Building construction pouring formwork

By designing structures such as the base frame, bottom formwork base, formwork adjustment components, and expansion slots, the problems of cumbersome assembly and inconvenient dimensions of existing formwork have been solved, enabling rapid assembly and stability of the formwork, and improving construction efficiency and adaptability.

CN223991573UActive Publication Date: 2026-03-13SHANXI CHANGFENG WANLI CONSTRUCTION ENGINEERING CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2025-04-10
Publication Date
2026-03-13

AI Technical Summary

Technical Problem

In current building construction, the assembly of concrete pouring formwork is cumbersome, and the fixed dimensions are not easy to adjust, resulting in low construction efficiency and poor quality.

Method used

The structure includes a base frame, bottom mold base, template adjustment assembly, and template. The template can be quickly assembled and its length adjusted by means of a two-way screw rod, mounting bracket, and guide rod. The template's stability is ensured by the detachable connection of the expansion slot and the expansion template, and by the fixing method of positioning ribs and positioning pins.

Benefits of technology

It enables rapid mold assembly and disassembly, adapts to the size requirements of different construction scenarios, and improves construction efficiency, adaptability, and stability of the mold.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN223991573U_ABST
    Figure CN223991573U_ABST
Patent Text Reader

Abstract

The utility model discloses a building construction pouring template which comprises a bottom frame, a bottom die holder, templates and a template adjusting assembly, the bottom die holder is installed on the bottom frame, the template adjusting assembly is installed on the bottom frame and located below the bottom die holder, and the templates are symmetrically installed at the two ends of the template adjusting assembly and located above the bottom die holder. The die plate adjusting assembly is used for adjusting and controlling die opening and closing of the die plate, and guiding sealing strips are symmetrically arranged on the two sides of the top of the bottom die base and used for conducting sealing, guiding and limiting on the die plate. The utility model relates to the technical field of building template tools, through the template, splicing can be conveniently carried out, the length of the template can be adjusted according to use requirements, and the use convenience and flexibility are improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This utility model relates to the field of formwork and tooling technology for building construction, specifically to formwork for pouring concrete during building construction. Background Technology

[0002] Currently, in building construction, the assembly of concrete pouring formwork typically requires the use of multiple fixing devices, and each step is quite cumbersome. This assembly process not only increases construction time but also makes disassembly and reassembly of the formwork inconvenient, leading to reduced construction efficiency. Furthermore, most existing formwork is of fixed size, making it difficult to adjust its length according to actual needs to adapt to different pouring requirements, further affecting pouring speed and quality. Therefore, improvements are needed to address this issue. Utility Model Content

[0003] In view of the above situation and to overcome the current technical defects, this utility model provides a construction pouring template that is easy to use. This template can be easily assembled and its length can be adjusted according to the needs of use, thus improving the convenience and flexibility of use.

[0004] The technical solution adopted by this utility model is as follows: The building construction pouring template provided by this solution includes a base frame, a bottom formwork base, a template, and a template adjustment assembly. The bottom formwork base is installed on the base frame, and the template adjustment assembly is installed on the base frame and located below the bottom formwork base. The template is symmetrically installed at both ends of the template adjustment assembly and located above the bottom formwork base. The template adjustment assembly is used for adjusting and controlling the opening and closing of the template. Guide sealing strips are symmetrically provided on both sides of the top of the bottom formwork base. The guide sealing strips are used for sealing, guiding, and limiting the template.

[0005] Preferred technical solution 1: The template adjustment assembly includes a bidirectional lead screw, a mounting bracket, and guide rods. The bidirectional lead screw is rotatably located in the lower middle part of the base frame. One end of the bidirectional lead screw is provided with a hand crank. The mounting bracket is symmetrically threaded to both ends of the bidirectional lead screw. The guide rods are symmetrically installed at the lower end of the base frame and located on both sides of the bidirectional lead screw. The guide rods are used to guide and limit the mounting bracket.

[0006] Preferred technical solution 2: The template consists of two sets of templates arranged in a U-shape, and the two sets of templates are detachably installed on the mounting frame by bolts.

[0007] Preferred technical solution 3: The front ends of both sides of the template are symmetrically provided with expansion grooves, and an expansion template is sealed and inserted into the expansion groove. The expansion template is sealed and fixed to the two sets of templates through the expansion groove.

[0008] Preferred technical solution four: Positioning ribs can be detachably installed on both the template and the extended template. Positioning pins are provided on both sides of the lower end of the positioning ribs. Positioning pin holes that are adapted to the positioning pins are provided on the template and the extended template. The positioning ribs fix and limit the template and the extended template through the cooperation of the positioning pins and the positioning pin holes.

[0009] Preferred technical solution five: The extended template and the positioning rib are provided in multiple sets, wherein the lengths of the multiple sets of extended templates are different.

[0010] The beneficial effects of this utility model by adopting the above structure are as follows:

[0011] 1. The template size can be easily adjusted by the template adjustment components, thereby enabling quick template closing and opening and closing, reducing the tedious disassembly and reassembly of templates during construction.

[0012] 2. By using the expansion slots on the template and multiple sets of expansion templates of different lengths, the length of the template can be flexibly adjusted according to different pouring requirements, so as to adapt to the size requirements of different construction scenarios, thereby improving the adaptability and versatility of the template.

[0013] 3. The positioning ribs and positioning pins ensure the fixation and stability of the formwork and extended formwork during use, preventing the formwork from shifting or deforming during the pouring process. Attached Figure Description

[0014] The accompanying drawings are provided to further illustrate the present invention and form part of the specification. They are used together with the embodiments of the present invention to explain the present invention, but do not constitute a limitation thereof. In the drawings:

[0015] Figure 1 This is a three-dimensional structural diagram of the formwork for pouring concrete during building construction according to this utility model. Figure 1 ;

[0016] Figure 2 This is a three-dimensional structural diagram of the formwork for pouring concrete during building construction according to this utility model. Figure 1 ;

[0017] Figure 3 This is a three-dimensional structural diagram of the formwork for pouring concrete during building construction according to this utility model. Figure 3 ;

[0018] Figure 4 This is a schematic diagram of the combination of the template and the extended template for the building construction pouring template of this utility model.

[0019] The components are: 1. base frame, 2. bottom mold base, 3. template, 4. template adjustment assembly, 5. guide sealing strip, 6. two-way screw, 7. mounting bracket, 8. guide rod, 9. hand crank, 10. expansion slot, 11. expansion template, 12. positioning rib, 13. positioning pin, and 14. positioning pin hole. Detailed Implementation

[0020] The technical solutions of the present utility model will be clearly and completely described below with reference to the accompanying drawings of the embodiments of the present utility model. Obviously, the described embodiments are only some embodiments of the present utility model, and not all embodiments. All other embodiments obtained by those skilled in the art based on the embodiments of the present utility model without creative effort are within the protection scope of the present utility model.

[0021] It should be noted that the terms “front,” “back,” “left,” “right,” “up,” and “down” used in the following description refer to the directions shown in the attached diagram, while the terms “inside” and “outside” refer to the directions toward or away from the geometric center of a specific component, respectively.

[0022] Example 1

[0023] like Figure 1 , Figure 2 , Figure 3 and Figure 4 As shown, the technical solution adopted by this utility model is as follows: The building construction pouring template provided by this solution includes a base frame 1, a bottom formwork base 2, a template 3, and a template adjustment assembly 4. The bottom formwork base 2 is installed on the base frame 1, and the template adjustment assembly 4 is installed on the base frame 1 and located below the bottom formwork base 2. The template 3 is symmetrically installed at both ends of the template adjustment assembly 4 and located above the bottom formwork base 2. The template adjustment assembly 4 is used for adjusting and controlling the opening and closing of the template 3. Guide sealing strips 5 are symmetrically provided on both sides of the top of the bottom formwork base 2. The guide sealing strips 5 are used for sealing, guiding, and limiting the template 3. The template adjustment assembly 4 includes a bidirectional screw rod 6 and an installation... The frame 7 and guide rod 8 are provided. The bidirectional screw 6 is rotatably located in the lower middle part of the base frame 1. One end of the bidirectional screw 6 is provided with a hand crank 9. The mounting frame 7 is symmetrically threaded to both ends of the bidirectional screw 6. The guide rod 8 is symmetrically installed at the lower end of the base frame 1 and located on both sides of the bidirectional screw 6. The guide rod 8 is used to guide and limit the mounting frame 7. The template 3 consists of two sets of templates 3 arranged in a U-shape. The two sets of templates 3 are detachably installed on the mounting frame 7 by bolts. The front ends of both sides of the template 3 are symmetrically provided with expansion grooves 10. Expansion templates 11 are sealed and inserted into the expansion grooves 10. The expansion templates 11 are sealed and fixed to the two sets of templates 3 through the expansion grooves 10.

[0024] Rotating the hand crank 9 in the forward direction drives the bidirectional lead screw 6 to rotate, which in turn causes the mounting frame 7 to move the two sets of U-shaped templates 3 toward each other. By inserting the expansion template 11 into the expansion slot 10, the template 3 forms a closed mold, which facilitates the pouring of concrete.

[0025] Example 2

[0026] Based on Example 1, to facilitate adjustment of the template length according to usage needs, as shown in the instruction manual... Figure 3 and Figure 4 As shown, the extended template 11 is provided in multiple sets, and the lengths of the multiple sets of extended template 11 are different. Positioning ribs 12 can be detachably installed on both template 3 and extended template 11. Positioning pins 13 are provided on both sides of the lower end of the positioning ribs 12. Positioning pin holes 14 that are adapted to the positioning pins 13 are provided on template 3 and extended template 11. The positioning ribs 12 fix and limit the template 3 and extended template 11 through the cooperation of positioning pins 13 and positioning pin holes 14.

[0027] When it is necessary to adjust the length of the casting template, extension templates 11 of different lengths can be selected to cooperate with template 3 so as to adjust the size according to the casting needs of the template. After the template is poured with concrete, the positioning rib plate 12 is inserted into the positioning pin hole 14 on template 3 and extension template 11 through positioning pin rod 13 to improve the stability of the template.

[0028] It should be noted that, in this document, relational terms such as "first" and "second" are used only to distinguish one entity or operation from another, and do not necessarily require or imply any such actual relationship or order between these entities or operations. Furthermore, the terms "comprising," "including," or any other variations thereof are intended to cover non-exclusive inclusion, such that a process, method, material, or apparatus that comprises a list of elements includes not only those elements but also other elements not expressly listed, or elements inherent to such process, method, material, or apparatus.

[0029] Unless otherwise expressly specified and limited, the terms "set up," "install," "connect," and "link" should be interpreted broadly. For example, they can refer to a fixed connection, a detachable connection, or an integral connection; they can refer to a mechanical connection or an electrical connection; they can refer to a direct connection or an indirect connection through an intermediate medium; and they can refer to the internal connection between two components. Those skilled in the art can understand the specific meaning of the above terms in this application based on the specific circumstances.

[0030] Although embodiments of the present invention have been shown and described, it will be understood by those skilled in the art that various changes, modifications, substitutions and alterations can be made to these embodiments without departing from the principles and spirit of the present invention, the scope of which is defined by the appended claims and their equivalents.

Claims

1. A construction formwork for pouring concrete, comprising a base frame (1) and a base formwork (2), characterized in that: The template (3) and the template adjusting assembly (4) are also included, the bottom die base (2) is installed on the chassis (1), the template adjusting assembly (4) is installed on the chassis (1) and below the bottom die base (2), the template (3) is symmetrically installed on both ends of the template adjusting assembly (4) and above the bottom die base (2), the template adjusting assembly (4) is used for mold opening and closing adjustment control of the template (3), and the guiding sealing strips (5) are symmetrically arranged on both sides of the top of the bottom die base (2), and the guiding sealing strips (5) are used for sealing, guiding and limiting the template (3).

2. The building construction formwork according to claim 1, wherein: The template adjusting assembly (4) comprises a bidirectional screw rod (6), a mounting frame (7) and a guide rod (8), the bidirectional screw rod (6) is rotatably arranged in the middle of the chassis (1), one end of the bidirectional screw rod (6) is provided with a hand crank (9), the mounting frame (7) is symmetrically and threadedly connected to both ends of the bidirectional screw rod (6), and the guide rod (8) is symmetrically arranged at the lower end of the chassis (1) and on both sides of the bidirectional screw rod (6). The guide rod (8) is used for guiding and limiting the mounting frame (7).

3. The building construction formwork according to claim 1, wherein: The template (3) is two groups of templates (3) arranged in a U-shaped structure, and the two groups of templates (3) are detachably installed on the mounting frame (7) through bolts.

4. The construction formwork according to claim 1 or 3, wherein: The template (3) is two groups of templates (3) arranged in a U-shaped structure, and the two groups of templates (3) are detachably installed on the mounting frame (7) through bolts.

5. The building construction formwork according to claim 4, wherein: The template (3) and the expansion template (11) are detachably installed with the positioning rib plate (12), the positioning rib plate (12) is provided with the positioning pin rod (13) on both sides of the lower end, the template (3) and the expansion template (11) are provided with the positioning pin hole (14) matched with the positioning pin rod (13), and the positioning rib plate (12) is fixed and limited to the template (3) and the expansion template (11) through cooperation of the positioning pin rod (13) and the positioning pin hole (14).

6. The building construction formwork according to claim 5, wherein: The expansion template (11) and the positioning rib plate (12) are provided with a plurality of groups, and the lengths of the plurality of groups of the expansion template (11) are different.