation of the earthwork (506) is higher than the top surface of the wall beam (1), the earthwork (506) covers and wraps the wall beam (1) located outside the protected building (5); when the backfill elevation of the earthwork (506) is lower than the top surface of the wall beam (1), the decorative panel covers and wraps the wall beam (1) located outside the protected building (5).
Citation Information
Patent Citations
Shallow foundation protection building integral underpinning structure and construction method
CN115822315A