Tailing wastewater treatment pond for iron ore mining

By installing a detachable and expandable working platform on the outer wall of the sedimentation tank, the problem of difficult sampling in existing tailings wastewater sedimentation treatment tanks has been solved, enabling convenient sampling and efficient operation.

CN223914759UActive Publication Date: 2026-02-17LINYI HUIBAOLING IRON ORE CO LTD FENGHUANGSHAN IRON ORE
View PDF 1 Cites 0 Cited by

Patent Information

Application Number
CN202520083036.4
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2025-01-14
Publication Date
2026-02-17
Estimated Expiration
2035-01-14

AI Technical Summary

Technical Problem

The existing tailings wastewater settling tanks lack operating platforms, making it difficult for operators to easily obtain wastewater samples from the settling tanks, and the sampling process is time-consuming and labor-intensive.

Method used

A detachable extension platform is installed on the outer wall of the sedimentation tank body. It is connected to the sedimentation tank through detachable connectors, including sliding side rails and locking bolts, to ensure the stability of the platform and easy assembly and disassembly.

Benefits of technology

This allows operators to easily access the platform for sampling, improving work efficiency and enhancing the practicality and compactness of the sedimentation tank.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN223914759U_ABST
    Figure CN223914759U_ABST
Patent Text Reader

Abstract

The utility model relates to a tailing wastewater treatment pond for iron ore exploitation, and belongs to the technical field of wastewater treatment production. Comprising a sedimentation tank body placed on the ground, an expansion operation platform is detachably installed on the outer wall of one side of the sedimentation tank body, a crawling ladder is installed at the bottom of the side, away from the sedimentation tank body, of the expansion operation platform in a hinged mode, and the other end of the crawling ladder is supported on the ground; the expansion operation platform is detachably mounted on the outer wall of the sedimentation tank body through a detachable connecting piece. Compared with the prior art, the sedimentation tank has the following beneficial effects that the expanded operation platform is additionally arranged on the outer wall of the sedimentation tank body, so that an operator can conveniently climb on the expanded operation platform to collect and sample sewage in the sedimentation tank body, the working efficiency is improved, and the practicability is enhanced; and the expanding operation platform can be additionally arranged on the sedimentation tank body in the later period through the detachable connecting piece, and the expanding operation platform and the detachable connecting piece are compact and reasonable in overall structure and convenient to disassemble and assemble.
Need to check novelty before this filing date? Find Prior Art

Description

TECHNICAL FIELD

[0001] The utility model relates to a tailing wastewater treatment pool for iron ore exploitation belongs to wastewater treatment production technical field. BACKGROUND

[0002] The sedimentation tank is a common wastewater treatment technology, which is used for removing suspended solids, organic matter and harmful substances in wastewater. It utilizes physical principles to make the particulate matter and flocculation in wastewater settle to the bottom of the tank by gravity, thereby realizing solid-liquid separation.

[0003] The utility model with patent application number 202322046390.3 discloses a tailing wastewater sedimentation treatment pool for iron ore exploitation, which comprises a treatment pool body, a water outlet pipe interface fixedly connected to the bottom of the treatment pool body, a first water outlet pipe fixedly connected to the inner side of the water outlet pipe interface, a sludge discharge pipe fixedly connected to the bottom of the first water outlet pipe, a backflush valve fixedly sleeved to one side of the sludge discharge pipe, a filter screen fixedly sleeved to the inner side of the sludge discharge pipe, a reflux pipe fixedly connected to one side of the backflush valve, the backflush valve performs directional flushing on the reflux pipe, a water inlet pipe fixedly connected to one side of the treatment pool body, a second water outlet pipe fixedly connected to the other side of the treatment pool body, a first fixed plate fixedly connected to the top of the treatment pool body, a first motor fixedly connected to one side of the top of the first fixed plate, a second motor fixedly connected to the top of the first fixed plate, and a third motor fixedly connected to the top of the first fixed plate.

[0004] The current tailing wastewater sedimentation treatment pool has the following disadvantages: during the wastewater treatment process, it is necessary to take samples of the wastewater in the sedimentation tank multiple times. The existing tailing wastewater sedimentation treatment pool lacks an operation platform, making it difficult to climb, and it is difficult for operators to obtain the wastewater in the sedimentation tank, resulting in time-consuming and laborious sampling.

[0005] To solve one of the above problems, there is an urgent need for a tailing wastewater treatment pool for iron ore exploitation. Utility model content

[0006] In view of the above shortcomings in the prior art, the technical problem to be solved by the utility model is how to install an expanded operation platform on the outer wall of the sedimentation tank body, so that operators can conveniently climb onto the expanded operation platform to collect and sample the wastewater in the sedimentation tank body. Therefore, a tailing wastewater treatment pool for iron ore exploitation is provided.

[0007] The iron mining tailings wastewater treatment pool of the utility model discloses, including the sedimentation tank body of placing on the ground, the outer wall of the one side of sedimentation tank body detachably installs the expansion work platform, it is characterized in that: the bottom of the one side of expansion work platform far from the sedimentation tank body is hinged and is installed with the cat ladder, the other end of cat ladder is supported on the ground, the outer wall of the expansion work platform is detachably installed in the sedimentation tank body through the detachable connecting piece.

[0008] Preferably, the detachable connecting piece includes left side fixed slide beam, right side fixed slide beam and vertically arranged upper layer slide platform, the left side fixed slide beam is provided with sliding edge rail A sliding along its length direction, the right side fixed slide beam is provided with sliding edge rail B sliding along its length direction, the upper part of the upper layer slide platform is connected with sliding edge rail A through upper connecting seat, the bottom of the upper layer slide platform is connected with sliding edge rail B through lower connecting seat, the end of the expansion work platform is vertically welded with the bottom of the detachable connecting piece.

[0009] Preferably, it further includes locking bolt, the middle part of the upper layer slide platform is provided with through hole for locking bolt to penetrate, the threaded section of the locking bolt is threadedly connected with threaded pipe, the threaded pipe is fixed on the outer wall of the sedimentation tank body, after the locking bolt is connected with the threaded pipe, the sliding of the upper layer slide platform relative to the left side fixed slide beam and the right side fixed slide beam is limited.

[0010] Preferably, the outer wall surface of the sliding edge rail A is provided with nylon slide strip A cooperating with the left side fixed slide beam to slide, the outer wall surface of the sliding edge rail B is provided with nylon slide strip B cooperating with the right side fixed slide beam to slide.

[0011] Preferably, the sliding edge rail A and the sliding edge rail B are both rectangular steel pipes, and the left side fixed slide beam and the right side fixed slide beam are both welded with the sedimentation tank body.

[0012] Preferably, the left side fixed slide beam and the right side fixed slide beam are both channel steels, and the openings of the two are oppositely arranged.

[0013] Preferably, the expansion work platform and the upper layer slide platform are both steel plates.

[0014] Preferably, the sedimentation tank body is a steel sedimentation tank body, which is an existing structure and is welded by steel plates and steel pipes.

[0015] Preferably, vertical reinforcing ribs are arranged on the outer wall of the sedimentation tank body, the left side fixed slide way beam and the right side fixed slide way beam are welded and fixed with the vertical reinforcing ribs, and the tail end of the threaded pipe is connected with a tail seat which is detachably mounted on the corresponding vertical reinforcing rib through screws.

[0016] Compared with the prior art, the iron mine tailing wastewater treatment tank has the following beneficial effects:

[0017] The iron mine tailing wastewater treatment tank has the following beneficial effects: the operator can conveniently get on the expansion work platform to collect and sample the wastewater in the sedimentation tank body, work efficiency is improved, practicality is enhanced, the expansion work platform can be detachably connected to the sedimentation tank body in the later period, and the expansion work platform and the detachable connecting piece have compact and reasonable overall structures and are convenient to disassemble and assemble.

[0018] The iron mine tailing wastewater treatment tank has the following beneficial effects: the operator can conveniently get on the expansion work platform to collect and sample the wastewater in the sedimentation tank body, work efficiency is improved, practicality is enhanced, the expansion work platform can be detachably connected to the sedimentation tank body in the later period, and the expansion work platform and the detachable connecting piece have compact and reasonable overall structures and are convenient to disassemble and assemble.

[0019] The iron mine tailing wastewater treatment tank has the following beneficial effects: the operator can conveniently get on the expansion work platform to collect and sample the wastewater in the sedimentation tank body, work efficiency is improved, practicality is enhanced, the expansion work platform can be detachably connected to the sedimentation tank body in the later period, and the expansion work platform and the detachable connecting piece have compact and reasonable overall structures and are convenient to disassemble and assemble. BRIEF DESCRIPTION OF DRAWINGS

[0020] In order to more clearly illustrate the specific embodiments of the present application or the technical solutions in the prior art, the drawings needed to be used in the specific embodiments or the prior art description will be briefly introduced below. In all the drawings, similar elements or parts are generally identified by similar reference numerals. In the drawings, the elements or parts are not necessarily drawn according to the actual proportions.

[0021] Figure 1 It is a structural schematic view of the present application;

[0022] Figure 2 It is a partial structural schematic view of the present application;

[0023] Figure 3 It is an installation view of the present application.

[0024] In the figure: 1, the sedimentation tank body 2, the expansion work platform 3, the ladder 4, the detachable connecting piece 5, the left side fixed slide beam 6, the right side fixed slide beam 7, the sliding edge rail A 8, the sliding edge rail B 9, the upper layer sliding table 10, the upper connecting seat 11, the lower connecting seat 12, the locking bolt 13, the threaded tube 14, the vertical reinforcing rib 15, the tail seat 16, the nylon sliding strip A. DETAILED DESCRIPTION

[0025] The utility model will be further described below in combination with the drawings: the utility model is further described below through specific embodiment, but is not used to limit the utility model, any modification, equivalent replacement, improvement etc. that is made within the spirit and principle of the present application should be included in the protection scope of the utility model.

[0026] Embodiment 1, as shown in the figure, the tailings wastewater treatment pool for iron ore exploitation, a tailings wastewater treatment pool for iron ore exploitation, including the sedimentation tank body 1 that places on the ground, the outer wall of one side of the sedimentation tank body 1 detachably installs expansion work platform 2, the bottom of the side of expansion work platform 2 away from the sedimentation tank body 1 is hingedly installed with ladder 3, the other end of ladder 3 is supported on the ground, expansion work platform 2 is detachably installed on the outer wall of the sedimentation tank body 1 by detachable connecting piece 4. Figures 1-2 Through the expansion work platform 2 of detachably installing on the outer wall of the sedimentation tank body 1, operator can more conveniently board expansion work platform 2, and the sewage in the sedimentation tank body 1 is collected sampling operation, improves work efficiency, and enhances practicality.Easy to disassemble and assemble.

[0027] Embodiment 2, as shown in the figure, the tailings wastewater treatment pool for iron ore exploitation, a tailings wastewater treatment pool for iron ore exploitation, including the sedimentation tank body 1 that places on the ground, the outer wall of one side of the sedimentation tank body 1 detachably installs expansion work platform 2, the bottom of the side of expansion work platform 2 away from the sedimentation tank body 1 is hingedly installed with ladder 3, the other end of ladder 3 is supported on the ground, expansion work platform 2 is detachably installed on the outer wall of the sedimentation tank body 1 by detachable connecting piece 4.

[0028] Figures 1-3 Through the expansion work platform 2 of detachably installing on the outer wall of the sedimentation tank body 1, operator can more conveniently board expansion work platform 2, and the sewage in the sedimentation tank body 1 is collected sampling operation, improves work efficiency, and enhances practicality.Easy to disassemble and assemble.

[0029] ​Further, the detachable connecting piece 4 comprises a left fixed slide beam 5, a right fixed slide beam 6 and an upper slide platform 9 arranged vertically and in parallel with each other, the left fixed slide beam 5 is provided with a sliding edge rail A 7 sliding along the length direction thereof, the right fixed slide beam 6 is provided with a sliding edge rail B 8 sliding along the length direction thereof, the upper part of the upper slide platform 9 is connected with the sliding edge rail A 7 through an upper connecting seat 10, the bottom of the upper slide platform 9 is connected with the sliding edge rail B 8 through a lower connecting seat 11, and the end of the expanded working platform 2 is vertically welded with the bottom of the detachable connecting piece 4. The sliding edge rail A 7 and the sliding edge rail B 8 are simultaneously slid into the left fixed slide beam 5 and the right fixed slide beam 6 from one end of the left fixed slide beam 5 and the right fixed slide beam 6 respectively through sliding, and then the position of the upper slide platform 9 is locked through the cooperation of the locking bolt 12 and the threaded tube 13, which is convenient to disassemble and ensures the structural strength of the expanded working platform 2.

[0030] Further, the detachable connecting piece 4 comprises a left fixed slide beam 5, a right fixed slide beam 6 and an upper slide platform 9 arranged vertically and in parallel with each other, the left fixed slide beam 5 is provided with a sliding edge rail A 7 sliding along the length direction thereof, the right fixed slide beam 6 is provided with a sliding edge rail B 8 sliding along the length direction thereof, the upper part of the upper slide platform 9 is connected with the sliding edge rail A 7 through an upper connecting seat 10, the bottom of the upper slide platform 9 is connected with the sliding edge rail B 8 through a lower connecting seat 11, and the end of the expanded working platform 2 is vertically welded with the bottom of the detachable connecting piece 4. The sliding edge rail A 7 and the sliding edge rail B 8 are simultaneously slid into the left fixed slide beam 5 and the right fixed slide beam 6 from one end of the left fixed slide beam 5 and the right fixed slide beam 6 respectively through sliding, and then the position of the upper slide platform 9 is locked through the cooperation of the locking bolt 12 and the threaded tube 13, which is convenient to disassemble and ensures the structural strength of the expanded working platform 2.

[0031] Further, the outer wall surface of the sliding edge rail A 7 is provided with a nylon sliding strip A 16 cooperating with the left fixed slide beam 5 to slide, and the outer wall surface of the sliding edge rail B 8 is provided with a nylon sliding strip B cooperating with the right fixed slide beam 6 to slide, which ensures the smoothness of the sliding of the sliding edge rail A 7 and the sliding edge rail B 8 during disassembly.

[0032] Further, the sliding edge rail A 7 and the sliding edge rail B 8 are both rectangular steel pipes, and the left fixed slide beam 5 and the right fixed slide beam 6 are both welded with the sedimentation tank body 1.

[0033] Further, the left fixed slide beam 5 and the right fixed slide beam 6 are both channel steels, and the openings of the two are oppositely arranged.

[0034] Further, the expanded working platform 2 and the upper slide platform 9 are both steel plates.

[0035] Further, the sedimentation tank body 1 is a steel sedimentation tank body 1, which is a structure existing in the art and is welded by steel plates and steel pipes.

[0036] Further, the outer wall of the sedimentation tank body 1 is provided with vertical reinforcing ribs 14, the left side fixed slide way beam 5 and the right side fixed slide way beam 6 are welded and fixed with the vertical reinforcing ribs 14, and the tail end of the threaded pipe 13 is connected with a tail seat 15 which is detachably mounted on the corresponding vertical reinforcing rib 14 through screws.

[0037] The iron mine tailing wastewater treatment pool has the advantages that the operator can conveniently get on the expansion operation platform to collect and sample the wastewater in the sedimentation tank body, work efficiency is improved, practicality is enhanced, the expansion operation platform can be detachably connected to the sedimentation tank body in the later period, the expansion operation platform and the detachable connecting piece have compact and reasonable overall structure, and the expansion operation platform and the detachable connecting piece are convenient to disassemble and assemble.

[0038] The iron mine tailing wastewater treatment pool has the advantages that the operator can conveniently get on the expansion operation platform to collect and sample the wastewater in the sedimentation tank body, work efficiency is improved, practicality is enhanced, the expansion operation platform can be detachably connected to the sedimentation tank body in the later period, the expansion operation platform and the detachable connecting piece have compact and reasonable overall structure, and the expansion operation platform and the detachable connecting piece are convenient to disassemble and assemble.

[0039] The iron mine tailing wastewater treatment pool has the advantages that the operator can conveniently get on the expansion operation platform to collect and sample the wastewater in the sedimentation tank body, work efficiency is improved, practicality is enhanced, the expansion operation platform can be detachably connected to the sedimentation tank body in the later period, the expansion operation platform and the detachable connecting piece have compact and reasonable overall structure, and the expansion operation platform and the detachable connecting piece are convenient to disassemble and assemble.

[0040] The basic principle, main features and advantages of the utility model are shown and described above. It should be understood by the person skilled in the art that the utility model is not limited by the above-mentioned embodiments, and the above-mentioned embodiments and the description in the specification only illustrate the principle of the utility model, and the utility model can have various changes and improvements without departing from the spirit and scope of the utility model, and these changes and improvements all fall within the scope of the utility model claimed. The scope of protection of the utility model is defined by the appended claims and their equivalents.

[0041] The parts not described in the utility model are the known technology of the person skilled in the art.

Claims

1. An iron ore mining tailings wastewater treatment pond comprising a sedimentation tank body placed on the ground, a detachable extension work platform is installed on the outer wall of one side of the sedimentation tank body, characterized in that: The expansion work platform is hingedly installed at the bottom of the side of the sedimentation tank body away from the bottom of the sedimentation tank body, the other end of the ladder is supported on the ground, the expansion work platform is detachably installed on the outer wall of the sedimentation tank body through a detachable connecting piece, the detachable connecting piece comprises a left side fixed slide beam, a right side fixed slide beam and an upper slide table arranged vertically and parallel to each other, the left side fixed slide beam is provided with a sliding edge rail A sliding along the length direction thereof, the right side fixed slide beam is provided with a sliding edge rail B sliding along the length direction thereof, the upper part of the upper slide table is connected with the sliding edge rail A through an upper connecting seat, the bottom of the upper slide table is connected with the sliding edge rail B through a lower connecting seat, and the end of the expansion work platform is vertically welded with the bottom of the detachable connecting piece.

2. The iron ore mining tailings wastewater treatment pond of claim 1, wherein, A locking bolt is further included, a through hole is formed in the middle part of the upper slide table for the locking bolt to penetrate, the threaded section of the locking bolt is threadedly connected with a threaded pipe, the threaded pipe is fixed on the outer wall of the sedimentation tank body, and after the locking bolt is connected with the threaded pipe, the sliding of the upper slide table relative to the left side fixed slide beam and the right side fixed slide beam is limited.

3. The iron ore mining tailings wastewater treatment pond of claim 2, wherein, A nylon sliding strip A is arranged on the outer wall surface of the sliding edge rail A to cooperate with the left side fixed slide beam to slide, and a nylon sliding strip B is arranged on the outer wall surface of the sliding edge rail B to cooperate with the right side fixed slide beam to slide.

4. The iron ore mining tailings wastewater treatment pond of claim 3, wherein, The left side fixed slide beam and the right side fixed slide beam are both channel steels, and the openings of the two are oppositely arranged.

5. The iron ore mining tailings wastewater treatment pond of claim 4, wherein, The expansion work platform and the upper slide table are both steel plates.

6. The iron ore mining tailings wastewater treatment pond of claim 5, wherein, The sedimentation tank body is a steel sedimentation tank body.

7. The iron ore mining tailings wastewater treatment pond of claim 6, wherein, Vertical reinforcing ribs are arranged on the outer wall of the sedimentation tank body, the left side fixed slide beam and the right side fixed slide beam are welded and fixed with the vertical reinforcing ribs, and a tail seat is connected to the tail end of the threaded pipe, and the tail seat is detachably installed on the corresponding vertical reinforcing rib through a screw.

Citation Information

Patent Citations

  • Tailing wastewater sedimentation treatment pond for iron ore mining

    CN220550078U