Building structure suitable for rural dwellings
By laying brick piers in the foundation construction channel and using concrete filling layers and reinforcing rods to form a high-strength load-bearing system, the problem of changes in the foundation channel affecting the stability of the building was solved, and the bearing capacity of the foundation and the overall safety of the building were improved.
Patent Information
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- 刘鹏权
- Filing Date
- 2025-04-27
- Publication Date
- 2026-04-21
AI Technical Summary
After existing building foundations are constructed and treated inside the foundation channel, the foundation channel is prone to changes after long-term use, affecting the stability of the base frame and building structure.
Piers are dug at equal intervals in the construction channel of the building foundation, and brick piers are laid in the pits. The gap between the brick piers and the pits is filled with concrete. Reinforcing rods are inserted into the side holes to form a tightly integrated structure. The brick piers and the top layer are laid with bricks and combined with concrete pouring to form a high-strength load-bearing system.
It enhances the foundation's resistance to overturning, improves the building's load-bearing capacity, ensures the stability and safety of the building structure, and adapts to diverse building needs, including the load-bearing requirements of multi-story buildings.
Smart Images

Figure CN224148754U_ABST
Abstract
Description
Technical Field
[0001] This utility model belongs to the field of building structure technology, and more specifically, it relates to building structures suitable for rural dwellings. Background Technology
[0002] With the deepening of rural revitalization and the integration of urban and rural development, rural areas have put forward higher requirements for the functionality, comfort and sustainability of residential buildings under the influence of multiple factors such as industrial upgrading, changes in population structure and transformation of lifestyle. Traditional rural houses are mostly built with materials such as brick, wood, earth and stone. At the same time, the foundation needs to be laid with bricks and stones in the early stage of construction. In order to increase the comfort of living, a building structure is needed.
[0003] Based on existing technology, it has been found that existing building foundations are usually constructed and treated inside the foundation channel. In order to maintain the stability of the foundation, the foundation and the foundation channel must be consistent. However, after long-term use, the foundation channel is prone to change, which will affect the base frame and building structure. Utility Model Content
[0004] In order to solve the above-mentioned technical problems, this utility model relates to a building structure applicable to rural dwellings, which solves the problem that the existing building foundations are usually built inside the foundation channel. In order to maintain the stability of the foundation, the foundation and the foundation channel must be consistent. However, after long-term use, the foundation channel is prone to change, which affects the base frame and building structure.
[0005] This utility model provides a building structure suitable for rural dwellings, achieved through the following specific technical means:
[0006] A building structure suitable for rural dwellings includes: a ground layer; a construction path is provided on the surface of the ground layer; piers are provided at equal intervals inside the construction path; side insertion holes are provided at equal intervals on the inner wall of the piers; brick piers are built inside the piers using concrete; concrete is poured into the gap between the brick piers and the piers; reinforcing rods are provided in the gap between the brick piers; and a top layer is fixed to the top of the piers using concrete.
[0007] Preferably, the construction road is excavated according to the distribution of the building foundation.
[0008] Preferably, the brick pier is made of bricks.
[0009] Preferably, the concrete between the brick pier and the pit forms a concrete filling layer after solidification.
[0010] Preferably, the reinforcing rod is fixed within the concrete filling layer, and the end of the reinforcing rod is inserted into the side insertion hole.
[0011] Preferably, the top layer is laid inside the construction channel; the top layer is made of bricks.
[0012] The architectural structure for rural dwellings proposed in this utility model has the following beneficial effects:
[0013] 1. By building brick piers in the pit and filling the gap between the brick piers and the pit with concrete filling layer, a tight and stable structure is formed. One end of the reinforcing rod is inserted into the side insertion hole and the other end is fixed in the concrete filling layer, which effectively restricts the lateral displacement of the brick piers and enhances their anti-overturning ability.
[0014] 2. Both the brick piers and the top layer are paved with bricks and combined with concrete pouring to form a high-strength load-bearing system. The brick piers are evenly distributed in the pier pits of the building path, distributing the upper load of the building to the ground and avoiding local stress concentration. The reinforcing rods and the concrete filling layer work together to further enhance the support strength of the brick piers, significantly improving the foundation bearing capacity. This can meet the diverse building needs of rural dwellings, including the load-bearing requirements of multi-story buildings, and ensure the safety of the building structure. Attached Figure Description
[0015] Figure 1 This is a schematic diagram of the three-dimensional assembly structure of this utility model.
[0016] Figure 2 This is a schematic diagram of the three-dimensional assembly structure of this utility model from a bottom view.
[0017] Figure 3 This is an exploded structural diagram of the present invention.
[0018] Figure 4 This is an exploded bottom view structural diagram of this utility model.
[0019] Figure 5 This is a partial cross-sectional structural diagram of the present invention.
[0020] In the diagram, the correspondence between component names and drawing numbers is as follows:
[0021] 1. Ground layer; 101. Constructing path; 102. Pier pit; 103. Side insertion hole; 2. Brick pier; 3. Concrete filling layer; 4. Reinforcing rod; 5. Top layer. Detailed Implementation
[0022] The embodiments of this utility model will be described in further detail below with reference to the accompanying drawings and examples.
[0023] Example 1: As shown in the attached document Figure 1 To be continued Figure 5As shown: This utility model provides a building structure suitable for rural dwellings, including: a ground layer 1; a construction channel 101 is provided on the surface of the ground layer 1; the construction channel 101 is used for constructing the foundation of the building to facilitate construction; pier pits 102 are provided at equal intervals inside the construction channel 101; the pier pits 102 are used to construct brick piers 2 with concrete to assist in supporting the foundation of the building after construction, so as to maintain the stability of the building structure; side insertion holes 103 are provided at equal intervals on the inner wall of the pier pits 102; the side insertion holes 103... 3 is used to cooperate with the reinforcing rod 4 and the concrete filling layer 3 to construct the brick pier 2; the brick pier 2 is constructed with concrete inside the pier pit 102; the brick pier 2 is used to construct with concrete and to support the top layer 5 after construction is completed, so as to assist in supporting the building structure while maintaining stability and ensuring the overall stability of the building structure; concrete is poured in the gap between the brick pier 2 and the pier pit 102; the reinforcing rod 4 is provided in the gap of the brick pier 2; the top layer 5 is fixed to the top of the pier pit 102 with concrete.
[0024] Example 2: Based on Example 1, as shown in the appendix Figure 1 To be continued Figure 5 As shown, the construction path 101 is excavated according to the building foundation distribution; the brick piers 2 are paved with bricks; the concrete between the brick piers 2 and the pit 102 forms a concrete filling layer 3 after solidification; the concrete filling layer 3 is used to increase the overall stability of the brick piers 2 in conjunction with the reinforcing rods 4 after solidification, thereby increasing the overall support strength of the brick piers 2, so as to facilitate the support of the building and make it easier to use; the reinforcing rods 4 are fixed in the concrete filling layer 3, and the ends of the reinforcing rods 4 are inserted into the side insertion holes 103; the reinforcing rods 4 are used to increase the overall stability of the brick piers 2 in conjunction with the concrete filling layer 3 by being inserted into the side insertion holes 103, thereby increasing the overall support strength of the brick piers 2, so as to facilitate the support of the building; the top layer 5 is laid in the construction path 101; the top layer 5 is paved with bricks; the top layer 5 is used to construct the building foundation structure to facilitate the construction of the building.
[0025] The specific usage and function of this embodiment are as follows:
[0026] In this invention, excavation equipment is used to excavate and construct a road 101 on the ground according to the planned location and dimensions. The excavation depth and width must meet the design requirements to ensure that the subsequent brick piers 2 and the top layer 5 structure can be accommodated. Inside the road 101, pier pits 102 are opened at equal intervals according to the design spacing. Measuring tools are used to precisely control the position, depth, and diameter of the pier pits 102 to ensure that each pier pit 102 is of the same specification. Side insertion holes 103 are opened at equal intervals on the inner wall of the pier pits 102. The depth and angle of the side insertion holes 103 must meet the installation requirements of the reinforcing rods 4. A layer of bricks is laid at the bottom of the pier pits 102. A level is used to ensure that the surface of the bricks is flat. Then, bricks are laid layer by layer upwards, and mortar is used to bond the bricks between each layer. To ensure the stability of the brick structure, the reinforcing rod 4 is inserted into the side insertion hole 103, and the other end of the reinforcing rod 4 is fixed in the gap of the brick pier 2. It is ensured that the reinforcing rod 4 is installed firmly and at the correct angle. Concrete is poured in the gap between the brick pier 2 and the pit 102 to form a concrete filling layer 3. During the pouring process, the concrete is vibrated with a vibrating device to ensure that the concrete is dense and tightly bonded to the brick pier 2 and the pit 102. After all the brick piers 2 are built and the concrete filling layer 3 has reached a certain strength, a top layer 5 is laid on the top of the pit 102 using bricks. Mortar is also used to bond the bricks during the laying process to ensure that the surface of the top layer 5 is flat. After the whole structure is completely fixed, the foundation is constructed.
[0027] The following points should be noted in this article:
[0028] 1. The accompanying drawings of the embodiments disclosed herein only relate to the structures involved in the embodiments disclosed herein; other structures can be referred to in general design.
[0029] 2. Where there is no conflict, the embodiments of this disclosure and the features in the embodiments can be combined with each other to obtain new embodiments.
[0030] The above are merely specific embodiments of this disclosure, but the scope of protection of this disclosure is not limited thereto. Any variations or substitutions that can be easily conceived by those skilled in the art within the scope of the technology disclosed in this disclosure should be included within the scope of protection of this disclosure. Therefore, the scope of protection of this disclosure should be determined by the scope of the claims.
Claims
1. A building structure suitable for use in rural dwellings, comprising: Stratum (1); characterized in that: A construction channel (101) is provided on the surface of the stratum (1); The interior of the construction channel (101) is provided with equidistant pits (102); Side insertion holes (103) are provided at equal intervals on the inner wall of the pit (102); The interior of the pit (102) is constructed of concrete with brick piers (2); The gap between the brick pier (2) and the pit (102) is filled with concrete; The gaps in the brick piers (2) are provided with reinforcing rods (4); The top of the pier (102) is fixed with a top layer (5) by concrete.
2. The building structure suitable for rural habitation as claimed in claim 1 wherein: The construction road (101) is excavated according to the distribution of the building foundation.
3. The building structure suitable for rural habitation as claimed in claim 1 wherein: The brick pier (2) is made of bricks.
4. The building structure suitable for rural habitation as claimed in claim 1 wherein: The concrete between the brick pier (2) and the pit (102) forms a concrete filling layer (3) after solidification.
5. The building structure suitable for rural habitation as claimed in claim 4 wherein: The reinforcing rod (4) is fixed in the concrete filling layer (3), and the end of the reinforcing rod (4) is inserted into the side insertion hole (103).
6. The building structure suitable for rural habitation as claimed in claim 1 wherein: The top layer (5) is laid inside the construction channel (101); the top layer (5) is made of bricks.