Precise-control mounting and fixing device for cooling pipe of bearing platform
By using a combination of adjusting screws and clamps inside the steel profile, the problems of slow installation speed and unstable fixing of the cooling pipes in the foundation were solved, achieving efficient and precise support point fixing and reducing construction complexity and cost.
Patent Information
- Application Number
- CN202422482511.3
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-10-15
- Publication Date
- 2025-12-05
- Estimated Expiration
- 2034-10-15
AI Technical Summary
The existing installation and fixing of cooling pipes on the foundation has problems such as slow installation speed, difficulty in adjusting brackets, difficulty in aligning with the elevation point, difficulty in binding and insecure fixation, and high cost.
An adjusting screw with a threaded connection inside the steel profile is used, and a clamp is connected to the cantilever end. By rotating the adjusting screw, the distance between the clamp and the steel profile is changed, thereby fixing the fulcrum of the cooling pipe. The clamp is used for clamping, and precise positioning is achieved by combining the adjusting nut and the set screw.
It improves construction efficiency, prevents cooling pipes from tilting or moving during use, simplifies the fulcrum fixing process, and reduces construction complexity and cost.
Smart Images

Figure CN223630587U_ABST
Abstract
Description
TECHNICAL FIELD
[0001] The utility model belongs to the support platform cooling pipe installation fulcrum fixing technical field especially relates to a support platform cooling pipe precision control installation fixing device. BACKGROUND
[0002] For the support platform bulk concrete installation cooling pipe, the current technical method for fixing the cooling pipe installation fulcrum is according to the actual situation on site, erecting profile steel and bracket welding, bracket and the installed cooling pipe steel binding, which has the disadvantages that the communication of construction personnel is not smooth, the spirit and physical consumption are big, and the efficiency is low.
[0003] The bracket height is easily influenced by site environment, error is big, and there is much repeated labor, when large area construction, the workload is big, such as the accurate lofting of the fulcrum position of each row of cooling pipes, the control difficulty is big, such as the accurate control of the fulcrum elevation of cooling pipe, the steel wire binding of cooling pipe is easy to fall off, such as the steel wire is easy to fall off in the process of pouring concrete and vibrating, the steel wire is easy to fall off in the process of the first time water adding of cooling pipe, and the operation of such method is complex, needs many people to cooperate measurement, the measurement positioning error is big, the cooling pipe fulcrum fixing step is complex, and the steel wire binding is easy to fall off.
[0004] Therefore, the current support platform cooling pipe installation fixing has the conditions of slow installation and use speed, bracket adjustment difficulty, not easy to directly aim at the elevation point, bracket and cooling pipe binding difficulty, not easy to fix firmly and high cost. SUMMARY
[0005] The utility model embodiment aims at providing a support platform cooling pipe precision control installation fixing device, and aims at solving the technical problem of the current support platform cooling pipe installation fixing having the conditions of slow installation and use speed, bracket adjustment difficulty, not easy to directly aim at the elevation point, bracket and cooling pipe binding difficulty, not easy to fix firmly and high cost.
[0006] The utility model embodiment is realized as follows:
[0007] A support platform cooling pipe precision control installation fixing device, the precision control installation fixing device includes the adjusting screw of screwing in the profile steel, the cantilever end of adjusting screw is connected with the clamp of fixing cooling pipe, and rotating adjusting screw can change the position of clamp distance profile steel.
[0008] Further, the clamp includes left side hoop and right side hoop, the end of left side hoop is equipped with left ear seat, the end of right side hoop is equipped with right ear seat, left ear seat and right ear seat are connected together through bolt, and are fastened by nut.
[0009] Further, the middle part of right side hoop is connected with the adjusting screw, and the adjusting screw is screwing in the threaded hole of profile steel.
[0010] Further, the outer side of the adjusting screw is threadedly connected with an adjusting nut, and the side surface of the adjusting nut is in contact with the surface of the profile steel.
[0011] Further, the middle part of the hoop is welded with a connecting sleeve, and the connecting sleeve is sleeved on the end of the adjusting screw.
[0012] Further, the wall of the connecting sleeve is provided with a threaded hole, and a clamping screw is threadedly connected in the threaded hole, and when the adjusting screw and the adjusting nut are adjusted, the clamping screw is tightened to realize the fixed connection of the right hoop and the adjusting screw.
[0013] The positive effect of the utility model is: through the adjusting screw which is threadedly connected in the profile steel, the cantilever end of the adjusting screw is connected with the hoop which fixes the cooling pipe, the original bracket is replaced with the hoop and the adjusting screw, the support point of the cooling pipe is fixed, the inclination and movement of the cooling pipe in the use process are prevented, the construction efficiency is improved, the support point fixing device is erected, the distance between the hoop and the profile steel is changed through rotating the adjusting screw to realize the control of the support point position of the cooling pipe, the cooling pipe is clamped by the hoop, and the support point position of the cooling pipe is inspected, and the adjusting screw is rotated to change the distance between the hoop and the profile steel to eliminate the deviation. BRIEF DESCRIPTION OF DRAWINGS
[0014] Figure 1 It is a structural schematic diagram of a bearing platform cooling pipe precision control installation fixing device.
[0015] Figure 2 It is Figure 1 It is an enlarged view of E of the utility model of a bearing platform cooling pipe precision control installation fixing device shown in the figure.
[0016] Legend: 1 - concrete bearing platform, 2 - cooling pipe, 3 - left hoop, 4 - bolt, 5 - left ear seat, 6 - right ear seat, 7 - nut, 8 - right hoop, 9 - adjusting nut, 10 - profile steel, 11 - adjusting screw, 12 - connecting sleeve, 13 - clamping screw. DETAILED DESCRIPTION
[0017] The utility model will be described in detail in combination with the drawings and specific embodiments:
[0018] In the description of the utility model, it is understood that the orientation or positional relationship indicated by the terms "center", "longitudinal", "transverse", "length", "width", "thickness", "upper", "lower", "front", "rear", "left", "right", "vertical", "horizontal", "top", "bottom", "inner", "outer", "clockwise", "counterclockwise", "axial", "radial", "circumferential" is based on the orientation or positional relationship shown in the drawings, and is only for the convenience of describing the utility model and simplifying the description, and therefore cannot be understood as limiting the utility model.
[0019] In order to make the purpose, technical scheme and advantages of the utility model clearer and more apparent, the utility model will be further described in detail below in combination with the drawings and examples.
[0020] As Figure 1 and Figure 2 shown, a structure diagram of a bearing platform cooling pipe precision control installation fixing device provided by the utility model embodiment, including the adjusting screw rod that is screwed in the section steel, the cantilever end of the adjusting screw rod is connected with the hoop that fixes the cooling pipe, and the hoop distance section steel position can be changed by rotating the adjusting screw rod.
[0021] In the utility model embodiment, the cantilever end of the adjusting screw rod that is screwed in the section steel is connected with the hoop that fixes the cooling pipe, the original bracket is replaced with the hoop and adjusting screw rod, the fulcrum fixing of the cooling pipe is realized, the inclination, movement and other conditions in the cooling pipe use process are prevented, the construction efficiency is improved, the fulcrum fixing device is erected, the fulcrum position control of the cooling pipe is realized by rotating the adjusting screw rod and changing the hoop distance section steel position, then the cooling pipe is clamped with the hoop, the fulcrum position of the cooling pipe is inspected, and the adjusting screw rod can be rotated to change the hoop distance section steel position and eliminate the deviation if there is deviation.
[0022] Specifically, as Figure 1 and Figure 2 shown, a bearing platform cooling pipe precision control installation fixing device includes the adjusting screw rod 11 that is screwed in the section steel, the cantilever end of the adjusting screw rod is connected with the hoop that fixes the cooling pipe, and the hoop distance section steel position can be changed by rotating the adjusting screw rod.
[0023] The hoop includes the left side hoop 3 and the right side hoop 8, the end of the left side hoop 3 is provided with the left ear seat 5, the end of the right side hoop 8 is provided with the right ear seat 6, the left ear seat 5 and the right ear seat 6 are connected together through the bolt 4 and are fastened by the nut 7.
[0024] The middle part of the right side hoop 8 is connected with the adjusting screw 11, and the adjusting screw is threadedly connected in the threaded hole of the section steel 10;
[0025] The outer side of the adjusting screw 11 is threadedly connected with the adjusting nut 9, and the side surface of the adjusting nut 9 is in contact with the surface of the section steel 10; when the adjusting screw 11 is rotated, the position of the adjusting nut on the adjusting screw 11 is changed, so that the position adjustment and fixation of the adjusting screw 11 are realized;
[0026] The middle part of the right side hoop is welded with the connecting sleeve 12, and the connecting sleeve 12 is sleeved on the end part of the adjusting screw 11; when the adjusting screw 11 is rotated, the connecting sleeve 12 is movably connected with the end part of the adjusting screw 11, so that the direction of the hoop can be kept unchanged;
[0027] Preferably, the wall of the connecting sleeve 12 is provided with a threaded hole, and the threaded hole is threadedly connected with the fixing screw 13; when the adjustment of the adjusting screw 11 and the adjusting nut 9 is completed, the fixing screw 13 is tightened, so that the fixed connection of the right side hoop 8 and the adjusting screw 11 is realized;
[0028] Preferably, the connecting sleeve 12 is threadedly connected with the adjusting screw; when the adjustment of the adjusting screw 11 and the adjusting nut 9 is completed, if the right side hoop 8 is twisted with the cooling pipe 2, that is, the axis of the cooling pipe 2 and the axis of the right side hoop 8 do not coincide or have a tendency of not coinciding, the adjustment can be realized through the thread connection between the connecting sleeve 12 and the adjusting screw.
[0029] Such design realizes:
[0030] The erection of the section steel and the adjustable connection of the adjusting screw can realize the adjustment of the fixed device, and after the replacement of the fixed device, the weight of the fixed device is about 1 / 6 of the original, and the volume is about 1 / 3 of the original;
[0031] The hoop is selected to be clamped, one hoop is arranged every 90cm in each row, and the two ends of the hoop are fixed by 3cm thick fixing screws; after the installation of the fulcrum fixing device, the lifting adjustment on the section steel can be realized, and this can be realized through the position of the threaded hole in the section steel matched with the adjusting screw, and a plurality of dry threaded holes can be arranged; the section steel is internally provided with the adjusting screw with a diameter of 10mm and a length of 12cm, and the adjustment and accurate alignment of the target point are realized through the adjusting nut.
[0032] The original bracket is replaced by the hoop and the adjusting screw, the fulcrum of the cooling pipe is fixed, the inclination and movement of the cooling pipe in the use process are prevented, and the construction efficiency is improved.
[0033] After the erection of the fulcrum fixing device, the position control of the fulcrum of the cooling pipe is realized through the adjustment of the adjusting nut and the adjusting screw, the cooling pipe hoop is clamped, and when the position of the fulcrum of the cooling pipe is inspected to be deviated, the deviation can be eliminated through the adjustment of the adjusting nut and the adjusting screw.
[0034] The foregoing has outlined some of the more pertinent aspects and features of the various embodiments. This description serves as a basis for the subsequent claims. Other aspects and features of the disclosure will become apparent to those skilled in the art from a consideration of the description or from practice of the embodiments as disclosed herein. It is the intent of the inventors that variations and modifications be made to the embodiments in light thereof to the full extent of the scope of the claims.
[0035] The above embodiment has made a detailed description of the present application. Of course, the above description is not a limitation of the present application, and the present application is not limited to the above examples. Changes, modifications, additions or reductions, and replacements made by related technical personnel within the essential scope of the present application also belong to the protection scope of the present application.
Claims
1. A precision installation fixing device for cooling pipes of a pile cap, characterized in that, The fine control mounting fixing device comprises an adjusting screw threadedly connected in the section steel, a clamping hoop for fixing the cooling pipe connected at the cantilever end of the adjusting screw, and the distance between the clamping hoop and the section steel can be changed by rotating the adjusting screw.
2. The fixed installation device for the cooling pipe of the bearing platform according to claim 1, characterized in that, The clamping hoop comprises a left clamping hoop and a right clamping hoop, the end of the left clamping hoop is provided with a left ear seat, the end of the right clamping hoop is provided with a right ear seat, the left ear seat and the right ear seat are connected by bolts, and are fastened by nuts.
3. The cooling pipe installation fixing device according to claim 2, wherein The middle part of the right clamping hoop is connected with the adjusting screw, and the adjusting screw is threadedly connected in the threaded hole of the section steel.
4. The fixed installation device for the cooling pipe of the bearing platform according to claim 3, characterized in that, The outer side of the adjusting screw is threadedly connected with an adjusting nut, and the side surface of the adjusting nut is in contact with the surface of the section steel.
5. The fixed installation device for the precision control of the cooling pipe of the pile cap according to any one of claims 1 to 4, characterized in that, The middle part of the clamping hoop is welded with a connecting sleeve, and the connecting sleeve is sleeved at the end of the adjusting screw.
6. The fixed installation device for the cooling pipe of the bearing platform according to claim 5, characterized in that, The wall of the connecting sleeve is provided with a threaded hole, a locking screw is threadedly connected in the threaded hole, and when the adjusting of the adjusting screw and the adjusting nut is completed, the locking screw is tightened to realize the fixed connection of the right clamping hoop and the adjusting screw.