Viaduct and suspension type monorail bridge combined construction structure

By pre-setting support beams and stay cables before pouring the piers, the problem of the difficulty in constructing suspended platforms under viaducts was solved, and the stability and construction of the suspended platforms were simplified.

CN223562007UActive Publication Date: 2025-11-18JINAN YULIAN CONSTRUCTION ENGINEERING CO LTD
View PDF 1 Cites 0 Cited by

Patent Information

Application Number
CN202423161054.4
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-12-20
Publication Date
2025-11-18
Estimated Expiration
2034-12-20

AI Technical Summary

Technical Problem

In existing technologies, when elevated bridges and suspended monorail bridges are built together, the construction of suspended platforms is difficult, especially when the road surface below the elevated bridge is wide, making it difficult to achieve stable fixation.

Method used

Before the piers are poured, support beams and tie rods are pre-installed. The suspended platform is fixed to the piers through the support beams and stay cables. The support beams and stay cables provide stable support and tension, and the suspended platform and piers form a stable connection.

Benefits of technology

It achieves stable fixation of the suspended platform, reduces additional construction, adapts to different road widths, and simplifies the construction process of the suspended platform.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN223562007U_ABST
    Figure CN223562007U_ABST
Patent Text Reader

Abstract

The utility model belongs to the field of bridges, and relates to a viaduct and suspension type monorail bridge combined construction structure which comprises a pier, a box girder, a track beam and a suspension platform, a plurality of supporting beams extending outwards are preset on the pier, a plurality of mounting grooves corresponding to the supporting beams are formed in the lower side of the suspension platform, and the box girder and the track beam are arranged in the mounting grooves. The supporting beam is inserted into the mounting groove, a positioning bolt used for positioning the suspended platform is arranged on the side face of the mounting groove, a connector is arranged at the end, away from the pier, of the suspended platform and connected with a stay cable, the upper end of the stay cable is connected with a pull rod, and one end of the pull rod is inserted into the pier. The prefabricated suspended platform is used, the supporting beam and the pull rod are preset before the pier is poured, the supporting beam and the pull rod are stably fixed after the pier is poured, the suspended platform can be conveniently fixed through the supporting beam and the pull rod, and the suspended platform fixing device is arranged below the pier and is not limited by the width of a road surface.
Need to check novelty before this filing date? Find Prior Art

Description

TECHNICAL FIELD

[0001] The utility model belongs to bridge field relates to a kind of structure of viaduct and suspension monorail bridge combined construction. BACKGROUND

[0002] The application file with the application number CN202323315840.0 discloses a kind of structure of new viaduct and suspension monorail bridge combined construction, in its technical scheme: including new large cantilever pier unit, connecting structure unit, track beam unit and suspension monorail vehicle, new large cantilever pier unit is fixedly connected with track beam unit by connecting structure unit, suspension monorail vehicle is suspended and connected in track beam unit. The design improves the bridge transport capacity, provides a new way for relieving urban traffic pressure, but the design is not easy to build platform like subway, subway needs to be excavated in space underground, and suspension monorail vehicle needs to cooperate with overhanging platform, but if the highway pavement under viaduct is wide, the difficulty of building overhanging platform is greater. UTILITARY MODEL CONTENT

[0003] The utility model provides a viaduct with overhanging platform for the above problems.

[0004] In order to achieve the above purpose, the utility model adopts the technical scheme that a kind of structure of viaduct and suspension monorail bridge combined construction, including pier, box girder, track beam, further including overhanging platform, the pier is pre-set with several support beams extending outward, the overhanging platform is provided with several installation grooves at the lower side corresponding to several support beams, the support beam is inserted into the installation groove, the installation groove side is provided with positioning bolt for positioning overhanging platform, the end of overhanging platform away from pier is provided with adapter, the adapter is connected with cable-stayed cable, the upper end of cable-stayed cable is connected with pull rod, and the pull rod one end is inserted into pier.

[0005] As preferred, the overhanging platform is connected with inclined ladder.

[0006] As preferred, the overhanging platform is T-shaped in perspective view.

[0007] As preferred, the overhanging platform is provided with guardrail.

[0008] Compared with prior art, the utility model has the advantages and positive effects that:

[0009] The utility model uses prefabricated overhanging platform, and preset support beam and pull rod before pier pouring, and the support beam and pull rod are stably fixed after pier pouring, so that the overhanging platform is fixed by the support beam and pull rod conveniently, and the utility model is arranged below pier, not limited by road width. BRIEF DESCRIPTION OF DRAWINGS

[0010] To more clearly illustrate the technical solutions of the embodiments of this utility model, the drawings used in the description of the embodiments will be briefly introduced below. Obviously, the drawings described below are some embodiments of this utility model. For those skilled in the art, other drawings can be obtained based on these drawings without creative effort.

[0011] Figure 1 This is a schematic diagram of a structure that combines an elevated bridge and a suspended monorail bridge.

[0012] Figure 2 This is a view of the suspended platform from above.

[0013] In the above figures, 1 is the bridge pier; 11 is the supporting beam; 12 is the tie rod; 2 is the box girder; 3 is the track beam; 4 is the monorail; 5 is the suspended platform; 51 is the mounting slot; 52 is the connector; 6 is the inclined ladder; and 7 is the stay cable. Detailed Implementation

[0014] To better understand the above-mentioned objectives, features, and advantages of this utility model, the present utility model will be further described below with reference to the accompanying drawings and embodiments. It should be noted that, unless otherwise specified, the embodiments and features described in these embodiments can be combined with each other.

[0015] Many specific details are set forth in the following description in order to provide a full understanding of the present invention. However, the present invention may also be implemented in other ways different from those described herein. Therefore, the present invention is not limited to the specific embodiments disclosed in the following specification.

[0016] like Figure 1 , Figure 2 As shown, a structure combining an elevated bridge and a suspended monorail bridge includes a pier 1, a box girder 2 above the pier 1, and a track beam 3 suspended below the box girder 2. The track beam 3 is used to run a monorail vehicle 4. The above is prior art and will not be described in detail here. To facilitate the construction of the suspended platform, this utility model also includes a prefabricated steel structure suspended platform 5. Since the pier 1 is a reinforced concrete structure, several outwardly extending support beams 11 are pre-installed on the pier 1 before the concrete is poured. After the concrete is poured, the support beams 11 are firmly fixed. Several installation slots 51 are provided on the lower side of the suspended platform 5 corresponding to the support beams 11. The support beams 11 are inserted into the installation slots 51. Positioning bolts for positioning the suspended platform 5 are provided on the side of the installation slots 51. The positioning bolts connect the installation slots 51 to the support beams to facilitate the installation of the suspended platform 5. A connector 52 is provided at the end of the suspended platform 5 away from the pier 1. The connector 52 is connected to a stay cable 7. A tie rod 12 is connected to the upper end of the stay cable 7. One end of the tie rod 12 is inserted into the pier 1. That is, the tie rod 12 and the support beams 11 are also fixed after the concrete is poured.

[0017] Specifically, the high bridge in the middle of the wide road, the distance from the roadside to the high bridge is long, and the difficulty of constructing the suspended platform 5 is large, therefore, the utility model constructs the suspended platform 5 under the high bridge, and utilizes the pier 1 as the support, reduces the additional construction, the support beam 11 provides the support for the suspended platform 5, and the inhaul cable 7 provides the pulling force for the end of the suspended platform 5 far from the pier 1, so that the utility model realizes fixing the suspended platform 5 on the high bridge.

[0018] Further, the suspended platform 5 is connected with the inclined ladder 6, and the lower end of the inclined ladder 6 is placed on the ground.

[0019] Further, the suspended platform 5 is in T shape from the perspective of looking down.

[0020] Further, the suspended platform 5 is provided with the guardrail.

[0021] The above is only the preferred embodiment of the utility model, and is not other forms of the limitation of the utility model, any skilled person in the art can utilize the disclosed technical content to make changes or modifications into the equivalent embodiment applied to other fields, but any simple modification, equivalent change and modification made according to the technical essence of the utility model to the above embodiment without departing from the technical scheme content of the utility model still belongs to the protection scope of the technical scheme of the utility model.

Claims

1. A structure of combined construction of overhead bridge and suspended monorail bridge, comprising a bridge pier, a box girder and a track beam, characterized in that, Also include the overhanging platform, the pier is provided with several outwardly extending support beams, the lower side of the overhanging platform is provided with several mounting slots corresponding to the several support beams, the support beams are inserted into the mounting slots, the side of the mounting slot is provided with a positioning bolt for positioning the overhanging platform, one end of the overhanging platform away from the pier is provided with a connector, the connector is connected with a cable-stayed cable, the upper end of the cable-stayed cable is connected with a pull rod, one end of the pull rod is inserted into the pier.

2. The structure of claim 1, wherein The overhanging platform is connected with an inclined ladder.

3. The structure of claim 2, wherein the overhead bridge is a bridge having a height of 5 to 15 m. The overhanging platform has a T-shaped top view.

4. The structure of claim 3, wherein The overhanging platform is provided with a guardrail.

Citation Information

Patent Citations

  • Combined construction structure of newly-built viaduct and suspended monorail bridge

    CN221255187U