A soil seepage deformation compensation structure with elastic buffer

By introducing a combination of reinforcing and permeable layers into the vertical cutoff wall, and utilizing porous buffer materials and flexible connections, the problems of increased pore water pressure and soil particle loss caused by seepage deformation in existing technologies have been solved, achieving effective buffering of soil seepage deformation and stable drainage.

CN224955039UActive Publication Date: 2026-11-10CHENGDU TRADE UNION CADRE SCHOOL (CHENGDU WORKERS UNIVERSITY)
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202522497496.4
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2025-11-25
Publication Date
2026-11-10
Estimated Expiration
2035-11-25

AI Technical Summary

Technical Problem

Existing vertical cutoff walls lack elastic buffering capacity, which leads to increased pore water pressure or soil particle loss during seepage deformation, and cannot effectively suppress the risk of seepage deformation.

Method used

The structure adopts a combination of vertical impermeable wall, reinforcing layer and permeation layer, including thickened wear-resistant layer, aerogel felt, permeation layer, elastic polyester fiber mesh and porous elastic buffer layer. The porous structure buffers the impact of water flow, and the flexible connection allows soil displacement. The porous elastic buffer layer is made of highly absorbent resin and elastic acrylic emulsion, and is used in conjunction with permeable pipe drainage.

Benefits of technology

It effectively buffers the impact of water flow during seepage deformation, reduces pore water pressure, prevents soil particle loss, adapts to soil settlement or expansion deformation, reduces the risk of seepage deformation, and maintains the stability of soil structure.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN224955039U_ABST
    Figure CN224955039U_ABST
Patent Text Reader

Abstract

This utility model discloses a soil seepage deformation compensation structure with elastic buffering, relating to the technical field of soil seepage deformation compensation structures. It includes a vertical seepage barrier wall, a reinforcing layer, and a permeation layer. The vertical seepage barrier wall comprises a reinforcing layer, a thickened wear-resistant layer, an aerogel felt, a permeation layer, an elastic polyester fiber mesh, and a porous elastic buffer layer. The thickened wear-resistant layer is fixed to the inner side of the reinforcing layer, and an aerogel felt is adhered to the outer side of the reinforcing layer. The permeation layer is located on the outer side of the aerogel felt, and an elastic polyester fiber mesh is fixed to the outer side of the permeation layer. In this soil seepage deformation compensation structure with elastic buffering, the steel plate of the reinforcing layer enhances the supporting strength; the outer and inner rubber layers provide buffering; the outermost porous elastic buffer layer fills soil fissures while buffering the impact force of seepage water flow; and the permeation layer filters the discharged seepage water flow, thereby guiding the water flow and reducing pore water pressure.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This utility model relates to the field of soil seepage deformation compensation structure technology, specifically a soil seepage deformation compensation structure with elastic buffer. Background Technology

[0002] Soil seepage deformation compensation structure refers to a combination of "filter soil drainage + pressure reduction and slope stabilization" set up in the seepage path to offset the adverse hydraulic effects caused by seepage, reduce the seepage gradient, and protect soil particles from being carried away. Its core purpose is to suppress or compensate for the risk of seepage deformation through "upper blocking and lower drainage, filter soil drainage, and outlet protection", so that seepage can still pass safely without damaging the soil structure.

[0003] Existing vertical cutoff walls mostly use rigid materials such as pure concrete and rigid steel plates, which have no elastic buffering capacity. They either focus on seepage prevention, blocking water flow but failing to drain seepage water, leading to increased pore water pressure and exacerbating soil seepage deformation; or they focus on drainage, which easily causes soil particle loss, causing piping and soil erosion, thus limiting their use. Utility Model Content

[0004] The purpose of this invention is to provide a soil seepage deformation compensation structure with elastic buffer to solve the problems mentioned in the background art.

[0005] To achieve the above objectives, this utility model provides the following technical solution: a soil seepage deformation compensation structure with elastic buffer, comprising a vertical seepage barrier wall, a reinforcing layer, and a permeation layer. The vertical seepage barrier wall comprises a reinforcing layer, a thickened wear-resistant layer, an aerogel felt, a permeation layer, an elastic polyester fiber mesh, and a porous elastic buffer layer. The thickened wear-resistant layer is fixed to the inner side of the reinforcing layer, and an aerogel felt is adhered to the outer side of the reinforcing layer. A permeation layer is provided on the outer side of the aerogel felt, and an elastic polyester fiber mesh is fixed to the outer side of the permeation layer. A porous elastic buffer layer is provided on the outer side of the elastic polyester fiber mesh.

[0006] Furthermore, the reinforcing layer includes an outer rubber layer, a steel plate, and an inner rubber layer. The steel plate is disposed inside the outer rubber layer, and the inner rubber layer is disposed inside the steel plate.

[0007] Furthermore, the reinforcing layer also includes geotextile, the outer rubber layer and the inner rubber layer have the same thickness, and geotextile is fixed to the inner side of the inner rubber layer.

[0008] Furthermore, protective protrusions are fixed at equal intervals on the inner side of the thickened wear-resistant layer, and the protective protrusions have an arc-shaped protrusion structure.

[0009] Furthermore, the bottom of the reinforcing layer is vertically fixed with ground nails, and the ground nails are distributed at equal intervals.

[0010] Furthermore, the infiltration layer includes a pebble layer, a gravel layer, and a fine sand layer, with a gravel layer disposed inside the pebble layer and a fine sand layer disposed inside the gravel layer.

[0011] Furthermore, a water-permeable pipe extends through the lower inner side of the reinforcing layer, and filter screens are fixed on both the front and rear sides of the water-permeable pipe.

[0012] Furthermore, the permeable pipe has a circular hollow structure, and the interior of the permeable pipe is filled with porous permeable filler.

[0013] This utility model provides a soil seepage deformation compensation structure with elastic buffering, which has the following beneficial effects:

[0014] This utility model is equipped with a vertical anti-seepage wall and a reinforcing layer. The vertical anti-seepage wall can be installed on both sides of the river channel that is prone to seepage deformation. The ground nails can be driven into the bottom of the riverbed to support the vertical anti-seepage wall and form a stable support. The two adjacent vertical anti-seepage walls can be connected by flexible snap-fit, allowing relative displacement of adjacent plates. The overall structure can move synchronously with the soil settlement. The steel plate of the reinforcing layer can enhance the support strength. The outer rubber layer and inner rubber layer can play a buffer role. The thickened wear-resistant layer is made of alloy material with good wear resistance. Its inner side is fixed with protective protrusions at equal intervals to resist the impact of water flow.

[0015] This invention features a vertical anti-seepage wall and a permeation layer. The outermost porous elastic buffer layer is made of highly absorbent resin as the core pore-forming material, combined with elastic acrylic emulsion and cementitious binder. While filling soil fissures, it can buffer the impact of seepage water flow. The elastic polyester fiber mesh provides basic elasticity and can adapt to small-amplitude settlement or expansion deformation of the soil. The permeation layer consists of three layers: a pebble layer, a gravel layer, and a fine sand layer. It can filter the discharged seepage water flow, guide the water flow, and reduce pore water pressure. The aerogel felt can buffer the impact of seepage water flow through its porous structure, while reducing soil shrinkage and expansion caused by temperature changes, thus achieving a gradient synergy of buffering and anti-seepage. The filtered water flow can pass through the permeable pipe on the lower side, thereby both discharging seepage water flow and reducing pore water pressure, and preventing soil particle loss. Attached Figure Description

[0016] Figure 1 This is a three-dimensional structural diagram of a soil seepage deformation compensation structure with elastic buffer according to the present invention.

[0017] Figure 2 This is a schematic diagram of the reinforcing layer structure of a soil seepage deformation compensation structure with elastic buffer according to the present invention;

[0018] Figure 3 This is a schematic diagram of the infiltration layer structure of a soil seepage deformation compensation structure with elastic buffer according to the present invention.

[0019] In the diagram: 1. Vertical seepage barrier wall; 2. Reinforcing layer; 201. Outer rubber layer; 202. Steel plate; 203. Inner rubber layer; 204. Geotextile; 3. Thickened wear-resistant layer; 4. Protective protrusions; 5. Ground nails; 6. Aerogel felt; 7. Infiltration layer; 701. Pebble layer; 702. Gravel layer; 703. Fine sand layer; 8. Elastic polyester fiber mesh; 9. Porous elastic buffer layer; 10. Permeable pipe; 11. Filter screen. Detailed Implementation

[0020] The embodiments of this utility model will be described in further detail below with reference to the accompanying drawings and examples. The following examples are for illustrative purposes only and should not be construed as limiting the scope of this utility model.

[0021] like Figures 1-3 As shown, a soil seepage deformation compensation structure with elastic buffer includes a vertical seepage barrier wall 1, a reinforcing layer 2, and a permeation layer 7. The vertical seepage barrier wall 1 includes a reinforcing layer 2, a thickened wear-resistant layer 3, an aerogel felt 6, a permeation layer 7, an elastic polyester fiber mesh 8, and a porous elastic buffer layer 9. The thickened wear-resistant layer 3 is fixed to the inner side of the reinforcing layer 2, and the aerogel felt 6 is pasted to the outer side of the reinforcing layer 2. The reinforcing layer 2 includes an outer rubber layer 201, a steel plate 202, and an inner rubber layer 203. The steel plate 202 is disposed inside the outer rubber layer 201, and the inner rubber layer 203 is disposed inside the steel plate 202. The reinforcing layer 2 also includes geotextile 204. The outer rubber layer 201 and the inner rubber layer 203 have equal thicknesses, and the geotextile 204 is fixed to the inner side of the inner rubber layer 203. The inner side of the thick wear-resistant layer 3 is fixed with protective protrusions 4 at equal intervals, and the protective protrusions 4 have an arc-shaped protrusion structure. The bottom of the reinforcing layer 2 is vertically fixed with ground nails 5, and the ground nails 5 are distributed at equal intervals. The vertical seepage barrier wall 1 can be installed on both sides of the river channel that is prone to seepage deformation. The ground nails 5 can penetrate into the bottom of the riverbed to support the vertical seepage barrier wall 1 and form a stable support. The two adjacent vertical seepage barrier walls 1 can be connected by flexible snap-fit, allowing relative displacement of adjacent plates. The overall structure can move synchronously with the soil settlement. The steel plate 202 of the reinforcing layer 2 can enhance the support strength. The outer rubber layer 201 and the inner rubber layer 203 can play a buffering role. The thickened wear-resistant layer 3 is made of alloy material with good wear resistance. The protective protrusions 4 fixed at equal intervals on its inner side can resist the impact of water flow.

[0022] An aerogel felt 6 has a permeation layer 7 on its outer side, and an elastic polyester fiber mesh 8 is fixed to the outer side of the permeation layer 7. A porous elastic buffer layer 9 is also provided on the outer side of the elastic polyester fiber mesh 8. The permeation layer 7 includes a pebble layer 701, a gravel layer 702, and a fine sand layer 703. A gravel layer 702 is provided inside the pebble layer 701, and a fine sand layer 703 is provided inside the gravel layer 702. A permeable pipe 10 penetrates the lower inner side of the reinforcing layer 2, and filter screens 11 are fixed to both the front and rear sides of the permeable pipe 10. The permeable pipe 10 has a circular hollow structure, and its interior is filled with porous permeable filler. The outermost porous elastic buffer layer 9 uses highly absorbent resin as the core pore-forming material, combined with elastic acrylic resin. It is prepared by acid ester emulsion and cement binder. While filling soil cracks, it can buffer the impact of seepage water flow. The elastic polyester fiber mesh 8 can provide basic elasticity and adapt to small-scale settlement or expansion deformation of the soil. The infiltration layer 7 is composed of three layers: pebble layer 701, gravel layer 702, and fine sand layer 703. It can filter the discharged seepage water flow, guide the water flow, and reduce pore water pressure. The aerogel felt 6 can buffer the impact of seepage water flow through the porous structure, and at the same time reduce the soil shrinkage and expansion caused by temperature changes, thereby achieving a gradient synergy of buffering and seepage resistance. The filtered water flow can pass through the permeable pipe 10 on the lower side, so as to both discharge the seepage water flow and reduce pore water pressure, and prevent soil particle loss.

[0023] In summary, as Figures 1-3As shown, this soil seepage deformation compensation structure with elastic buffer can be used by first installing vertical cut-off walls 1 on both sides of the river channel prone to seepage deformation. Ground nails 5 can penetrate deep into the riverbed to support the vertical cut-off walls 1, forming a stable support. Adjacent vertical cut-off walls 1 can be connected by flexible snap-fit ​​connections, allowing relative displacement between adjacent sections. The overall structure can shift synchronously with soil settlement. During use, the outermost porous elastic buffer layer 9 is made with highly absorbent resin SAP as the core pore-forming material, combined with elastic acrylic emulsion and cementitious binder. While filling soil fissures, it can buffer the impact of seepage water flow. The elastic polyester fiber mesh 8 provides basic elasticity, adapting to small-amplitude soil settlement or expansion deformation. The infiltration layer 7 consists of a pebble layer 701, The structure consists of three layers: a gravel layer 702, a fine sand layer 703, and a soil permeability layer 704. This structure filters and guides the discharged permeable water flow, reducing pore water pressure. The aerogel felt 6 buffers the impact of the permeable water flow through its porous structure, while also reducing soil shrinkage and expansion caused by temperature changes, thus achieving a gradient synergy between buffering and anti-seepage. In addition, the steel plate 202 of the reinforcing layer 2 enhances the support strength. The outer rubber layer 201 and the inner rubber layer 203 provide buffering. The filtered water flow can pass through the permeable pipe 10 on the lower side, thereby both discharging the permeable water flow and reducing pore water pressure, while preventing soil particle loss. The innermost thickened wear-resistant layer 3 is made of alloy material with good wear resistance. Protective protrusions 4 are fixed at equal intervals on its inner side to resist water flow impact. This completes the application process of the soil permeability deformation compensation structure with elastic buffering.

[0024] The embodiments of this utility model are given for illustrative and descriptive purposes only, and are not intended to be exhaustive or to limit the utility model to the forms disclosed. Many modifications and variations will be apparent to those skilled in the art. The embodiments were chosen and described in order to better illustrate the principles and practical applications of this utility model, and to enable those skilled in the art to understand this utility model and design various embodiments with various modifications suitable for a particular purpose.

Claims

1. A soil seepage deformation compensation structure with elastic buffer, comprising a vertical seepage barrier (1), a reinforcing layer (2), and a filter layer (7), characterized in that, The vertical impermeable wall (1) includes a reinforcing layer (2), a thickened wear-resistant layer (3), an aerogel felt (6), a permeation layer (7), an elastic polyester fiber mesh (8), and a porous elastic buffer layer (9). The thickened wear-resistant layer (3) is fixed to the inner side of the reinforcing layer (2), and the aerogel felt (6) is pasted to the outer side of the reinforcing layer (2). The permeation layer (7) is provided on the outer side of the aerogel felt (6), and the elastic polyester fiber mesh (8) is fixed to the outer side of the permeation layer (7). The porous elastic buffer layer (9) is provided on the outer side of the elastic polyester fiber mesh (8).

2. The soil seepage deformation compensation structure with elastic buffer according to claim 1, characterized in that, The reinforcing layer (2) includes an outer rubber layer (201), a steel plate (202) and an inner rubber layer (203). The steel plate (202) is disposed on the inner side of the outer rubber layer (201), and the inner rubber layer (203) is disposed on the inner side of the steel plate (202).

3. A soil seepage deformation compensation structure with elastic buffer according to claim 2, characterized in that, The reinforcing layer (2) also includes geotextile (204), the outer rubber layer (201) and the inner rubber layer (203) are of equal thickness, and geotextile (204) is fixed on the inner side of the inner rubber layer (203).

4. A soil seepage deformation compensation structure with elastic buffer as described in claim 1, characterized in that, The inner side of the thickened wear-resistant layer (3) is fixed with protective protrusions (4) at equal intervals, and the protective protrusions (4) have an arc-shaped protrusion structure.

5. A soil seepage deformation compensation structure with elastic buffer according to claim 1, characterized in that, The bottom of the reinforcing layer (2) is vertically fixed with ground nails (5), and the ground nails (5) are evenly distributed.

6. A soil seepage deformation compensation structure with elastic buffer according to claim 1, characterized in that, The infiltration layer (7) includes a pebble layer (701), a gravel layer (702), and a fine sand layer (703). The gravel layer (702) is disposed inside the pebble layer (701), and the fine sand layer (703) is disposed inside the gravel layer (702).

7. A soil seepage deformation compensation structure with elastic buffer according to claim 1, characterized in that, The reinforcing layer (2) has a permeable pipe (10) running through its lower interior side, and filter screens (11) are fixed on both the front and rear sides of the permeable pipe (10).

8. A soil seepage deformation compensation structure with elastic buffer according to claim 7, characterized in that, The permeable pipe (10) has a circular hollow structure, and the interior of the permeable pipe (10) is filled with porous permeable filler.