The design of the track-type pipe clamp solves the problems of low installation efficiency and high noise of existing pipe clamps, and realizes an efficient and civilized pipe installation process.

CN223635553UActive Publication Date: 2025-12-05浙江中财管道科技股份有限公司
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202520377523.1
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2025-03-05
Publication Date
2025-12-05
Estimated Expiration
2035-03-05

AI Technical Summary

Technical Problem

The existing method of installing pipes on the ground using pipe clamps is inefficient and generates a lot of construction noise, which affects construction efficiency and civilized construction practices.

Method used

The pipe clamps are rail-type and consist of a guide rail, a sliding mounting base, and the clamp body. They are fixed to the ground by the guide rail, and the sliding mounting base can be adjusted. The clamps are used to fix the pipes, reducing drilling into the ground and noise.

Benefits of technology

It improves pipeline installation efficiency, reduces construction noise, achieves civilized construction, and facilitates the addition or reduction of pipeline quantity as needed.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN223635553U_ABST
    Figure CN223635553U_ABST
Patent Text Reader

Abstract

The utility model discloses a track type pipeline clamp which comprises a guide rail, a sliding installation seat and a pipe clamp body, installation plates capable of being fixed on the ground are fixedly connected to the lower sides of the two ends of the guide rail, installation holes are formed in the installation plates, a sliding groove is formed in the upper side of the guide rail in the length direction, and the end of the sliding groove penetrates through the end of the guide rail. The sliding block is connected in the sliding groove in a sliding mode, the pull rod is fixedly connected with the sliding block and vertically penetrates through a groove opening of the sliding groove, the pipe clamp body comprises a split bolt and a hoop body capable of tightly holding a pipeline, the hoop body is arranged on the upper side of the pull rod, the split bolt penetrates through the lower side of the hoop body and is in threaded connection with the pull rod, and the lower side of the hoop body abuts against the upper side of the guide rail. According to the rail type pipeline clamp, the installation efficiency is improved, and the construction noise is reduced.
Need to check novelty before this filing date? Find Prior Art

Description

TECHNICAL FIELD

[0001] The utility model relates to pipeline installation technical field, especially track type pipeline pipe clamp. BACKGROUND

[0002] The pipe clamp for ground installation pipeline, especially the pipe clamp for ground heating pipeline, needs to arrange a plurality of pipelines on the ground, the above-mentioned pipeline needs to be fixed by a plurality of pipe clamps, the pipe clamps are independent of each other, and each pipe clamp is fixed on the ground by expansion screws, which affects construction efficiency on the one hand and causes large noise when expansion screws are screwed on the ground, easily disturbs people and is not conducive to civilized construction. CONTENT OF THE UTILITY MODEL

[0003] The utility model discloses a track type pipeline pipe clamp to improve installation efficiency and reduce construction noise.

[0004] To achieve the above-mentioned purpose, the utility model adopts the following technical scheme:

[0005] A track type pipeline pipe clamp, comprising a guide rail, a sliding mounting seat and a pipe clamp body, the lower side of both ends of the guide rail is fixedly connected with an installation plate that can be fixed on the ground, the installation plate is provided with an installation hole, the upper side of the guide rail is provided with a sliding groove along the length direction, the end of the sliding groove penetrates the end of the guide rail, the sliding mounting seat comprises a sliding block and a pull rod, the sliding block is slidingly connected in the sliding groove, the pull rod is fixedly connected with the sliding block and vertically penetrates the slot of the sliding groove, the pipe clamp body comprises a draw bolt, a clamp body that can tightly hold the pipeline, the clamp body is arranged on the upper side of the pull rod, the draw bolt penetrates the lower side of the clamp body and is threadedly connected with the pull rod, and the lower side of the clamp body abuts against the upper side of the guide rail.

[0006] Through the above-mentioned arrangement, first, the pipe clamp installation is more efficient, second, when installing, only the both ends of the guide rail need to be fixed on the ground, the noise is smaller when fixing the pipeline by the pipe clamp body, and the construction is more civilized, third, the sliding mounting seat can slide freely on the guide rail, facilitating the adjustment of the position of the pipe clamp body, and fourth, the number of the sliding mounting seat can be freely increased or decreased according to the number of the pipeline.

[0007] Further, the clamp body comprises a lower pipe clamp, an upper pipe clamp and a fastener, the lower pipe clamp abuts against the upper side of the guide rail, the fastener penetrates the lower pipe clamp and is threadedly connected with the upper end of the pull rod, and the upper pipe clamp is arranged above the lower pipe clamp and connected with the both ends of the lower pipe clamp through the fastener.

[0008] Through the above-mentioned arrangement, the fastener is tightened, and the upper pipe clamp and the lower pipe clamp tightly hold the pipeline.

[0009] Further, the slider is a cylindrical structure, the slot width of the sliding slot is less than the outer diameter of the slider, the pull rod comprises a first rod segment and a second rod segment, the outer diameter of the first rod segment is equal to the slot width of the sliding slot, the first rod segment vertically penetrates the slot of the sliding slot and is fixedly connected with the slider, the outer diameter of the second rod segment is greater than the outer diameter of the first rod segment, the second rod segment is fixedly connected to the upper end of the first rod segment, the lower side of the lower pipe clamp is provided with a groove, the second rod segment is arranged in the groove, and the draw bolt is threadedly connected with the second rod segment.

[0010] Further, the lower side of the lower pipe clamp is provided with a circular arc surface, and the circular arc surface is attached to the upper side of the guide rail.

[0011] Further, the end cover is arranged at the both ends of the guide rail to block the end of the sliding slot.

[0012] Through the above arrangement, the transportation of the sliding mounting base is facilitated.

[0013] Further, the mounting plate is fixedly connected to the lower side of the both ends of the guide rail through the stand column, and the mounting plate is provided with a connecting hole.

[0014] Through the above arrangement, the mounting plate is fixed to the ground.

[0015] Further, the guide rail is made of aluminum alloy.

[0016] Through the above arrangement, the guide rail is prevented from rusting. DETAILED DESCRIPTION

[0017] Fig. 1 It is a schematic view of the pipe clamp of the embodiment.

[0018] Fig. 2 It is an exploded view of the pipe clamp of the embodiment.

[0019] Fig. 3 It is a partial sectional view of the pipe clamp of the embodiment.

[0020] Fig. 4 It is a schematic view of the pipe clamp of the embodiment. DETAILED DESCRIPTION

[0021] The technical scheme of the present application will be further specifically explained below by means of embodiments and in combination with the drawings.

[0022] As Figs. 1 to 4As shown, a rail type pipeline pipe clamp comprises a guide rail 3, a sliding mounting base 4 and a pipe clamp body 5. The lower side of the two ends of the guide rail 3 is fixedly connected with mounting plates 6 which can be fixed on the ground. The mounting plates 6 are provided with mounting holes 7. The upper side of the guide rail 3 is provided with a sliding groove 8 along the length direction. The end of the sliding groove 8 penetrates the end of the guide rail 3. The sliding mounting base 4 comprises a sliding block 41 and a pull rod 42. The sliding block 41 is slidingly connected in the sliding groove 8. The pull rod 42 is fixedly connected with the sliding block 41 and vertically penetrates the slot of the sliding groove 8. The pipe clamp body 5 comprises a tension bolt 51 and a clamp body 52 which can tightly hold the pipeline. The clamp body 52 is arranged on the upper side of the pull rod 42. The tension bolt 51 penetrates the lower side of the clamp body 52 and is threadedly connected with the pull rod 42. The lower side of the clamp body 52 abuts against the upper side of the guide rail 3.

[0023] Through the above arrangement, first, the installation of the pipe clamp is more efficient. Second, when installing, only the two ends of the guide rail 3 need to be fixed on the ground. The noise is smaller when fixing the pipeline by the pipe clamp body 5, and the construction is more civilized. Third, the sliding mounting base 4 can freely slide on the guide rail 3, which facilitates the adjustment of the position of the pipe clamp body 5. Fourth, the number of the sliding mounting bases 4 can be freely increased or decreased according to the number of pipelines.

[0024] When the pipe clamp of the present application is used, the two ends of the guide rail 3 are horizontally fixed on the ground through the mounting plates 6. The mounting plates 6 can be fixed on the ground through expansion screws. The sliding mounting base 4 can freely enter and exit the sliding groove 8 through the end of the sliding groove 8, so as to adjust the number of the sliding mounting bases 4. Specifically, according to the number of pipelines to be fixed, the corresponding number of sliding mounting bases 4 are slid into the sliding groove 8. The sliding mounting base 4 can only make linear motion along the sliding groove 8 and cannot rotate around the axis of the sliding groove 8. Then the clamp body 52 is installed on the upper end of the pull rod 42 through the tension bolt 51. At this time, the tension bolt 51 is not tightened, the lower side of the clamp body 52 is not pressed on the upper side of the guide rail 3, and the sliding mounting base 4 and the clamp body 52 can freely slide along the sliding groove 8. After the sliding mounting base 4 is slid to the desired position, the tension bolt 51 is tightened. The bolt head at the upper end of the tension bolt 51 presses the clamp body 52 on the upper side of the guide rail 3, and the position of the sliding mounting base 4 and the clamp body 52 is locked. After the pipeline passes through the clamp body 52, the clamp body 52 tightly holds the pipeline. Thus, one pipeline is fixed. When more pipelines need to be fixed, the above steps can be repeated. One sliding mounting base 4 is slid into the sliding groove 8, and one pipeline can be fixed. During the process of fixing the pipeline, expansion screws do not need to be punched, the construction is more efficient, the construction noise is smaller, and the construction is more civilized.

[0025] As an implementation manner, the clamp body 52 comprises a lower pipe clamp 521, an upper pipe clamp 522 and a fastener 523. The lower pipe clamp 521 abuts against the upper side of the guide rail 3. The fastener 523 penetrates the lower pipe clamp 521 and is threadedly connected with the upper end of the pull rod 42. The upper pipe clamp 522 is arranged above the lower pipe clamp 521. The two ends of the upper pipe clamp 522 are connected with the two ends of the lower pipe clamp 521 through the fastener 523.

[0026] Through the above setting, the upper pipe clamp 522 and the lower pipe clamp 521 hold the pipe tightly by tightening the fastener 523.

[0027] The upper pipe clamp 522 and the lower pipe clamp 521 of the present application are both circular arc shapes, and the openings are opposite. The radii of the upper pipe clamp 522 and the lower pipe clamp 521 are adapted to the outer diameter of the pipe to be fixed. When fixing the pipe, the inner side of the upper pipe clamp 522 is attached to the upper side of the pipe, and the inner side of the lower pipe clamp 521 is attached to the lower side of the pipe. The draw bolt 51 vertically penetrates the middle part of the lower pipe clamp 521 and is threadedly connected with the draw bar 42. The middle part of the lower pipe clamp 521 is provided with a avoiding slot, and the bolt head of the draw bolt 51 is hidden in the avoiding slot. The fastener 523 specifically adopts bolts or screws and the like, which are used to tighten the two ends of the upper pipe clamp 522 and the lower pipe clamp 521, so as to hold the pipe tightly by the upper pipe clamp 522 and the lower pipe clamp 521.

[0028] As an implementation manner, the sliding block 41 is a cylindrical structure, the slot width of the sliding groove 8 is less than the outer diameter of the sliding block 41, the draw bar 42 includes a first rod segment 421 and a second rod segment 422, the outer diameter of the first rod segment 421 is equal to the slot width of the sliding groove 8, the first rod segment 421 vertically penetrates the slot of the sliding groove 8 and is fixedly connected with the sliding block 41, the outer diameter of the second rod segment 422 is greater than that of the first rod segment 421, the second rod segment 422 is fixedly connected to the upper end of the first rod segment 421, the lower side of the lower pipe clamp 521 is provided with a groove 524, and the second rod segment 422 is arranged in the groove 524. The draw bolt 51 is threadedly connected with the second rod segment 422.

[0029] The first rod segment 421 and the second rod segment 422 of the present application are coaxially arranged. Since the inner thread for connecting with the draw bolt 51 needs to be arranged in the second rod segment 422, the second rod segment 422 needs to be thicker to ensure the strength. The first rod segment 421 is mainly used for the transmission of the tension force between the second rod segment 422 and the sliding block 41, and can be thinner than the second rod segment 422.

[0030] As an implementation manner, the lower side of the lower pipe clamp 521 is provided with a circular arc surface 9, which is attached to the upper side of the guide rail 3.

[0031] As an implementation manner, the end caps 10 are arranged at the two ends of the guide rail 3 to block the ends of the sliding groove 8.

[0032] Through the above setting, the transportation of the sliding mounting seat 4 is facilitated.

[0033] When the pipe clamp of the present application is transported, the sliding mounting seat 4 can be slid into the sliding groove 8 in advance, thereby saving the transportation volume. The ends of the sliding groove 8 are blocked by the end caps 10 to prevent the sliding mounting seat 4 from sliding out of the sliding groove 8.

[0034] As an implementation manner, the mounting plate 6 is fixedly connected to the lower sides of the two ends of the guide rail 3 through the stand columns 11, and the mounting plate 6 is provided with connecting holes 12.

[0035] Through the above setting, the mounting plate 6 is conveniently fixed on the ground.

[0036] The connecting hole 12 of the application is circular in particular, facilitating the mounting plate 6 to be fixed on the ground through expansion screws.

[0037] As an implementation manner, the guide rail 3 is made of aluminum alloy.

[0038] Through the above setting, the guide rail 3 is prevented from rusting.

[0039] It should be understood that, for those skilled in the art, improvements or changes can be made according to the above description, and all these improvements and changes shall belong to the protection scope of the appended claims of the utility model.

Claims

1. A rail-type pipe clamp, characterized by, The utility model provides a pipe clamp, including guide rail, sliding mounting base and pipe clamp body, the lower side fixed connection of both ends of guide rail can be fixed on the mounting plate of ground, be provided with mounting hole on the mounting plate, the upper side of guide rail is provided with the sliding slot along the length direction, the sliding slot end penetrates the end of guide rail, the sliding mounting base includes sliding block and pull rod, the sliding block is connected in the sliding slot, the pull rod is fixedly connected with sliding block, and vertically penetrates the notch of sliding slot, the pipe clamp body includes the pull bolt with the clamp body of can embrace the pipeline, the clamp body sets up the upper side of pull rod, the pull bolt penetrates the lower side of clamp body and is connected with pull rod screw, and the lower side of clamp body is opposite with the upper side of guide rail.

2. A rail pipe clamp according to claim 1, wherein, The clamp body includes lower pipe clamp, upper pipe clamp and fastener, the lower pipe clamp is opposite with the upper side of guide rail, the fastener penetrates the lower pipe clamp and is connected with the upper end of pull rod screw, the upper pipe clamp is set up above the lower pipe clamp, and the upper pipe clamp both ends are connected with the both ends of lower pipe clamp through fastener.

3. A rail pipe clamp according to claim 2, wherein, The sliding block is cylindrical structure, the notch width of sliding slot is less than the outer diameter of sliding block, the pull rod includes first rod segment and second rod segment, the outer diameter of first rod segment is equal to the notch width of sliding slot, the first rod segment vertically penetrates the notch of sliding slot and is fixedly connected with sliding block, the outer diameter of second rod segment is greater than the outer diameter of first rod segment, the second rod segment is fixedly connected on the upper end of first rod segment, the lower side of lower pipe clamp is provided with recess, the second rod segment is set up in recess, and the pull bolt is connected with second rod segment screw.

4. A rail pipe clamp according to claim 1, wherein, The lower side of lower pipe clamp is provided with circular arc surface and is attached with the upper side of guide rail.

5. A rail pipe clamp according to claim 1, wherein, The both ends cover of guide rail is provided with end cover to block the end of sliding slot.

6. A rail pipe clamp according to claim 1, wherein, The mounting plate is fixedly connected in the lower side of both ends of guide rail through stand column, and be provided with connecting hole on the mounting plate.