Temporary suspension device of wharf cast-in-place cross beam or abutment template supporting system
By using suspension units composed of spreader beams and positioning blocks in dock construction to replace the main beams suspended by lifting equipment, the problem of long-term occupation of large lifting equipment was solved, and construction efficiency and equipment utilization were improved.
Patent Information
- Application Number
- CN202520046266.3
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2025-01-09
- Publication Date
- 2025-12-26
- Estimated Expiration
- 2035-01-09
AI Technical Summary
When the tide level is high, existing technology requires the use of large lifting equipment to occupy the formwork support system for a long time, resulting in low construction efficiency and unreasonable equipment occupation, which affects the construction progress in other areas.
A suspension unit consisting of a spreader beam, positioning blocks, and lifting lugs is adopted. The main beam is suspended by a hand-operated hoist, and the elevation is adjusted using positioning blocks and drive components, which replaces the lifting equipment to temporarily suspend the main beam, forming a temporary suspension system.
This avoids the prolonged occupation of large lifting equipment, improves construction efficiency, and is applicable to various types of PHC pipe piles, achieving reasonable synchronization of equipment use and construction progress.
Smart Images

Figure CN223723690U_ABST
Abstract
Description
TECHNICAL FIELD
[0001] The utility model relates to wharf construction technical field, concretely is a kind of temporary suspension device of wharf cast-in-place crossbeam or pier platform formwork support system. BACKGROUND
[0002] The formwork support stress form of wharf crossbeam or pier cast-in-place construction generally has two ways of hoop and hanging rib, the hoop way is installed in pile body by hoop at certain elevation, relies on the friction with pile body to bear external load, the hanging rib way is that round steel is placed on pile top, end is welded with profile steel girder, relies on the support force of pile top and the strength of round steel to bear external load.
[0003] When tidal level is higher, hoop way is not suitable, at this time, hanging rib form is more suitable.The main girder of the formwork support system of wharf crossbeam or pier cast-in-place construction is generally H-shaped steel, when selecting hanging rib as the stress structure of formwork support system, main girder H-shaped steel needs to be lifted and installed by hoisting equipment, until after hanging rib installation reinforcement is completed, hoisting equipment can be removed, but, large hoisting equipment needs to be used all the time in this process, in the process of on-site construction, large hoisting equipment is very few, long time occupation of large hoisting equipment will delay the construction process of other areas, makes large hoisting equipment not be used reasonably, reduces the total construction efficiency, and overall economy is poor. UTILITY MODEL CONTENTS
[0004] In order to solve the problems of the prior art, the utility model provides a kind of temporary suspension device of wharf cast-in-place crossbeam or pier platform formwork support system, can replace hoisting equipment and temporarily hang main girder, avoid long time occupation of large hoisting equipment.
[0005] To achieve the above object, the utility model provides the following technical scheme: a kind of temporary suspension device of wharf cast-in-place crossbeam or pier platform formwork support system, including multiple for suspending main girder's suspension unit, the suspension unit includes pole beam, the positioning block for inserting the top of PHC pipe pile, the lifting lug fixedly connected at the both ends of the pole beam, the positioning block is fixedly connected in the middle of pole beam.
[0006] Using the above structure design, when large hoisting equipment is lifted to the installation position of PHC pipe pile, main girder can be hung at the both ends of pole beam by lifting lug, and large hoisting equipment can be removed, to avoid long time occupation of large hoisting equipment.
[0007] Preferably, the lifting lug is hung with hand-operated hoist.
[0008] Using the above structure design, main girder is lifted by hand-operated hoist, and its elevation is adjusted, main girder is adjusted to the height of mark, and finally the connection and installation of hanging rib and main girder profile steel are completed.
[0009] Preferably, the suspension unit is provided in two groups, the adjacent flat beam is fixedly connected through a cross beam, the cross beam is provided with a plurality of and symmetrically arranged at both ends of the flat beam, a fixing bolt is arranged on the cross beam, and a through hole matched with the cross beam is formed on the flat beam.
[0010] The above structure is adopted to connect the suspension units with each other, so that the flat beam is prevented from being disturbed under the action of external force.
[0011] Preferably, the positioning block comprises a first positioning plate fixedly connected to the flat beam, a second positioning plate slidably connected to the flat beam, and a driving assembly for driving the first positioning plate to slide on the flat beam, the driving assembly comprises a first hinged rod and a second hinged rod which are hingedly connected at the middle portion, a first sliding block hingedly connected to the upper end of the first hinged rod, a second sliding block hingedly connected to the upper end of the second hinged rod, and a driving screw threadedly arranged on the first sliding block, the upper end of the driving screw being rotatably connected to the flat beam, the lower end of the first hinged rod being hingedly connected to the first positioning plate, and the lower end of the second hinged rod being hingedly connected to the second positioning plate.
[0012] The above structure is adopted, the driving assembly can adjust the distance between the first positioning plate and the second positioning plate according to the diameter of the PHC pipe pile, the outer side walls of the first positioning plate and the second positioning plate abut against the inner wall of the PHC pipe pile, the device is stably connected to the top end of the PHC pipe pile, the flat beam is prevented from being disturbed under the action of external force, and the device can be applied to most models of PHC pipe piles.
[0013] Compared with the prior art, the device has the following beneficial effects:
[0014] 1) The device can replace the hoisting equipment to temporarily suspend the main beam, and adjust the main beam to the elevation, so that the large hoisting equipment can be reasonably used, and the total construction efficiency is improved.
[0015] 2) The device can be applied to most models of PHC pipe piles. BRIEF DESCRIPTION OF DRAWINGS
[0016] Figure 1 The structure schematic view for construction use of the device is shown in the figure;
[0017] Figure 2 The structure schematic view for construction use of the device is shown in the figure;
[0018] Figure 3 The structure schematic view for construction use of the device is shown in the figure; DETAILED DESCRIPTION
[0019] Please refer to Figure 1 , Figure 2 , Figure 3This utility model provides a technical solution: a temporary suspension device for a formwork support system for cast-in-place crossbeams or piers at wharves, including multiple suspension units for suspending the main beam. Each suspension unit includes a spreader beam 1, a positioning block 2 for inserting into the top of a PHC pipe pile 7, and lifting lugs 3 fixedly connected to both ends of the spreader beam 1. The positioning block 2 is fixedly connected to the middle of the spreader beam 1.
[0020] In one embodiment of this utility model, the positioning block 2 is cylindrical, and the diameter of the positioning block 2 is equal to the inner diameter of the PHC pipe pile. After the positioning block 2 is inserted into the top of the PHC pipe pile, it can restrict the spreader beam 1. When the main beam is suspended on the end of the spreader beam 1, the main beam can be suspended at both ends of the spreader beam 1 at the same time, or the main beam can be suspended on one side of the spreader beam 1.
[0021] The middle part of the upper surface of the spreader beam 1 is fixedly connected to the lifting ring 6 for connecting the lifting device.
[0022] The hook on the lifting lug 3 is used to hang the hand-operated hoist 4.
[0023] The suspension unit is provided in two sets, with adjacent spreader beams 1 fixedly connected by crossbeams 5. Multiple crossbeams 5 are provided and symmetrically arranged at both ends of the spreader beams 1, such as... Figure 1 As shown, the spreader beam 1 and the crossbeam 5 form a rectangular frame structure. Fixing bolts 51 are installed on the crossbeam 5, and through holes matching those on the spreader beam 1 are formed on the crossbeam 5. Multiple through holes for the fixing bolts 51 are formed on the crossbeam 5, allowing workers to adjust the position of the spreader beam 1 on the crossbeam 5 according to the distance between adjacent PHC pipe piles.
[0024] The positioning block comprises a first positioning plate 21 fixedly connected to the beam 1, a second positioning plate 22 slidably connected to the beam 1, and a driving assembly for driving the first positioning plate 21 to slide on the beam 1. The driving assembly comprises a first hinged rod 201 and a second hinged rod 202 hingedly connected to each other in the middle, a first sliding block 203 hingedly connected to the upper end of the first hinged rod 201, a second sliding block 204 hingedly connected to the upper end of the second hinged rod 202, and a driving screw 205 threaded through the first sliding block 203. The upper end of the driving screw 205 is rotatably connected to the beam 1, and the upper end of the driving screw 205 is not threaded. The first sliding block 203 is slidably connected to the second positioning plate 22, and the second positioning plate 22 is provided with a first sliding groove matched with the first sliding block 203. The second sliding block 204 is slidably connected to the first positioning plate 21, and the first positioning plate 21 is provided with a second sliding groove matched with the second sliding block 204. The lower end of the first hinged rod 201 is hingedly connected to the first positioning plate 21, and the lower end of the second hinged rod 202 is hingedly connected to the second positioning plate 22. The upper end of the driving screw 205 passes through the beam 1 upwardly, and the upper end of the driving screw 205 is rotatably connected to the beam 1. The upper end of the driving screw 205 is fixedly connected to a hand wheel for facilitating rotation of the driving screw 205.
[0025] Working principle: first, the operator rotates the hand wheel to make the first sliding block 203 slide, and the first hinged rod 203 and the second hinged rod 204 contract or expand, so that the distance between the first positioning plate 21 and the second positioning plate 22 matches the inner diameter of the PHC pipe pile. Then, the operator places the temporary suspension device on the top of the PHC pipe pile 7 by using the lifting equipment to hoist the lifting ring 6, and inserts the positioning block 2 into the hole of the PHC pipe pile 7. The temporary suspension device is placed on the top of two PHC pipe piles 7 in the same row to ensure that two or more lifting points are formed on the same side. After the suspension device is placed, the main beam is hoisted below the suspension device by using the lifting equipment, and then the main beam is hoisted by the hoist connected to the hand-operated hoist 4, forming a temporary suspension system. At this time, the lifting equipment for hoisting the main beam can be removed, and the steel is adjusted to the preset position and elevation by the hand-operated hoist 4. After the formwork support system is formed by using the lifting rib and other methods, the hand-operated hoist 4 is loosened, and the temporary suspension device is removed for use in the next working face.
[0026] The structure, proportion, size and the like shown in the drawings of the specification are only used to cooperate with the content disclosed in the specification, to be understood and read by those skilled in the art, and do not have technical substantial meaning, and any modification of the structure, change of the proportion relationship or adjustment of the size, without affecting the effects and purposes that can be achieved by the utility model, should still fall within the scope of the technical content disclosed by the utility model. Meanwhile, the terms such as "upper", "lower", "left", "right", "middle" and "one" and the like cited in the specification are only for the convenience of clear description, and are not used to limit the scope of the utility model, and the change or adjustment of the relative relationship, without substantially changing the technical content, is also regarded as the scope of the utility model.
[0027] The utility model has been described above with reference to the preferred embodiments, but the protection scope of the utility model is not limited thereto, and all the technical solutions falling within the scope of the claims are within the protection scope of the utility model. Various improvements can be made and the components therein can be replaced with equivalents without departing from the scope of the utility model. In particular, as long as there is no structural conflict, each technical feature mentioned in each embodiment can be combined in any manner.
Claims
1. A temporary suspension device for a wharf cast-in-place beam or pier formwork support system, characterised in that: The application relates to a suspension unit for suspending a main beam, which comprises a flat beam (1), a positioning block (2) for being inserted into the top end of a PHC pipe pile, and a lifting lug (3) fixedly connected to the two ends of the flat beam (1), wherein the positioning block (2) is fixedly connected to the middle part of the flat beam (1).
2. A temporary suspension device for a wharf cast-in-place beam or pier formwork support system according to claim 1, characterised in that: A hand chain hoist (4) is hung on the lifting lug (3).
3. A temporary suspension device for a wharf cast-in-place beam or pier formwork support system according to claim 1, characterised in that: Two groups of the suspension units are arranged, adjacent flat beams (1) are fixedly connected through a cross beam (5), a plurality of the cross beams (5) are symmetrically arranged at the two ends of the flat beam (1), a fixing bolt (51) is arranged on the cross beam (5), and a through hole matched with the cross beam (5) is formed in the flat beam (1).
4. A temporary suspension device for a wharf cast-in-place beam or pier formwork support system according to any one of claims 1 to 3, characterised in that: The positioning block comprises a first positioning plate (21) fixedly connected to the flat beam (1), a second positioning plate (22) slidably connected to the flat beam (1), and a driving assembly for driving the first positioning plate (21) to slide on the flat beam (1), wherein the driving assembly comprises a first hinged rod (201) and a second hinged rod (202) which are hingedly connected to each other in the middle part, a first sliding block (203) hingedly connected to the upper end of the first hinged rod (201), a second sliding block (204) hingedly connected to the upper end of the second hinged rod (202), a driving screw (205) threadedly arranged on the first sliding block (203), the upper end of the driving screw (205) being rotatably connected to the flat beam (1), the lower end of the first hinged rod (201) being hingedly connected to the first positioning plate (21), and the lower end of the second hinged rod (202) being hingedly connected to the second positioning plate (22).