Supporting device for installation of cast-in-place pile pouring guide pipe

By using a disc support and working platform mechanism in the construction of cast-in-place piles, the problems of large vibration of the pouring guide pipe and limited working surface in ultra-thick sand layers were solved, thus improving the construction quality and safety.

CN223723754UActive Publication Date: 2025-12-26GUANGZHOU CONSTRUCTION ENGINEERING CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202520012159.9
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2025-01-02
Publication Date
2025-12-26
Estimated Expiration
2035-01-02

AI Technical Summary

Technical Problem

When constructing cast-in-place piles in ultra-thick sand layers, the large vibration amplitude of the pouring guide pipe, the limited working surface, and serious safety hazards pose significant challenges. Existing technologies cannot effectively solve the problems of construction quality, efficiency, and safety.

Method used

The support device, which includes a steel casing, a disc support mechanism, and a working platform mechanism, is used to fix the pouring pipe twice through the first and second guide holes, thereby reducing the vibration amplitude and providing additional working space and safety protection.

Benefits of technology

It effectively reduces vibration of the pouring pipe, increases working space, improves construction efficiency, ensures construction safety, and reduces safety hazards.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN223723754U_ABST
    Figure CN223723754U_ABST
Patent Text Reader

Abstract

The utility model relates to a supporting device for installation of a cast-in-place pile pouring guide pipe. The supporting device comprises a steel casing, a disc supporting mechanism, an operation platform mechanism and the pouring guide pipe. The disc supporting mechanism comprises a supporting ring frame and a first clamping plate, the supporting ring frame is installed at an upper hole opening of the steel casing, the first clamping plate is connected with the supporting ring frame, a first guide pipe hole is formed in the first clamping plate, and the first clamping plate can cover an inner opening of the supporting ring frame; the operation platform mechanism comprises a platform supporting frame and a second clamping plate, the platform supporting frame is arranged on the supporting ring frame, the second clamping plate is connected with the platform supporting frame, a second guide pipe hole is formed in the second clamping plate, the pouring guide pipe penetrates through the first guide pipe hole and the second guide pipe hole at the same time, and the pouring guide pipe can be fixed through the first guide pipe hole and the second guide pipe hole. The utility model belongs to the technical field of cast-in-place pile construction.
Need to check novelty before this filing date? Find Prior Art

Description

TECHNICAL FIELD

[0001] The utility model relates to the field of cast-in-place pile construction technology, and particularly relates to a supporting device for cast-in-place pile pouring guide pipe installation. BACKGROUND

[0002] In building engineering, especially in the case of high bearing capacity requirement and complex geological conditions, cast-in-place piles are constructed in the foundation pit. Before the foundation pit is excavated, a steel casing is driven into the original ground. After the steel casing is vibrated into place by a vibrating machine, the position of the bottom surface of the steel casing is the position of the bottom surface of the foundation pit. After the silt in the steel casing is removed, a pouring guide pipe is installed for pouring. For cast-in-place pile construction in super-thick sand layers, the traditional cast-in-place pile construction method faces many challenges due to the special geological conditions. Specifically, the following problems exist:

[0003] First, the pouring guide pipe vibration problem: super-thick sand layers have high permeability and low cohesion, which makes any disturbance during construction likely to cause instability of the stratum, thereby affecting construction quality and efficiency. During the pouring of cast-in-place piles, the vibrations generated by pouring equipment (such as concrete pump trucks and vibrators) can be transmitted to the surrounding sand layer. Due to the loose structure and easy movement of the sand layer, under the action of vibration, it will be directly transmitted to the pouring guide pipe through the fixing device of the pouring guide pipe, causing the guide pipe to vibrate with a large amplitude. For super-thick sand layers, this vibration effect is particularly pronounced, because the instability of the sand layer easily amplifies the influence of vibration, and a large vibration amplitude of the pouring guide pipe will adversely affect the pouring operation.

[0004] Second, the operation surface limitation: there is often not enough operation space around the opening of the steel casing, making it difficult for the operating personnel to effectively complete the installation and removal of the guide pipe. This not only increases the construction difficulty, but also negatively affects the construction efficiency.

[0005] Third, the lack of safety protection: after the pouring of cast-in-place piles in the steel casing is completed, the top of some cast-in-place piles may be lower than the original ground, and the upper part of the steel casing is empty and not poured. If effective protective measures are not taken in time at the opening of the steel casing, there is a high risk of accidents, such as personnel falling into the steel casing hole, causing personal injury accidents. This not only threatens the safety of the personnel on site, but also may delay the progress of the entire project.

[0006] In summary, the current technology and equipment are obviously unable to fully meet the actual engineering requirements in view of the above-mentioned problems existing in the construction process of cast-in-place piles in super-thick sand layers. Especially, while ensuring construction quality and improving work efficiency, the safety of the construction site also needs to be ensured, which is one of the key problems to be solved at present. UTILITY MODEL CONTENT

[0007] The technical problems existing in the prior art are solved, and the purpose of the utility model is to provide a support device for pouring pile pouring guide pipe installation, which has a double fixing and supporting effect on the pouring guide pipe, reduces the vibration amplitude of the pouring guide pipe, and is beneficial to the smooth pouring of the pouring pile.

[0008] In order to achieve the above purpose, the utility model adopts the following technical scheme:

[0009] A support device for pouring pile pouring guide pipe installation, including steel casing, disc support mechanism, operation platform mechanism and pouring guide pipe, the disc support mechanism includes support ring frame and first clamping plate, the support ring frame is installed at the orifice of the steel casing, the first clamping plate is connected with the support ring frame, the first clamping plate is provided with first guide pipe hole, and the first clamping plate can cover the inner mouth of the support ring frame, the operation platform mechanism includes platform support frame and second clamping plate, the platform support frame is arranged on the support ring frame, the second clamping plate is connected with the platform support frame, the second clamping plate is provided with second guide pipe hole, the pouring guide pipe passes through the first guide pipe hole and the second guide pipe hole at the same time, and the first guide pipe hole and the second guide pipe hole can fix the pouring guide pipe.

[0010] As a kind of preferred, first clamping plate includes two first half clamping plates, two first half clamping plates are respectively hinged with support ring frame, first half clamping plate inside is provided with first circular arc gap, and two first half clamping plates are spliced after covering the inner mouth of support ring frame and first guide pipe hole is formed by two first circular arc gaps.

[0011] As a kind of preferred, second clamping plate includes two second half clamping plates, two second half clamping plates are respectively hinged with platform support frame, second half clamping plate inside is provided with second circular arc gap, and two second half clamping plates are spliced and second guide pipe hole is formed by two second circular arc gaps.

[0012] As a kind of preferred, support ring frame bottom surface is provided with circular groove, and the circular groove is embedded in the outer periphery of the orifice of the steel casing.

[0013] As a kind of preferred, platform support frame includes one support plate and two step-shaped groove frames, two step-shaped groove frames are fixedly connected through support plate, support plate is provided with round hole for pouring guide pipe to pass through, one second half clamping plate is hinged with one step-shaped groove frame, and the other second half clamping plate is hinged with the other step-shaped groove frame;Platform support frame is erected on support ring frame, the bottom of step-shaped groove frame is provided with step, and the upper portion of support ring frame is provided with inner groove, and the step is embedded in the inner groove.

[0014] As a kind of preferred, step is circular arc, and inner groove is circular.

[0015] As a kind of preferred, the main materials of support ring frame, first half clamping plate, platform support frame, second half clamping plate and pouring guide pipe are all steel.

[0016] As a preferred, the first half clamping plate is provided with a first handle, and the second half clamping plate is provided with a second handle.

[0017] The utility model has the advantages that:

[0018] (1) The supporting device is provided with a disc supporting mechanism and an operation platform mechanism, the first guide pipe hole of the disc supporting mechanism and the second guide pipe hole of the operation platform mechanism double limit and fix the pouring guide pipe, effectively reducing the vibration amplitude of the pouring guide pipe, and being beneficial to pouring operation.

[0019] (2) The disc supporting mechanism is arranged on the orifice of the steel casing, and the operation personnel can walk and operate on the first half clamping plate, thereby increasing the operation space compared with the prior art.

[0020] (3) The disc supporting mechanism is arranged, the supporting ring frame is installed at the orifice of the steel casing, the two first half clamping plates are hingedly connected with the supporting ring frame, the two first half clamping plates are laid flat and spliced to cover the orifice in the supporting ring frame, the orifice of the steel casing is covered by the disc supporting mechanism, and personnel falling into the steel casing through the orifice is prevented. BRIEF DESCRIPTION OF DRAWINGS

[0021] In order to more clearly illustrate the technical scheme in the embodiments of the utility model or the prior art, the drawings needed to be used in the embodiment or the prior art description will be briefly introduced below, and obviously, the drawings in the following description are only some embodiments of the utility model, and those skilled in the art can also obtain other drawings according to these drawings without creating creative labor.

[0022] Fig. 1 It is a structural schematic view of the supporting device during installation of the utility model.

[0023] Fig. 2 It is a sectional view of the supporting device after installation of the utility model is completed.

[0024] Fig. 3 It is a top view of the connection between the supporting ring frame and the first half clamping plate of the utility model.

[0025] Wherein, 1, steel casing;2, pouring guide pipe;3, supporting ring frame;4, first half clamping plate;5, first guide pipe hole;6, platform support frame;7, second half clamping plate;8, second guide pipe hole;9, circular groove;10, first hinge;11, inner groove;12, supporting plate;13, stepped groove frame;14, step;15, first handle;16, second handle;17, outer flange;18, second hinge. DETAILED DESCRIPTION

[0026] The technical solutions of the embodiments of this utility model will be clearly and completely described below with reference to the accompanying drawings. Obviously, the described embodiments are only some embodiments of this utility model, and not all embodiments. Based on the embodiments of this utility model, all other embodiments obtained by those skilled in the art without creative effort are within the protection scope of this utility model.

[0027] like Figs. 1 to 3 As shown, a support device for installing a casting guide pipe for cast-in-place piles includes a steel casing 1, a disc support mechanism, a working platform mechanism, and a casting guide pipe 2. This embodiment is for the construction of cast-in-place piles in ultra-thick sand layers. The steel casing 1 is a long casing. The disc support mechanism includes a support ring frame 3 and a first clamping plate. The first clamping plate includes two first half clamping plates 4. The support ring frame 3 is installed at the opening on the steel casing 1. A circular groove 9 is opened on the bottom surface of the support ring frame 3. The inner diameter of the circular groove 9 is larger than the outer diameter of the steel casing 1, so that the circular groove 9 fits around the opening on the steel casing 1. The two first half clamping plates 4 are respectively hinged to the support ring frame 3 through a first hinge 10. A first arc notch is opened on the inner side of the first half clamping plate 4. The hinge point between the first half clamping plate 4 and the support ring frame 3 is on the side of the first half clamping plate 4 away from the first arc notch. A through inner opening is opened in the middle of the support ring frame 3. After the two first half clamping plates 4 are laid flat and spliced ​​together, they cover the inner opening and the two first arc notches form a first guide pipe hole 5. The working platform mechanism includes a platform support frame 6 and a second clamping plate. The second clamping plate includes two second half clamping plates 7. The platform support frame 6 is set on the support ring frame 3. The two second half clamping plates 7 are respectively hinged to the platform support frame 6 through a second hinge 18. A second arc notch is opened on the inner side of the second half clamping plate 7. The hinge point between the second half clamping plate 7 and the platform support frame 6 is on the side of the second half clamping plate 7 away from the second arc notch. After the two second half clamping plates 7 are laid flat and spliced ​​together, the two second arc notches form a second guide hole 8. The second guide hole 8 is directly above the first guide hole 5. The casting guide 2 passes through both the first guide hole 5 and the second guide hole 8. An outer flange 17 is provided on the upper part of the casting guide 2. The diameters of the first guide hole 5 and the second guide hole 8 are both smaller than the outer diameter of the outer flange 17 to ensure that the casting guide 2 at the top of the outer flange 17 will not fall down from the first guide hole 5 or the second guide hole 8. The first guide hole 5 and the second guide hole 8 can both fix the casting guide 2.

[0028] The platform support frame 6 comprises a support plate 12 and two stepped groove frames 13, the two stepped groove frames 13 are fixedly connected through the support plate 12, the support plate 12 is fixedly connected between the inner side lower parts of the two stepped groove frames 13, the support plate 12 is provided with a circular hole for the pouring guide pipe 2 to pass through, the diameter of the circular hole is larger than the outer diameter of the outer flange 17 of the pouring guide pipe 2, so that the circular hole can pass through the outer flange 17 of the pouring guide pipe 2. One second half clamping plate 7 is hinged to the upper part of the inner side of one stepped groove frame 13, and the other second half clamping plate 7 is hinged to the upper part of the inner side of the other stepped groove frame 13; the platform support frame 6 is erected on the support ring frame 3, the bottom of the stepped groove frame 13 is provided with a step 14, the upper part of the support ring frame 3 is provided with an inner recess 11, the step 14 is arc-shaped, and the inner recess 11 is circular, the step 14 is embedded in the inner recess 11, so that the stepped groove frame 13 is erected on the support ring frame 3, and the outer bottom surface of the step 14 is arranged on the upper edge of the inner recess 11 of the support ring frame 3.

[0029] The main materials of the support ring frame 3, the first half clamping plate 4, the platform support frame 6, the second half clamping plate 7 and the pouring guide pipe 2 are steel.

[0030] Each first half clamping plate 4 is provided with two first handles 15, and the operation personnel can lift the first handles 15 to open or lay down the first half clamping plate 4 to fix the pouring guide pipe 2; each second half clamping plate 7 is provided with a second handle 16, and the operation personnel can lift the second handle 16 to open or lay down the second half clamping plate 7 to fix the pouring guide pipe 2.

[0031] The installation process of the support device for the pouring guide pipe 2 of the cast-in-place pile is as follows: the operation personnel embeds the support ring frame 3 into the hole of the steel casing 1, inserts the pouring guide pipe 2 into the steel casing 1, lays down and fixes the two first half clamping plates 4, limits and fixes the pouring guide pipe 2 through the first guide pipe hole 5, embeds the operation platform mechanism in the inner recess 11 through the step 14, places the operation platform mechanism on the support ring frame 3, passes the circular hole of the support plate 12 through the outer flange 17 of the pouring guide pipe 2, lays down and fixes the two second half clamping plates 7, limits and fixes the pouring guide pipe 2 through the second guide pipe hole 8, and finally arranges the outer flange 17 of the pouring guide pipe 2 on the top surface of the second half clamping plate 7.

[0032] After the pouring construction of the cast-in-place pile is completed, the operation platform mechanism can be unloaded, and the disc support mechanism is left at the hole of the steel casing 1 as a temporary protection measure. After the cast-in-place pile reaches a certain strength, the disc support mechanism is moved to other steel casings 1 for use.

[0033] The support device for the pouring guide pipe 2 of the cast-in-place pile fixes the pouring guide pipe 2 through the first guide pipe hole 5 and the second guide pipe hole 8, effectively reduces the vibration amplitude of the pouring guide pipe 2, significantly reduces the vibration displacement of the pouring guide pipe 2 in the pouring process, and greatly improves the pouring efficiency of the concrete.

[0034] The support device supports the orifice of the steel casing 1 through the disc support mechanism, and the operator can walk on the first half clamping plate 4 to work, which increases the working space, is flexible in construction, and is practical.

[0035] The two first half clamping plates 4 are horizontally combined to cover the inner orifice of the support ring frame 3, the orifice of the steel casing 1 is covered by the disc support mechanism, and personnel falling into the steel casing 1 through the orifice is prevented.

[0036] The disc support mechanism and the working platform mechanism are embeddedly installed, are convenient to disassemble and assemble, are high in installation and disassembly efficiency, are convenient to move, and have high turnover rate.

[0037] The utility model is further described above with the help of specific embodiments, but it should be understood that the specific description herein should not be understood as the limitation on the essence and scope of the utility model, and various modifications made by the ordinary skilled in the art after reading the specification to the above embodiments all belong to the scope protected by the utility model.

Claims

1. A support device for installation of a cast-in-place pile pouring conduit, characterised in that: The utility model relates to a steel casing (1), disc support mechanism, operation platform mechanism and pouring guide pipe (2) are included. The disc support mechanism includes a support ring frame (3) and a first clamping plate, the support ring frame (3) is installed on the steel casing (1) at the orifice, the first clamping plate is connected with the support ring frame (3), the first clamping plate is provided with a first guide pipe hole (5), and the first clamping plate can cover the inner orifice of the support ring frame (3). The operation platform mechanism includes a platform support frame (6) and a second clamping plate, the platform support frame (6) is arranged on the support ring frame (3), the second clamping plate is connected with the platform support frame (6), the second clamping plate is provided with a second guide pipe hole (8), the pouring guide pipe (2) passes through the first guide pipe hole (5) and the second guide pipe hole (8) simultaneously, and the first guide pipe hole (5) and the second guide pipe hole (8) can fix the pouring guide pipe (2).

2. The support device for installation of a pouring pile pouring duct according to claim 1, characterized in that: The first clamping plate includes two first half clamping plates (4), the two first half clamping plates (4) are hinged with the support ring frame (3) respectively, a first circular arc notch is formed in the inner side of the first half clamping plate (4), and the two first half clamping plates (4) are spliced to cover the inner orifice of the support ring frame (3) and form the first guide pipe hole (5) by the two first circular arc notches.

3. A support device for installation of a pouring pile pouring conduit according to claim 2, characterized in that: The second clamping plate includes two second half clamping plates (7), the two second half clamping plates (7) are hinged with the platform support frame (6) respectively, a second circular arc notch is formed in the inner side of the second half clamping plate (7), and the two second half clamping plates (7) are spliced to form the second guide pipe hole (8) by the two second circular arc notches.

4. The support device for installation of a pouring pile pouring duct according to claim 1, characterized in that: The bottom surface of the support ring frame (3) is provided with a circular groove (9), and the circular groove (9) is embedded on the outer periphery of the orifice of the steel casing (1).

5. The support device for installation of a pouring pile pouring duct according to claim 3, characterized in that: The platform support frame (6) includes a support plate (12) and two step-shaped groove frames (13), the two step-shaped groove frames (13) are fixedly connected through the support plate (12), the support plate (12) is provided with a circular hole for the pouring guide pipe (2) to pass through, one second half clamping plate (7) is hinged with one step-shaped groove frame (13), and the other second half clamping plate (7) is hinged with the other step-shaped groove frame (13); the platform support frame (6) is arranged on the support ring frame (3), the bottom of the step-shaped groove frame (13) is provided with a step (14), the upper portion of the support ring frame (3) is provided with an inner groove (11), and the step (14) is embedded in the inner groove (11).

6. A support device for installation of a pouring pile pouring conduit according to claim 5, characterized in that: The step (14) is in the shape of an arc, and the inner groove (11) is circular.

7. The support device for installation of a pouring pile pouring duct according to claim 3, characterized in that: The main materials of the support ring frame (3), the first half clamping plate (4), the platform support frame (6), the second half clamping plate (7) and the pouring guide pipe (2) are all steel.

8. The support device for installation of a pouring pile pouring duct according to claim 3, characterized in that: The first half clamping plate (4) is provided with a first handle (15), and the second half clamping plate (7) is provided with a second handle (16).