Pavement pouring formwork with dowel bar supporting frame

By using pavement casting formwork with built-in dowel bar support frames, and employing right-angled trapezoidal brackets and adjustable-height support rods, combined with wedge blocks and steel pins for fixing, the problems of difficult steel formwork fixing and dowel bar offset were solved, thus simplifying the construction process and improving efficiency.

CN223880154UActive Publication Date: 2026-02-06云南建投第四建设有限公司
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202520331446.6
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2025-02-28
Publication Date
2026-02-06
Estimated Expiration
2035-02-28

AI Technical Summary

Technical Problem

Existing technologies make it difficult to fix steel formwork during pavement construction, dowel bars are prone to axial displacement, and the number of holes is too large and it is difficult to ensure the parallelism of the holes, resulting in high construction complexity.

Method used

Design a pavement casting template with a built-in force transmission rod support frame. It adopts a right-angled trapezoidal bracket and an adjustable-height horizontal support rod, combined with wedge blocks and steel pins for fixation, which saves half of the drilling work. The force transmission rod is fixed by the support frame to avoid axial displacement.

Benefits of technology

It simplifies the template installation process, reduces construction difficulty, avoids axial displacement of the dowel bars, and improves construction efficiency.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN223880154U_ABST
    Figure CN223880154U_ABST
Patent Text Reader

Abstract

The utility model discloses a pavement pouring template with a dowel bar support frame, which comprises a template body, a support and a dowel bar, the support is of a right trapezoid structure and is used for supporting the template body, the template body is provided with a first through hole used for installing the dowel bar, the pavement pouring template further comprises a horizontal support rod, and the horizontal support rod is provided with a second through hole used for installing the dowel bar. A second through hole coaxial with the first through hole is formed in the horizontal supporting rod, and the dowel bar extends into the first through hole through the second through hole; the horizontal supporting rod is supported by at least two height-adjustable supporting frames. The dowel bar can be supported by arranging the dowel bar supporting frame, meanwhile, the dowel bar can be prevented from axially deviating in the construction process, and besides, when the formwork is erected, half of drilled holes are omitted.
Need to check novelty before this filing date? Find Prior Art

Description

TECHNICAL FIELD

[0001] The utility model relates to the technical field of pavement construction, especially to a pavement pouring formwork with a force transmission rod support frame. BACKGROUND

[0002] When constructing an airplane apron pavement or a highway pavement, a formwork needs to be erected and supported, and then concrete is poured into the forming cavity of the formwork to realize the construction of the pavement.

[0003] In the prior art, a steel formwork is fixed by drilling two parallel holes in the ground with an electric drill and then by a steel rod to prevent displacement of the steel formwork; a force transmission rod needs to be supported by a force transmission rod support frame (the force transmission rod support frame is a long rod with a raised pad) to maintain horizontality; the aforementioned construction process has the following disadvantages: because the steel formwork is long, the number of holes drilled is too large; in addition, the two holes need to be parallel to increase the difficulty of erecting the formwork; finally, the force transmission rod is supported only by the force transmission rod support frame, and the force transmission rod is radially limited, so the construction process may cause axial deviation between the force transmission rod and the force transmission rod mounting hole on the formwork. SUMMARY

[0004] The utility model aims at overcoming the defects of the prior art and providing a pavement pouring formwork with a force transmission rod support frame, which can provide support for the force transmission rod and avoid axial deviation of the force transmission rod during construction; in addition, half of the drilling workload is saved when the formwork is erected, greatly reducing the difficulty of formwork installation.

[0005] The utility model is achieved by the following technical solutions:

[0006] The utility model provides a pavement pouring formwork with a force transmission rod support frame, which comprises a formwork body, a support frame and a force transmission rod, the support frame is in a right-angled trapezoidal structure, the support frame is used for supporting the formwork body, a first through hole for mounting the force transmission rod is arranged on the formwork body, and a horizontal support rod is further arranged, a second through hole coaxial with the first through hole is arranged on the horizontal support rod, and the force transmission rod extends into the first through hole through the second through hole.

[0007] The horizontal support rod is supported by at least two support frames with adjustable height.

[0008] Further, a vertical fixing sleeve is arranged on the outer side of the support frame, a steel rod is arranged in the fixing sleeve, and a wedge-shaped block is arranged between the steel rod and the support frame.

[0009] Further, the wedge-shaped block is made of wood.

[0010] Further, the horizontal support rod is a square steel

[0011] Further, the support frame comprises a support round pipe, a support screw rod, a support screw sleeve and a support ring plate, the bottom end of the support round pipe is provided with a base, and the top end of the round pipe is open;

[0012] The support ring plate is fixedly sleeved outside the support screw sleeve, the size of the support ring plate is greater than the inner diameter of the support round pipe, the support screw sleeve is threadedly connected outside the support screw rod, the bottom end of the support screw rod extends into the support round pipe, and the top end of the support screw rod is fixedly connected with a limiting support plate.

[0013] The limiting support plate is used for supporting the horizontal support rod and limiting the axial displacement of the horizontal support rod along the second through hole.

[0014] Further, the limiting support plate is a C-shaped steel.

[0015] Further, the base and the support round pipe are welded as a whole, and the support ring plate and the support screw sleeve are welded as a whole.

[0016] The beneficial effects of the utility model are:

[0017] The utility model discloses a force transmission rod support frame, which can provide support for the force transmission rod, avoid axial deviation of the force transmission rod during construction, and greatly reduce the difficulty of template installation when the template is erected. BRIEF DESCRIPTION OF DRAWINGS

[0018] Figure 1 It is a front view of a pavement pouring template provided with a force transmission rod support frame before installation of the support frame in the embodiment of the utility model;

[0019] Figure 2 It is a side view of the pavement pouring template provided with the force transmission rod support frame before installation of the support frame;

[0020] Figure 3 It is a front view of the pavement pouring template provided with the force transmission rod support frame after installation of the support frame;

[0021] Figure 4 It is a side view of the pavement pouring template provided with the force transmission rod support frame after installation of the support frame;

[0022] Figure 5 It is a structural schematic view of the support frame;

[0023] In the drawing, 1, template body; 2, support; 3, force transmission rod; 4, first through hole; 5, limiting support plate; 6, horizontal support rod; 7, second through hole; 8, fixed sleeve; 9, steel drill; 10, wedge block; 11, support frame; 12, support round pipe; 13, support screw rod; 14, support ring plate; 15, base; 16, support screw sleeve. DETAILED DESCRIPTION

[0024] The technical solutions of the present application will be described clearly and completely in combination with the embodiments. Obviously, the described embodiments are only some of the embodiments of the present application, but not all the embodiments. Based on the embodiments in the present application, all the other embodiments obtained by those skilled in the art without creative effort are within the scope of the present application.

[0025] Referring to Figures 1-5 , the present application provides a technical solution:

[0026] Embodiments:

[0027] As Figures 1-5 shown, a pavement pouring formwork with a force transmission rod support frame comprises a formwork body 1, a support frame 2 and a force transmission rod 3, the support frame 2 is a right-angled trapezoidal structure, the support frame 2 is used for supporting the formwork body 1, the formwork body 1 is provided with a first through hole 4 for mounting the force transmission rod 3, and further comprises a horizontal support rod 6, the horizontal support rod 6 is provided with a second through hole 7 coaxial with the first through hole 4, and the force transmission rod 3 extends into the first through hole 4 through the second through hole 7.

[0028] Among them, the support frame 2 is welded by four profile steels, one long and one short vertical parallel profile steels are arranged, one horizontal profile steel is arranged between the two vertical profile steels, and the last profile steel is arranged at the top end of the two vertical profile steels.

[0029] The horizontal support rod 6 is supported by at least two height-adjustable support frames 11.

[0030] The outer side of the support frame 2 is provided with a vertical fixing sleeve 8, the fixing sleeve 8 is provided with a steel drill 9, and a wedge block 10 is arranged between the steel drill 9 and the support frame 2.

[0031] The wedge block 10 is made of wooden material. The wooden material can be but is not limited to bamboo wood and raw wood.

[0032] The horizontal support rod 6 is a square steel.

[0033] As Figures 3-5 shown, the support frame 11 comprises a support circular pipe 12, a support screw rod 13, a support screw sleeve 16 and a support ring plate 14, the bottom end of the support circular pipe 12 is provided with a base 15, and the top end of the circular pipe is open;

[0034] The support ring plate 14 is arranged outside the support screw sleeve 16, the size of the support ring plate 14 is greater than the inner diameter of the support circular pipe 12, the support screw sleeve 16 is threadedly connected outside the support screw rod 13, the bottom end of the support screw rod 13 extends into the support circular pipe 12, and the top end of the support screw rod 13 is fixedly connected with a limiting support plate 5.

[0035] The limiting support plate 5 is used for supporting the horizontal support rod 6 and limiting the axial displacement of the horizontal support rod 6 along the second through hole 7.

[0036] The limiting support plate 5 is a C-shaped steel.

[0037] The base 15 is welded with the support circular pipe 12 as a whole, and the support ring plate 14 is welded with the support screw sleeve 16 as a whole.

[0038] When the formwork is erected, a row of fixed holes corresponding to the upper and lower fixed sleeves 8 is first drilled along the length direction of the formwork, and the fixed holes are arranged at equal intervals. Then the steel drill 9 is inserted into the fixed hole from the fixed sleeve 8, and since the inner diameter of the fixed sleeve 8 is larger than the outer diameter of the steel drill 9, the formwork will be displaced in the horizontal direction. At this time, the wedge-shaped block 10 is clamped between the support 2 and the steel drill 9, and in this process, the wedge-shaped block 10 is downwardly extruded on the steel drill 9, the steel drill 9 is inclined, the vertical surface of the wedge-shaped block 10 is attached to the vertical surface of the support 2, and when the wedge-shaped block 10 cannot continue to go down, the steel formwork is fixed.

[0039] Then the horizontal support rod 6 is horizontally inserted into the trapezoidal hole of the support 2, the horizontal support rod 6 is lifted to keep the second through hole 7 coaxial with the first through hole 4, and at this time, the support frame 11 is installed at the bottom of the horizontal support rod 6, so that the fixation of the horizontal support rod 6 is completed.

[0040] Then the force transmission rod 3 is inserted into the first through hole 4 from the second through hole 7 of the horizontal support rod 6, so that the erection of the formwork is completed. Since the force transmission rod 3 is limited by the first through hole 4 and the second through hole 7, the axial displacement of the force transmission rod 3 will not occur.

[0041] The height of the support frame 11 is adjustable, so that it can be applied to formworks with different heights of the first through hole 4. The height adjustment process of the support frame 11 is that the support screw sleeve 16 is rotated, the support screw sleeve 16 is raised / lowered along the support screw rod 13, so that the length of the support screw rod 13 entering the support circular pipe 12 at the bottom is increased / decreased, and then the lifting / lowering of the limiting support plate 5 is realized. When the support frame 11 is used, the limiting support plate 5 can limit the axial displacement of the horizontal support rod 6 along the second through hole 7.

[0042] The utility model discloses a force transmission rod support frame can provide support for the force transmission rod, and the axial displacement of the force transmission rod during construction can be avoided.

[0043] The above merely describes preferred embodiments of the present application, and it should be understood that the present application is not limited to the forms disclosed herein, and should not be considered as excluding other embodiments, but can be used in various other combinations, modifications and environments, and can be modified within the scope of the concepts described herein, by the above teachings or related art or knowledge. Any modification and change made by those skilled in the art without departing from the spirit and scope of the present application shall be within the protection scope of the claims of the present application.

Claims

1. A pavement pouring formwork with a force transmission rod support frame, comprising a formwork body, a support frame and a force transmission rod, the support frame is a right-angled trapezoidal structure, the support frame is used for supporting the formwork body, a first through hole for mounting the force transmission rod is arranged on the formwork body, characterized in that: The horizontal support rod is provided with a second through hole coaxial with the first through hole, and the force transmission rod extends into the first through hole through the second through hole. The horizontal support rod is supported by at least two height-adjustable support frames.

2. The pavement pouring formwork of claim 1, wherein: A vertical fixing sleeve is arranged outside the support frame, and a steel drill is arranged in the fixing sleeve.

3. The track pouring formwork with a self-force transmission rod support frame according to claim 2, characterized in that: The wedge-shaped block is made of wood material.

4. The pavement pouring formwork of claim 1, wherein: The horizontal support rod is square steel.

5. The track pouring formwork with a self-force-transferring rod support frame according to claim 4, characterized in that: The support frame comprises a support circular tube, a support screw rod, a support screw sleeve and a support ring plate. The support ring plate is fixedly sleeved outside the support screw sleeve, and the size of the support ring plate is greater than the inner diameter of the support circular tube. The support screw sleeve is threadedly connected outside the support screw rod.

6. The track pouring formwork with a self-force transmission rod support frame according to claim 5, characterized in that: The limiting support plate is used for supporting the horizontal support rod and limiting the axial displacement of the horizontal support rod along the second through hole.

7. The track pouring formwork with a self-force transmission rod support frame according to claim 5, characterized in that: The limiting support plate is C-shaped steel. The base and the support circular tube are welded as a whole, and the support ring plate and the support screw sleeve are welded as a whole.