Waterproof and mildew-proof wall body structure for hotel bathroom

By employing a multi-layered structural design and expansion screw connections in the hotel bathroom walls, the problem of dampness and mold growth caused by water seepage through cement grouting was solved, achieving waterproofing, mold prevention, and easy maintenance.

CN223675605UActive Publication Date: 2025-12-16何康喜
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202520059978.9
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2025-01-10
Publication Date
2025-12-16
Estimated Expiration
2035-01-10

AI Technical Summary

Technical Problem

Existing waterproof wall structures in hotel bathrooms are prone to water seepage through cement grout during use. Prolonged moisture penetration leads to dampness and mold growth on the walls, and the walls are difficult to maintain once damaged.

Method used

It adopts a multi-layer structure design, including a concrete base layer, a heat insulation layer, a sound insulation layer, a thermal insulation layer, and a waterproof layer. It is connected to the spliced ​​waterproof layer by expansion screw sleeves, and the waterproof ceramic tile board and the connecting strip are fixed by expansion screws, which facilitates the replacement of damaged parts.

Benefits of technology

It achieves waterproof, mildew-proof, and soundproof effects, while facilitating the replacement of damaged parts, reducing the impact of external temperature on the bathroom interior, and preventing moisture penetration that could cause dampness and mold growth on the walls.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN223675605U_ABST
    Figure CN223675605U_ABST
Patent Text Reader

Abstract

The utility model belongs to the technical field of waterproof walls, and particularly relates to a hotel bathroom waterproof and mildew-proof wall structure which comprises a concrete base layer, a heat insulation layer is arranged at the left end of the concrete base layer, a sound insulation layer is arranged at the left end of the heat insulation layer, a heat preservation layer is arranged at the left end of the sound insulation layer, and an anti-permeation layer is arranged at the left end of the heat preservation layer. According to the utility model, the three-way connecting block, the two-way connecting block, the four-way connecting block, the waterproof connecting strip I, the waterproof connecting strip II, the expansion screw and the expansion screw sleeve are matched with one another, so that the waterproof ceramic tile plate can be conveniently taken down from the impermeable layer when the waterproof ceramic tile plate is damaged in the use process of the wall body; and then the damaged waterproof ceramic tile plate can be conveniently replaced, the waterproof effect of the wall is prevented from being affected, and therefore the situation that an existing wall structure is inconvenient to maintain when damaged can be effectively solved through the device.
Need to check novelty before this filing date? Find Prior Art

Description

TECHNICAL FIELD

[0001] The utility model belongs to waterproof wall body technical field, concretely relates to a hotel bathroom waterproof mildew wall body structure. BACKGROUND

[0002] The hotel bathroom is usually used for people to take a bath, which makes the bathroom relatively humid, so a hotel bathroom waterproof wall body structure is needed to avoid the internal wall of the hotel bathroom from being damp and mildewed for a long time.

[0003] Problems of prior art:

[0004] The existing hotel bathroom waterproof wall body structure is prone to water seepage during use, and the water vapor seeps in for a long time, which can easily cause the wall to be damp and mildewed, and it is not convenient to maintain the wall after it is damaged. INVENTION CONTENTS

[0005] The utility model discloses a hotel bathroom waterproof mildew wall body structure, which can solve the problems of the existing hotel bathroom waterproof wall body structure, such as water seepage during use, water vapor seepage for a long time, wall dampness and mildew, and inconvenient maintenance after wall damage.

[0006] The technical scheme adopted by the utility model is as follows:

[0007] A hotel bathroom waterproof mildew wall body structure includes a concrete base layer, a heat insulation layer is arranged at the left end of the concrete base layer, a sound insulation layer is arranged at the left end of the heat insulation layer, a thermal insulation layer is arranged at the left end of the sound insulation layer, a permeation prevention layer is arranged at the left end of the thermal insulation layer, and the permeation prevention layer is screw-connected with a spliced waterproof layer through a plurality of expansion screws sleeves arranged inside.

[0008] Four limiting blocks are arranged at the left end of the concrete base layer, and the four limiting blocks are clamped with the heat insulation layer having four limiting holes arranged inside the right end.

[0009] The heat insulation layer is clamped with the middle part of four connecting protrusions one through the fitting grooves arranged inside the upper and lower ends, and the four connecting protrusions one are clamped with the concrete base layer and the sound insulation layer having two connecting grooves arranged inside the upper and lower ends.

[0010] The sound insulation layer is clamped with one end of four connecting protrusions two through the two other connecting grooves arranged inside the upper and lower ends, and the other end of the four connecting protrusions two is clamped with the thermal insulation layer having two connecting grooves arranged inside the upper and lower ends.

[0011] The heat preservation layer is connected with the four other connecting protrusions two through two other connecting grooves arranged in the upper and lower ends, and the other ends of the four other connecting protrusions two are connected with the anti-permeation layer with connecting grooves arranged in the upper and lower ends, and the connecting grooves and the embedded grooves are filled with sealing glue.

[0012] The spliced waterproof layer comprises four waterproof ceramic tile plates, and four plug-in plates are fixedly connected to the four outer side walls of the four waterproof ceramic tile plates.

[0013] Eight plug-in plates are connected with eight waterproof connection strips two, two splicing grooves are arranged in the front end of the four waterproof connection strips one and the eight waterproof connection strips two, and a through hole is arranged in each splicing groove.

[0014] The opposite close ends of the four waterproof connection strips one are spliced through four four-way connecting blocks, and the opposite far ends of the four waterproof connection strips one are spliced with one end of the eight waterproof connection strips two through four three-way connecting blocks.

[0015] The other ends of the eight waterproof connection strips two are spliced through four double-way connecting blocks, the splicing ends of the double-way connecting blocks, the three-way connecting blocks and the four-way connecting blocks are provided with expansion screws, the expansion screws are subjected to waterproof and rustproof treatment, and each expansion screw is threadedly connected with a corresponding expansion screw sleeve through the through hole arranged in the corresponding splicing groove.

[0016] The right ends of the waterproof ceramic tile plate, the waterproof connection strip one, the waterproof connection strip two, the double-way connecting block, the three-way connecting block and the four-way connecting block are tightly combined with the left end of the anti-permeation layer.

[0017] The utility model discloses obtain the technical effect for:

[0018] This utility model, through the coordinated arrangement of a three-way connecting block, a two-way connecting block, a four-way connecting block, a waterproof connecting strip one, a waterproof connecting strip two, expansion screws, and expansion screw sleeves, allows for easy removal of damaged waterproof ceramic tiles from the anti-seepage layer during use. This facilitates convenient replacement of damaged tiles, preventing any impact on the wall's waterproofing effect. This device effectively solves the problem of inconvenient maintenance of existing wall structures when damaged. The coordinated arrangement of the insulation and heat-insulating layers not only provides insulation for the bathroom interior but also effectively reduces the impact of external temperatures on the bathroom's internal temperature. The coordinated arrangement of the waterproof and anti-seepage layers ensures excellent waterproofing while preventing moisture penetration into the wall, effectively preventing dampness and mold growth after prolonged use. The inclusion of a sound-insulating layer further enhances the wall's functionality by providing sound insulation. Attached Figure Description

[0019] Figure 1 This is a front-view three-dimensional structural schematic diagram of the present invention;

[0020] Figure 2 This is an exploded view of the structure in this utility model;

[0021] Figure 3 This is a front-view three-dimensional structural diagram of the spliced ​​waterproof layer in this utility model;

[0022] Figure 4 This is an exploded view of the spliced ​​waterproof layer structure in this utility model;

[0023] Figure 5 This is a front-view three-dimensional structural diagram of the heat insulation board in this utility model;

[0024] Figure 6 This is a schematic diagram of the main three-dimensional structure of the concrete base layer in this utility model;

[0025] Figure 7 This is a front-view three-dimensional structural schematic diagram of the anti-penetration layer in this utility model;

[0026] Figure 8 This is a front-view three-dimensional structural schematic diagram of the insulation layer in this utility model;

[0027] Figure 9 This is a front-view three-dimensional structural schematic diagram of the sound insulation layer in this utility model.

[0028] The attached diagram lists the components represented by each number as follows:

[0029] 1, concrete base layer; 2, heat insulation layer; 3, sound insulation layer; 4, heat preservation layer; 5, impermeable layer; 6, spliced waterproof layer; 61, waterproof ceramic tile board; 62, waterproof connecting strip two; 63, double-pass connecting block; 64, expansion screw; 65, waterproof connecting strip one; 66, four-way connecting block; 67, three-way connecting block; 68, plug-in board; 7, connecting groove; 8, fitting groove; 9, expansion screw sleeve; 10, limiting block; 11, connecting protrusion one; 12, connecting protrusion two; 13, limiting hole. DETAILED DESCRIPTION

[0030] In order to make the purpose and advantages of the utility model more clear and obvious, the utility model is specifically described below in combination with examples. It should be understood that the following text is only used to describe one or several specific embodiments of the utility model, and does not strictly limit the specific protection scope requested by the utility model.

[0031] As Figures 1-9 shown, a hotel bathroom waterproof and mildew-proof wall structure, including concrete base layer 1, the left end of concrete base layer 1 is provided with heat insulation layer 2, the left end of heat insulation layer 2 is provided with sound insulation layer 3, the left end of sound insulation layer 3 is provided with heat preservation layer 4, the left end of heat preservation layer 4 is provided with impermeable layer 5, impermeable layer 5 is screw-connected with spliced waterproof layer 6 through multiple expansion screw sleeves 9 arranged in the interior thereof, the mutual cooperation between heat insulation layer 2 and heat preservation layer 4 can effectively reduce the influence of external temperature on the temperature inside the bathroom under the premise of playing the heat preservation of the interior of the hotel bathroom, the mutual cooperation between impermeable layer 5 and spliced waterproof layer 6 arranged can achieve the effects of waterproof and water vapor penetration prevention, the sound insulation layer 3 arranged can make the wall have good sound insulation effect.

[0032] Further, the left end of the concrete base 1 is provided with four limiting blocks 10, the four limiting blocks 10 are clamped with the heat insulation layer 2 which is internally provided with four limiting holes 13 at the right end, the heat insulation layer 2 is clamped with the middle part of the four connecting protrusions one 11 through the fitting grooves 8 which are internally provided at the upper and lower ends of the heat insulation layer 2, the four connecting protrusions one 11 are clamped with the concrete base 1 and the sound insulation layer 3 which are internally provided with two connecting grooves 7 at the upper and lower ends, the sound insulation layer 3 is clamped with the four connecting protrusions two 12 through the other two connecting grooves 7 which are internally provided at the upper and lower ends of the sound insulation layer 3, the other end of the four connecting protrusions two 12 is clamped with the thermal insulation layer 4 which is internally provided with two connecting grooves 7 at the upper and lower ends, the thermal insulation layer 4 is clamped with the four other connecting protrusions two 12 through the other two connecting grooves 7 which are internally provided at the upper and lower ends of the thermal insulation layer 4, the other end of the four other connecting protrusions two 12 is clamped with the anti-permeation layer 5 which is internally provided with connecting grooves 7 at the upper and lower ends, the inside of each connecting groove 7 and fitting groove 8 is filled with sealant, the connecting protrusions one 11 and connecting protrusions two 12 can make the connection between the concrete base 1, sound insulation layer 3, thermal insulation layer 4, heat insulation layer 2 and anti-permeation layer 5 more stable.

[0033] Further, the spliced waterproof layer 6 comprises four waterproof ceramic tile plates 61, the four outer side walls of the four waterproof ceramic tile plates 61 are fixedly connected with plug-in plates 68, the eight plug-in plates 68 in the inside are respectively clamped with four waterproof connecting strips one 65 which are provided with two insertion grooves in the inside, the eight plug-in plates 68 on the outer side are respectively clamped with eight waterproof connecting strips two 62 which are provided with another insertion groove in the inside, the eight waterproof connecting strips two 62 and the front ends of the four waterproof connecting strips one 65 are respectively provided with two splicing grooves, and the inside of each splicing groove is provided with a through hole, the opposite close ends of the four waterproof connecting strips one 65 are spliced through four four-way connecting blocks 66, the opposite distant ends of the four waterproof connecting strips one 65 are spliced with one end of the eight waterproof connecting strips two 62 through four three-way connecting blocks 67, the other end of the eight waterproof connecting strips two 62 is spliced through the four double-way connecting blocks 63, the splicing ends of the double-way connecting blocks 63, the three-way connecting blocks 67 and the four-way connecting blocks 66 are provided with expansion screws 64, and each expansion screw 64 is respectively screwed with a corresponding expansion screw sleeve 9 through the through hole in the inside of the corresponding splicing groove, the right ends of each waterproof ceramic tile plate 61, waterproof connecting strip one 65, waterproof connecting strip two 62, double-way connecting block 63, three-way connecting block 67 and four-way connecting block 66 are tightly attached to the left end of the impermeable layer 5, the expansion screw 64 is separated from the corresponding expansion screw sleeve 9 through the setting of the rotating expansion screw 64, so that the spliced waterproof layer 6 can be conveniently taken off from the impermeable layer 5, the waterproof ceramic tile plate 61, the waterproof connecting strip one 65, the waterproof connecting strip two 62, the plug-in plate 68, the double-way connecting block 63, the three-way connecting block 67 and the four-way connecting block 66 are spliced, so that the damaged waterproof ceramic tile plate 61 can be conveniently replaced during the use of the waterproof ceramic tile plate 61, thereby avoiding the damage of the waterproof ceramic tile plate 61 and affecting the waterproof effect of the wall body, and the wall body is conveniently maintained.

[0034] The working principle of the utility model is:

[0035] The mutual cooperation between the spliced waterproof layer 6 and the anti-permeation layer 5 can effectively prevent the water and steam generated in the bathroom from entering the wall body, thereby avoiding the wall body from being damp and moldy. The mutual cooperation between the thermal insulation layer 4, the sound insulation layer 3 and the heat insulation layer 2 can achieve the effects of thermal insulation and sound insulation. When the spliced waterproof layer 6 is damaged during use, the expansion screw 64 on the spliced waterproof layer 6 is removed from the inside of the corresponding expansion screw sleeve 9, and then the spliced waterproof layer 6 is removed from the anti-permeation layer 5. After the damaged part is replaced and reassembled, the expansion screw 64 and the expansion screw sleeve 9 are cooperated to reinstall the spliced waterproof layer 6 on the anti-permeation layer 5, thereby completing the maintenance of the spliced waterproof layer 6.

[0036] The above is only the preferred embodiment of the present application, and it should be pointed out that for those skilled in the art, without departing from the principles of the present application, a number of improvements and refinements can be made, and these improvements and refinements should be considered as the protection scope of the present application. The structures, devices and operation methods not specifically described and explained in the present application are implemented according to the conventional means in the art, unless otherwise specified and limited.

Claims

1. A waterproof and mildew-proof wall structure for a hotel bathroom, comprising a concrete base layer (1), characterized in that: The left end of the concrete base (1) is provided with a heat insulation layer (2), the left end of the heat insulation layer (2) is provided with a sound insulation layer (3), the left end of the sound insulation layer (3) is provided with a heat preservation layer (4), the left end of the heat preservation layer (4) is provided with a anti-permeable layer (5), the anti-permeable layer (5) is threadedly connected with a spliced waterproof layer (6) through a plurality of expansion screw sleeves (9) arranged in the anti-permeable layer (5).

2. A waterproof and mildew-proof wall structure for a hotel bathroom according to claim 1, characterized in that: The left end of the concrete base (1) is provided with four limiting blocks (10), and the four limiting blocks (10) are clamped with the heat insulation layer (2) which is internally provided with four limiting holes (13) at the right end.

3. A waterproof and mold-proof wall structure for a hotel bathroom according to claim 2, characterized in that: The heat insulation layer (2) is clamped with the middle part of the four first connecting protrusions (11) through the fitting grooves (8) arranged at the upper and lower ends of the heat insulation layer (2), and the four first connecting protrusions (11) are clamped with the concrete base (1) and the sound insulation layer (3) which are internally provided with two connecting grooves (7) at the upper and lower ends.

4. A bathroom waterproof and mildew-proof wall structure for a hotel according to claim 3, characterized in that: The sound insulation layer (3) is clamped with one end of the four second connecting protrusions (12) through the two other connecting grooves (7) arranged at the upper and lower ends of the sound insulation layer (3), and the other end of the four second connecting protrusions (12) is clamped with the heat preservation layer (4) which is internally provided with two connecting grooves (7) at the upper and lower ends.

5. A bathroom waterproof and mildew-proof wall structure for a hotel according to claim 4, characterized in that: The heat preservation layer (4) is clamped with one end of the four other second connecting protrusions (12) through the two other connecting grooves (7) arranged at the upper and lower ends of the heat preservation layer (4), and the other end of the four other second connecting protrusions (12) is clamped with the anti-permeable layer (5) which is internally provided with connecting grooves (7) at the upper and lower ends, and the inner part of each connecting groove (7) and fitting groove (8) is filled with sealant.

6. A waterproof and mold-proof wall structure for a hotel bathroom according to claim 1, characterized in that: The spliced waterproof layer (6) comprises four waterproof ceramic tile boards (61), and the four outer side walls of the four waterproof ceramic tile boards (61) are fixedly connected with four plug-in plates (68), and the inner part of the eight plug-in plates (68) is clamped with the four waterproof connecting strips (65) which are internally provided with two plug-in grooves.

7. A bathroom waterproof and mildew-proof wall structure for a hotel according to claim 6, characterized in that: The outer eight plug-in plates (68) are clamped with the eight waterproof connecting strips (62) which are internally provided with another plug-in groove, and the front end of the eight waterproof connecting strips (62) and the four waterproof connecting strips (65) are provided with two spliced grooves, and the inner part of each spliced groove is provided with a through hole.

8. A waterproof and mold-proof wall structure for a hotel bathroom according to claim 7, characterized in that: The opposite close ends of the four waterproof connecting strips (65) are spliced through the four four-way connecting blocks (66), and the opposite far ends of the four waterproof connecting strips (65) are spliced with one end of the eight waterproof connecting strips (62) through the four three-way connecting blocks (67).

9. A bathroom waterproof and mildew-proof wall structure of a hotel according to claim 8, characterized in that: The other end of the eight waterproof connecting strips (62) is spliced through the four double-way connecting blocks (63), and the spliced ends of the double-way connecting blocks (63), the three-way connecting blocks (67) and the four-way connecting blocks (66) are provided with expansion screws (64), and each expansion screw (64) is threadedly connected with the corresponding expansion screw sleeve (9) through the through hole arranged in the inner part of the corresponding spliced groove.

10. A waterproof and mold-proof wall structure for a hotel bathroom according to claim 9, characterized in that: The right end of each of the waterproof ceramic tile board (61), the waterproof connecting strip one (65), the waterproof connecting strip two (62), the double-pass connecting block (63), the three-pass connecting block (67) and the four-pass connecting block (66) is tightly attached to the left end of the impermeable layer (5).