An emergency ash discharge pipe structure for an energy-saving circulating fluidized bed boiler
By separating the slag flow channel and the slag removal tool channel in the emergency slag discharge pipe of the circulating fluidized bed boiler, and using control valves to control the slag flow direction, the problem of scalding from high-temperature ash slag self-flow has been solved, achieving safe and efficient slag discharge and low-cost maintenance.
Patent Information
- Application Number
- CN202522675071.8
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2025-12-17
- Publication Date
- 2026-11-17
- Estimated Expiration
- 2035-12-17
AI Technical Summary
The existing ash discharge pipe structure of circulating fluidized bed boilers is prone to causing high-temperature ash to flow freely, posing a safety hazard of burns to personnel. In addition, the structure is complex and the maintenance cost is high.
An emergency slag discharge pipe structure was designed to separate the slag flow direction from the slag removal tool channel. The first channel is used for slag discharge, and the second channel is used for the slag removal tool to enter. The slag flow direction is controlled by the first and second emergency slag discharge valves to prevent high-temperature ash slag from directly contacting personnel.
It achieves safe and reliable slag discharge, avoids burn accidents, and has a simple structure, reducing maintenance costs.
Smart Images

Figure CN224984061U_ABST
Abstract
Description
Technical Field
[0001] This utility model belongs to the field of boiler technology and relates to a boiler emergency slag discharge pipe structure, specifically to an environmentally friendly and energy-saving circulating fluidized bed boiler emergency slag discharge pipe structure. Background Technology
[0002] Circulating fluidized bed combustion is a clean coal combustion technology with good fuel adaptability, wide load adjustment ratio, and high combustion efficiency. Circulating fluidized bed boilers can control the generation of sulfur dioxide and nitrogen oxides at low cost during combustion, which is of great value to my country, where primary energy is mainly coal. The continuous increase in total coal consumption has put enormous pressure on the environment. To resolve the contradiction between energy and environmental protection, the development of circulating fluidized bed boiler technology has become an inevitable trend. Its working principle is that fuel and air are mixed and burned in a fluidized state in the furnace, exchanging heat with the heating surfaces. The emergency ash discharge pipe of a fluidized bed boiler, also known as the emergency ash discharge pipe or emergency ash release pipe, is a key component of the boiler safety system. It is mainly used to quickly discharge bed material under abnormal operating conditions to prevent boiler damage or the escalation of accidents. Its core function is emergency ash discharge: when the boiler bed pressure rises abnormally (such as bed material accumulation, ash discharge system failure, coking, etc.), the bed material is quickly released through the emergency ash discharge pipe to avoid excessive fluidizing air resistance leading to deterioration of bed fluidization or a sudden increase in furnace pressure. Secondly, it prevents coking: If the bed temperature is too high (such as abnormal combustion), it may cause local melting and coking of the bed material. The emergency slag discharge pipe can promptly discharge high-temperature materials and immediately discharge the coking bed material through the emergency slag discharge pipe to remove heat sources and adhering materials, prevent the coking area from expanding, and avoid the entire air distribution plate or furnace being blocked by a large piece of coke, resulting in significant losses due to long-term boiler shutdown. Thirdly, it protects the air cap and air distribution plate: Excessive bed pressure may damage the air cap or air distribution plate. Emergency slag discharge can reduce bed pressure and protect critical equipment. Structure and operation characteristics: Usually directly connected to the air chamber or below the air distribution plate. Discharges high-temperature, high-concentration, coarse-particle bed material (large pipe diameter to ensure rapid slag discharge), manually operated by operators. Purpose of normal slag discharge pipe (cooler): Continuous and balanced operation: Under normal operating conditions, the position is connected to the lower dense phase zone of the furnace. The discharge state is controllable flow, cooled ash and slag, connected to the cooler, and transported after cooling, achieved through automatic and continuous adjustment.
[0003] The core function of the emergency ash discharge pipe is to quickly and urgently empty the bed material in the event of a serious boiler malfunction, preventing equipment damage and the escalation of the accident. It serves as the last line of defense for the boiler's safety. Normal ash discharge pipes are like the human body's "urinary system," responsible for daily metabolism and maintaining internal balance. Emergency ash discharge pipes, on the other hand, are like "emergency floodgates," not used under normal circumstances, but opened immediately in the event of a "flood" (accident) to prevent the "dam" (boiler) from collapsing. The conventional structure of emergency ash discharge pipes in circulating fluidized bed boilers typically uses a straight pipe structure with a 45-degree inclination. With this structure, when ash blockage occurs and manual ash removal is required, the high-temperature ash slides out from the 45-degree inclination pipe, easily leading to gravity flow and potentially causing hot ash to fall to the ground and burn personnel. Utility Model Content
[0004] To overcome the limitations of existing technologies, this utility model provides an emergency slag discharge pipe structure for an energy-saving circulating fluidized bed boiler. This emergency slag discharge pipe separates the slag flow direction from the slag removal tool channel, and has the advantages of simple structure, convenient operation, and safety and reliability.
[0005] An emergency ash discharge pipe structure for an energy-saving circulating fluidized bed boiler includes a first channel, a second channel, a third channel, a first emergency ash discharge valve, and a second emergency ash discharge valve. The first channel is inclined and connected to the ash discharge pipe. The second channel is vertically arranged and fixedly connected to the first channel. The third channel is located at the outlet of the first channel and fixedly connected to the second channel. The centerline of the third channel is collinear with that of the first channel. The inner diameter of the third channel is smaller than that of the first channel. The outlet of the second channel is equipped with a first emergency ash discharge valve, and the outlet of the third channel is equipped with a second emergency ash discharge valve.
[0006] Furthermore, the first emergency slag discharge valve includes a steel plate and a first sealing box; the first sealing box is installed at the outlet of the second channel, the steel plate passes through the first sealing box and can slide relative to the first sealing box, the first sealing box is provided with a first hole communicating with the second channel, and the steel plate has a second hole adapted to the first hole.
[0007] Furthermore, the second emergency slag discharge valve includes a pull plate and a second sealing box; the second sealing box is installed at the outlet of the third channel, the pull plate passes through the second sealing box and can slide relative to the second sealing box, the second sealing box is provided with a third hole communicating with the third channel, and the pull plate has a fourth hole adapted to the third hole.
[0008] The advantages of this utility model compared to the prior art are:
[0009] This utility model's emergency slag discharge pipe structure separates the slag flow direction from the slag removal tool's channel. The third channel is used for the slag removal tool to enter, while the second channel is used for slag discharge. This utility model structure ensures personnel safety and enables smooth slag discharge. It is simple in structure, easy to manufacture, and has low cost and maintenance. It avoids the risk of personnel burns caused by the positive pressure in the furnace and the slag temperature reaching over 900 degrees Celsius, which could lead to the separated slag being sprayed out in a jet-like manner.
[0010] The present invention will be further described below with reference to the accompanying drawings and embodiments: Attached Figure Description
[0011] Figure 1 This is a schematic diagram of the emergency slag discharge pipe structure of the energy-saving circulating fluidized bed boiler of this utility model;
[0012] Figure 2 for Figure 1 Enlarged image;
[0013] Figure 3 for Figure 2 Side view;
[0014] Figure 4 for Figure 2 Sectional view along line BB;
[0015] Figure 5 for Figure 2 A cross-sectional view along line AA. Detailed Implementation
[0016] The embodiments of the technical solutions of this application will now be described in detail with reference to the accompanying drawings. Unless otherwise stated, the technical or scientific terms used in this application have the ordinary meanings understood by those skilled in the art.
[0017] Example 1, Reference Figures 2-4 The emergency slag discharge pipe structure of an energy-saving circulating fluidized bed boiler provided in this embodiment includes a first channel 1, a second channel 2, a third channel 3, a first emergency slag discharge valve 4, and a second emergency slag discharge valve 5.
[0018] The ash and slag are located inside the furnace 11. The first channel 1 is inclined at 45° and connected to the ash discharge pipe 12 (cold ash machine or cold slag machine connector). The ash discharge pipe 12 is located below the air distribution plate 10 and passes through the air chamber to connect to the inside of the furnace. The second channel 2 is vertically arranged and fixed to the first channel 1. The third channel 3 is located at the outlet of the first channel 1 and fixed to the second channel 2. The third channel 3 is arranged parallel to the first channel 1 and the center line of the third channel 3 is collinear with that of the first channel 1. The inner diameter of the third channel 3 is smaller than that of the first channel 1. The first channel 1, the second channel 2 and the third channel 3 are interconnected. The acute angle θ formed by the axes of the second channel 2 and the third channel 3 is 45°. The outlet of the second channel 2 is equipped with a first emergency ash discharge valve 4 and the outlet of the third channel 3 is equipped with a second emergency ash discharge valve 5.
[0019] This embodiment separates the slag flow direction from the slag-clearing tool's channel. The third channel 3 is used for the slag-clearing tool to enter, while the first channel 1 is used for slag discharge. For example, the first channel 1 and the second channel 2 are both large-diameter steel pipes, such as 133mm or 159mm, while the third channel 3 is a small-diameter steel pipe, such as 76mm. This ensures both personnel safety and smooth slag discharge.
[0020] Example 2, exemplary, referring to Figure 4 The first emergency discharge valve 4 includes a steel plate 41 and a first sealing box 42; the first sealing box 42 is installed at the outlet of the second channel 2, the steel plate 41 passes through the first sealing box 42 and can slide relative to the first sealing box 42, the first sealing box 42 is provided with a first hole 421 communicating with the second channel 2, and the steel plate 41 has a second hole 411 adapted to the first hole 421.
[0021] For example, refer to Figure 5 The second emergency discharge valve 5 includes a pull plate 51 and a second sealing box 52; the second sealing box 52 is installed at the outlet of the third channel 3, the pull plate 51 passes through the second sealing box 52 and can slide relative to the second sealing box 52, the second sealing box 52 is provided with a third hole 521 communicating with the third channel 3, and the pull plate 51 has a fourth hole 511 adapted to the third hole 521.
[0022] Operating mode: When emergency slag discharge is required, the first emergency slag discharge valve 4 and the second emergency slag discharge valve 5 are opened simultaneously. When operating the second emergency slag discharge valve 5, the end of the pull plate 51 away from the third hole 521 has a handle 512. The operator pulls the handle 512 to align the fourth hole 511 on the pull plate 51 with the third hole 521 in the second sealing box 52. The slag removal tool can then enter through this hole. The third channel serves to remove slag and prevent small amounts of ash and small particles of slag from falling and clogging the first channel 1, making it difficult for ash and slag to be discharged from the second channel 2. At the same time, the first emergency slag discharge valve 4 is activated. The end of the steel plate 41 away from the first hole 421 has a U-shaped hole 412. The operator uses an iron hook to hook the U-shaped hole 412 and align the first hole 421 in the first sealing box 42 of the first emergency slag discharge valve 4 with the second hole 411 on the steel plate 41. In this way, the high-temperature ash and slag will fall vertically to the ground from the hole, avoiding burns to personnel. Optionally, both the first hole 421 and the second hole 411 are circular holes.
[0023] Typically, there are four ash discharge pipes inside the furnace. Two of the ash discharge pipes are connected to the ash cooler, and the other two are connected to the slag cooler. Each ash discharge pipe is connected to the emergency ash discharge pipe structure of this embodiment. By adopting the above operating mode, selective ash discharge can be achieved.
[0024] Compared to previous emergency slag discharge pipe designs, the emergency slag discharge pipe structure in the above embodiment separates the slag flow direction from the channel for slag removal tools. The third channel 3 is used for the entry of slag removal tools, while the second channel 2 is used for slag discharge. Due to the positive pressure in the furnace 11 and the slag temperature reaching over 900 degrees Celsius, the separated slag is prone to spraying out in a jet-like manner, causing burns to personnel. This new structure ensures personnel safety while achieving smooth slag discharge. It is simple in structure, easy to manufacture, and has low cost and maintenance.
[0025] This application has been disclosed above with preferred embodiments, but it is not intended to limit this application. Any person skilled in the art can make some changes or modifications to the above-disclosed structure and technical content to create equivalent embodiments without departing from the scope of the technical solution of this application, and all such modifications and modifications are within the scope of the technical solution of this application.
Claims
1. An emergency slag tapping pipe structure of an energy saving circulating fluidized bed boiler, characterized by: The first channel, the second channel, the third channel, the first emergency slag discharge valve and the second emergency slag discharge valve are provided. The first channel is obliquely arranged and connected with the slag falling pipe, the second channel is vertically arranged and fixedly connected with the first channel, the third channel is located at the outlet of the first channel and fixedly connected with the second channel, the third channel is collinear with the center line of the first channel, the inner diameter of the third channel is smaller than that of the first channel, the outlet of the second channel is provided with the first emergency slag discharge valve, and the outlet of the third channel is provided with the second emergency slag discharge valve.
2. The emergency slag tapping channel structure of an energy-saving circulating fluidized bed boiler according to claim 1, characterized in that: The first emergency slag discharge valve comprises a steel plate and a first sealing box. The first sealing box is arranged at the outlet of the second channel, the steel plate passes through the first sealing box and is slidable relative to the first sealing box, the first sealing box is provided with a first hole communicated with the second channel, and the steel plate is provided with a second hole matched with the first hole.
3. The emergency slag tapping arrangement of an energy saving circulating fluidized bed boiler according to claim 1, characterized in that: The second emergency slag discharge valve comprises a pull plate and a second sealing box, the second sealing box is arranged at the outlet of the third channel, the pull plate passes through the second sealing box and is slidable relative to the second sealing box, the second sealing box is provided with a third hole communicated with the third channel, and the pull plate is provided with a fourth hole matched with the third hole.
4. The emergency slag tapping channel structure of the energy-saving circulating fluidized bed boiler according to claim 2, characterized in that: The end of the steel plate away from the second hole is provided with a U-shaped hole.
5. The emergency slag tapping arrangement of an energy saving circulating fluidized bed boiler according to claim 3, characterized in that: The end of the pull plate away from the fourth hole is provided with a handle.
6. The emergency slag tapping arrangement of an energy saving circulating fluidized bed boiler according to claim 1, characterized in that: The second channel and the third channel are arranged at an acute angle of 45°.