Concrete floor thickness control tool facilitating thickness measurement
By pre-embedding detachable PVC plastic pipes and positioning sleeve structures in concrete floor slabs, combined with a rotating sleeve design, the complexity of concrete floor slab thickness control and the risk of damage during subsequent measurement in existing technologies are solved, enabling convenient and accurate thickness measurement and control.
Patent Information
- Application Number
- CN202423163298.6
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-12-20
- Publication Date
- 2025-11-28
- Estimated Expiration
- 2034-12-20
AI Technical Summary
Existing methods for controlling the thickness of concrete floor slabs are cumbersome to operate, make it difficult to guarantee the uniformity and consistency of thickness, and the subsequent measurement process is prone to damaging the structure and increasing costs.
The system employs detachable PVC plastic pipes and an adjustable positioning sleeve structure. Pre-embedded PVC plastic pipes are used to assist in measuring the thickness of concrete floor slabs. Combined with a rotatable inner and outer sleeve design and a network layer, the system ensures the accuracy and flexibility of the measurement.
It improves the convenience and accuracy of concrete slab thickness measurement, reduces construction complexity and cost, and enhances the flexibility and consistency of thickness control.
Smart Images

Figure CN223608225U_ABST
Abstract
Description
TECHNICAL FIELD
[0001] The utility model relates to the technical field of building construction, specifically relates to a concrete floor thickness control tool convenient for measuring thickness. BACKGROUND
[0002] At present, the management and measurement of concrete floor thickness generally rely on two technical means, namely, the reinforcement bar observation method and the secondary hole opening method. However, these two methods have exposed a series of problems and deficiencies in the actual application process.
[0003] Specifically, although the reinforcement bar observation method can realize the preliminary control of floor thickness to a certain extent, its operation process is relatively complicated, and the technical level of the construction personnel is required to be high. At the same time, this method performs poorly in controlling the overall flatness of the floor, and it is difficult to ensure the uniformity and consistency of the floor thickness.
[0004] The secondary hole opening method is a post-measurement means after the completion of floor pouring. Although this method can intuitively obtain the data of floor thickness, it is easy to cause the risks of punching through the line pipe and damaging the floor structure during the hole opening process, thereby causing the quality problems such as floor leakage. In addition, the hole opening operation also increases the additional construction cost and construction period, and reduces the economic benefit of the project.
[0005] In summary, the existing concrete floor thickness control has certain limitations in practicability and economy. Moreover, it is not convenient for assisting the measurement of the thickness of the concrete floor in the later stage. SUMMARY
[0006] The utility model provides a concrete floor thickness control tool convenient for measuring thickness to solve the technical problem that the concrete floor thickness control in the prior art is poor in practicability and flexibility and inconvenient for assisting the measurement of the thickness of the concrete floor in the later stage.
[0007] To solve the above problems, the concrete floor thickness control tool convenient for measuring thickness provided by the utility model adopts the following technical scheme:
[0008] The bottom mold plate is provided with positioning columns at the four corners, PVC plastic pipes are slidably arranged outside the positioning columns, detachable positioning sleeves are arranged on the positioning columns, the positioning sleeves are above the PVC plastic pipes, and the lower surface of the positioning sleeve abuts against the upper surface of the PVC plastic pipe.
[0009] The network layer fixed and supported by the positioning sleeve is further included, and the network layer is used for limiting the thickness of the concrete floor. The positioning sleeve includes an inner sleeve pipe and an outer sleeve pipe rotatably arranged outside the inner sleeve pipe. One side of the outer sleeve pipe is provided with a connecting piece for fixing the network layer.
[0010] Further, the bottom outer wall of the inner sleeve is provided with an annular boss, and the inner wall of the outer sleeve is provided with an annular groove corresponding to the annular boss.
[0011] Further, the bottom surface of the outer sleeve is flush with the bottom surface of the inner sleeve, and the bottom surface of the inner sleeve abuts against the upper surface of the PVC plastic pipe.
[0012] Further, the network layer is a mesh structure formed by cotton threads, and connecting threads for external hanging are arranged at four corners.
[0013] The connecting piece is a lug arranged on one side of the outer sleeve, and the connecting piece is provided with a connecting hole.
[0014] Further, the bottom surface of the outer sleeve is provided with a lug for positioning the connecting thread, and the opening of the lug faces the PVC plastic pipe.
[0015] Further, the upper surface of the bottom of the lug is formed by a slope surface.
[0016] Further, the outer wall of the positioning column is provided with an external thread, the inner wall of the inner sleeve is provided with an internal thread, the inner sleeve is detachably sleeved on the positioning column through the threads, and the height of the inner sleeve on the positioning column is adjustable.
[0017] The concrete floor thickness control tool provided by the utility model has the beneficial effects that:
[0018] 1. The detachable PVC plastic pipe is arranged as a reference to assist in controlling the thickness of the concrete floor, and then is embedded into the concrete floor, so that the thickness of the concrete floor can be known by measuring the height of the PVC plastic pipe in the later period, and the convenience of measuring the concrete floor in the later period is improved.
[0019] 2. In the utility model, the PVC plastic pipes with different heights are slidably sleeved on the positioning column to adapt to concrete floors with different thicknesses, and the height of the inner sleeve can also be freely adjusted on the positioning column, so that the flexibility of thickness adaptation is further improved.
[0020] 3. In the utility model, the relative rotation design between the inner sleeve and the outer sleeve allows the outer sleeve and the connecting piece thereon to remain in a fixed position when the position of the inner sleeve is adjusted. This effectively avoids the problem of entanglement and interference of the connecting thread in the rotation process, and ensures the smooth progress of the adjustment work.
[0021] 4. In the utility model, the lug arranged on the bottom surface of the outer sleeve not only further assists in leveling the network layer, but also ensures the horizontal consistency of the network layer and the top end of the PVC plastic pipe. The accuracy of measuring the thickness of the concrete floor through the PVC plastic pipe in the later period is improved. BRIEF DESCRIPTION OF DRAWINGS
[0022] The above and other objects, features and advantages of the present application will become more apparent from the following detailed description read in conjunction with the accompanying drawings, in which several embodiments of the present application are illustrated. In the drawings, the same or corresponding parts are denoted by the same or corresponding reference numerals, and:
[0023] Figure 1 is a structural schematic view of the present application;
[0024] Figure 2 is a partial enlarged view of the area A shown in the figure; Figure 1
[0025] Figure 3 is a structural schematic view of the cooperation of the positioning column, the PVC plastic pipe and the positioning sleeve in the present application;
[0026] Figure 4 is a partial enlarged view of the area B shown in the figure; Figure 1
[0027] Figure 5 is a sectional view of the cooperation of the positioning column, the PVC plastic pipe and the positioning sleeve in the present application;
[0028] Figure 6 is a partial enlarged view of the area C shown in the figure. Figure 5
[0029] Explanation of reference numerals:
[0030] 1, base plate; 2, positioning column; 3, PVC plastic pipe; 4, positioning sleeve; 41, inner sleeve; 411, annular boss; 42, outer sleeve; 421, connecting piece; 421a, connecting hole; 422, annular groove; 43, hanging ear; 431, inclined surface; 5, network layer; 51, connecting line. DETAILED DESCRIPTION
[0031] The technical solutions in the embodiments of the present application will be described clearly and completely below with reference to the accompanying drawings in the embodiments of the present application. It should be known by those skilled in the art that the embodiments described below are only part of the embodiments of the present disclosure, rather than all the embodiments. Based on the embodiments in the present application, all other embodiments obtained by those skilled in the art without creative labor fall within the scope of protection of the present application.
[0032] Any number of elements in the drawings is used for example, not limitation, and any naming is only used for distinction, not having any limiting meaning.
[0033] The principles and spirits of the present application will be explained in detail below with reference to several representative embodiments of the present application.
[0034] The embodiment of the concrete floor thickness control tool convenient for measuring thickness provided by the utility model has the advantages that the PVC plastic pipe 3 is sleeved outside the positioning column 2, the positioning sleeve 4 is sleeved on the positioning column 2, the lower surface of the positioning sleeve 4 is in abutment with the upper surface of the PVC plastic pipe 3, and the network layer 5 is fixed and supported through the positioning sleeve 4.
[0035] As shown in the figure, it comprises a bottom formwork 1, positioning columns 2 are arranged at the four corners of the bottom formwork 1, PVC plastic pipes 3 are sleeved outside the positioning columns 2, detachable positioning sleeves 4 are sleeved on the positioning columns 2, the positioning sleeves 4 are above the PVC plastic pipes 3, and the lower surface of the positioning sleeve 4 is in abutment with the upper surface of the PVC plastic pipe 3. Figures 1 to 6 It further comprises a network layer 5 fixed and supported through the positioning sleeve 4, and the network layer 5 is used for limiting the thickness of the concrete floor.
[0036] Specifically, the PVC plastic pipe 3 is sleeved outside the positioning column 2 according to the requirement, wherein the height of the PVC plastic pipe 3 is the same as the thickness of the pre-poured concrete, then the four corners of the network layer 5 are fixed and supported through the four positioning sleeves 4 respectively, the network layer 5 serves as the boundary for controlling the thickness of the concrete floor, after the concrete floor to be poured is formed, the bottom formwork 1 is removed, and the pre-buried PVC plastic pipe 3 can be used as an auxiliary tool for measuring the thickness of the concrete floor in the later period.
[0037] In the embodiment, the outer wall of the positioning column 2 is provided with external threads, the inner wall of the inner sleeve 41 is provided with internal threads, and the inner sleeve 41 is detachably sleeved on the positioning column 2 through the threads and the height of the inner sleeve 41 on the positioning column 2 is adjustable.
[0038] The inner sleeve 41 and the positioning column 2 are matched through threads, on the one hand, the inner sleeve 41 can be conveniently detached from the positioning column 2, and on the other hand, the position of the inner sleeve 41 on the positioning column 2 can be adjusted according to the PVC plastic pipes 3 of different heights, so that the requirement of the concrete floor of different thicknesses can be met.
[0039] The positioning sleeve 4 comprises an inner sleeve 41 and an outer sleeve 42 rotatably arranged outside the inner sleeve 41. Specifically, the bottom outer wall of the inner sleeve 41 is provided with an annular boss 411, and the inner wall of the outer sleeve 42 is provided with an annular groove 422 corresponding to the annular boss 411. Through the cooperation of the annular boss 411 and the annular groove 422, on the one hand, the vertical position of the inner sleeve 41 and the outer sleeve 42 is positioned, and on the other hand, the relative rotation between the inner sleeve 41 and the outer sleeve 42 is realized.
[0040]
[0041] The outer sleeve 42 is provided with a connecting piece 421 for fixing the network layer 5 on one side. Through the relative rotation between the inner sleeve 41 and the outer sleeve 42, it can be ensured that the connecting piece 421 for fixing the network layer 5 can be fixed in a position when the inner sleeve 41 is in the rotation adjustment position. Avoiding the winding interference of the connecting wire 51 when the position of the inner sleeve 41 is adjusted.
[0042] The network layer 5 is a mesh structure formed by cotton threads, and the connecting wire 51 for external hanging is provided at the four corners. The connecting piece 421 is a lug provided on one side of the outer sleeve 42, and the connecting hole 421a is provided on the connecting piece 421.
[0043] The connecting wire 51 is fixed in the connecting hole 421a by knotting. The network layer 5 is pulled flat by the four corners, which is convenient for assisting in controlling the thickness of the concrete floor.
[0044] The bottom surface of the outer sleeve 42 is flush with the bottom surface of the inner sleeve 41, and the bottom surface of the outer sleeve 42 is in abutment with the upper surface of the PVC plastic pipe 3.
[0045] The connecting piece 421 for fixing the network layer 5 can be fixed in a position
[0046] In this embodiment, the bottom surface of the outer sleeve 42 is provided with a lug 43 for positioning the connecting wire 51, and the opening of the lug 43 faces the PVC plastic pipe 3.
[0047] The upper surface of the bottom of the lug 43 forms a slope surface 431.
[0048] The lug 43 further assists in pulling the network layer 5 flat, and also assists in achieving that the top end of the network layer 5 and the PVC plastic pipe 3 are in the same horizontal plane. The accuracy of measuring the thickness of the concrete floor through the PVC plastic pipe 3 in the later stage is improved.
[0049] In addition, through the structural design of the slope surface 431, the connecting wire 51 is assisted to be clamped into the lug 43.
[0050] In the specific use of the concrete floor thickness control tool for facilitating thickness measurement of the embodiment, the PVC plastic pipe 3 is sleeved on the positioning column 2 according to the thickness of the pre-poured concrete floor, and then the connecting wire 51 of the network layer 5 is fixed in the connecting hole 421a, and then the position of the positioning sleeve 4 is adjusted by rotation, so that the lower surface of the positioning sleeve 4 is in abutment with the upper surface of the PVC plastic pipe 3. Then pull the connecting wire 51 to assist in tensioning the network layer 5. After pouring, the bottom formwork 1 is disassembled, and the pre-buried PVC plastic pipe 3 is an auxiliary tool for measuring the thickness of the plate in the later stage.
[0051] According to the above description of the present specification, those skilled in the art can also understand that the terms used such as "upper", "lower", "front", "rear", "left", "right", "width", "horizontal", "top", "bottom", "inner", "outer" and the like indicating the orientation or positional relationship are based on the orientation or positional relationship shown in the drawings of the present specification, which are only for the purpose of facilitating the description of the scheme of the present application and simplifying the description, and are not explicitly or implicitly indicated that the devices or elements involved must have the specific orientation, be constructed and operated in a specific orientation, therefore the above orientation or positional relationship terms cannot be understood or interpreted as a limitation on the scheme of the present application.
[0052] In addition, in the description of the present specification, the meaning of "a plurality of" is at least two, such as two, three or more, etc., unless otherwise explicitly and specifically limited.
Claims
1. A concrete floor thickness control tool for facilitating the measurement of thickness comprising a base template (1) characterised in that, The bottom template (1) is provided with positioning columns (2) at four corners, the positioning columns (2) are externally sleeved with PVC plastic pipes (3), the positioning columns (2) are sleeved with detachable positioning sleeves (4), the positioning sleeves (4) are above the PVC plastic pipes (3), and the lower surface of the positioning sleeves (4) abuts against the upper surface of the PVC plastic pipes (3); Further comprising a network layer (5) fixed and supported by the positioning sleeves (4), the network layer (5) is used for limiting the thickness of the concrete floor slab, the positioning sleeve (4) comprises an inner sleeve pipe (41) and an outer sleeve pipe (42) rotatably arranged outside the inner sleeve pipe (41), and one side of the outer sleeve pipe (42) is provided with a connecting piece (421) used for fixing the network layer (5).
2. The concrete floor thickness control tool for facilitating thickness measurement of claim 1, wherein, The bottom outer wall of the inner sleeve pipe (41) is provided with an annular boss (411), and the inner wall of the outer sleeve pipe (42) is provided with an annular groove (422) corresponding to the annular boss (411).
3. The concrete floor thickness control tool for facilitating thickness measurement of claim 1, wherein, The bottom surface of the outer sleeve pipe (42) is flush with the bottom surface of the inner sleeve pipe (41), and the bottom surface of the inner sleeve pipe (41) abuts against the upper surface of the PVC plastic pipe (3).
4. The concrete floor thickness control tool for facilitating thickness measurement of claim 3, wherein, The network layer (5) is a grid structure formed by cotton threads, and is provided with connecting threads (51) used for external hanging at four corners. The connecting piece (421) is a lug arranged on one side of the outer sleeve pipe (42), and the connecting piece (421) is provided with a connecting hole (421a).
5. The concrete floor thickness control tool for facilitating thickness measurement of claim 4, wherein, The bottom surface of the outer sleeve pipe (42) is provided with a lug (43) used for positioning the connecting thread (51), and the opening of the lug (43) faces the PVC plastic pipe (3).
6. The concrete floor thickness control tool for facilitating thickness measurement of claim 5, wherein, The upper surface of the bottom of the lug (43) is formed by a slope surface (431).
7. The concrete floor thickness control tool for facilitating thickness measurement of claim 1, wherein, The outer wall of the positioning column (2) is provided with external threads, the inner wall of the inner sleeve pipe (41) is provided with internal threads, and the inner sleeve pipe (41) is detachably sleeved on the positioning column (2) through the threads and the height of the inner sleeve pipe (41) on the positioning column (2) is adjustable.