Emergency shut-off devices and ship power distribution systems

By integrating the shut-off signals of marine fans and pumps onto the main power distribution board, the problems of cumbersome design and high cost of emergency shut-off systems in existing technologies are solved, achieving the effects of simplified design, reduced costs, and easier maintenance.

CN224986903UActive Publication Date: 2026-11-17SUMEDA SHIPPING CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202522329546.8
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2025-11-03
Publication Date
2026-11-17
Estimated Expiration
2035-11-03

AI Technical Summary

Technical Problem

The existing emergency shutdown system for ship power distribution is cumbersome and costly to design, putting enormous pressure on shipyard construction.

Method used

The shut-off signals for marine fans and pumps are integrated into the main distribution board, and shut-off is achieved through switches on the main distribution board. Wiring is then laid at each location where operation is required, simplifying the wiring design.

Benefits of technology

It simplifies the design of emergency shutdown systems, reduces raw material and labor costs, simplifies wiring configuration, and facilitates fault diagnosis and repair.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN224986903U_ABST
    Figure CN224986903U_ABST
Patent Text Reader

Abstract

This application provides an emergency shut-off device and a ship's power distribution system. The emergency shut-off device includes: a main ship switchboard; and an emergency switch connected in series with the main ship switchboard to the power supply lines of various ship facilities. The power supply lines for each ship facility include lines for engine room fans and oil pumps, cabin fans, galley equipment, and engine room area fans. This application provides an emergency shut-off circuit structure that integrates all shipboard fans and pumps onto the main switchboard, allowing all shut-off operations to be performed via the main switchboard's switch.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This application belongs to the technical field of electrical design, and relates to an emergency shut-off device, and more particularly to an emergency shut-off device and a ship power distribution system. Background Technology

[0002] Currently, ships possess relatively comprehensive emergency facilities. Among these, the emergency shutdown design of the ship's electrical distribution system is a core component of the ship's safety system. Its core objective is to quickly, reliably, and safely shut off non-essential power to relevant areas in the event of fire, severe flooding, major mechanical equipment failure, or other emergencies. This eliminates the risk of electric shock, prevents the spread of fire, avoids equipment damage, and creates conditions for personnel evacuation and emergency operations. The emergency shutdown device controls all the ship's fan and oil pump systems, such as engine room fans, fuel pumps, and cargo oil pumps.

[0003] Typically, the emergency power cut-off system for shipboard power distribution is designed as a separate system that integrates the cut-off signals of marine fans and pumps. While this design meets the specifications and usage requirements, it places enormous pressure on shipyard construction and costs. Utility Model Content

[0004] This application provides an emergency shut-off device and a ship power distribution system to solve the problems of cumbersome design and high cost of existing emergency shut-off systems.

[0005] In a first aspect, this application provides an emergency shut-off device, which includes: a ship's main power distribution board; and an emergency switch connected in series with the power supply lines from the ship's main power distribution board to various ship facilities; wherein the power supply lines for each ship facility include oil pump lines for engine room fans, cabin fan lines, galley equipment lines, and engine room area fan lines.

[0006] In one implementation of the first aspect, the emergency switch includes a nacelle entrance emergency switch, which is fixedly connected to the emergency operation area at the nacelle entrance via the wiring arrangement of the wind turbine oil pump at the nacelle entrance machine location.

[0007] In one implementation of the first aspect, the emergency switch includes a central control room emergency switch, which is fixedly connected to the emergency operation area of ​​the central control room through the wiring arrangement of the fan oil pump in the machine space of the central control room.

[0008] In one implementation of the first aspect, the emergency switch includes a cab emergency switch, which is fixedly connected to the emergency operation area of ​​the cab via wiring of the cab cabin fan and the cab machine space fan oil pump.

[0009] In one implementation of the first aspect, the emergency switch includes a fire control room emergency switch, which is fixedly connected to the emergency operation area of ​​the fire control room through the wiring arrangement of the fire control room cabin fan and the fire control room machine space fan oil pump.

[0010] In one implementation of the first aspect, the emergency switch includes a kitchen exit emergency switch, which is fixedly connected to the emergency operation area of ​​the kitchen exit through the wiring of the kitchen equipment power supply.

[0011] In one implementation of the first aspect, the emergency switch includes a first starter panel emergency switch, which is fixedly connected to the emergency operation area at the starter panel of the nacelle equipment assembly through the wiring layout of the nacelle area fan.

[0012] In one implementation of the first aspect, the emergency switch includes a second starter panel emergency switch, which is fixedly connected to the emergency operation area at the starter panel of the bow cabin fan via the wiring arrangement of the bow cabin fan.

[0013] In one implementation of the first aspect, the emergency switch includes a third starter panel emergency switch and a distribution box emergency switch. The third starter panel emergency switch is fixedly connected to the emergency operation area at the starter panel of the living quarters fan through the wiring arrangement of the living quarters fan. The distribution box emergency switch is fixedly connected to the emergency operation area at the power distribution box of the living quarters fan through the wiring arrangement of the living quarters fan.

[0014] Secondly, this application provides a ship power distribution system, the ship power distribution system comprising: the aforementioned emergency disconnection device; the ship's main power distribution board in the emergency disconnection device includes a disconnecting switch and an insulation detector; the disconnecting switch is connected in series in the three-phase AC power lines of the ship's main power distribution board; the insulation detector is connected in series between the three-phase AC power lines and the ground wire.

[0015] As described above, the emergency shut-off device and ship power distribution system described in this application have the following beneficial effects:

[0016] This application integrates all marine fans and pumps onto the main switchboard. All shutdowns can be performed via switches on the main switchboard, and wiring then runs from the main switchboard to all locations requiring operation (such as the bridge, fire control station, and engine room entrance). This simplifies the design of existing emergency shutdown systems, reduces raw material costs, and lowers labor costs. It also simplifies the wiring configuration and facilitates troubleshooting of faulty lines. Attached Figure Description

[0017] Figure 1 The diagram shown is an emergency shutdown diagram in the prior art.

[0018] Figure 2 The diagram shown is a structural schematic of the emergency shut-off device of this application in one embodiment.

[0019] Figure 3 The diagram shown is a schematic of the cabin entrance emergency cut-off circuit in one embodiment of the emergency cut-off device of this application.

[0020] Figure 4 The diagram shown is a schematic representation of the overall circuit structure of the emergency disconnection device of this application in one embodiment.

[0021] Figure 5 The diagram shown is a schematic representation of the emergency cutting structure of the emergency cutting device of this application in one embodiment.

[0022] Figure 6 The diagram shown is a structural schematic of a ship power distribution system according to one embodiment of this application.

[0023] Component designation explanation

[0024] 2. Emergency shut-off device

[0025] 21. Ship's main electrical control panel

[0026] 211 Disconnecting switch

[0027] 212 Insulation Monitor

[0028] 22 Emergency Switch Detailed Implementation

[0029] The following specific examples illustrate the implementation of this application. Those skilled in the art can easily understand other advantages and effects of this application from the content disclosed in this specification. This application can also be implemented or applied through other different specific embodiments, and various details in this specification can also be modified or changed based on different viewpoints and applications without departing from the spirit of this application. It should be noted that, unless otherwise specified, the following embodiments and features in the embodiments can be combined with each other.

[0030] It should be noted that the illustrations provided in the following embodiments are only schematic representations of the basic concept of this application. Therefore, the illustrations only show the components related to this application and are not drawn according to the number, shape and size of the components in actual implementation. In actual implementation, the form, quantity and proportion of each component can be arbitrarily changed, and the layout of the components may also be more complex.

[0031] The following will describe in detail the principle and implementation of an emergency cut-off device and a ship power distribution system according to the present embodiment, with reference to the accompanying drawings, so that those skilled in the art can understand the emergency cut-off device and ship power distribution system of the present embodiment without creative effort.

[0032] Please see Figure 1 This is a schematic diagram of emergency shutdown in existing technology. For example... Figure 1 As shown, ES is an abbreviation for EMERGENCYSTOP. 1, 2, 3, 4, 5, and 6 represent the cut-off group numbers. 1 represents the oil pump, 2 represents the fan, 3 represents the oil pump and fan in the engine room, 4 represents the cabin fan, and 5 represents the galley fan and equipment.

[0033] like Figure 1 As shown, the bridge deck is equipped with a bridge, and the bridge is equipped with a control panel, which is equipped with an ES1 emergency cut-off button and an ES4 emergency cut-off button.

[0034] Figure 1 In the middle, on the left side of the main engine room entrance FR19 on the upper deck (stern), there is an engine room changing room, which includes an ES1 emergency cut-off button and an ES2 emergency cut-off button.

[0035] like Figure 1 As shown, the engine room control room of platform A is equipped with an engine room control console and a main power distribution board, both of which are connected to the emergency disconnect box (JUNCTION BOX FOREMERGENCY STOP SYSTEM) at the fire control station.

[0036] Figure 1 In the middle, the ES3 emergency shut-off button is located on the right side of the FR30 outside the oil separator room door on platform B of the engine room.

[0037] like Figure 1 As shown, the ES5 emergency shut-off button is located on the right side of the kitchen entrance FR25 on deck A. The emergency generator room on deck A is equipped with an emergency power distribution board, which can be used to shut off ES1, ES2, ES3, and ES4 in an emergency.

[0038] Figure 1 The carbon dioxide chamber on the upper deck (stern) is equipped with ES1, ES2, ES3, and ES5 emergency shut-off buttons. The fire control station on the upper deck (stern) is equipped with a fire control panel, which includes ES1, ES2, ES3, ES4, and ES5 emergency shut-off buttons.

[0039] like Figure 1 As shown, the bottom floor of the engine room is equipped with a No. 4 local combined starter panel (which displays a diesel delivery pump, etc.).

[0040] Therefore, Figure 1 The emergency power cut-off system for ship power distribution in China has a separate cut-off system that integrates the cut-off signals of marine fans and pumps into the system. Although this design meets the specifications and usage requirements, it has brought enormous pressure to shipyard construction and costs.

[0041] This application provides an emergency shut-off device, the emergency shut-off device comprising:

[0042] Ship's main electrical control panel;

[0043] An emergency switch is connected in series in the power supply lines from the ship's main switchboard to each ship facility; wherein the power supply lines for each ship facility include the oil pump lines for the engine room fans, the cabin fans, the galley equipment lines, and the engine room area fans.

[0044] Please see Figure 2 The diagram shown is a structural schematic of the emergency shut-off device of this application in one embodiment. Figure 2 As shown, this application provides an emergency shut-off device 2, which includes: a ship's main power distribution board 21 and an emergency switch 22.

[0045] The emergency switch 22 is connected in series in the power supply lines from the ship's main power distribution board 21 to each ship facility.

[0046] The power supply lines for various ship facilities include oil pump lines for engine room fans, cabin fan lines, galley equipment lines, and engine room area fan lines. Specifically, line 1 can be an oil pump line for engine room fans, equipped with an emergency switch 22; line 2 can be a cabin fan line, equipped with an emergency switch 22; line 3 can be a galley equipment line, equipped with an emergency switch 22; and line 4 can be an engine room area fan line, equipped with an emergency switch 22.

[0047] In one embodiment, the emergency switch includes a nacelle entrance emergency switch, which is fixedly connected to the emergency operation area at the nacelle entrance via the wiring arrangement of the wind turbine oil pump at the nacelle entrance machine space.

[0048] Please see Figure 3 The diagram shows a schematic of the cabin entrance emergency cut-off circuit in one embodiment of the emergency cut-off device of this application. Figure 3 As shown, one of the power supply lines of the ship's main switchboard 21 is the engine room fan oil pump line. The engine room entrance emergency switch 22 is connected in series to the engine room fan oil pump line. The connecting lines at both ends of the engine room entrance emergency switch 22 are stretched so that the engine room entrance emergency switch 22 can be placed at a sufficiently far distance to meet the placement requirements of the engine room entrance emergency switch.

[0049] Please see Figure 4 The diagram shows the overall circuit structure of the emergency disconnection device according to one embodiment of this application. Figure 4 As shown, in addition to the emergency switch at the nacelle entrance in the machine space fan oil pump circuit mentioned above, the emergency switch includes a central control room emergency switch, which is fixedly connected to the emergency operation area of ​​the central control room through the circuit layout of the machine space fan oil pump in the central control room.

[0050] like Figure 4 As shown, the emergency switch includes a cab emergency switch, which is fixedly connected to the emergency operation area of ​​the cab through the wiring of the cab cabin fan and the oil pump of the cab machine space fan.

[0051] Figure 4 In this context, the emergency switch includes a fire control room emergency switch, which is fixedly connected to the emergency operation area of ​​the fire control room through the wiring arrangement of the fire control room cabin fan and the fire control room machine space fan oil pump.

[0052] like Figure 4 As shown, the emergency switch includes a kitchen exit emergency switch, which is fixedly connected to the emergency operation area at the kitchen exit through the power supply lines of the kitchen equipment.

[0053] Figure 4 The emergency switch includes a first starter panel emergency switch, which is fixedly connected to the emergency operation area at the starter panel of the nacelle equipment assembly through the wiring layout of the fan in the nacelle area.

[0054] like Figure 4 As shown, the emergency switch includes a second starter panel emergency switch, which is fixedly connected to the emergency operation area at the starter panel of the bow cabin fan through the wiring arrangement of the bow cabin fan.

[0055] Figure 4 The emergency switch includes a third starter panel emergency switch and a distribution box emergency switch. The third starter panel emergency switch is fixedly connected to the emergency operation area at the starter panel of the living quarters fan through the wiring layout of the living quarters fan. The distribution box emergency switch is fixedly connected to the emergency operation area at the power distribution box of the living quarters fan through the wiring layout of the living quarters fan.

[0056] It should be noted that the wiring layout described in this application refers to extending the connecting lines at both ends of each emergency switch while ensuring that the power transmission principle of the main distribution board remains unchanged, so that each emergency switch can be placed at a sufficiently long distance to meet the placement requirements of emergency switches at the engine room entrance, central control room, cockpit, fire control room, galley exit, and distribution boxes.

[0057] Please see Figure 5 The diagram shows a schematic representation of the emergency cut-off structure of the emergency cut-off device according to one embodiment of this application. Figure 5 As shown, the main switchboard (MSB) is equipped with an emergency cut-off circuit for the 1SBE engine room entrance, connected in series to the emergency cut-off circuit for the machinery space fan and oil pump. This includes an ES1 emergency cut-off button (i.e., emergency switch), an ES2 emergency cut-off button, and an ES4 emergency cut-off button. The main switchboard (MSB) is also equipped with an emergency cut-off circuit for the 2SBE engine room entrance, connected in series to the emergency cut-off circuit for the machinery space fan and oil pump. This includes an ES1 emergency cut-off button, an ES2 emergency cut-off button, and an ES4 emergency cut-off button. The main switchboard (MSB) is equipped with an emergency cut-off circuit for the 3SBE central control room (ECC), connected in series to the emergency cut-off circuit for the machinery space fan and oil pump. This includes an ES1 emergency cut-off button, an ES2 emergency cut-off button, and an ES4 emergency cut-off button. The main switchboard (MSB) is also equipped with an emergency cut-off circuit for the 3SBE1 bridge WHC, connected in series to the emergency cut-off circuits for the cabin fans and the machinery space fan and oil pump. This includes an ES1 emergency cut-off button, an ES2 emergency cut-off button, an ES3 emergency cut-off button, and an ES4 emergency cut-off button. The main switchboard (MSB) is equipped with 3SBE2 fire control room emergency cutoff, connected in series to the emergency cutoff circuits for cabin fans and engine room fan oil pumps, including ES1, ES2, ES3, and ES4 emergency cutoff buttons. The main switchboard (MSB) is also equipped with 6SBE galley exit emergency cutoff, connected in series to the galley equipment power supply emergency cutoff circuit, including ES6 emergency cutoff button. The main switchboard (MSB) is equipped with 6GSP-ES engine room equipment combination starter panel emergency cutoff, connected in series to the engine room area fans emergency cutoff circuit, including ES1 and ES4 emergency cutoff buttons. The main switchboard (MSB) is also equipped with 7GSP-ES bow cabin fan starter panel emergency cutoff, connected in series to the cabin fan emergency cutoff circuit, including ES3 and ES4 emergency cutoff buttons. The main distribution board (MSB) is equipped with an 8GSP-ES living quarters fan starter emergency cutoff function, connected in series to the cabin fan emergency cutoff circuit, including ES3 and ES4 emergency cutoff buttons. The main distribution board (MSB) is also equipped with a 3P-ES living quarters fan power distribution box emergency cutoff function, connected in series to the cabin fan emergency cutoff circuit, including an ES3 emergency cutoff button.

[0058] Therefore, this application integrates all marine fans and pumps onto the main switchboard. All shutdowns can be performed via switches on the main switchboard, and wiring is then routed from the main switchboard to all locations requiring operation (such as the bridge, fire control station, and engine room entrance). This simplifies the design of existing emergency shutdown systems, reduces raw material costs, and lowers labor costs. It also simplifies the wiring configuration and facilitates troubleshooting of faulty circuits.

[0059] This application provides a ship power distribution system, which includes: the aforementioned emergency disconnection device.

[0060] The ship's main power distribution board in the emergency disconnection device includes a disconnecting switch and an insulation tester; the disconnecting switch is connected in series in the three-phase AC power line of the ship's main power distribution board; the insulation tester is connected in series between the three-phase AC power line and the ground wire.

[0061] Please see Figure 6 The diagram shown is a structural schematic of the ship power distribution system according to one embodiment of this application. Figure 6 As shown, the ship's power distribution system includes: the emergency cut-off device 2.

[0062] The ship's main power distribution board 21 in the emergency disconnection device 2 includes a disconnecting switch 211 and an insulation tester 212; the disconnecting switch 211 is connected in series in the three-phase AC power line of the ship's main power distribution board 21; the insulation tester 212 is connected in series between the three-phase AC power line and the ground wire.

[0063] like Figure 5 As shown, the main distribution board (MSB) is equipped with an emergency shut-off circuit for the 1SBE nacelle entrance, which is connected in series to the emergency shut-off circuit for the fan oil pump in the machine space. This circuit includes an ES1 emergency shut-off button (i.e., an emergency switch), an ES2 emergency shut-off button, and an ES4 emergency shut-off button.

[0064] Figure 5 In the main distribution board (MSB), there is a 2SBE nacelle inlet emergency cut-off circuit, which is connected in series to the machine space fan oil pump emergency cut-off circuit, including ES1 emergency cut-off button, ES2 emergency cut-off button and ES4 emergency cut-off button.

[0065] like Figure 5 As shown, the main distribution board (MSB) is equipped with a 3SBE central control room ECC emergency cut-off device, which is connected in series to the machine space fan oil pump emergency cut-off circuit, including ES1 emergency cut-off button, ES2 emergency cut-off button and ES4 emergency cut-off button.

[0066] Figure 5In the middle, the main distribution board MSB is equipped with 3SBE1 cab WHC emergency cut-off, which is connected in series to the cabin fan emergency cut-off line and the machine space fan oil pump emergency cut-off line, including ES1 emergency cut-off button, ES2 emergency cut-off button, ES3 emergency cut-off button and ES4 emergency cut-off button.

[0067] like Figure 5 As shown, the main distribution board (MSB) is equipped with a 3SBE2 fire control room emergency cut-off circuit, which is connected in series to the cabin fan emergency cut-off circuit and the machine space fan oil pump emergency cut-off circuit. It includes an ES1 emergency cut-off button, an ES2 emergency cut-off button, an ES3 emergency cut-off button and an ES4 emergency cut-off button.

[0068] Figure 5 In the main distribution board (MSB), there is a 6SBE kitchen outlet emergency cut-off circuit, which is connected in series to the kitchen equipment power emergency cut-off circuit, including the ES6 emergency cut-off button.

[0069] like Figure 5 As shown, the main distribution board (MSB) is equipped with an emergency cut-off switch for the 6GSP-ES nacelle equipment combination starter panel, which is connected in series to the wind turbine emergency cut-off lines in the nacelle area, including the ES1 emergency cut-off button and the ES4 emergency cut-off button.

[0070] Figure 5 In the middle, the main distribution board (MSB) is equipped with an emergency cut-off device for the 7GSP-ES bow compartment fan starter panel, which is connected in series to the compartment fan emergency cut-off line, including the ES3 emergency cut-off button and the ES4 emergency cut-off button.

[0071] like Figure 5 As shown, the main distribution board (MSB) is equipped with an 8GSP-ES living quarters fan starter emergency cut-off device, which is connected in series to the cabin fan emergency cut-off line, including the ES3 emergency cut-off button and the ES4 emergency cut-off button.

[0072] Figure 5 In the middle, the main distribution board (MSB) is equipped with an emergency cut-off device for the 3P-ES living quarters fan power distribution box, which is connected in series to the emergency cut-off line for the cabin fans, including the ES3 emergency cut-off button.

[0073] also, Figure 5 In the emergency disconnection device, the ship's main power distribution board includes a disconnecting switch and an insulation tester; the disconnecting switch (current parameter: maximum current withstand 2500A) is connected in series in the three-phase AC power (AC450V, 60Hz, 3Ph, BUS-A) line of the ship's main power distribution board; the insulation tester IRM is connected in series between the three-phase AC power line and the ground wire.

[0074] The insulation resistance meter (IRM) is used to monitor leakage current in the system. If leakage is detected, an alarm will be triggered. Specifically, the ship's insulation resistance meter measures the insulation resistance between different circuits in the electrical system to determine the insulation performance. When the resistance value falls below a set threshold, an alarm is triggered. The core principle of the insulation resistance meter is that it monitors the insulation resistance of each line in the ship's electrical network to ground or between phases in real time and compares the resistance value with a preset threshold. If the resistance value is lower than the threshold (usually several hundred to several thousand megohms), the device will trigger an alarm through audible and visual cues, digital display, etc., indicating the location of the fault.

[0075] The disconnect switch is used to disconnect two busbars in the main distribution board. If one busbar fails, the other can continue to be used.

[0076] In summary, the emergency shut-off device and ship power distribution system described in this application integrate all marine fans and pumps onto the main switchboard. All shut-off operations can be performed via switches on the main switchboard, and wiring is then routed from the main switchboard to all locations requiring operation (such as the bridge, fire control station, and engine room entrance). This simplifies the design of existing emergency shut-off systems, reduces raw material costs, and lowers labor costs. It also simplifies the wiring configuration and facilitates troubleshooting of faulty circuits.

[0077] The above embodiments are merely illustrative of the principles and effects of this application and are not intended to limit this application. Any person skilled in the art can modify or alter the above embodiments without departing from the spirit and scope of this application. Therefore, all equivalent modifications or alterations made by those skilled in the art without departing from the spirit and technical concept disclosed in this application should still be covered by the claims of this application.

Claims

1. An emergency shut-off device, characterized in that The emergency shut-off device includes: Ship's main electrical control panel; An emergency switch is connected in series in the power supply lines from the ship's main switchboard to each ship facility; wherein the power supply lines for each ship facility include the oil pump lines for the engine room fans, the cabin fans, the galley equipment lines, and the engine room area fans.

2. The emergency shut-off device according to claim 1, characterized in that: The emergency switch includes an emergency switch for the engine room entrance, which is fixedly connected to the emergency operation area at the engine room entrance through the wiring layout of the fan oil pump at the engine room entrance.

3. The emergency shut-off device according to claim 1, characterized in that: The emergency switch includes a central control room emergency switch, which is fixedly connected to the emergency operation area of ​​the central control room through the wiring layout of the fan oil pump in the machine space of the central control room.

4. The emergency shut-off device according to claim 1, characterized in that: The emergency switch includes a cab emergency switch, which is fixedly connected to the emergency operation area of ​​the cab through the wiring of the cab cabin fan and the oil pump of the engine room fan in the cab.

5. The emergency shut-off device according to claim 1, characterized in that: The emergency switch includes a fire control room emergency switch, which is fixedly connected to the emergency operation area of ​​the fire control room through the wiring of the fire control room cabin fan and the oil pump of the fire control room machine space fan.

6. The emergency shut-off device according to claim 1, characterized in that: The emergency switch includes a kitchen exit emergency switch, which is fixedly connected to the emergency operation area at the kitchen exit through the power supply wiring of the kitchen equipment.

7. The emergency shut-off device according to claim 1, characterized in that: The emergency switch includes a first starter panel emergency switch, which is fixedly connected to the emergency operation area at the starter panel of the nacelle equipment assembly through the wiring layout of the fan in the nacelle area.

8. The emergency shut-off device according to claim 1, characterized in that: The emergency switch includes a second starter panel emergency switch, which is fixedly connected to the emergency operation area at the starter panel of the bow cabin fan through the wiring arrangement of the bow cabin fan.

9. The emergency shut-off device according to claim 1, characterized in that: The emergency switches include a third starter panel emergency switch and a distribution box emergency switch. The third starter panel emergency switch is fixedly connected to the emergency operation area at the starter panel of the living quarters fan through the wiring layout of the living quarters fan. The distribution box emergency switch is fixedly connected to the emergency operation area at the power distribution box of the living quarters fan through the wiring layout of the living quarters fan.

10. A shipboard power distribution system, characterized in that, The ship's power distribution system includes: the emergency shut-off device as described in any one of claims 1-9; The ship's main power distribution board in the emergency disconnection device includes a disconnecting switch and an insulation tester; the disconnecting switch is connected in series in the three-phase AC power line of the ship's main power distribution board; the insulation tester is connected in series between the three-phase AC power line and the ground wire.