Steam boiler pipeline mounting structure

By adjusting the spacing of the hangers on the wall and using a structure with horizontal support beams, the problem of adjusting the position of the steam boiler pipes and beams during installation was solved, improving installation efficiency and enhancing support capacity.

CN223725660UActive Publication Date: 2025-12-26DIER GRP CO LTD
View PDF 1 Cites 0 Cited by

Patent Information

Application Number
CN202520039221.3
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2025-01-08
Publication Date
2025-12-26
Estimated Expiration
2035-01-08

Smart Images

  • Figure CN223725660U_ABST
    Figure CN223725660U_ABST
Patent Text Reader

Abstract

The utility model relates to a steam boiler pipeline installation structure, and belongs to the technical field of pipeline installation. Comprising a first suspender and a second suspender which are vertically arranged at intervals, a first pipe hoop and a second pipe hoop which are used for fixing a pipeline are arranged in the middles of the first suspender and the second suspender correspondingly, the top end of the first suspender is fixed to the front side face of a cross beam through a beam fixing base A, and the top end of the second suspender is fixed to the rear side face of the cross beam through a beam fixing base B; the bottom end of the first hanging rod is vertically connected with a horizontal supporting beam A, the bottom end of the second hanging rod is vertically connected with a horizontal supporting beam B, the other end of the horizontal supporting beam A and the other end of the horizontal supporting beam B are both connected with a wall installation base installed on a wall, and the distance between the first hanging rod and the second hanging rod can be adjusted through the wall installation base. The wall mounting device has the advantages that the distance between the first hanging rod and the second hanging rod can be adjusted through the wall mounting base so as to be matched with cross beams with different thicknesses, the mounting efficiency is improved, and the pipeline mounting difficulty is reduced.
Need to check novelty before this filing date? Find Prior Art

Description

TECHNICAL FIELD

[0001] The utility model relates to a steam boiler pipeline installation structure and belongs to the technical field of pipeline installation. BACKGROUND

[0002] The working principle of a steam boiler is a complex heat conversion and transfer process, involving fuel combustion, heat transfer, water vaporization, steam separation and superheating, and steam transportation and use, etc. Through the coordinated action of these links, the steam boiler can efficiently convert the chemical energy of fuel into heat energy and power energy of steam, providing important energy support for industrial production.

[0003] Through the search, the patent with the authorized announcement number CN210014089U discloses a pipeline support structure. The pipeline support structure comprises: an adjusting rod, at least two adjusting holes are arranged on the adjusting rod in the height direction, and the adjusting holes are used for adjusting the support height of the pipeline; a support beam, the pipeline is arranged on the support beam, and a first fixing hole is arranged on the support beam; a fastener can pass through the first fixing hole and the adjusting hole to connect the support beam and the adjusting rod.

[0004] The current technology does not consider comprehensively, and has the following disadvantages: the installation of the steam boiler pipeline needs to pre-position the hanger for installation, so as to ensure that the pipeline can be fixed by multiple groups of hangers during the installation process. When it needs to be installed with the cross beam and the wall at the same time, due to the influence of the thickness of the cross beam, a large amount of time and manpower needs to be spent to adjust the position of the hanger in the actual operation, which greatly reduces the installation efficiency.

[0005] In order to solve one of the above problems, a steam boiler pipeline installation structure is urgently needed. UTILITY MODEL CONTENTS

[0006] According to the above deficiencies in the prior art, the technical problem to be solved by the utility model is: how to adjust the distance between the first hanger and the second hanger through the wall mounting seat, so as to match the cross beams with different thicknesses, improve the installation efficiency, and reduce the installation difficulty of the pipeline. Therefore, a steam boiler pipeline installation structure is provided.

[0007] The utility model discloses steam boiler pipeline installation structure, including vertical and interval first derrick, second derrick, the middle part of first derrick and second derrick is provided with first pipe clamp, second pipe clamp for fixing pipeline, it is characterized by: the top of first derrick is fixed on the front side of crossbeam through beam fixing seat A, the top of second derrick is fixed on the back side of crossbeam through beam fixing seat B, the bottom of first derrick is vertically connected with horizontal support beam A, the bottom of second derrick is vertically connected with horizontal support beam B, the other end of horizontal support beam A, horizontal support beam B is connected with wall mounting seat installed on wall, can adjust the interval between first derrick, second derrick through wall mounting seat.

[0008] First, wall mounting seat is fixed on wall, then adjust the interval between horizontal support beam A and horizontal support beam B, first derrick, second derrick respectively with horizontal support beam A, horizontal support beam B movement, so that the beam fixing seat A on first derrick and the beam fixing seat B on second derrick can be attached to the both sides of crossbeam, then beam fixing seat A, beam fixing seat B are fixed on the both sides of crossbeam, can realize the position fixing of first derrick, second derrick, then pipeline is detachably connected with first derrick, second derrick through first pipe clamp, second pipe clamp, can complete the installation of pipeline. The advantage of the application is that the interval between first derrick and second derrick can be adjusted through wall mounting seat, to match the crossbeam of different thickness, improve installation efficiency, reduce the installation difficulty of pipeline.

[0009] Preferably, the wall mounting seat includes a back plate, the two ends of the back plate are respectively connected with a first end plate and a second end plate, a threaded rod and an optical axis parallel to each other are arranged between the first end plate and the second end plate, the threaded rod penetrates through the horizontal support beam A and the horizontal support beam B, a first sliding seat is installed on the end of the horizontal support beam A through a tail seat A, a second sliding seat is installed on the end of the horizontal support beam B through a tail seat B, the first sliding seat and the second sliding seat slide with the optical axis, lock nuts A and B are arranged on the threaded rods on the two sides of the horizontal support beam A, lock nuts C and D are arranged on the threaded rods on the two sides of the horizontal support beam B.

[0010] The back plate is fixed to the wall through expansion bolts C, the mounting position of the back plate is fixed first, generally, the back plate is required to be horizontally mounted, then the lock nuts D and C are driven by a wrench to move away from the horizontal support beam B, the horizontal support beam B has a space for adjustment along the length direction of the threaded rod, meanwhile, the lock nuts B and A are driven by a wrench to move away from the horizontal support beam A, the horizontal support beam A has a space for adjustment along the length direction of the threaded rod, the distance between the horizontal support beam A and the horizontal support beam B is adjusted, the first hanging rod and the second hanging rod move along with the horizontal support beam A and the horizontal support beam B respectively, the beam fixing seat A on the first hanging rod and the beam fixing seat B on the second hanging rod can be attached to the two sides of the cross beam, then the beam fixing seat A and the beam fixing seat B are fixed on the two sides of the cross beam, the position of the first hanging rod and the second hanging rod is fixed, then the horizontal support beam B is locked by the lock nuts D and C, meanwhile, the horizontal support beam A is locked by the lock nuts A and B, the reliability of the structure connection is ensured. The optical axis provides a guiding effect for the adjustment of the horizontal support beam A and the horizontal support beam B, and the adjustment is smooth. The upper ends of the first hanging rod and the second hanging rod are connected with the cross beam, and the horizontal support beam A and the horizontal support beam B are connected with the wall mounting seat, so that the bottom of the first hanging rod and the second hanging rod is supported, the bearing capacity of the first hanging rod and the second hanging rod is improved, and the support effect on the pipeline is improved.

[0011] Preferably, the horizontal support beam A and the horizontal support beam B are respectively provided with a circular hole one and a circular hole two for the threaded rod to penetrate, the horizontal support beam A is clamped between the lock nuts A and the lock nuts B, and the horizontal support beam B is clamped between the lock nuts C and the lock nuts D. The structure is simple and reasonable, and can be prefabricated in a workshop, and then debugged and installed on site.

[0012] Preferably, the first hanging rod, the second hanging rod, the horizontal support beam A and the horizontal support beam B are all rectangular steel pipes. The structural strength is ensured.

[0013] Preferably, the beam fixing seat A and the beam fixing seat B are fixed on the front and rear two sides of the cross beam through expansion bolts A and expansion bolts B respectively, and the back plate is fixed to the wall through expansion bolts C. The on-site installation is convenient.

[0014] Preferably, the back plate is a steel plate, and the back plate, the first end plate and the second end plate are integrally formed. The installation efficiency is improved.

[0015] Preferably, a second reinforcing rib plate is arranged between the second hanging rod and the horizontal support beam B, and a first reinforcing rib plate is arranged between the first hanging rod and the horizontal support beam A. The structural strength is improved.

[0016] Compared with the prior art, the utility model has the following beneficial effects:

[0017] The steam boiler pipeline installation structure has the advantages that the distance between the first lifting rod and the second lifting rod can be adjusted through the wall mounting seat to match the cross beams with different thicknesses, the installation efficiency is improved, and the installation difficulty of the pipeline is reduced.

[0018] The steam boiler pipeline installation structure has the advantages that the distance between the first lifting rod and the second lifting rod can be adjusted through the wall mounting seat to match the cross beams with different thicknesses, the installation efficiency is improved, and the installation difficulty of the pipeline is reduced.

[0019] The steam boiler pipeline installation structure has the advantages that the distance between the first lifting rod and the second lifting rod can be adjusted through the wall mounting seat to match the cross beams with different thicknesses, the installation efficiency is improved, and the installation difficulty of the pipeline is reduced. BRIEF DESCRIPTION OF DRAWINGS

[0020] In order to more clearly illustrate the specific embodiments of the present application or the technical solutions in the prior art, the drawings needed to be used in the specific embodiments or the prior art description will be briefly introduced below. In all the drawings, similar elements or parts are generally identified by similar reference numerals. In the drawings, the elements or parts are not necessarily drawn according to the actual scale.

[0021] Figure 1 It is a front view of the utility model embodiment one and embodiment two;

[0022] Figure 2 It is a front view of the utility model embodiment one and embodiment two;

[0023] Figure 3 It is an external structure schematic view of the utility model embodiment three;

[0024] In the drawings: 1, first lifting rod 2, second lifting rod 3, beam fixing seat A 4, beam fixing seat B 5, wall mounting seat 6, first pipe clamp 7, second pipe clamp 8, horizontal support beam A 9, horizontal support beam B 10, cross beam 11, wall 12, back plate 13, first end plate 14, second end plate 15, tail seat A 16, tail seat B 17, threaded rod 18, locking nut A 19, locking nut B 20, locking nut C 21, locking nut D 22, optical axis 23, first sliding seat 24, second sliding seat 25, pipeline 26, first reinforcing rib plate. DETAILED DESCRIPTION

[0025] The utility model is further described below in combination with the drawings: the utility model is further described below through specific embodiments, but is not used to limit the utility model, any modification, equivalent replacement, improvement and the like made within the spirit and principle of the present application should be included in the protection scope of the utility model.

[0026] Embodiment one, as Figures 1-2 The utility model discloses a steam boiler pipeline mounting structure, including vertical and interval arrangement's first derrick 1, second derrick 2, the middle part of first derrick 1 and second derrick 2 are provided with first pipe clamp 6, second pipe clamp 7 for fixed pipeline 25, the top of first derrick 1 is fixed on the front side of crossbeam 10 through beam fixing seat A3, the top of second derrick 2 is through the rear side of crossbeam 10, the bottom of first derrick 1 is vertically connected with horizontal support beam A8, the bottom of second derrick 2 is vertically connected with horizontal support beam B9, the other end of horizontal support beam A8, horizontal support beam B9 all are connected with wall mounting seat 5 installed on wall 11, can adjust the interval between first derrick 1 and second derrick 2 through wall mounting seat 5.

[0027] First, wall mounting seat 5 is fixed on wall 11, then adjust the interval between horizontal support beam A8 and horizontal support beam B9, first derrick 1 and second derrick 2 respectively with horizontal support beam A8, horizontal support beam B9 movement, so that the beam fixing seat A3 on first derrick 1 and the beam fixing seat B4 on second derrick 2 can be attached to the both sides of crossbeam 10, then beam fixing seat A3, beam fixing seat B4 are fixed on the both sides of crossbeam 10, can realize the position fixation of first derrick 1 and second derrick 2, then pipeline 25 is through first pipe clamp 6, second pipe clamp 7 respectively with first derrick 1, second derrick 2 detachable connection, can complete the installation of pipeline 25. The advantage of the application lies in that the interval between first derrick 1 and second derrick 2 can be adjusted through wall mounting seat 5 to match the crossbeam 10 of different thickness, improve the installation efficiency, reduce the installation difficulty of pipeline 25.

[0028] Embodiment two, as Figures 1-2As shown, the steam boiler pipeline mounting structure comprises vertically and spacedly arranged first hanger 1 and second hanger 2, the middle parts of the first hanger 1 and the second hanger 2 are respectively provided with first pipe clamp 6 and second pipe clamp 7 for fixing pipeline 25, the top end of the first hanger 1 is fixed on the front side of cross beam 10 through beam fixing seat A3, the top end of the second hanger 2 is fixed on the rear side of cross beam 10, the bottom end of the first hanger 1 is vertically connected with horizontal support beam A8, the bottom end of the second hanger 2 is vertically connected with horizontal support beam B9, the other ends of the horizontal support beam A8 and the horizontal support beam B9 are both connected with wall mounting seat 5 mounted on wall 11, the interval between the first hanger 1 and the second hanger 2 can be adjusted through the wall mounting seat 5. Cross beam 10 and wall 11 are both concrete structures, which belong to the basic part of the factory building, and pipeline 25 needs to pass below cross beam 10.

[0029] Further, the wall mounting seat 5 comprises back plate 12, the two ends of the back plate 12 are respectively vertically connected with first end plate 13 and second end plate 14, screw rod 17 and optical axis 22 parallel to each other are arranged between the first end plate 13 and the second end plate 14, the screw rod 17 penetrates through horizontal support beam A8 and horizontal support beam B9, first slide 23 is mounted on the end of horizontal support beam A8 through tail seat A15, second slide 24 is mounted on the end of horizontal support beam B9 through tail seat B16, the first slide 23 and the second slide 24 are both matched with optical axis 22 to slide, lock nut A18 and lock nut B19 are respectively arranged on the screw rod 17 on both sides of horizontal support beam A8, lock nut C20 and lock nut D21 are respectively arranged on the screw rod 17 on both sides of horizontal support beam B9.

[0030] The back plate 12 is fixed to the wall 11 by expansion bolts C, the installation position of the back plate 12 is fixed first, generally the back plate 12 is required to be installed horizontally, then the lock nut D21 and the lock nut C20 are driven by a wrench to move away from the horizontal support beam B9, so that the horizontal support beam B9 has a space for adjustment along the length direction of the threaded rod 17, at the same time, the lock nut B19 and the lock nut A18 are driven by a wrench to move away from the horizontal support beam A8, so that the horizontal support beam A8 has a space for adjustment along the length direction of the threaded rod 17, by adjusting the distance between the horizontal support beam A8 and the horizontal support beam B9, the first boom 1 and the second boom 2 move along the horizontal support beam A8 and the horizontal support beam B9 respectively, so that the beam fixing seat A3 on the first boom 1 and the beam fixing seat B4 on the second boom 2 can be attached to the two sides of the cross beam 10, then the beam fixing seat A3 and the beam fixing seat B4 are fixed on the two sides of the cross beam 10, so that the position of the first boom 1 and the second boom 2 is fixed, then the horizontal support beam B9 is locked by the lock nut D21 and the lock nut C20, at the same time, the horizontal support beam A8 is locked by the lock nut A18 and the lock nut B19, so as to ensure the reliability of the structure connection. The optical axis 22 provides a guiding effect for the adjustment of the horizontal support beam A8 and the horizontal support beam B9, and ensures the smoothness of the adjustment. The upper end of the first boom 1 and the second boom 2 is connected with the cross beam 10, and the horizontal support beam A8 and the horizontal support beam B9 are connected with the wall mounting seat 5, which provides support for the bottom of the first boom 1 and the second boom 2, improves the carrying capacity of the first boom 1 and the second boom 2, and improves the support effect on the pipeline 25.

[0031] Further, the horizontal support beam A8 and the horizontal support beam B9 are respectively provided with a circular hole one and a circular hole two for the threaded rod 17 to penetrate, the horizontal support beam A8 is clamped between the lock nut A18 and the lock nut B19, and the horizontal support beam B9 is clamped between the lock nut C20 and the lock nut D21. The structure is simple and reasonable, and can be prefabricated in the workshop, and then debugged and installed on site.

[0032] Further, the first boom 1, the second boom 2, the horizontal support beam A8 and the horizontal support beam B9 are all rectangular steel pipes. The structural strength is guaranteed.

[0033] Further, the beam fixing seat A3 and the beam fixing seat B4 are respectively fixed on the front and rear sides of the cross beam 10 by expansion bolts A and expansion bolts B, and the back plate 12 is fixed to the wall 11 by expansion bolts C. The on-site installation is convenient.

[0034] Further, the back plate 12 is a steel plate, and the back plate 12, the first end plate 13 and the second end plate 14 are integrally formed. The installation efficiency is improved.

[0035] Example three, asFigure 3 The difference between the embodiment two and the embodiment three is that the second reinforcing rib plate is arranged between the second suspender 2 and the horizontal support beam B9, and the first reinforcing rib plate 26 is arranged between the first suspender 1 and the horizontal support beam A8.

[0036] The steam boiler pipeline mounting structure has the advantages that the spacing between the first suspender and the second suspender can be adjusted through the wall mounting seat to match the cross beams with different thicknesses, the mounting efficiency is improved, and the pipeline mounting difficulty is reduced.

[0037] The steam boiler pipeline mounting structure has the advantages that the spacing between the first suspender and the second suspender can be adjusted through the wall mounting seat to match the cross beams with different thicknesses, the mounting efficiency is improved, and the pipeline mounting difficulty is reduced.

[0038] The steam boiler pipeline mounting structure has the advantages that the spacing between the first suspender and the second suspender can be adjusted through the wall mounting seat to match the cross beams with different thicknesses, the mounting efficiency is improved, and the pipeline mounting difficulty is reduced.

[0039] The basic principle, main features and advantages of the steam boiler pipeline mounting structure are shown and described above.

[0040] The details of the steam boiler pipeline mounting structure are not described, which are the known technology of the technical personnel in the technical field.

Claims

1. A steam boiler piping installation structure comprising a first hanger and a second hanger vertically and spacedly arranged, a middle portion of the first hanger and the second hanger being provided with a first pipe clamp and a second pipe clamp for fixing a pipe, respectively, characterized in that: The top end of the first boom is fixed on the front side of the cross beam through a beam fixing base A, the top end of the second boom is fixed on the rear side of the cross beam through a beam fixing base B, the bottom end of the first boom is vertically connected with a horizontal support beam A, the bottom end of the second boom is vertically connected with a horizontal support beam B, the other end of the horizontal support beam A and the horizontal support beam B is connected with a wall mounting base mounted on the wall, and the distance between the first boom and the second boom can be adjusted through the wall mounting base.

2. The steam boiler piping installation structure according to claim 1, wherein The wall mounting base comprises a back plate, the two ends of the back plate are vertically connected with a first end plate and a second end plate respectively, a threaded rod and an optical axis parallel to each other are arranged between the first end plate and the second end plate, the threaded rod penetrates through the horizontal support beam A and the horizontal support beam B, the end of the horizontal support beam A is provided with a first sliding seat through a tail seat A, the end of the horizontal support beam B is provided with a second sliding seat through a tail seat B, the first sliding seat and the second sliding seat slide in cooperation with the optical axis, the threaded rods on the two sides of the horizontal support beam A are provided with a locking nut A and a locking nut B respectively, and the threaded rods on the two sides of the horizontal support beam B are provided with a locking nut C and a locking nut D respectively.

3. The steam boiler piping installation structure according to claim 2, wherein The horizontal support beam A and the horizontal support beam B are respectively provided with a circular hole one and a circular hole two for the threaded rod to penetrate, the horizontal support beam A is clamped between the locking nut A and the locking nut B, and the horizontal support beam B is clamped between the locking nut C and the locking nut D.

4. The steam boiler piping installation structure according to claim 3, wherein The first boom, the second boom, the horizontal support beam A and the horizontal support beam B are all rectangular steel pipes.

5. The steam boiler piping installation structure according to claim 4, wherein The beam fixing base A and the beam fixing base B are fixed on the front and rear sides of the cross beam through expansion bolts A and expansion bolts B respectively, and the back plate is fixed on the wall through expansion bolts C.

6. The steam boiler piping installation structure according to claim 5, wherein The back plate is a steel plate, and the back plate, the first end plate and the second end plate are integrally formed.

7. The steam boiler piping installation structure according to claim 6, wherein Second reinforcing rib plates are arranged between the second boom and the horizontal support beam B, and first reinforcing rib plates are arranged between the first boom and the horizontal support beam A. Second reinforcing rib plates are arranged between the second boom and the horizontal support beam B, and first reinforcing rib plates are arranged between the first boom and the horizontal support beam A.