Underground coal mine water prevention and control early warning device

By installing through holes and filter gauze in the underground water control early warning device in coal mines, and by adjusting the screw and fixing parts, the problem of easy clogging of the seepage outlet was solved, the accuracy of water level measurement and flexible installation were achieved, and a timely early warning function was provided.

CN224149641UActive Publication Date: 2026-04-21SHANXI COAL PLANNING & DESIGN INST (GRP) CO LTD
View PDF 1 Cites 0 Cited by

Patent Information

Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
SHANXI COAL PLANNING & DESIGN INST (GRP) CO LTD
Filing Date
2025-06-17
Publication Date
2026-04-21

AI Technical Summary

Technical Problem

The seepage inlet of the underground water control early warning device in the coal mine is easily blocked by impurities such as coal slag, resulting in inaccurate water level measurement.

Method used

A device was designed that includes a platform, an extension plate, a water level measuring box, an early warning spacing adjustment platform, a pressure sensor, a floating plate, and a sinking box. By providing through holes in the surface wall of the sinking box and inserting filter gauze, impurities are prevented from entering. At the same time, the length and height of the device are adjusted by using a screw and fixing parts to adapt to different construction spacings, and early warning is achieved through a pressure sensor and an alarm.

Benefits of technology

It effectively prevents impurities from clogging the system, ensuring the accuracy and flexibility of water level measurement, and achieving flexible installation adaptability and timely early warning functions.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN224149641U_ABST
    Figure CN224149641U_ABST
Patent Text Reader

Abstract

The utility model relates to the field of water prevention and control early warning, in particular to a coal mine underground water prevention and control early warning device, which comprises a bedplate, extension plates, a water level measuring box, an early warning distance adjusting table, a pressure sensor, a floating plate, a sinking box body and a first lifting plate, the extension plates are mounted at four corners of the upper side of the bedplate, and the sinking box body is mounted on the lower side of the bedplate; a water level measuring box is arranged in the sinking box body, a first lifting plate is installed on the upper side of the water level measuring box, an early warning distance adjusting table and a floating plate are arranged in the water level measuring box, the floating plate is located below the early warning distance adjusting table, and a pressure sensor is installed at the bottom of the early warning distance adjusting table.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This utility model relates to the field of water prevention and early warning, specifically to a water prevention and early warning device for underground coal mines. Background Technology

[0002] Coal mines are areas where humans extract coal resources from coal-rich areas. During coal mining, accidents such as water inrush can occur. A Chinese patent (authorization announcement number CN222162723 U) discloses a coal mine underground water prevention and early warning device. This patented technology uses a handwheel to rotate a threaded rod, which in turn moves a horizontal plate upwards. The horizontal plate then moves a measuring box upwards, positioning the measuring box at a suitable height. When water seeps into the coal mine, it enters the inner cavity through the inlet trough, causing the water level to rise. The buoyancy of the water causes a float to move upwards along the inner cavity, causing a contact block to move upwards along one side of the contact strip. When one side of the contact block contacts the water level warning height of the contact strip, the alarm device will sound. However, due to the large amount of impurities in coal mine water, there is a problem of the seepage point being blocked by coal slag and other impurities. Therefore, those skilled in the art have provided a coal mine underground water prevention and early warning device to solve the problems mentioned in the background art. Utility Model Content

[0003] To solve the above-mentioned technical problems, this utility model provides a coal mine underground water control early warning device, including a platform, an extension plate, a water level measuring box, an early warning interval adjustment platform, a pressure sensor, a floating plate, a sinking box, and a No. 1 lifting plate. The extension plate is installed at the four corners of the upper part of the platform, and the sinking box is installed on the lower part of the platform. The water level measuring box is installed inside the sinking box, and the No. 1 lifting plate is installed on the upper part of the water level measuring box. The early warning interval adjustment platform and the floating plate are installed inside the water level measuring box. The floating plate is located below the early warning interval adjustment platform, and the pressure sensor is installed at the bottom of the early warning interval adjustment platform.

[0004] Preferably, the surface of the submerged box is provided with multiple through holes, and a retaining plate is installed on the inside of the submerged box. Filter gauze can be inserted between the retaining plate and the submerged box.

[0005] Preferably, rail seats are installed at the four corners of the side wall of the platform, and extension plates are installed inside the rail seats. The extension plates are provided with multiple No. 2 fixing holes, and No. 1 fixing parts can be nailed into the No. 2 fixing holes.

[0006] Preferably: The platform is provided with a first fixing hole, into which a second fixing component can be nailed; the platform is provided with a shaft hole, into which the bottom connecting end of a first lead screw is installed; a first auxiliary rod is installed at the upper left end of the platform; a first lifting plate is installed on the first auxiliary rod and the first lead screw; a ring plate is installed at the upper middle position of the first lifting plate; and a water level measuring box is installed on the lower side of the first lifting plate.

[0007] Preferably, the bottom side wall of the water level measuring box is provided with multiple seepage holes, four sliding rods are installed inside the water level measuring box, sliding cylinders can slide on the sliding rods, the sliding cylinders are connected to the float plate, and a convex plate is installed on the upper side of the float plate;

[0008] Preferably: A second auxiliary rod is installed at the upper left end of the first lifting plate, a second lead screw is installed at the upper right end of the first lifting plate, a second lifting plate is installed on the second auxiliary rod and the second lead screw, the second lifting plate is installed on the outer wall of the warning interval adjustment platform, and an alarm is installed on the top of the warning interval adjustment platform.

[0009] The technical effects and advantages of this utility model are as follows:

[0010] 1. The sunken box is placed in the pre-set recess in the coal mine. The fixation is achieved by nailing the No. 2 fixing piece into the No. 1 fixing hole and into the soil layer. The length of the platform can be adjusted according to the construction and installation spacing by pulling the extension plate outward on the rail seat. The fixation is achieved by nailing the No. 1 fixing piece into the No. 2 fixing hole, which is highly flexible.

[0011] 2. The surface of the submerged tank has multiple through holes, and a retaining plate is installed on the inside of the submerged tank. Filter gauze can be inserted between the retaining plate and the submerged tank to ensure normal water seepage while blocking impurities such as coal slag from entering the submerged tank and preventing them from seeping into the seepage holes at the bottom of the water level measuring box, thus avoiding blockage. Attached Figure Description

[0012] Figure 1 This is a schematic diagram of the structure of a coal mine underground water control early warning device provided in an embodiment of this application. Figure 1 ;

[0013] Figure 2 This is a schematic diagram of the structure of a coal mine underground water control early warning device provided in an embodiment of this application. Figure 2 ;

[0014] Figure 3 This is a schematic diagram of a partial explosion structure in a coal mine underground water prevention and control early warning device provided in an embodiment of this application;

[0015] Figure 4 This application provides an embodiment of a coal mine underground water control early warning device. Figure 3 Enlarged schematic diagram of structure A;

[0016] Figure 5 This is a partial structural schematic diagram of a coal mine underground water control early warning device provided in an embodiment of this application;

[0017] Figure 6 This application provides an embodiment of a coal mine underground water control early warning device. Figure 5 An enlarged schematic diagram of the B structure.

[0018] In the diagram: 1. Platform; 2. Extension plate; 3. Filter gauze; 4. Water level measuring box; 5. Early warning spacing adjustment platform; 6. Pressure sensor; 7. Floating plate; 8. Lead screw No. 1; 9. Lead screw No. 2; 10. Fixing component No. 1; 11. Fixing component No. 2; 101. Rail base; 102. Fixing hole No. 1; 103. Shaft hole; 104. Submerged box; 105. Through hole; 106. Clamping plate; 107. Auxiliary rod No. 1; 201. Fixing hole No. 2; 401. Lifting plate No. 1; 402. Ring plate; 403. Water seepage hole; 404. Sliding rod; 405. Auxiliary rod No. 2; 501. Alarm; 502. Lifting plate No. 2; 701. Sliding cylinder; 702. Convex plate. Detailed Implementation

[0019] The present invention will now be described in further detail with reference to the accompanying drawings and specific embodiments. The embodiments of the present invention are given for illustrative and descriptive purposes only, and are not intended to be exhaustive or to limit the present invention to the disclosed forms. Many modifications and variations will be apparent to those skilled in the art. The embodiments were chosen and described to better illustrate the principles and practical applications of the present invention, and to enable those skilled in the art to understand the present invention and design various embodiments with various modifications suitable for a particular purpose. Example

[0020] Please see Figures 1-6 This embodiment provides a coal mine underground water control early warning device, including a platform 1, an extension plate 2, a water level measuring box 4, an early warning interval adjustment platform 5, a pressure sensor 6, a floating plate 7, a sinking box 104, and a first lifting plate 401. The extension plate 2 is installed at the four corners of the upper side of the platform 1, and the sinking box 104 is installed on the lower side of the platform 1. The water level measuring box 4 is provided inside the sinking box 104. The first lifting plate 401 is installed on the upper side of the water level measuring box 4. The early warning interval adjustment platform 5 and the floating plate 7 are provided inside the water level measuring box 4. The floating plate 7 is located below the early warning interval adjustment platform 5, and the pressure sensor 6 is installed at the bottom of the early warning interval adjustment platform 5.

[0021] Specifically, the surface of the submerged box 104 has multiple through holes 105. A retaining plate 106 is installed inside the submerged box 104. Filter gauze 3 can be inserted between the retaining plate 106 and the submerged box 104. Rail seats 101 are installed at the four corners of the upper side wall of the platform 1. An extension plate 2 is installed inside the rail seat 101. The extension plate 2 has multiple second fixing holes 201. A first fixing component 10 can be nailed into the second fixing hole 201. The platform 1 has a first fixing hole 102. A second fixing component 11 can be nailed into the first fixing hole 102. The platform 1 has a shaft hole 103. The bottom connecting end of a first lead screw 8 is installed in the shaft hole 103. An auxiliary rod 107 is installed at the upper left end of the platform 1. A lifting plate 401 is installed on the auxiliary rod 107 and the first lead screw 8. A ring plate 402 is installed in the middle of the side. A water level measuring box 4 is installed under the first lifting plate 401. The bottom side wall of the water level measuring box 4 has multiple seepage holes 403. Four sliding rods 404 are installed inside the water level measuring box 4. A sliding cylinder 701 can slide on the sliding rod 404. The sliding cylinder 701 is connected to the floating plate 7. A convex plate 702 is installed on the upper side of the floating plate 7. A second auxiliary rod 405 is installed at the upper left end of the first lifting plate 401. A second lead screw 9 is installed at the upper right end of the first lifting plate 401. A second lifting plate 502 is installed on the second auxiliary rod 405 and the second lead screw 9. The second lifting plate 502 is installed on the outer wall of the warning interval adjustment platform 5. An alarm 501 is installed on the top of the warning interval adjustment platform 5. A wire is inserted inside the warning interval adjustment platform 5 to connect the pressure sensor 6 and the alarm 501.

[0022] The working principle of this utility model is as follows:

[0023] In using a coal mine underground water control and early warning device, the submerged box 104 is placed in a pre-set recess in the coal mine. Fixing is achieved by nailing the second fixing piece 11 into the first fixing hole 102 and into the soil. The length of the platform 1 can be adjusted according to the construction and installation spacing by pulling the extension plate 2 outwards on the rail base 101. Fixing is achieved by nailing the first fixing piece 10 into the second fixing hole 201, providing high flexibility. The surface wall of the submerged box 104... Multiple through holes 105 are provided. A retaining plate 106 is installed inside the submerged box 104. Filter gauze 3 can be inserted between the retaining plate 106 and the submerged box 104 to ensure normal water seepage while blocking impurities such as coal slag, preventing them from entering the submerged box 104 and seeping into the seepage hole 403 at the bottom of the water level measuring box 4, thus avoiding blockage. The height of the water level measuring box 4 can be adjusted by the first lead screw 8, and the height of the warning interval adjustment platform 5 can be adjusted by the second lead screw 9.

[0024] Obviously, the described embodiments are only a part of the embodiments of this utility model, and not all of them. All other embodiments obtained by those skilled in the art and related fields based on the embodiments of this utility model without creative effort should fall within the protection scope of this utility model. Structures, devices, and operating methods not specifically described and explained in this utility model, unless otherwise specified or limited, shall be implemented according to conventional means in the art.

Claims

1. A coal mine underground water prevention and control early warning device, characterized in that, The system includes a platform (1), an extension plate (2), a water level measuring box (4), an early warning interval adjustment platform (5), a pressure sensor (6), a floating plate (7), a sinking box (104), and a first lifting plate (401). The extension plate (2) is installed at the four corners of the upper side of the platform (1). The sinking box (104) is installed on the lower side of the platform (1). The water level measuring box (4) is installed inside the sinking box (104). The first lifting plate (401) is installed on the upper side of the water level measuring box (4). The early warning interval adjustment platform (5) and the floating plate (7) are installed inside the water level measuring box (4). The floating plate (7) is located below the early warning interval adjustment platform (5). The pressure sensor (6) is installed at the bottom of the early warning interval adjustment platform (5).

2. The water-prevention and early-warning device for underground coal mine of claim 1, wherein, The surface of the sunken box (104) is provided with multiple through holes (105), and a card plate (106) is installed on the inner side of the sunken box (104). Filter gauze (3) can be inserted between the card plate (106) and the sunken box (104).

3. The water-prevention and early-warning device for underground coal mine of claim 1, wherein, The platform (1) has four corners of the upper side wall of the platform (1) with rail seats (101) installed. An extension plate (2) is installed inside the rail seat (101). The extension plate (2) has multiple second fixing holes (201). A first fixing piece (10) can be nailed into the second fixing hole (201).

4. The water-prevention and early-warning device for underground coal mine of claim 3, wherein, The platform (1) is provided with a first fixing hole (102), in which a second fixing part (11) can be nailed. The platform (1) is provided with a shaft hole (103), in which the bottom connecting end of a first lead screw (8) is installed. An auxiliary rod (107) is installed on the upper left side of the platform (1).

5. The water-prevention and early-warning device for underground coal mine of claim 4, wherein, A lifting plate (401) is installed on the first auxiliary rod (107) and the first lead screw (8). A ring plate (402) is installed at the middle position on the upper side of the first lifting plate (401). A water level measuring box (4) is installed on the lower side of the first lifting plate (401).

6. The water-prevention and early-warning device for underground coal mine of claim 5, wherein, The bottom side wall of the water level measuring box (4) is provided with multiple seepage holes (403). Four sliding rods (404) are installed inside the water level measuring box (4). Sliding cylinders (701) can slide on the sliding rods (404). The sliding cylinders (701) are connected to the floating plate (7). A convex plate (702) is installed on the upper side of the floating plate (7).

7. The water-prevention and early-warning device for underground coal mine of claim 6, wherein, A second auxiliary rod (405) is installed on the upper left side of the first lifting plate (401), a second lead screw (9) is installed on the upper right side of the first lifting plate (401), and a second lifting plate (502) is installed on the second auxiliary rod (405) and the second lead screw (9).

8. The water-prevention early warning device for underground coal mine of claim 7, wherein, The second lifting plate (502) is installed on the outer wall of the warning interval adjustment platform (5), and an alarm (501) is installed on the top of the warning interval adjustment platform (5).

Citation Information

Patent Citations

  • Underground coal mine water prevention and control early warning device

    CN222162723U