Climbing device for building construction
By designing a foldable climbing device for construction, utilizing risers, curved guardrails, and locking mechanisms, the problem of high transportation costs caused by the large space occupied by protective structures was solved, thus achieving convenient transportation.
Patent Information
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2025-03-05
- Publication Date
- 2026-03-20
AI Technical Summary
Existing construction climbing devices have protective structures that occupy a large space and cannot be folded, increasing transportation costs.
A climbing device was designed, comprising a riser, an arc-shaped guardrail, a linkage rod, and a locking mechanism. The arc-shaped guardrail can be folded using the linkage rod and the locking mechanism, reducing the area occupied.
The protective device can be folded, which reduces transportation costs and facilitates transportation.
Smart Images

Figure CN224017154U_ABST
Abstract
Description
TECHNICAL FIELD
[0001] The utility model relates to the technical field of building construction, specifically is a kind of climbing device for building construction. BACKGROUND
[0002] Building construction refers to the production activities in the implementation phase of engineering construction, and is the construction process of various buildings, which can also be described as the process of converting various lines on design drawings into physical objects at specified locations. It includes foundation engineering construction, main structure construction, roofing engineering construction, decoration engineering construction, etc. The place of construction work is called "building construction site" or "construction site". In the process of building construction, climbing ladder is the instrument commonly used by people.
[0003] In the patent with announcement number CN220415237U, a kind of climbing device for building construction with protective structure, including support rod, pedal, first rotating rod, limiting stop lever, linkage rod, second rotating rod. In the device, protective space is formed by setting the protective net of semicircular structure, so that the staff can climb inside the protective net, and then protect the upper space of the staff, avoid high-altitude falling object to hurt the staff, eliminate security risks.
[0004] The above patent has the following problems:
[0005] The occupation space of protective structure is large, and the protective structure is welded on the climbing device, which cannot be folded, increases transportation cost, and brings inconvenience to transportation, so we launch a kind of climbing device for building construction. UTILITY MODEL CONTENT
[0006] The utility model aims at providing a kind of climbing device for building construction, it is convenient to fold protective device, substantially reduce the occupation area of protective device, reduce transportation cost, facilitate transportation, to solve the problems raised in the above background technology.
[0007] To achieve the above object, the utility model provides the following technical scheme:
[0008] A kind of climbing device for building construction, including two vertical pipes, multiple horizontal rods are evenly welded between the two vertical pipes, multiple arc-shaped protective rods are evenly rotatably arranged between the pipe walls of the two vertical pipes opposite each other, and a rotating shaft is rotatably arranged at the outer pipe wall of the two vertical pipes opposite each other at the position of the multiple arc-shaped protective rods. The two ends of the arc-shaped protective rod are fixedly connected with the corresponding rotating shaft, and the two ends of the multiple arc-shaped protective rods are rotatably connected with the outer pipe wall of the vertical pipe through rolling bearings. The vertical pipe is provided with a locking mechanism for locking the multiple arc-shaped protective rods.
[0009] Preferably, the locking mechanism comprises a movable rod, the movable rod is slidably arranged in the stand pipe, a spring is fixedly arranged on the upper end of the movable rod, the upper end of the spring is fixedly connected with the top of the stand pipe, a strip-shaped hole is arranged on the pipe wall of the stand pipe at the upper side of the rotating shaft, a horizontal push rod is slidably arranged in the strip-shaped hole, one end of the push rod is fixedly connected with the movable rod, a vertical clamping rod is fixedly arranged on the lower side of the other end of the push rod, and a clamping hole matched with the clamping rod is arranged on the arc-shaped protection rod.
[0010] Preferably, one end of the push rod outside the stand pipe is fixedly provided with a pull ring.
[0011] Preferably, the upper side of the rod wall of the cross rod is fixedly provided with an antiskid pad.
[0012] Preferably, the antiskid pad is a high-temperature-resistant rubber pad.
[0013] Preferably, linkage rods are hingedly connected between the middle portions of the plurality of arc-shaped protection rods.
[0014] Compared with the prior art, the building construction climbing device has the beneficial effects that:
[0015] The building construction climbing device, through the linkage rod, the arc-shaped protection rod, the stand pipe, the antiskid pad, the cross rod, the movable rod, the rotating shaft, the push rod, the pull ring, the clamping rod and the spring, the pull ring is pulled upward, the movable rod is driven upward by the push rod, the spring is pressed, the movable rod drives the plurality of push rods to move upward, when the clamping rods at the lower ends of the plurality of push rods are all moved out of the clamping holes, the plurality of arc-shaped protection rods are simultaneously rotated downward, the folding of the protection device is facilitated, the occupied area of the protection device is greatly reduced, the transportation cost is reduced, and transportation is facilitated. BRIEF DESCRIPTION OF DRAWINGS
[0016] Figure 1 It is a structural schematic view of a building construction climbing device.
[0017] Figure 2 It is an internal structural schematic view of a building construction climbing device.
[0018] Figure 3 It is Figure 1 It is an enlarged schematic view of a partial A portion.
[0019] Figure 4 It is Figure 2 It is an enlarged schematic view of a partial B portion.
[0020] In the figure: 1, linkage rod; 2, arc-shaped protection rod; 3, stand pipe; 4, antiskid pad; 5, cross rod; 6, movable rod; 7, rotating shaft; 8, push rod; 9, pull ring; 10, clamping rod; 11, spring. DETAILED DESCRIPTION
[0021] Clearly, the described embodiments are merely a part of the embodiments of the present application, rather than all the embodiments. Based on the embodiments of the present application, all other embodiments obtained by those skilled in the art without creative efforts under the premise that no creative efforts are made belong to the scope of protection of the present application.
[0022] Please refer to Figures 1 to 4 The present application provides a technical scheme:
[0023] A climbing device for building construction, comprising two vertical pipes 3, a plurality of horizontal rods 5 are uniformly welded between the two vertical pipes 3, a plurality of arc-shaped protective rods 2 are uniformly rotatably arranged between the pipe walls on the sides of the two vertical pipes 3 away from each other, and a rotating shaft 7 is rotatably arranged at the outer pipe wall on the side of the two vertical pipes 3 away from each other at the plurality of arc-shaped protective rods 2, the two ends of the arc-shaped protective rod 2 are fixedly connected with the corresponding rotating shaft 7, the two ends of the plurality of arc-shaped protective rods 2 are rotatably connected with the outer pipe wall of the vertical pipe 3 through rolling bearings, and the vertical pipe 3 is provided with a locking mechanism capable of locking the plurality of arc-shaped protective rods 2.
[0024] The locking mechanism comprises a movable rod 6, the movable rod 6 is slidingly arranged in the vertical pipe 3, a spring 11 is fixedly arranged at the upper end of the movable rod 6, the upper end of the spring 11 is fixedly connected with the top of the vertical pipe 3, a strip-shaped hole is formed in the pipe wall of the vertical pipe 3 at the upper side of the rotating shaft 7, a horizontal push rod 8 is slidingly arranged in the strip-shaped hole, one end of the push rod 8 is fixedly connected with the movable rod 6, and a vertical clamping rod 10 is fixedly arranged at the other end of the push rod 8.
[0025] One end of the push rod 8 located outside the vertical pipe 3 is fixedly provided with a pull ring 9, the pull ring 9 facilitates pulling the push rod 8 and moving the clamping rod 10 out of the clamping hole.
[0026] A non-slip pad 4 is fixedly arranged at the upper side of the rod wall of the horizontal rod 5, and the non-slip pad 4 improves the non-slip property of the upper end of the horizontal rod 5.
[0027] The non-slip pad 4 is a high-temperature-resistant rubber pad, which is not easy to deform under high temperature and has a long service life.
[0028] Linkage rods 1 are hingedly connected between the middle portions of the plurality of arc-shaped protective rods 2, and the linkage rods 1 can simultaneously drive the plurality of arc-shaped protective rods 2 to move.
[0029] When folding, the pull ring 9 is pulled upward, the pull ring 9 drives the movable rod 6 to slide upward through the push rod 8, the spring 11 is simultaneously compressed, the movable rod 6 drives the plurality of push rods 8 to move upward, when the clamping rods 10 at the lower ends of the plurality of push rods 8 are all moved out of the clamping holes, the plurality of arc-shaped protective rods 2 are simultaneously rotated downward, the folding of the protective device is facilitated, the occupied area of the protective device is greatly reduced, the transportation cost is reduced, and transportation is facilitated.
[0030] While the embodiments of the present application have been illustrated and described, it will be understood by those skilled in the art that various changes, modifications, substitutions and alterations can be made therein without departing from the spirit and scope of the application, which is defined by the appended claims and their equivalents.
Claims
1. A climbing device for building construction, comprising two risers (3), characterized in that: Multiple crossbars (5) are evenly welded between the two risers (3). Multiple arc-shaped protective rods (2) are evenly rotated between the opposite sides of the pipe walls of the two risers (3). Rotating shafts (7) are rotatably provided on the opposite sides of the outer pipe walls of the two risers (3) at the multiple arc-shaped protective rods (2). The two ends of the arc-shaped protective rods (2) are fixedly connected to the corresponding rotating shafts (7). The two ends of the multiple arc-shaped protective rods (2) are rotatably connected to the outer pipe wall of the riser (3) through rolling bearings. A locking mechanism is provided inside the riser (3) to lock the multiple arc-shaped protective rods (2).
2. The climbing device for building construction according to claim 1, characterized in that: The locking mechanism includes a movable rod (6), which is slidably disposed inside the riser (3). A spring (11) is fixedly disposed at the upper end of the movable rod (6). The upper end of the spring (11) is fixedly connected to the top of the riser (3). A strip-shaped hole is opened on the wall of the riser (3) above the rotating shaft (7). A horizontal push rod (8) is slidably disposed inside the strip-shaped hole. One end of the push rod (8) is fixedly connected to the movable rod (6). A vertical locking rod (10) is fixedly disposed on the lower side of the other end of the push rod (8). A locking hole that cooperates with the locking rod (10) is opened on the arc-shaped protective rod (2).
3. The climbing device for building construction according to claim 2, characterized in that: The push rod (8) is fixed with a pull ring (9) at one end outside the riser (3).
4. The climbing device for building construction according to claim 1, characterized in that: The upper side of the crossbar (5) is fixed with an anti-slip pad (4).
5. A climbing device for building construction according to claim 4, characterized in that: The anti-slip mat (4) is a high-temperature resistant rubber mat.
6. A climbing device for building construction according to claim 1, characterized in that: A linkage rod (1) is hinged together between the middle parts of the multiple arc-shaped protective rods (2).