A roof structure
By using a layered and cross-shaped design of split prefabricated composite mesh and steel mesh, and modular splicing, the complex transportation and construction problems in traditional buildings are solved, achieving a lightweight, rapid construction and highly stable roof structure.
Patent Information
- Application Number
- CN202522487731.X
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2025-11-24
- Publication Date
- 2026-11-10
- Estimated Expiration
- 2035-11-24
AI Technical Summary
In traditional building construction, prefabricated walls are large and heavy, resulting in high transportation costs and complex construction, making it difficult to achieve efficient hoisting and rapid construction. In addition, the excessive self-weight of the structure increases the load on the building foundation.
The design employs a layered and cross-shaped structure of prefabricated composite mesh and steel mesh, which is prefabricated in the factory and modularly assembled on site. Combined with supporting and connecting structures, it optimizes stress distribution and ease of construction, reduces component volume and weight, and enhances structural stability and adaptability.
It significantly improves transportation efficiency, reduces transportation costs, minimizes on-site construction steps, and creates a high-strength, highly stable, and easy-to-construct roof structure that can adapt to roof requirements of different spans and shapes.
Smart Images

Figure CN224955307U_ABST
Abstract
Description
Technical Field
[0001] This application relates to the field of architecture, and more particularly to a roof structure. Background Technology
[0002] In traditional building construction, the construction of wall structures typically relies on multiple processes, including on-site rebar tying, formwork erection, concrete pouring, and formwork removal. These processes are not only time-consuming and labor-intensive but also require a high level of technical skill from the construction workers. With the development of industrialized construction and prefabricated buildings, the technology combining factory prefabrication and on-site assembly has gradually become the mainstream.
[0003] However, existing technologies still face significant bottlenecks in terms of transportation efficiency, on-site construction convenience, and lightweight structures. For example, traditional precast walls are large and heavy, resulting in high transportation costs, and on-site hoisting requires large machinery, leading to long construction cycles. In addition, while some precast components are cast with cement, which improves structural strength, it has not effectively solved the problems of transportation and hoisting efficiency. Utility Model Content
[0004] This application provides a roof structure to address the issues of transportation and hoisting efficiency.
[0005] In a first aspect, embodiments of this application provide a roof structure, including: At least one reinforcing steel cage; the reinforcing steel cage forms a casting space inside, and the reinforcing steel cage is used to provide forming constraints and support for the flowing concrete during construction pouring; the reinforcing steel cage includes at least one composite mesh and at least one steel mesh; the composite mesh and the steel mesh are fixedly connected; the composite mesh and the steel mesh are prefabricated in the factory and transported to the construction site; A composite mesh and a steel mesh are connected to form a mesh section, and a casting space is formed between the two mesh sections; the edges of the two mesh sections are connected by a number of connecting structures. A plurality of support structures are disposed between two mesh portions, thereby restricting the shape of the two mesh portions.
[0006] In one possible implementation, the composite mesh includes: At least one set of first reinforcing mesh; the first reinforcing mesh includes a plurality of first reinforcing bars arranged at intervals; At least one set of second reinforcing mesh, the second reinforcing mesh including a plurality of spaced second reinforcing bars; the second reinforcing mesh is connected to the first reinforcing mesh; the second reinforcing mesh is set at an angle to the first reinforcing mesh, and multiple sets of the first reinforcing mesh are set at an angle to multiple sets of the second reinforcing mesh and are stacked.
[0007] In one possible implementation, the extension direction of the first rib is perpendicular to the extension direction of the second rib.
[0008] In one possible implementation, the reinforcing mesh includes: At least one set of first steel mesh, the first steel mesh comprising a plurality of spaced first steel bars; At least one set of second steel mesh, the second steel mesh comprising a plurality of spaced second steel bars; multiple sets of first steel mesh and multiple sets of second steel bars are arranged at an angle and stacked.
[0009] In one possible implementation, the extension direction of the first reinforcing bar is perpendicular to the extension direction of the second reinforcing bar.
[0010] In one possible implementation, the connection structure includes: The body is adapted to be connected to the first reinforcing bar and the second reinforcing bar; both ends of the body are provided with mounting parts.
[0011] In one possible implementation, the mounting portion includes a first mounting groove and a second mounting groove, the extension directions of the first mounting groove and the second mounting groove respectively corresponding to the first reinforcing bar and the second reinforcing bar; the first reinforcing bar is engaged in the first mounting groove, and the second reinforcing bar is engaged in the second mounting groove.
[0012] In one possible implementation, the support structure has the same shape as the connecting structure.
[0013] In one possible implementation, the support structure includes: The main body of the support plate is adapted to resist the pressure generated during concrete pouring. At least one wing plate is fixed to the edge of the support plate body; the wing plate is provided with an assembly groove, and is snapped into the mesh part through the assembly groove.
[0014] In one possible implementation, there are two wing plates, which are respectively disposed on both sides of the support plate body, and the assembly groove is a "U" shaped groove, which is adapted to accommodate the first reinforcing bar or the second reinforcing bar.
[0015] In one possible implementation, the support plate body is provided with through holes, and adjacent support plates are connected to each other through the through holes.
[0016] In one possible implementation, there are four wing plates, which are respectively disposed at the four corners of the support plate body; the assembly groove is a "U" shaped groove, which is adapted to accommodate the first reinforcing bar or the second reinforcing bar; the support plate body is provided with through holes, and adjacent support plates are connected to each other through the through holes.
[0017] In one possible implementation, the support structure includes a plurality of triangular steel bars; the plurality of triangular steel bars form a space truss.
[0018] In one possible implementation, when there are multiple composite nets, it further includes at least one warp connector and at least one weft connector; the warp connector is used to connect the first reinforcing nets in different composite nets, and the weft connector is used to connect the second reinforcing nets in different composite nets. The ends of the warp and weft connectors are formed with hooks, and the warp and weft connectors are used to connect the first and second reinforcing meshes respectively through the hooks. The warp and weft connectors are fixedly connected to the main body of the support plate through through holes.
[0019] This application provides a roof structure comprising at least one steel reinforcement frame and several supporting structures. By using a split prefabricated composite mesh and steel mesh, the volume and weight of individual components are significantly reduced, thereby improving transportation efficiency and lowering transportation costs. The layered and cross-design of the composite mesh and steel mesh (e.g., the first and second reinforcing meshes are arranged perpendicularly) optimizes the stress distribution, ensuring structural strength while reducing material usage and achieving lightweighting goals. The supporting structure, through the combination design of the supporting plate body and the flange, enhances the stability of the pouring space and prevents deformation or displacement of the mesh section during concrete pouring. The connecting structure, by fixing the edges of the mesh section, ensures the consistency of the overall shape and avoids structural defects caused by construction errors. The through-hole design allows for rapid splicing of adjacent supporting structures, adapting to roof requirements of different spans and shapes, further improving construction efficiency and structural adaptability. The combination of factory prefabrication and on-site modular splicing reduces on-site construction steps, eliminating the need for complex formwork or large-scale mechanical hoisting, ultimately forming a high-strength, highly stable, and easily constructed roof structure. Attached Figure Description
[0020] The accompanying drawings, which are incorporated in and form part of this specification, illustrate embodiments consistent with this application and, together with the description, serve to explain the principles of this application.
[0021] Figure 1 This application provides a schematic diagram of the supporting structure for a roof structure. Figure 2 for Figure 1Enlarged view of point D in the middle; Figure 3 A schematic diagram of a ribbed connector for a roof structure provided in this application; Figure 4 for Figure 3 Enlarged view of point A in the middle; Figure 5 for Figure 3 Enlarged view of point B in the middle; Figure 6 A schematic diagram of a weft bar connector for a roof structure provided in this application; Figure 7 This application provides a schematic diagram of a sandwich mesh roof structure. Figure 8 for Figure 7 Enlarged view of point C in the middle; Figure 9 This is a schematic diagram of an alternative structure for the support structure of a roof structure provided in this application.
[0022] Figure label: 100. Reinforcing steel frame; 200. Composite mesh; 210. First reinforcing mesh; 211. First reinforcing bar; 220. Second reinforcing mesh; 221. Second reinforcing bar; 230. Sandwich mesh; 231. Receiving groove; 240. Warp reinforcing bar connector; 250. Weft reinforcing bar connector; 300, Reinforcing mesh; 310, First reinforcing mesh; 311, First reinforcing bar; 320, Second reinforcing mesh; 321, Second reinforcing bar; 400. Insulation layer; 500. Support structure; 510. Support plate body; 520. Wing plate; 521. Assembly groove; 530. Through hole; The accompanying drawings illustrate specific embodiments of this application, which will be described in more detail below. These drawings and descriptions are not intended to limit the scope of the concept in any way, but rather to illustrate the concept of this application to those skilled in the art through reference to particular embodiments. Detailed Implementation
[0023] Exemplary embodiments will now be described in detail, examples of which are illustrated in the accompanying drawings. When the following description relates to the drawings, unless otherwise indicated, the same numbers in different drawings denote the same or similar elements. The embodiments described in the following exemplary embodiments do not represent all embodiments consistent with this application. Rather, they are merely examples of apparatuses and methods consistent with some aspects of this application as detailed in the appended claims.
[0024] In traditional building construction, the construction of wall structures typically relies on multiple processes, including on-site rebar tying, formwork erection, concrete pouring, and formwork removal. These processes are not only time-consuming and labor-intensive but also require a high level of technical skill from the construction workers. With the development of industrialized construction and prefabricated buildings, the technology combining factory prefabrication and on-site assembly has gradually become the mainstream.
[0025] In existing technologies, precast roof components are large and heavy, resulting in high transportation costs and susceptibility to damage. On-site casting, on the other hand, relies on manual rebar tying and formwork erection, leading to long construction cycles and inconsistent quality. For example, in high-rise building construction, traditional precast components require significant transportation resources, and on-site hoisting necessitates large lifting equipment, resulting in high construction risks. Furthermore, in the construction of complex curved roofs, on-site rebar tying and formwork erection require extensive manual labor, making it difficult to guarantee structural accuracy. In addition, traditional rebar cage designs do not consider lightweight requirements, leading to excessive structural weight and increased foundation load. This application solves these problems through modular precasting, standardized connections, and structural optimization, while simultaneously meeting the comprehensive needs of modern architecture for rapid construction, energy conservation, environmental protection, and structural safety.
[0026] Starting with existing technological problems, the inventors first addressed the issue of transportation efficiency by proposing to decompose the overall prefabricated component into two parts: a composite mesh and a steel mesh, achieving lightweight design through factory prefabrication. Secondly, to solve the problem of high on-site construction complexity, standardized connection structures (such as integrated connection and support structures) and modular splicing methods were designed to reduce manual operation steps. Simultaneously, to improve structural strength and stability, the stress distribution was optimized through the layered and cross-design of the composite mesh and steel mesh (such as the perpendicular arrangement of the first and second reinforcing meshes), and the compressive strength of the casting space was enhanced through the snap-fit design of the support structure (such as the U-shaped groove connection between the flange and the mesh section). Finally, through-hole design enabled rapid connection of adjacent support structures, and the hooks of the warp and weft reinforcing bar connectors connected different composite meshes, further improving the overall structural coordination and durability. This technological evolution process embodies an innovative logic from problem-oriented to systemic optimization.
[0027] This application provides a roof structure comprising at least one steel reinforcement frame and several supporting structures. By using a split prefabricated composite mesh and steel mesh, the volume and weight of individual components are significantly reduced, thereby improving transportation efficiency and lowering transportation costs. The layered and cross-design of the composite mesh and steel mesh (e.g., the first and second reinforcing meshes are arranged perpendicularly) optimizes the stress distribution, ensuring structural strength while reducing material usage and achieving lightweighting goals. The supporting structure, through the combination design of the supporting plate body and the flange, enhances the stability of the pouring space and prevents deformation or displacement of the mesh section during concrete pouring. The connecting structure, by fixing the edges of the mesh section, ensures the consistency of the overall shape and avoids structural defects caused by construction errors. The through-hole design allows for rapid splicing of adjacent supporting structures, adapting to roof requirements of different spans and shapes, further improving construction efficiency and structural adaptability. The combination of factory prefabrication and on-site modular splicing reduces on-site construction steps, eliminating the need for complex formwork or large-scale mechanical hoisting, ultimately forming a high-strength, highly stable, and easily constructed roof structure.
[0028] The technical solution of this application and how the technical solution of this application solves the above-mentioned technical problems are described in detail below with specific embodiments. These specific embodiments can be combined with each other, and the same or similar concepts or processes may not be described again in some embodiments. The embodiments of this application will now be described with reference to the accompanying drawings.
[0029] like Figure 1 and Figure 2 As shown in the illustration, this application provides a roof structure including at least one steel reinforcement frame 100 and several supporting structures 500. The steel reinforcement frame 100 forms a casting space inside and is used to provide forming constraints and support for the flowing concrete during construction and pouring. The steel reinforcement frame 100 includes at least one composite mesh 200 and at least one steel mesh 300. The composite mesh 200 and the steel mesh 300 are fixedly connected. The composite mesh 200 and the steel mesh 300 are prefabricated in a factory and transported to the construction site. One composite mesh 200 and one steel mesh 300 are connected to form a mesh section, and a casting space is formed between two mesh sections. The edges of the two mesh sections are connected by several connecting structures. Several supporting structures 500 are disposed between the two mesh sections, and the shapes of the two mesh sections are restricted by the supporting structures 500.
[0030] like Figure 2As shown, the use of a split prefabricated composite mesh 200 and steel mesh 300 significantly reduces the volume and weight of individual components, thereby improving transportation efficiency and reducing transportation costs. The layered and cross-design of the composite mesh 200 and steel mesh 300 (such as the first reinforcing mesh 210 and the second reinforcing mesh 220 arranged perpendicularly) optimizes the stress distribution, ensuring structural strength while reducing material usage and achieving the goal of lightweighting. The support structure 500, through the combination design of the support plate body 510 and the wing plate 520, enhances the stability of the pouring space and prevents deformation or displacement of the mesh section during concrete pouring. The connecting structure ensures the consistency of the overall shape by fixing the edges of the mesh section, avoiding structural defects caused by construction errors. The through-hole design 530 allows for the rapid splicing of adjacent support structures 500, adapting to the needs of roofs with different spans and shapes, further improving construction efficiency and structural adaptability. Through the combination of factory prefabrication and on-site modular splicing, on-site construction steps are reduced, eliminating the need for complex formwork support or large-scale mechanical hoisting, ultimately forming a high-strength, high-stability, and easy-to-construct roof structure.
[0031] The roof structure is constructed by layering and cross-arranging prefabricated composite mesh 200 and steel mesh 300 in the factory, and then welding or binding them to form mesh panels. A casting space is formed between two mesh panels by a support structure 500 (support plate body 510 and wing plate 520). The support plate body 510 resists the pressure during concrete pouring, and the wing plate 520 is fixed to the steel reinforcement of the mesh panels by snap-fitting or welding to prevent deformation of the mesh panels during pouring. The edges of the two mesh panels are fixed by a connecting structure to ensure overall shape stability. Through holes 530 on the support structure 500 are used to splice adjacent support structures 500 to form an integrated support system. The modular design of the mesh panels and support structure 500 allows for rapid assembly on-site, eliminating the need for complex formwork or large-scale mechanical hoisting.
[0032] It should be noted that the support structure 500 is provided with the through hole 530 for connecting adjacent support structures 500.
[0033] It should be noted that the building structure consists of front, back, left, and right wall structures and top and bottom roof structures, with the 400 insulation layer only installed inside the walls.
[0034] The composite mesh 200 includes at least one set of first reinforcing mesh 210 and at least one set of second reinforcing mesh 220. The first reinforcing mesh 210 includes a plurality of spaced-apart first reinforcing ribs 211; the second reinforcing mesh 220 includes a plurality of spaced-apart second reinforcing ribs 221; the second reinforcing mesh 220 is connected to the first reinforcing mesh 210; the second reinforcing mesh 220 is angled to the first reinforcing mesh 210, and multiple sets of first reinforcing mesh 210 and multiple sets of second reinforcing mesh 220 are arranged at angles and stacked. For example, the first reinforcing rib 211 is a round steel bar with a diameter of 6mm. The second reinforcing rib 221 is a round steel bar with a diameter of 6mm.
[0035] Specifically, the extension direction of the first rib 211 is perpendicular to the extension direction of the second rib 221.
[0036] It should be noted that the angle between the extension direction of the first rib 211 and the extension direction of the second rib 221 can also be 30°, 45° or 60°, etc.
[0037] like Figure 3 and Figure 4 , Figure 5 As shown, the first reinforcing mesh 210 and the second reinforcing mesh 220 are fixedly connected by welding or binding to form a three-dimensional mesh structure. Multiple sets of first reinforcing mesh 210 and multiple sets of second reinforcing mesh 220 are stacked at an angle, enhancing the overall load-bearing capacity of the structure through the principle of mechanical distribution. The spacing of the first reinforcing mesh 211 and the second reinforcing mesh 221 is optimized through spatial distribution, reducing material usage while improving structural stability.
[0038] The vertical extension directions of the first rib 211 and the second rib 221 are orthogonally arranged to form a stable grid structure. This design enhances the overall rigidity of the structure through the principle of mechanical symmetry. In particular, the orthogonal arrangement of the first rib 211 and the second rib 221 improves the structural symmetry of the three-dimensional grid, thereby enhancing the stability of the wall under complex loads.
[0039] It should be noted that the first rib 211 and the second rib 221 can also be referred to as warp ribs and weft ribs. In this embodiment, the composite mesh 200 consists of two warp ribs and a weft rib positioned between the two warp ribs. Traditional single-layer fabrics have extremely high strength in one direction but are very fragile in the vertical direction. This composite mesh 200 integrates high strength in two or more preset directions (such as +45° / -45° / 90°), enabling the fabric to possess both high strength and stiffness in multiple directions simultaneously.
[0040] Furthermore, when there are multiple composite nets 200, they also include at least one warp reinforcement connector 240 and at least one weft reinforcement connector 250; the warp reinforcement connector 240 is used to connect the first reinforcement nets 210 in different composite nets 200, and the weft reinforcement connector 250 is used to connect the second reinforcement nets 220 in different composite nets 200.
[0041] The warp-reinforcement connector 240 is used to connect structural members of the first reinforcement mesh 210 within different composite meshes 200. Example: U-shaped rebar hook. The weft-reinforcement connector 250 is used to connect structural members of the second reinforcement mesh 220 within different composite meshes 200. Example: U-shaped rebar hook.
[0042] The warp and weft connectors 240 and 250 are fixedly connected to the first and second reinforcing meshes 210 and 220 via hooks, forming a modular composite mesh 200 splicing structure. Furthermore, the modular splicing design of the warp and weft connectors 240 and 250 allows for flexible expansion of the composite mesh 200, thereby improving the adaptability of the wall structure.
[0043] Specifically, the ends of the warp reinforcement connector 240 and the weft reinforcement connector 250 form hook portions, which are used to connect the first reinforcement mesh 210 and the second reinforcement mesh 220, respectively. The hook portions represent the bent structure at the ends of the warp reinforcement connector 240 or the weft reinforcement connector 250. For example, a 90° bent end of a reinforcing bar.
[0044] The hook part is fixedly connected to the first rib mesh 210 and the second rib mesh 220 through the mechanical interlocking principle, which enhances the overall stability of the modular composite mesh 200.
[0045] The mechanical interlocking action of the hooks enhances the connection strength of the modular composite mesh 200, thereby preventing structural loosening.
[0046] Its like Figure 6 As shown, the reinforcing mesh 300 includes at least one set of first reinforcing mesh 310 and at least one set of second reinforcing mesh 320. The first reinforcing mesh 310 includes several spaced-apart first reinforcing bars 311; the second reinforcing mesh 320 includes several spaced-apart second reinforcing bars 321. Multiple sets of first reinforcing mesh 310 and multiple sets of second reinforcing bars 321 are arranged at an angle and stacked. The first reinforcing mesh 310 and the second reinforcing mesh 320, stacked at an angle, form the supporting structure 500 of the reinforcing mesh 300. This design enhances the stability of the insulation layer 400 through the principle of mechanical distribution. The angled stacking design of the first reinforcing mesh 310 and the second reinforcing mesh 320 increases the supporting strength of the reinforcing mesh 300 for the insulation layer 400, thereby preventing the insulation layer 400 from detaching.
[0047] Specifically, the extension direction of the first reinforcing bar 311 is perpendicular to the extension direction of the second reinforcing bar 321. The extension direction refers to the geometric orientation of either the first reinforcing bar 311 or the second reinforcing bar 321. For example, the first reinforcing bar 311 extends along the X-axis, and the second reinforcing bar 321 extends along the Y-axis.
[0048] The orthogonal arrangement of the first reinforcing bar 311 and the second reinforcing bar 321 enhances the overall rigidity of the reinforcing mesh 300 through the principle of mechanical symmetry. The orthogonal arrangement of the first reinforcing bar 311 and the second reinforcing bar 321 improves the structural symmetry of the reinforcing mesh 300, thereby enhancing the stability of the insulation layer 400.
[0049] It should be noted that the angle between the extension direction of the first reinforcing bar 311 and the extension direction of the second reinforcing bar 321 can also be 30°, 45° or 60°, etc.
[0050] Furthermore, in the roof structure provided in this application embodiment, the support structure 500 includes a support plate body 510 and at least one wing plate 520. The support plate body 510 is adapted to resist the pressure generated during concrete pouring. The wing plate 520 is fixed to the edge of the support plate body 510. An assembly groove 521 is provided on the wing plate 520, and it is snapped into connection with the mesh part through the assembly groove 521.
[0051] The main body 510 of the support plate and the wing plate 520 are combined to form the support structure 500. The assembly groove 521 of the wing plate 520 is engaged with the reinforcing bars of the mesh section to ensure the fixed connection between the support structure 500 and the mesh section. The main body 510 of the support plate resists the pressure during concrete pouring and prevents the mesh section from deforming; the wing plate 520 is engaged with the reinforcing bars through the assembly groove 521 to enhance the connection strength and prevent the mesh section from shifting during the pouring process.
[0052] The stability of the pouring space is enhanced through the combined design of the support plate body 510 and the wing plate 520, as well as the snap-fit connection between the assembly groove 521 and the reinforcing steel. The support plate body 510 directly resists the concrete pressure, preventing deformation of the mesh section; the assembly groove 521 of the wing plate 520 snaps into the reinforcing steel, ensuring reliable fixation of the support structure 500 and the mesh section, and avoiding structural displacement caused by pressure during pouring.
[0053] Furthermore, there are two wing plates 520, which are respectively disposed on both sides of the support plate body 510. The assembly groove 521 is a "U" shaped groove, which is suitable for accommodating the first reinforcing bar 311 or the second reinforcing bar 321.
[0054] The first reinforcing bar 311 or the second reinforcing bar 321 within different reinforcing meshes 300 are connected by a wing plate 520, thereby improving the overall stability.
[0055] Specifically, the main body 510 of the support plate is provided with through holes 530, and adjacent support plates are connected to each other through through holes 530.
[0056] By connecting the main support plates 510 together, the stability of the overall structure is further improved.
[0057] The composite mesh 200 includes at least one set of sandwich mesh 230, the sandwich mesh 230 being provided with a plurality of blocking holes, the blocking holes being adapted to block concrete from flowing out.
[0058] like Figure 7 and Figure 8 As shown, the sandwich mesh 230 can be a perforated metal mesh sheet, fixed by welding between the first reinforcing mesh 210 and the second reinforcing mesh 220 of the composite mesh 200. The sandwich mesh 230 controls concrete flow through its barrier holes; the distribution and shape of these holes ensure that concrete evenly fills the pouring space during the pouring process. The barrier holes reduce concrete overflow through physical obstruction, while the layered structure of the sandwich mesh 230 enhances the integrity of the composite mesh 200. Precise control of concrete flow through the barrier holes solves the structural defects caused by uneven concrete flow in traditional technologies. The gradient design of the barrier holes reduces material waste while improving pouring quality, ensuring the overall strength and forming accuracy of the building structure.
[0059] Furthermore, the sandwich mesh 230 is provided with a plurality of receiving grooves 231, which are adapted to receive one of the first rib 211 and the second rib 221.
[0060] like Figure 9 As shown, in one possible embodiment, the support structure 500 can also be a spatial triangle, which is formed by splicing together several triangular steel bars. It should be noted that this is a support structure composed of several spatial triangles. It arranges the members in three-dimensional space to form a highly stable three-dimensional unit. In one possible embodiment, the support structure 500 has the same shape as the connecting structure. When the support structure 500 has the same shape as the connecting structure, the connecting structure includes a support plate body 510 and at least one wing plate 520; In one possible embodiment, the support structure 500 and the connecting structure have different shapes. When the support structure 500 and the connecting structure have different shapes, the connecting structure includes a body, which is a square tube; both ends of the body are provided with mounting portions.
[0061] The main body is a rectangular square tube. The square tube structure enhances the rigidity of the connecting structure, thereby improving the overall stability of the wall.
[0062] Specifically, the mounting part includes a first mounting groove and a second mounting groove, the extension directions of the first mounting groove and the second mounting groove respectively corresponding to the first reinforcing bar 311 and the second reinforcing bar 321; the first reinforcing bar 311 is engaged in the first mounting groove, and the second reinforcing bar 321 is engaged in the second mounting groove.
[0063] The connection structure is connected to the first reinforcing bar 311 and the second reinforcing bar 321 by snapping together through the first mounting groove and the second mounting groove, thereby achieving the connection effect of the two reinforcing meshes 300. In this embodiment, the snap-fit method has the effect of quick disassembly.
[0064] It should be noted that a deformable material is embedded in the support plate body 510, and a pressure sensing layer is provided on the contact surface between the support plate body 510 and the mesh portion. The pressure sensing layer is electrically connected to the deformable material.
[0065] The deformable material inside the support plate body 510 undergoes shape changes under pressure. The pressure sensing layer detects the pressure distribution on the contact surface in real time and transmits the signal to the deformable material, triggering its local expansion or contraction to balance the pressure distribution.
[0066] By combining deformable materials with a pressure-sensitive layer, adaptive pressure regulation of the support structure 500 is achieved. The pressure-sensitive layer detects local pressure changes, triggering the deformable material to adjust its shape, balance the pressure distribution, prevent structural deformation or cracking caused by local stress concentration, and improve overall construction adaptability.
[0067] It should be noted that the composite mesh 200 includes a high-density mesh area and a low-density mesh area. The high-density mesh area is close to the pouring space, and the low-density mesh area is far from the pouring space. For example, the spacing between the reinforcing bars in the high-density mesh area is 5 cm, and the spacing between the reinforcing bars in the low-density mesh area is 10 cm.
[0068] High-density grid areas provide stronger restraint to resist concrete pressure, while low-density grid areas reduce material usage for lightweighting. Different spans or load requirements can be accommodated by adjusting the intersection angles or adding auxiliary reinforcement bars.
[0069] By employing a gradient density design, an optimized balance between stress and material usage is achieved. High-density grid areas provide stronger constraints at critical stress locations, preventing deformation of the mesh during casting; low-density grid areas reduce material redundancy and structural weight, while adjusting the grid density to adapt to different construction requirements.
[0070] Finally, it should be noted that other embodiments of this utility model will readily occur to those skilled in the art upon consideration of the specification and practice of the utility model disclosed herein. This utility model is intended to cover any variations, uses, or adaptations of this utility model that follow the general principles of this utility model and include common knowledge or customary techniques in the art not disclosed herein, and is not limited to the precise structures described above and shown in the accompanying drawings, and various modifications and changes can be made without departing from its scope. The scope of this utility model is limited only by the appended claims.
Claims
1. A roofing structure, characterized by, include: At least one reinforcing cage (100); the reinforcing cage (100) forms a casting space inside, and the reinforcing cage (100) is used to provide forming constraints and support for the flowing concrete during construction pouring; the reinforcing cage (100) includes at least one composite mesh (200) and at least one reinforcing mesh (300); the composite mesh (200) and the reinforcing mesh (300) are fixedly connected; the composite mesh (200) and the reinforcing mesh (300) are prefabricated in the factory and transported to the construction site; A composite mesh (200) and a steel mesh (300) are connected to form a mesh section, and a casting space is formed between the two mesh sections; the edges of the two mesh sections are connected by a plurality of connecting structures. A plurality of support structures (500) are disposed between two mesh portions, and the shape of the two mesh portions is restricted by the support structures (500).
2. The roofing structure according to claim 1, wherein The composite mesh (200) includes: At least one set of first reinforcing mesh (210); the first reinforcing mesh (210) includes a plurality of spaced first reinforcing bars (211); At least one set of second reinforcing mesh (220), the second reinforcing mesh (220) includes a plurality of spaced second reinforcing bars (221); the second reinforcing mesh (220) is connected to the first reinforcing mesh (210); the second reinforcing mesh (220) is set at an angle to the first reinforcing mesh (210), and multiple sets of the first reinforcing mesh (210) are set at an angle to multiple sets of the second reinforcing mesh (220) and are stacked.
3. The roofing structure according to claim 2, wherein The extension direction of the first rib (211) is perpendicular to the extension direction of the second rib (221).
4. The roofing structure according to claim 2, wherein The steel mesh (300) includes: At least one set of first steel mesh (310), the first steel mesh (310) includes a plurality of spaced first steel bars (311); At least one set of second steel mesh (320), the second steel mesh (320) includes a plurality of spaced second steel bars (321); multiple sets of first steel mesh (310) and multiple sets of second steel bars (321) are arranged at an angle and stacked.
5. The roofing structure according to claim 4, wherein The extension direction of the first reinforcing bar (311) is perpendicular to the extension direction of the second reinforcing bar (321).
6. The roofing structure according to claim 5, wherein The connection structure includes: The body is adapted to be connected to the first reinforcing bar (311) and the second reinforcing bar (321); both ends of the body are provided with mounting parts.
7. The roofing structure according to claim 6, wherein The mounting part includes a first mounting groove and a second mounting groove, the extension directions of the first mounting groove and the second mounting groove respectively corresponding to the first reinforcing bar (311) and the second reinforcing bar (321); the first reinforcing bar (311) is engaged in the first mounting groove, and the second reinforcing bar (321) is engaged in the second mounting groove.
8. The roofing structure according to claim 5, wherein The supporting structure (500) has the same shape as the connecting structure.
9. The roofing structure according to claim 5, wherein The support structure (500) includes: The support plate body (510) is adapted to resist the pressure generated during concrete pouring; At least one wing plate (520) is fixed to the edge of the support plate body (510); the wing plate (520) is provided with an assembly groove (521) and is snapped into the mesh part through the assembly groove (521).
10. The roofing structure according to claim 9, wherein There are two wing plates (520), which are respectively disposed on both sides of the main body of the support plate (510). The assembly groove (521) is a "U" shaped groove, which is suitable for accommodating the first reinforcing bar (311) or the second reinforcing bar (321). The main body of the support plate (510) is provided with through holes (530), and adjacent support plates are connected to each other through the through holes (530).
11. The roofing structure according to claim 10, wherein The wing plate (520) has four parts, and the four wing plates (520) are respectively arranged at the four corners of the support plate body (510); the assembly groove (521) is a "U" shaped groove, and the assembly groove (521) is suitable for accommodating the first steel bar (311) or the second steel bar (321).
12. The roof structure according to claim 5, characterized in that, The supporting structure (500) includes several triangular steel bars; the several triangular steel bars form a spatial truss.
13. The roof structure according to claim 9, characterized in that, When there are multiple composite nets (200), it further includes at least one warp connector (240) and at least one weft connector (250); the warp connector (240) is used to connect the first reinforcing mesh (210) in different composite nets (200), and the weft connector (250) is used to connect the second reinforcing mesh (220) in different composite nets (200). The ends of the warp connector (240) and the weft connector (250) are formed with hooks, and the warp connector (240) and the weft connector (250) are used to connect the first rib mesh (210) and the second rib mesh (220) respectively through the hooks. The warp and weft connectors (240) and the weft connectors (250) are fixedly connected to the support plate body (510) through through holes (530).