A flue gas condenser for boilers
By designing a flue gas condenser for boilers, which employs the coordinated use of filter cartridges, spiral coils, reverse-flushing cleaning components, and material guiding components, integrated flue gas filtration and condensation are achieved. This solves the problems of low equipment integration and incomplete cleaning and ash removal, and improves processing efficiency and stability.
Patent Information
- Application Number
- CN202522667703.6
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2025-12-16
- Publication Date
- 2026-11-17
- Estimated Expiration
- 2035-12-16
AI Technical Summary
The existing flue gas filtration and condensation equipment has low integration and an imperfect cleaning and ash removal mechanism, which leads to increased flue gas flow resistance, affects heat exchange efficiency and filtration effect, and cannot guarantee long-term stable operation.
Design a boiler flue gas condenser that uses a filter cartridge assembly, spiral coil, reverse-flushing cleaning assembly and material guiding assembly in synergy. The filter cartridge assembly is rotated by a drive mechanism to achieve full circumferential cleaning. Combined with exhaust pipes and material guiding assembly, the accumulated ash is collected centrally and discharged in a controlled manner, realizing integrated flue gas filtration and condensation treatment.
It improves the integration and efficiency of flue gas treatment, avoids filter clogging and ash accumulation, and ensures the long-term stable operation of the equipment.
Smart Images

Figure CN224976027U_ABST
Abstract
Description
Technical Field
[0001] This application relates to the field of flue gas treatment technology, and in particular to a flue gas condenser for boilers. Background Technology
[0002] During boiler operation, the flue gas produced usually contains a large amount of particulate matter and waste heat. Direct discharge will not only cause environmental pollution, but also lead to energy waste. Therefore, it is necessary to filter and purify the flue gas and recover the waste heat from condensation.
[0003] In existing technologies, flue gas filtration and condensation equipment is mostly a separate design with low integration, resulting in problems such as large footprint, complex flue gas treatment processes, and low treatment efficiency. While some integrated equipment attempts to combine filtration and condensation functions, they generally suffer from unreasonable ash removal structure designs. Filters are prone to clogging due to ash accumulation, leading to increased flue gas flow resistance. Furthermore, the filter cleaning and ash removal mechanisms are imperfect, thus affecting heat exchange efficiency and filtration effect, and failing to guarantee long-term stable operation. Therefore, there is an urgent need for a flue gas treatment device that can achieve integrated filtration and condensation, efficient ash removal, and stable operation to overcome the shortcomings of existing technologies. Utility Model Content
[0004] To address the issues of low integration of flue gas filtration and condensation equipment and imperfect cleaning and ash removal mechanisms, this application provides a flue gas condenser for boilers.
[0005] The technical solution for a boiler flue gas condenser provided in this application is as follows:
[0006] A flue gas condenser for boilers includes a housing, an exhaust pipe and an inlet pipe installed on the outside of the housing, and a filter cartridge assembly for filtering flue gas installed inside the housing. The filter cartridge assembly includes a cylinder support and a filter mesh wrapped around the circumferential sidewall of the cylinder support. One end of the cylinder support is connected to a rotating base tube extending to the outside of the housing. A drive mechanism for driving the rotating base tube to rotate is installed on the outside of the housing, and the exhaust pipe is sleeved on the rotating base tube.
[0007] The cylinder support is equipped with a spiral coil, and a drainage assembly for collecting condensate is installed below the spiral coil. The water inlet and outlet of the spiral coil both pass through the rotating base tube and extend to the outside of the exhaust pipe. A back-blowing cleaning assembly for cleaning the filter cloth is installed on the outside of the housing. The air outlet of the back-blowing cleaning assembly passes through the rotating base tube and extends to the inside of the filter cloth. A material guide assembly for discharging dust is provided at the bottom of the housing.
[0008] By adopting the above technical solution, flue gas enters the chamber through the inlet pipe. The filter cloth filters particulate matter in the flue gas. Cooling medium is introduced into the spiral coil to exchange heat with the filtered flue gas, achieving flue gas condensation. The drainage component collects and discharges the condensate dripping from the outside of the spiral coil to avoid contaminating the filter cartridge assembly. The back-flushing cleaning component blows gas into the inside of the filter cloth, using the gas to remove dust adhering to its surface. In conjunction with the drive mechanism, the rotating base tube rotates, causing the filter cartridge assembly to rotate synchronously, achieving the purpose of rotational cleaning. The dust falls to the bottom of the chamber and is collected and discharged by the material guide component. The filtered and condensed flue gas enters the exhaust pipe through the rotating base tube and is discharged. This achieves the purpose of integrated flue gas filtration and condensation, improving the integration and efficiency of flue gas treatment. It also has the functions of cleaning and ash removal, ensuring the long-term stable operation of the equipment.
[0009] Preferably, the drive mechanism includes a drive motor installed outside the housing, the output shaft of the drive motor is connected to drive teeth, and a gear ring that meshes with the drive teeth is fixed outside the rotating base tube.
[0010] By adopting the above technical solution, the output torque of the drive motor drives the drive teeth to rotate. The drive teeth and the gear ring mesh and transmit power to the rotating base tube, which drives the rotating base tube and the filter cartridge assembly connected to it to rotate smoothly. This achieves the purpose of reliable power transmission between the rotating base tube and the filter cartridge assembly, improves transmission efficiency and operational stability, reduces energy loss during power transmission, and has a compact structure that is easy to install and maintain.
[0011] Preferably, the exhaust pipe includes a sleeve rotatably fitted onto the end of the rotating base pipe, an exhaust pipe is connected to one side of the sleeve, and a support frame connected to the housing is fixed at the bottom end of the sleeve.
[0012] By adopting the above technical solution, the sleeve is fitted onto the end of the rotating base pipe in a rotating fit manner, forming a relatively rotatable sealed connection structure. This not only does not hinder the rotational movement of the rotating base pipe, but also prevents flue gas leakage. The support frame fixes the sleeve to the housing, ensuring the stability of the installation benchmark of the exhaust pipe. The treated flue gas enters the sleeve through the rotating base pipe and is then directionally discharged from the equipment through the exhaust pipe. This achieves the purpose of sealing the connection between the rotating component and the fixed exhaust component, ensuring the smoothness of flue gas emission, reducing the probability of flue gas leakage, and improving the installation firmness and structural stability of the exhaust pipe.
[0013] Preferably, the backflushing cleaning assembly includes an air pump installed outside the housing, the air pump's outlet end is connected to an air guide pipe, the end of the air guide pipe away from the air pump extends into the interior of the cylinder support in a horizontal manner, and an exhaust channel is provided on the outer wall of the air guide pipe, the exhaust channel being located above the inner side of the bottom end of the cylinder support.
[0014] By adopting the above technical solution, the high-pressure gas generated by the air pump is transported to the inside of the cylinder support through the air guide pipe. The high-pressure gas is then directionally injected into the inside of the filter cloth through the exhaust channel opened on the air guide pipe (located above the inner side of the bottom end of the cylinder support). The gas impact force causes the accumulated dust on the surface of the filter cloth to fall off, achieving the purpose of efficient dust removal from the filter cloth. This avoids the filter cloth from becoming clogged, which would increase the resistance to flue gas flow, ensuring the stable operation of the filtration function and extending the service life of the filter cloth.
[0015] Preferably, the material guiding assembly includes a collection trough box communicating with the bottom of the box body, an auger is rotatably installed in the collection trough box, a material guiding motor is installed on one side of the collection trough box and is driven by the shaft of the auger end, a material guiding pipe is connected to the bottom side of the collection trough box, and a sealing door is sleeved on the bottom end of the material guiding pipe.
[0016] By adopting the above technical solution, the ash that falls off during cleaning falls into the collection trough at the bottom of the box. The guide motor drives the auger to rotate, and the auger pushes the ash in the collection trough towards the guide pipe through the spiral blades. Under normal circumstances, the sealing door is closed to prevent flue gas from leaking from the guide pipe inside the box. When ash needs to be discharged, the sealing door is opened, and the ash is discharged through the guide pipe. This achieves the purpose of centralized collection and controllable discharge of ash, avoids the accumulation of ash at the bottom of the box from affecting the operation of the equipment, ensures the cleanliness of the equipment, and improves the convenience and safety of ash discharge operation.
[0017] Preferably, the end of the spiral coil away from the rotating base tube is connected to a support frame, and the end of the support frame away from the spiral coil passes through the cylindrical support and is fixedly connected to the inner wall of the box.
[0018] By adopting the above technical solution, one end of the support frame is connected to the end of the spiral coil away from the rotating base tube, and the other end passes through the cylinder support and is fixed to the inner wall of the box. It forms a cooperative support with the other end of the spiral coil through the rotating base tube extension and fixation structure, realizing the positioning support of the spiral coil at both ends, achieving the purpose of stable installation of the spiral coil, improving the structural stability of the spiral coil during equipment operation, avoiding displacement, deformation or damage of the spiral coil due to the rotation vibration of the filter cartridge assembly or the impact of flue gas flow, and ensuring the stable and efficient operation of the condensation heat exchange process.
[0019] Preferably, the bottom of the housing is equipped with symmetrical support bases.
[0020] By adopting the above technical solution, the symmetrically arranged support bases are fixedly connected to the bottom of the box, providing bottom support for the box and keeping it in a horizontal position. At the same time, the weight of the box and its internal components is evenly distributed to the support surface, thus achieving the purpose of stable placement of the box.
[0021] In summary, this application includes at least one of the following beneficial technical effects:
[0022] Through the coordinated operation of the housing, filter cartridge assembly (cassette support, filter screen), rotating base tube, drive mechanism, spiral coil, drainage assembly, backflushing cleaning assembly, exhaust pipe and material guiding assembly, integrated treatment of flue gas filtration and condensation is achieved. At the same time, the drive mechanism drives the filter cartridge assembly to rotate and cooperate with the backflushing cleaning assembly to achieve efficient cleaning in all directions. Then, the material guiding assembly completes the centralized and controllable discharge of accumulated ash. This not only improves the integration and heat exchange efficiency of flue gas treatment, but also avoids filter screen clogging and ash accumulation problems, ensuring the long-term stable operation of the equipment. Attached Figure Description
[0023] Figure 1 This is a first-person perspective stereoscopic diagram of this application;
[0024] Figure 2 This is a second-view stereoscopic diagram of the present application;
[0025] Figure 3 This is a three-dimensional schematic diagram of the interior of the box in this application;
[0026] Figure 4 This is a cross-sectional view of the present application;
[0027] Figure 5 This is a three-dimensional schematic diagram of the filter cartridge assembly in this application;
[0028] Figure 6 This is a three-dimensional schematic diagram of the backflushing cleaning component in this application.
[0029] Figure label:
[0030] 1. Box body;
[0031] 2. Exhaust pipe fittings;
[0032] 3. Drive mechanism; 31. Drive motor; 32. Drive gear; 33. Gear ring;
[0033] 4. Backflush cleaning assembly; 41. Air pump; 42. Air duct; 43. Exhaust channel;
[0034] 5. Material guiding assembly; 51. Collection trough; 52. Screwdriver; 53. Material guiding motor; 54. Material guiding pipe;
[0035] 6. Air intake pipe;
[0036] 7. Filter cartridge assembly; 71. Cartridge support; 72. Filter mesh; 73. Rotating base tube;
[0037] 8. Spiral coil;
[0038] 9. Support frame;
[0039] 10. Drainage components. Detailed Implementation
[0040] The following is in conjunction with the appendix Figures 1-6 This application will be described in further detail.
[0041] This application discloses a flue gas condenser for boilers.
[0042] Reference Figures 1-6 A boiler flue gas condenser includes a housing 1 and a filter cartridge assembly 7 installed inside the housing 1. The filter cartridge assembly 7 includes a housing support 71 and a filter mesh 72 wrapped around the circumferential side wall of the housing support 71. A rotating base tube 73 is coaxially fixedly connected to one end of the housing support 71. The end of the rotating base tube 73 away from the housing support 71 passes through the side wall of the housing 1 and extends to the outside of the housing 1. A sealed bearing is installed at the penetration point between the rotating base tube 73 and the side wall of the housing 1 to achieve rotational sealing. A drive mechanism 3 for driving the rotating base tube 73 to rotate is installed on the outer side wall of the housing 1 at the position corresponding to the rotating base tube 73. An exhaust pipe 2 that is rotatably connected to the end of the rotating base tube 73 is also installed on the outer side of the housing 1.
[0043] An air inlet pipe 6 is integrally formed at the end of the housing 1 away from the rotating base tube 73. The air inlet pipe 6 is connected to the inside of the housing 1, and the axis of the air inlet pipe 6 is parallel to the axis of the filter cartridge assembly 7. A spiral coil 8 is coaxially arranged inside the cylinder support 71. The water inlet and outlet ends of the spiral coil 8 pass through the internal channel of the rotating base tube 73 and extend to the outside of the exhaust pipe 2. The penetration point between the spiral coil 8 and the rotating base tube 73 is sealed with a sealing sleeve. A back-blowing cleaning assembly 4 is also installed on the outside of the housing 1 at the position corresponding to the rotating base tube 73. The air outlet of the back-blowing cleaning assembly 4 passes through the rotating base tube 73 and extends to the inside of the filter cloth 72. A material guide port is integrally formed at the bottom of the housing 1, and a material guide assembly 5 is fixedly connected to the material guide port. Two support seats are symmetrically welded at the bottom of the housing 1. The support seats are made of Q235 steel and have mounting holes at the bottom for easy installation of the equipment.
[0044] The filter cartridge assembly 7 is installed inside the housing 1 to construct the flue gas filtration chamber; the rotating base tube 73 provides installation support for the filter cartridge assembly 7 and serves as a flue gas discharge channel; the spiral coil 8 is placed inside the filter cartridge assembly 7 and can directly contact the filtered flue gas to improve heat exchange efficiency; the back-flushing cleaning assembly 4 cleans the dust from the inside of the filter mesh 72, and at the same time, the drive mechanism 3 is activated to drive the rotating base tube 73 to rotate, thereby driving the filter cartridge assembly 7 to rotate synchronously at a low speed and smoothly to ensure thorough cleaning; the material guiding assembly 5 receives and discharges the dust generated during cleaning, realizing centralized dust treatment. All components work together to complete the integrated treatment of flue gas filtration, condensation, cleaning, and ash discharge.
[0045] Reference Figure 1 and Figure 3 The drive mechanism 3 includes a drive motor 31 that is bolted to the outer side wall of the housing 1. The drive motor 31 is a servo motor, and its output shaft is fixedly connected to a drive gear 32 via a flat key. A gear ring 33 is welded to the section of the rotating base tube 73 that extends to the outside of the housing 1. The gear ring 33 meshes with the drive gear 32.
[0046] After the drive motor 31 starts, the output shaft drives the drive gear 32 to rotate. The drive gear 32 transmits power to the gear ring 33 through meshing, which in turn drives the rotating base tube 73 to rotate synchronously. This can convert the high-speed rotation of the drive motor 31 into the low-speed and stable rotation of the rotating base tube 73, providing suitable power for the rotation cleaning operation of the filter cartridge assembly 7.
[0047] Reference Figure 1 and Figure 3 The exhaust pipe fitting 2 includes a sleeve that is rotatably fitted onto the end of the rotating base pipe 73. A sealing ring is installed between the sleeve and the rotating base pipe 73. The sealing rings are spaced apart along the axial direction of the rotating base pipe 73 to improve the rotational sealing effect. An exhaust pipe is integrally formed on one side of the sleeve. The axis of the exhaust pipe is perpendicular to the axis of the sleeve. A flange is welded to the end of the exhaust pipe away from the sleeve to facilitate connection with the subsequent smoke exhaust pipe. A support frame is welded to the bottom of the sleeve. The support frame adopts an angle steel structure. The end of the support frame away from the sleeve is fixedly connected to the outer wall of the housing 1 by expansion bolts. Reinforcing pads are welded at the connection between the support frame, the sleeve, and the housing 1.
[0048] The sleeve is rotatably fitted onto the end of the rotating base pipe 73, and a sealing ring is used to achieve a rotary seal. This does not interfere with the rotational movement of the rotating base pipe 73, and also prevents flue gas from leaking from the joint between the rotating base pipe 73 and the sleeve. The support frame enhances the support strength through the angle steel structure and reinforcing pads, and firmly fixes the sleeve to the housing 1, ensuring the stability of the installation benchmark of the exhaust pipe fitting 2. The flue gas, after being filtered by the filter cartridge assembly 7 and condensed by the spiral coil 8, enters the sleeve from the internal channel of the rotating base pipe 73, and is then discharged to the subsequent pipeline through the exhaust pipe and flange, achieving directional and smooth emission of flue gas.
[0049] Reference Figure 1 , Figure 3 and Figure 4The backflushing cleaning assembly 4 includes an air pump 41 fixed to the outside of the housing 1 by bolts. The air pump 41 is a high-pressure vortex air pump. Its outlet end is connected to an air guide pipe 42 by a clamp. The air guide pipe is made of stainless steel. The end of the air guide pipe 42 away from the air pump 41 passes through the internal channel of the rotating base pipe 73 and extends into the inside of the cylinder support 71. The section of the air guide pipe 42 extending into the inside of the cylinder support 71 is horizontally arranged. Several exhaust channels 43 are evenly opened on the outer wall of the air guide pipe 42 located above the inner side of the bottom end of the cylinder support 71. The exhaust channels 43 are circular through holes with a diameter of 5mm. The distance between two adjacent exhaust channels is 30mm. The axis of the exhaust channel 43 forms a 45° angle with the inner wall of the filter cloth 72 to improve the gas impact effect.
[0050] High-pressure gas is generated by air pump 41 and transported to the inside of cylinder support 71 through air guide pipe 42. The high-pressure gas is injected into the inner side of filter cloth 72 at a 45° angle through exhaust channel 43 on air guide pipe 42. As the filter cylinder assembly 7 rotates continuously under the drive of drive mechanism 3, each area of filter cloth 72 can pass through the spray range of exhaust channel 43 in sequence to achieve the purpose of full circumferential dust removal.
[0051] Reference Figure 3 and Figure 4 The material guiding assembly 5 includes a collection trough 51 fixedly connected to the bottom material guiding port of the box 1 via a flange. The collection trough 51 has a U-shaped groove structure, and its inner wall is polished to reduce dust accumulation. An auger 52 is rotatably installed inside the collection trough 51 via bearings. The auger 52 includes a rotating shaft and spiral blades welded to the rotating shaft. The gap between the spiral blades and the inner wall of the collection trough 51 is 2mm to ensure that dust can be fully pushed. A material guiding motor 53 is fixedly installed on one side of the collection trough 51 via bolts. The output shaft of the material guiding motor 53 is connected to the end shaft of the auger 52 via a coupling. A material guiding pipe 54 is integrally formed on one side of the bottom of the collection trough 51. The material guiding pipe 54 communicates with the inside of the collection trough 51. A sealing door is fitted at the bottom of the material guiding pipe 54. The sealing door adopts a flip-top structure and is hinged to the material guiding pipe 54 via a hinge. A sealing gasket is installed at the contact point between the sealing door and the material guiding pipe 54. Under normal conditions, the sealing door closes under gravity to achieve a seal.
[0052] The dust blown off the filter screen 72 is collected in the collection box 51. Under the action of gravity, the dust falls into the U-shaped groove of the collection box 51. After the feed motor 53 is started, it drives the auger 52 to rotate through the coupling. The spiral blades push the dust in the collection box 51 towards the feed pipe 54. Under normal circumstances, the sealing door is closed under the action of gravity to prevent the flue gas in the box 1 from leaking from the feed pipe 54. When it is necessary to discharge dust, the sealing door is manually flipped. The dust pushed to the feed pipe 54 is discharged through the feed pipe 54 under the action of gravity and the pushing force of the spiral blades, realizing the centralized collection and controllable discharge of dust.
[0053] Reference Figure 3 , Figure 4 and Figure 6 The spiral coil 8 has a support frame 9 welded to the end away from the rotating base tube 73. The support frame 9 includes a cross-shaped bracket and a support shaft fixed at the center of the cross-shaped bracket. The cross-shaped bracket is welded and fixed to the end of the spiral coil 8. The support shaft passes through a through hole opened on the side wall of the cylinder support 71. The support shaft is fixed to the cylinder support 71 by a bearing. The end of the support shaft away from the cross is fixed to the inner wall of the housing 1 by bolts. The spiral coil 8 is made of 304 stainless steel. The diameter of the coil is 20mm and the pitch is 50mm to ensure sufficient contact area with the flue gas. Both the inlet and outlet ends of the spiral coil 8 are fitted with connectors to facilitate connection with external cooling medium pipes. In addition, a drainage assembly 10 for collecting condensate can be fixed directly below the spiral coil 8. The drainage assembly 10 includes a V-shaped stainless steel water receiving tray suspended at the bottom of the spiral coil 8. The bottom end of the water receiving tray is connected to a pipe that runs from the middle of the rotating base tube 73 and out of the sleeve. The end of the pipe can be connected to a suction pump to drain the condensate.
[0054] The cross-shaped bracket and support shaft of the support frame 9 provide stable support for the end of the spiral coil 8 away from the rotating base tube 73. The support shaft is fixed to the inner wall of the housing 1, so that the support frame 9 forms a fixed support reference. The other end of the spiral coil 8 extends to the outside through the internal channel of the rotating base tube 73, forming a two-end support structure with the support frame 9, ensuring the installation stability of the spiral coil 8 inside the filter cartridge assembly 7.
[0055] The implementation principle of a boiler flue gas condenser according to an embodiment of this application is as follows:
[0056] Before use, connect the air inlet pipe 6 to the boiler's flue gas pipe through a flange, and connect the exhaust pipe of the exhaust pipe fitting 2 to the subsequent treatment pipe through a flange; connect the water inlet and outlet of the spiral coil 8 to the external cooling medium circulation pipe respectively, and connect the air pump of the back-flushing cleaning assembly 4 to the compressed air source; finally, check the sealing status of each seal to ensure there is no risk of leakage.
[0057] When the equipment is running, the flue gas generated by the boiler enters the housing 1 through the inlet pipe 6. The flue gas diffuses in the housing 1 and passes through the filter cloth 72 of the filter cartridge assembly 7. The filter cloth 72 filters the particulate matter in the flue gas, and the filtered flue gas enters the interior of the filter cartridge assembly 7.
[0058] The external cooling medium enters the spiral coil 8 through the inlet end. During its flow inside the spiral coil 8, it exchanges heat with the filtered flue gas inside the filter cartridge assembly 7. The heat in the flue gas is absorbed by the cooling medium, achieving flue gas condensation. The condensate is collected in the water receiving tray directly below the spiral coil 8. A suction pump connected to the end of the pipe at one end of the water receiving tray pumps out the condensate. The cooling medium, after absorbing heat, is discharged from the outlet end of the spiral coil 8 and enters the external circulation system for cooling and reuse.
[0059] During the filtration and condensation process, the air pump 41 of the backflushing cleaning assembly 4 is activated. The high-pressure gas generated by the air pump 41 is transported to the inside of the cylinder support 71 through the air guide pipe 42, and is then directionally sprayed onto the inner side of the filter cloth 72 through the exhaust channel 43 on the air guide pipe 42. At the same time, the drive motor 31 of the drive mechanism 3 is activated. The drive motor 31 drives the drive gear 32 to rotate. The drive gear 32 drives the gear ring 33 and the rotating base tube 73 to rotate through meshing, thereby driving the filter cartridge assembly 7 to rotate synchronously at a low speed and smoothly. Each area of the filter cloth 72 is impacted by the high-pressure gas in turn, and the dust attached to the outside of the filter cloth 72 is blown off. The blown-off dust falls into the collection box 51 at the bottom of the box 1 under the action of gravity.
[0060] Start the guide motor 53 of the guide assembly 5. The guide motor 53 drives the auger 52 to rotate. The spiral blades push the dust in the collection box 51 towards the guide pipe 54. When it is necessary to discharge the dust, manually flip the sealing door. The dust is discharged and collected through the guide pipe 54. After the dust is discharged, loosen the sealing door. The sealing door closes under the action of gravity.
[0061] The clean flue gas, after being filtered and condensed, enters the internal channel of the rotating base tube 73 from inside the filter cartridge assembly 7, then flows into the sleeve of the exhaust pipe 2, and finally exits through the exhaust pipe to the subsequent treatment pipeline, completing the entire flue gas treatment process.
[0062] The above are merely optional embodiments of this application and are not intended to limit this application. Various modifications and variations can be made to this application by those skilled in the art. Any modifications, equivalent substitutions, improvements, etc., made within the spirit and principles of this application should be included within the protection scope of this application.
Claims
1. A flue gas condenser for boilers, characterized in that, The device includes a housing (1), an exhaust pipe (2) and an intake pipe (6) installed on the outside of the housing (1), a filter cartridge assembly (7) for filtering flue gas is provided inside the housing (1), the filter cartridge assembly (7) includes a cylinder support (71) and a filter mesh (72) wrapped around the circumferential side wall of the cylinder support (71), one end of the cylinder support (71) is connected to a rotating base tube (73) extending to the outside of the housing (1), a drive mechanism (3) for driving the rotating base tube (73) to rotate is installed on the outside of the housing (1), and the exhaust pipe (2) is sleeved on the rotating base tube (73); The cylinder support (71) is equipped with a spiral coil (8) inside. A drainage assembly (10) for collecting condensate is provided below the spiral coil (8). The inlet and outlet of the spiral coil (8) pass through the rotating base tube (73) and extend to the outside of the exhaust pipe (2). A back-blowing cleaning assembly (4) for cleaning the filter cloth (72) is installed on the outside of the box (1). The outlet of the back-blowing cleaning assembly (4) passes through the rotating base tube (73) and extends to the inside of the filter cloth (72). A material guide assembly (5) for discharging dust is provided at the bottom of the box (1).
2. A boiler flue gas condenser according to claim 1, characterized in that: The drive mechanism (3) includes a drive motor (31) installed outside the housing (1), the output shaft of the drive motor (31) is connected to a drive tooth (32), and a gear ring (33) that meshes with the drive tooth (32) is fixed outside the rotating base tube (73).
3. A boiler flue gas condenser according to claim 1, characterized in that: The exhaust pipe (2) includes a sleeve that is rotatably sleeved on the end side of the rotating base pipe (73), an exhaust pipe is connected to one side of the sleeve, and a support frame that is connected to the housing (1) is fixed at the bottom end of the sleeve.
4. A boiler flue gas condenser according to claim 1, characterized in that: The back-flushing cleaning assembly (4) includes an air pump (41) installed outside the housing (1). The air outlet of the air pump (41) is connected to an air guide pipe (42). The end of the air guide pipe (42) away from the air pump (41) extends into the interior of the cylinder support (71) and is horizontally arranged. An exhaust channel (43) is provided on the outer wall of the air guide pipe (42). The exhaust channel (43) is located above the inner side of the bottom end of the cylinder support (71).
5. A boiler flue gas condenser according to claim 1, characterized in that: The material guiding assembly (5) includes a collection trough (51) communicating with the bottom of the box (1). An auger (52) is rotatably installed inside the collection trough (51). A material guiding motor (53) connected to the shaft of the auger (52) is installed on one side of the collection trough (51). A material guiding pipe (54) is connected to one side of the bottom of the collection trough (51). A sealing door is fitted at the bottom of the material guiding pipe (54).
6. A boiler flue gas condenser according to claim 1, characterized in that: The spiral coil (8) is connected to a support frame (9) at one end away from the rotating base tube (73). The support frame (9) at one end away from the spiral coil (8) passes through the cylindrical support (71) and is fixedly connected to the inner wall of the box (1).
7. A boiler flue gas condenser according to claim 1, characterized in that: The bottom of the box (1) is equipped with symmetrical support seats.