Building engineering construction climbing frame

The modular design of the climbing scaffolding for building construction, utilizing main columns, secondary columns, and adjustable triangular connecting frames, combined with positioning mechanisms and quick-connecting parts, solves the problem of insufficient adaptability of existing climbing scaffolding systems, enabling flexible adjustment of the work platform and improving construction safety.

CN223937594UActive Publication Date: 2026-02-24SHANDONG HANGUANG CONSTR PROJECT MANAGEMENT CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202423297042.4
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-12-31
Publication Date
2026-02-24
Estimated Expiration
2034-12-31

AI Technical Summary

Technical Problem

Existing climbing scaffolding systems have limited adaptability, and fixed components are difficult to respond quickly to changes in construction progress, especially when adjusting the height or position of the work platform.

Method used

The modular design includes main columns, secondary columns, adjustable triangular connecting frames, and workbenches. The climbing frame can be flexibly assembled and disassembled through positioning mechanisms and quick-connect parts. The height of the workbench can be adjusted according to needs, and protective netting and fences enhance safety.

Benefits of technology

It improves the connection flexibility and adaptability of the climbing scaffold, enables rapid positioning and installation of the workbench, and enhances the safety and adaptability of construction.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN223937594U_ABST
    Figure CN223937594U_ABST
Patent Text Reader

Abstract

The utility model discloses a building engineering construction climbing frame which comprises a main stand column, an auxiliary stand column, an adjustable triangular connecting frame and a workbench. The main stand columns and the auxiliary stand columns are connected through at least one adjustable triangular connecting frame to form climbing frame supports, the climbing frame supports are perpendicular to the ground and are evenly arranged in the horizontal direction, and the climbing frame supports are connected to form a climbing frame. The workbench is arranged between the adjacent sets of climbing frame supports and fixed to the top face of the adjustable triangular connecting frame, and the adjustable triangular connecting frame is arranged between the main stand column and the auxiliary stand column in a sliding mode and limited and fixed through the positioning mechanism. Compared with the prior art, the modular climbing frame has the advantages that the modular climbing frame is introduced, the working table on the climbing frame is connected and fixed through assembly, the mounting height of the working table can be adjusted according to construction requirements, and the connecting flexibility, adaptability and safety of the climbing frame are remarkably improved through cooperation.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This utility model relates to the field of building engineering technology, specifically to a climbing formwork for building construction. Background Technology

[0002] In modern building construction, climbing formwork is widely used for the exterior wall construction of high-rise buildings. Traditional climbing formwork systems consist of multiple support poles, with support plates fixed between the poles, and then fitted with safety netting.

[0003] However, existing climbing scaffolding systems have limited adaptability, and the fixed component design makes it difficult to respond quickly to changes in the construction schedule, which is particularly inconvenient when it is necessary to temporarily adjust the height or position of the work platform.

[0004] Therefore, designing a climbing scaffold for building construction that is easy to adjust is particularly important. Utility Model Content

[0005] The technical problem this invention aims to solve is that fixed structures are inconvenient to assemble and difficult to adjust as needed. This invention provides a construction climbing formwork that is easy to adjust.

[0006] To solve the above-mentioned technical problems, the technical solution provided by this utility model is: a construction climbing formwork, including a main column, a secondary column, an adjustable triangular connecting frame and a work platform;

[0007] The main column and the secondary column are connected by at least one adjustable triangular connecting frame to form a climbing frame support. The climbing frame support is set vertically to the ground and multiple climbing frame supports are evenly arranged in the horizontal direction. Multiple climbing frame supports are connected to form a climbing frame.

[0008] The workbench is set between adjacent sets of climbing frame supports and fixed on the top surface of the adjustable triangular connecting frame. The adjustable triangular connecting frame is slidably set between the main column and the secondary column and is limited and fixed by the positioning mechanism.

[0009] As an improvement, the main column and the secondary column are provided with sliding grooves, and the adjustable triangular connecting frame slides between the main column and the secondary column through the sliding grooves;

[0010] The positioning mechanism includes positioning bolts and through holes. The through holes are opened on the side walls of the main column and the secondary column, and multiple through holes are evenly arranged in the vertical direction. The positioning bolt passes through any of the through holes and is fixedly connected to the adjustable triangular connecting frame, which facilitates the assembly of the device according to construction needs, thereby meeting different construction requirements.

[0011] As an improvement, the right-angled side of the adjustable triangular connecting frame is vertically located between the main column and the secondary column. A set of quick connectors is held on the right-angled side. The quick connectors have barbed structures at both ends. The bottom surface of the workbench has a slot for matching the quick connectors. After the workbench is positioned by the quick connectors on the adjacent climbing frame support, bolts are used to connect the workbench to the adjustable triangular connecting frame, which facilitates quick positioning of the workbench and makes installation and operation easier.

[0012] As an improvement, a protective net is also included, which is fixed to one side of the climbing frame by wire ties.

[0013] As an improvement, a fence is placed on the other side of the protective netting on the adjacent climbing frame support. The fence is set close to the top surface of the workbench, and the fence can improve the safety of the device.

[0014] The advantages of this utility model compared with the prior art are: the introduction of a modular climbing frame, the workbench on the climbing frame is fixed by assembly connection, the installation height of the workbench can be adjusted according to construction needs, which significantly improves the connection flexibility, adaptability and safety of the climbing frame;

[0015] The quick-connectors allow for rapid snap-fit ​​positioning of the workbench and also enable snap-fit ​​positioning between multiple climbing frame bodies, facilitating assembly and disassembly. Attached Figure Description

[0016] Figure 1 This is a first perspective view of a climbing scaffold for building construction according to this utility model.

[0017] Figure 2 This is a second perspective view of a climbing scaffold for building construction according to this utility model.

[0018] Figure 3 This is a diagram showing the assembly state of multiple climbing frame supports for a construction climbing frame according to this utility model.

[0019] Figure 4 This is a three-dimensional view of a climbing scaffold support for a building construction climbing scaffold, according to this utility model.

[0020] Figure 5 yes Figure 4 A schematic diagram of the structure of part A.

[0021] As shown in the figure: 1. Main column; 2. Secondary column; 3. Adjustable triangular connecting frame; 4. Workbench; 5. Protective net; 7. Positioning bolt; 8. Through hole; 9. Quick connector; 14. Fence; 15. Slide groove. Detailed Implementation

[0022] In the description of this utility model, it should be understood that the terms "center," "lateral," "upper," "lower," "left," "right," "vertical," "horizontal," "top," "bottom," "inner," and "outer," etc., indicating orientation or positional relationships based on the orientation or positional relationships shown in the accompanying drawings, are only for the convenience of describing this utility model and simplifying the description, and do not indicate or imply that the device or element referred to must have a specific orientation, or be constructed and operated in a specific orientation, and therefore should not be construed as a limitation of this utility model. Furthermore, the terms "first" and "second" are used for descriptive purposes only and should not be construed as indicating or implying relative importance or implicitly specifying the number of indicated technical features. Thus, a feature defined as "first" or "second" may explicitly or implicitly include one or more of that feature. In the description of this utility model, unless otherwise stated, "a plurality of" means two or more. Additionally, the term "comprising" and any variations thereof are intended to cover non-exclusive inclusion.

[0023] The present invention will now be described in further detail with reference to the accompanying drawings.

[0024] A type of climbing formwork for building construction, combined with attached Figure 1-5 As shown, it includes a main column 1, a secondary column 2, and an adjustable triangular connecting frame 3. The main column 1 and the secondary column 2 are connected by at least one adjustable triangular connecting frame 3 to form a climbing frame support. The climbing frame support is set vertically to the ground and multiple supports are evenly arranged in the horizontal direction. Multiple climbing frame supports are connected to form a climbing frame.

[0025] The workbench 4 is positioned between adjacent sets of climbing scaffold supports and fixed to the top surface of the adjustable triangular connecting frame 3. The adjustable triangular connecting frame is slidably positioned between the main column 1 and the secondary column 2 and is fixed by a positioning mechanism. The positioning mechanism includes positioning bolts 7, which pass through pre-drilled through holes 8 on the main column 1 and the secondary column 2 and are fixedly connected to the adjustable triangular connecting frame. Multiple through holes 8 are evenly arranged along the vertical direction to facilitate assembly of the device according to construction needs, thereby meeting different construction requirements. The right-angled side of the adjustable triangular connecting frame 3 is vertically located between the main column 1 and the secondary column 2, and a set of quick connectors 9 are clamped on the right-angled side. The quick connectors 9 have barbed structures at both ends. The bottom surface of the workbench 4 has a slot for matching the quick connectors 9. After the workbench 4 is positioned by the quick connectors 9 on the adjacent climbing scaffold supports, it is connected to the adjustable triangular connecting frame 3 with bolts, which facilitates quick positioning of the workbench 4 and makes installation easier.

[0026] Protective netting 5 is fixed to one side of the climbing frame with wire ties to improve the safety of the device.

[0027] The adjacent climbing frame support is fitted with a fence 14 located on the other side of the protective net 5. The fence 14 is set close to the top surface of the workbench 4. The fence can improve the safety of the device.

[0028] In a specific implementation of this utility model, the above structure is used to first assemble multiple climbing scaffold supports as needed (using adjustable triangular connecting frames 3 to fix the climbing scaffold supports). During assembly, the adjustable triangular connecting frames 3 are fixed at a suitable height according to construction requirements.

[0029] Afterwards, multiple climbing frame supports are connected. When assembling, the workbench 4 is first placed between adjacent climbing frame supports by the barbed structure on the quick connector 9, and then fixed with bolts. The protective net 5 is fixed to one side of the climbing frame by tie wire, and the fixed fence is placed on the other side between adjacent climbing frame supports.

[0030] When in use, the entire climbing frame is placed and fixed on one side of the building, with the fence 14 close to the building, and construction workers stand on the work platform 4 to carry out construction work.

[0031] The present invention and its embodiments have been described above. This description is not restrictive, and the accompanying drawings are only one embodiment of the present invention; the actual structure is not limited thereto. In conclusion, if those skilled in the art are inspired by this description and design similar structures and embodiments without departing from the inventive spirit of the present invention, such designs should fall within the protection scope of the present invention.

Claims

1. A climbing scaffold for building construction, characterized in that: It includes a main column (1), a secondary column (2), an adjustable triangular connecting frame (3), and a worktable (4). The main column (1) and the secondary column (2) are connected by at least one adjustable triangular connecting frame (3) to form a climbing frame support. The climbing frame support is set vertically to the ground and multiple climbing frame supports are evenly set in the horizontal direction. Multiple climbing frame supports are connected to form a climbing frame. The workbench (4) is set between an adjacent set of climbing frame supports and fixed on the top surface of the adjustable triangular connecting frame (3). The adjustable triangular connecting frame is slidably set between the main column (1) and the secondary column (2) and is fixed by a positioning mechanism.

2. The climbing formwork for building construction according to claim 1, characterized in that: The main column (1) and the secondary column (2) are provided with sliding grooves (15), and the adjustable triangular connecting frame (3) slides between the main column (1) and the secondary column (2) through the sliding grooves (15); The positioning mechanism includes a positioning bolt (7) and a through hole (8). The through holes (8) are opened on the side walls of the main column (1) and the secondary column (2), and multiple through holes are evenly arranged in the vertical direction. The positioning bolt (7) passes through any through hole (8) and is fixedly connected to the adjustable triangular connecting frame.

3. The climbing scaffolding for building construction according to claim 1, characterized in that: The right-angled side of the adjustable triangular connecting frame (3) is vertically located between the main column (1) and the secondary column (2). A set of quick connectors (9) is placed on the right-angled side. The quick connectors (9) have barbed structures at both ends. The bottom surface of the workbench (4) is provided with a slot to match the quick connectors (9). After the workbench (4) is positioned by the quick connectors (9) on the adjacent climbing frame support, bolts are used to pass through the workbench (4) and connect it to the adjustable triangular connecting frame (3).

4. The climbing formwork for building construction according to claim 1, characterized in that: It also includes a protective net (5), which is fixed to one side of the climbing frame by wire.

5. A climbing scaffold for building construction according to claim 4, characterized in that: The adjacent climbing frame support is fitted with a fence (14) located on the other side of the protective net (5), and the fence (14) is set close to the top surface of the workbench (4).